April 2003 Monthly Operating Report for South Texas Project Units 1 & 2
ML031420062
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 05/16/2003
From: Mallen F
South Texas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
G02, NOC-AE-03001531, STI: 31606930
Download: ML031420062 (14)


Text

w-Nuclear Operating Company I Sodh TEx y £m0 0pudr1rflibComp77 M n2J i a rz 2743 May 16,2003 NOC-AE-03001531 File No.: G02 10CFR50.71 STI: 31606930 U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 South Texas Project Units 1 and 2 Docket Nos. STN 50-498, STN 50-499 Monthly Operating Reports for April 2003 Pursuant to 10CFR50.71(a) and South Texas Project Electric Generating Station (STPEGS) Technical Specification 6.9.1.5, attached are the Monthly Operating Reports for April 2003. If you should have any questions on this matter, please contact R.L. Hill at (361) 972-7667.

F.H. Mallen Manager, Financial Controls Attachments: 1) STPEGS Unit 1 Monthly Operating Report - April 2003

2) STPEGS Unit 2 Monthly Operating Report - April 2003 1 2wA

cc:

(paper copy) (electronic copy)

Ellis W. Merschoff A. H. Gutterman, Esquire Regional Administrator, Region IV Morgan, Lewis & Bockius LLP U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 M. T. Hardt[W. C. Gunst Arlington, Texas 76011-8064 City Public Service U. S. Nuclear Regulatory Commission Mohan C. Thadani Attention: Document Control Desk U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike R. L. Balcom/D. G. Tees Rockville, MD 20852 Texas Genco, LP Richard A. Ratliff A. Ramirez Bureau of Radiation Control City of Austin Texas Department of Health 1100 West 49th Street C. A. Johnson/A. C. Bakken III Austin, TX 78756-3189 AEP - Central Power and Light Company Cornelius F. O'Keefe Jon C. Wood U. S. Nuclear Regulatory Commission Matthews & Branscomb P. O. Box 289, Mail Code: MN116 Wadsworth, TX 77483 C. M. Canady City of Austin Electric Utility Department 721 Barton Springs Road Austin, TX 78704

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 1 MONTHLY OPERATING REPORT APRIL 2003 STP NUCLEAR OPERATING COMPANY NRC DOCKET NO. 50-498 LICENSE NO. NPF-76 Approved By:

E.D. H(APIN Date

MONTHLY

SUMMARY

South Texas Project Unit 1 began the reporting period shutdown for refueling.

On April 12, during a scheduled boric acid inspection of the reactor coolant and associated systems, small deposits of boric acid were discovered on two (2) of the fifly-eight (58) bottom mounted instrumentation penetrations on the reactor pressure vessel. The investigation results indicate primary reactor coolant as the likely source of the residue.

The unit remained out of service following refueling to continue the investigation to determine the root cause, identify non-destructive examination methods and evaluate repair options.

OPERATING DATA REPORT DOCKET NO. 50-498 UNIT 1 DATE May 12, 2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 OPERATING STATUS

1. REPORTING PERIOD: 411/03-4130103 GROSS HOURS IN REPORTING PERIOD: 719
2. CURRENTLY AUTHORIZED POWER LEVEL (Mwt): 3.853 MAXIMUM DEPENDABLE CAPACITY (MWe-Net): 1,2506 DESIGN ELECTRICAL RATING (MWe-Net): 1250.6
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None
4. REASONS FOR RESTRICTION (IF ANY): N/A THIS MONTH YR TO DATE CUMULATIVE
5. NUMBER OF HOURS REACTOR CRITICAL 0.0 1,971.0 100,500.1
6. REACTOR RESERVE SHUTDOWN HOURS 0 0 0
7. HOURS GENERATOR ON LINE 0.0 98.856.9
8. UNIT RESERVE SHUTDOWN HOURS 0 1~~,96. 0 0
9. GROSS THERMAL ENERGY GENERATED (MWH) 0 7,348,061 369,298.524
10. NET ELECTRICAL ENERGY GENERATED (MWH) 0 2,463,746 120,679,801
11. REACTOR SERVICE FACTOR (%) 0.0 68.5 78.1
12. REACTOR AVAILABILITY FACTOR (%) 0.0 68.5 78.1
13. UNIT SERVICE FACTOR (%) 0.0 68.2 76.8
14. UNIT AVAILABILITY FACTOR (%) 0.0 68.2 76.8
15. UNIT CAPACITY FACTOR - Using MDC (%) 0.0 68.4 75.0
16. UNIT CAPACITY FACTOR - Using DER (%) 0.0 68.4 75.0
17. UNIT FORCED OUTAGE RATE (%) 100.0 13.0 13.4
18. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION OF EACH): N/A
19. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: 8/6/03

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-498 UNIT I DATE May 12,2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 MONTH APRIL DAY AVERAGE DAILY POWER DAY AVERAGE DAILY POWER LEVEL LEVEL (MWe-Net) (MWe-Net) 1 0 17 0 2 0 18 0 3 0 19 0 4 0 20 0 5 0 21 0 6 0 22 0 7 0 23 0 8 0 24 0 9 0 25 0 10 0 26 0 11 0 27 0 12 0 28 0 13 0 29 0 14 0 30 0 15 0 16 0

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-498 UNIT 1 DATE May 12. 2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 REPORT MONTH APRIL 1 ~~~~2 3 4 5 No. Date Type Duration Reason Method of Licensee System Component Cause & Corrective Action to Prevent Recurrence (Hours) Shutting Event Code Code Down Report#

Reactor 03-03 032603 S 478.0 C 1 N/A N/A N/A Refueling and scheduled maintenance outage.

03-04 04/20/03 F 241.0 F 9 01-03-003 RC PEN Investigate and repair bottom mounted instrumentation I I penetration indications.

1 2 3 4 5 F: Forced Reason: Method: IEEE 805-1983 IEEE 803-1983 S: Scheduled A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Cont. of Existing E-Operator Training & License Exam Outage F-Administrative 5-Reduction G-Operational Error (Explain) 9-Other H-Other (Explain)

PORVS AND SAFETY VALVE

SUMMARY

There were no PORV or Safety Valves challenged during the reporting period.

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 2 MONTHLY OPERATING REPORT APRIL 2003 STP NUCLEAR OPERATING COMPANY NRC DOCKET NO. 50-499 LICENSE NO. NPF-80 Approved By:

E.D. HALtIN Date

MONTHLY

SUMMARY

South Texas Project Unit 2 operated during the reporting period at full power with no unit shutdowns or significant power reductions.

OPERATING DATA REPORT DOCKETNO. 50-499 UNIT 2 DATE May 12, 2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 OPERATING STATUS

1. REPORTING PERIOD: 4/1103-4/30/03 GROSS HOURS IN REPORTING PERIOD: 719
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3,853 MAXIMUM DEPENDABLE CAPACITY (MWe-Net): 1,250.6 DESIGN ELECTRICAL RATING (MWe-Net): 1.250.
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None
4. REASONS FOR RESTRICTION (IF ANY): N/A THIS MONTH YR TO DATE CUMULATIVE
5. NUMBER OF HOURS REACTOR CRITICAL 719.0 1.265.7 95,823.4
6. REACTOR RESERVE SHUTDOWN HOURS 0 0
7. HOURS GENERATOR ON LINE 719.0 1.232.1 92,524.50
8. UNIT RESERVE SHUTDOWN HOURS 0 0
9. GROSS THERMAL ENERGY GENERATED (MWH) 2,744.392 4.518,381 348,932,032
10. NET ELECTRICAL ENERGY GENERATED (MWH) 916,279 1.495.644 113,673,611
11. REACTOR SERVICE FACTOR (%) 100.0 44.0 78.8
12. REACTOR AVAILABILITY FACTOR (%) 100.0 44.0 78.8
13. UNIT SERVICE FACTOR (%) 100.0 42.8 77.0
14. UNIT AVAILABILITY FACTOR (o) 100.0 42.8 77.0
15. UNIT CAPACITY FACTOR - Using MDC (%) 101.9 41.5 74.8
16. UNIT CAPACITY FACTOR - Using DER (%) 101.9 41.5 74.8
17. UNIT FORCED OUTAGE RATE (%) 0.0 57.2 14.7
18. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION OF EACH): N/A
19. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A

AVERAGE DAILY UNIT POWER LEVEL DOCKETNO. 50-499 UNIT 2 DATE May 12,2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 MONTH APRIL DAY AVERAGE DAILY POWER DAY AVERAGE DAILY POWER LEVEL LEVEL (MWe-Net) (MWe-Net) 1 1258 17 1276 2 1273 18 1275 3 1274 19 1272 4 1274 20 1273 5 1274 21 1273 6 1273 22 1273 7 1270 23 1271 8 1272 24 1272 9 1272 25 1272 10 1273 26 1273 11 1272 27 1272 12 1273 28 1274 13 1273 29 1275 14 1273 30 1274 15 1273 16 1276

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-499 UNIT 2 DATE May 12. 2003 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 REPORT MONTH APRIL 1 2 3 4 5 No. Date Type Duration Reason Method of Licensee System Component Cause & Corrective Action to Prevent Recurrence (Hours) Shutting Event Code Code Down Report #

Reactor THERE WERE NO UNIT SHUTDOWNS OR SIGNIFICANT POWER REDUCTIONS DURING THE REPORTING PERIOD

___l l l l l l l I 1 2 3 4 5 F: Forced Reason: Method: IEEE 805-1983 IEEE 803-1983 S: Scheduled A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Cont. of Existing E-Operator Training & License Exam Outage F-Administrative 5-Reduction G-Operational Error (Explain) 9-Other H-Other (Explain)

PORVS AND SAFETY VALVE

SUMMARY

There were no PORV or Safety Valves challenged during the reporting period.