NOC-AE-02001429, October 2002 Monthly Operating Report for South Texas Project Units 1 & 2

From kanterella
Jump to navigation Jump to search
October 2002 Monthly Operating Report for South Texas Project Units 1 & 2
ML023230329
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 11/14/2002
From: Mallen F
South Texas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NOC-AE-02001429
Download: ML023230329 (14)


Text

Nuclear Operating Company South Tc7s mfect FsPIchuGcnrcbngStanron PO.Box259 Wadsworth Tas77483 _ _ _ _ _ _-_

November 14, 2002 NOC-AE-02001429 File No.: G02 10CFR50.71 STI: 31519659 U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 South Texas Project Units 1 and 2 Docket Nos. STN 50-498, STN 50-499 Monthly Operating Reports for October 2002 Pursuant to IOCFR50.71(a) and South Texas Project Electric Generating Station (STPEGS) Technical Specification 6.9.1.5, attached are the Monthly Operating Reports for October 2002. If you should have any questions on this matter, please contact R.L.1',

Hill at (361) 972-7667.

F.H. Mallen Manager, Planning &

Controls Attachments: 1) STPEGS Unit 1 Monthly Operating Report - October 2002

2) STPEGS Unit 2 Monthly Operating Report - October 2002

NOC-AE-02001429 Page 2 cc:

(paper copy) (electronic copy)

Ellis W. Merschoff A. H. Gutterman, Esquire Regional Administrator, Region IV Morgan, Lewis & Bockius LLP U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 M. T. Hardt/W. C. Gunst Arlington, Texas 76011-8064 City Public Service U. S. Nuclear Regulatory Commission Mohan C. Thadani Attention: Document Control Desk U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike R. L. Balcom Rockville, MD 20852 Reliant Energy, Inc.

Richard A. Ratliff A. Ramirez Bureau of Radiation Control City of Austin Texas Department of Health 1100 West 49th Street C. A. Johnson Austin, TX 78756-3189 AEP - Central Power and Light Company Cornelius F. O'Keefe Jon C. Wood U. S. Nuclear Regulatory Commission Matthews & Branscomb P. 0. Box 289, Mail Code: MN1 16 Wadsworth, TX 77483 C. M. Canady City of Austin Electric Utility Department 721 Barton Springs Road Austin, TX 78704

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 1 MONTHLY OPERATING REPORT OCTOBER 2002 STP NUCLEAR OPERATING COMPANY NRC DOCKET NO. 50-498 LICENSE NO. NPF-76 Approved By:

E.D. bLPIN Date

MONTHLY

SUMMARY

South Texas Project Unit 1 operated during the reporting period at full power with no unit shutdowns or significant power reductions.

OPERATING DATA REPORT DOCKET NO. 50-498 UNIT I DATE Nov. 7, 2002 COMAPLETED BY R.L. Hill TELEPHONE 361.972.7667 OPERATING STATUS

1. REPORTING PERIOD: 10/1/02-10/31/02 GROSS HOURS IN REPORTING PERIOD: 745
2. CURRENTLY AUTHORIZED POWER LEVEL (Mwt): 3853 MAXIMUM DEPENDABLE CAPACITY (MWe-Net): 1,5 DESIGN ELECTRICAL RATING (MWe-Net): ,250.6
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None
4. REASONS FOR RESTRICTION (IF ANY): N/A THIS MONTH YR TO DATE CUMULATIVE 745.0 7,296 0 97*245.9
5. NUMBER OF HOURS REACTOR CRITICAL
6. REACTOR RESERVE SHUTDOWN HOURS 0 0 0
7. HOURS GENERATOR ON LINE 745.0 7,296.0 95A65.
8. UNIT RESERVE SHUTDOWN HOURS 0 0 0 2,843,146 27,813,297 357,111,637
9. GROSS THERMAL ENERGY GENERATED (MWH) 947,654 9,247,669 116,595,783
10. NET ELECTRICAL ENERGY GENERATED (MWH)
11. REACTOR SERVICE FACTOR (%) 1000 100.0 78.2
12. REACTOR AVAILABILITY FACTOR (%) 100.0 1000 78.2
13. UNIT SERVICE FACTOR (%) 100.0 100.0 76.9
14. UNIT AVAILABILITY FACTOR (%) 100.0 100.0 76.9
15. UNIT CAPACITY FACTOR - Using MDC (%) 101.7 101.4 75.0
16. UNIT CAPACITY FACTOR - Using DER (%) 101.7 101.4 75.0
17. UNIT FORCED OUTAGE RATE (%) 0.0 0.0 13.4
18. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION OF EACH):

Scheduled 21-day outage to allow scheduled refueling to begin on March 26, 2003.

19. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO. 50-498 UNIT 1 DATE Nov. 7, 2002 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 MONTH OCTOBER DAY AVERAGE DAILY POWER DAY AVERAGE DAILY POWER LEVEL LEVEL (MWe-Net) (MWe-Net) 1 1272 17 1278 2 1247 18 1276 3 1255 19 1276 4 1265 20 1275 5 1263 21 1274 6 1268 22 1276 7 1270 23 1272 8 1271 24 1269 9 1269 25 1279 10 1270 26 1279 11 1273 27 1279 12 1272 28 1274 13 1273 29 1275 14 1271 30 1281 15 1273 31 1280 16 1280

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-498 UNIT 1 DATE Nov 7, 2002 COMPLETED BY R.L Hill TELEPHONE 361.972 7667 REPORT MONTH OCTOBER 1 2 3 4 5 No. Date Type Duration Reason Method of Licensee System Component Cause & Corrective Action to Prevent Recurrence (Hours) Shutting Event Code Code Down Report #

Reactor THERE WERE NO UNIT SHUTDOWNS OR SIGNIFICANT POWER REDUCTIONS DURING THE REPORTING PERIOD II_ I I I I I 1 2 3 4 5 Method: IEEE 805-1983 IEEE 803-1983 F: Forced Reason:

S: Scheduled A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Cont. of Existing E-Operator Training & License Exam Outage F-Administrative 5-Reduction G-Operational Error (Explain) 9-Other H-Other (Explain)

PORVS AND SAFETY VALVE

SUMMARY

There were no PORV or Safety Valves challenged during the reporting period.

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 2 MONTHLY OPERATING REPORT OCTOBER 2002 STh NUCLEAR OPERATING COMPANY NRC DOCKET NO. 50-499 LICENSE NO. NPF-80 Approved By: /7 a cL E.D. HALPIN Date

MONTHLY

SUMMARY

South Texas Project Unit 2 began the reporting period operating at full power. On October 2, at 0001 the unit was removed from service for scheduled refueling and steam generator replacement.

OPERATING DATA REPORT DOCKETNO. 50-499 UNIT 2 DATE Nov. 7, 2002 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 OPERAkTING STATUS

1. REPORTING PERIOD: 10/1/02-10/31/02 GROSS HOURS IN REPORTING PERIOD: 745
2. CURRENTLY AUTHORIZED POWER LEVEL (MWt): 3800 MAXIMUM DEPENDABLE CAPACITY (MWe-Net): 1,250.6 DESIGN ELECTRICAL RATING (MWe-Net): 1,250.6
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None
4. REASONS FOR RESTRICTION (IF ANY): N/A THIS MONTH YR TO DATE CUMULATIVE
5. NUMBER OF HOURS REACTOR CRITICAL 24.2 6,480.3 94,294.3
6. REACTOR RESERVE SHUTDOWN HOURS 0 0 0
7. HOURS GENERATOR ON LINE 24.0 6,426.8 92,054.5
8. UNIT RESERVE SHUTDOWN HOURS 0 0 0 79,607 24,457,687 343,618,219
9. GROSS THERMAL ENERGY GENERATED (MWH)
10. NET ELECTRICAL ENERGY GENERATED (MWH) 25,445 7,962,417 111,920,538
11. REACTOR SERVICE FACTOR (%) 3.3 88.8 80.5
12. REACTOR AVAILABILITY FACTOR (%) 3.3 88.8 80.5
13. UNIT SERVICE FACTOR (%) 3.2 88.1 78.5
14. UNIT AVAILABILITY FACTOR (%) 3.2 88.1
15. UNIT CAPACITY FACTOR - Using MDC (%) 2.7 87.3 76.4
16. UNIT CAPACITY FACTOR - Using DER (%) 2.7 87.3 76.4
17. UNIT FORCED OUTAGE RATE (%) 0.0 2.3 13.2
18. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION OF EACH): N/A
19. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A

AVERAGE DAILY UNIT POWER LEVEL DOCKETNO. 50-499 UNIT 2 DATE Nov. 7, 2002 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 MONTH OCTOBER DAY AVERAGE DAILY POWER DAY AVERAGE DAILY POWER LEVEL LEVEL (MWe-Net) (MWe-Net) 1 1060 17 0 2 0 18 0 3 0 19 0 4 0 20 0 5 0 21 0 6 0 22 0 7 0 23 0 8 0 24 0 9 0 25 0 10 0 26 0 11 0 27 0 12 0 28 0 13 0 29 0 14 0 30 0 15 0 31 0 16 0

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-499 UNIT 2 DATE Nov. 7, 2002 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 REPORT MONTH OCTOBER 1 2 3 4 5 No. Date Type Duration Reason Method of Licensee System Component Cause & Corrective Action to Prevent Recurrence (Hours) Shutting Event Code Code Down Report #

Reactor 02-03 021002 S 721.0 C 1 N/A N/A N/A Scheduled outage to allow refueling and steam generator replacement.

1 2 3 4 5 F: Forced Reason: Method: IEEE 805-1983 IEEE 803-1983 S: Scheduled A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Cont. of Existing E-Operator Training & License Exam Outage F-Administrative 5-Reduction G-Operational Error (Explain) 9-Other H-Other (Explain)

PORVS AND SAFETY VALVE

SUMMARY

There were no PORV or Safety Valves challenged during the reporting period.