NOC-AE-02001414, September 2002 Monthly Operating Report for South Texas Project Units 1 and 2

From kanterella
Jump to navigation Jump to search
September 2002 Monthly Operating Report for South Texas Project Units 1 and 2
ML022890270
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 10/10/2002
From: Mallen F
South Texas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
G02, NOC-AE-02001414, STI: 31499179
Download: ML022890270 (14)


Text

Nuclear Operating Company Soakh To'z.%ftd Nxdo Oir" CoAmpmy 8m 219 05dwý PU2 ki 77433 October 10, 2002 NOC-AE-02001414 File No.: G02 10CFR50.71 STI: 31499179 U. S. Nuclear Regulatory Commission Attention: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852 South Texas Project Units 1 and 2 Docket Nos. STN 50-498, STN 50-499 Monthly Operating Reports for September 2002 Pursuant to 10CFR50.71(a) and South Texas Project Electric Generating Station (STPEGS) Technical Specification 6.9.1.5, attached are the Monthly Operating Reports for September 2002. If you should have any questions on this matter, please contact R.L.

Hill at (361) 972-7667.

F.H. Mallen Manager, Planning &

Controls Attachments: 1) STPEGS Unit 1 Monthly Operating Report - September 2002

2) STPEGS Unit 2 Monthly Operating Report - September 2002

cc:

(paper copy) (electronic copy)

Ellis W. Merschoff A. H. Gutterman, Esquire Regional Administrator, Region IV Morgan, Lewis & Bockius LLP U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 M. T. Hardt/W. C. Gunst Arlington, Texas 76011-8064 City Public Service U. S. Nuclear Regulatory Commission Mohan C. Thadani Attention: Document Control Desk U. S. Nuclear Regulatory Commission One White Flint North 11555 Rockville Pike R. L. Balcom/D. G. Tees Rockville, MD 20852 Reliant Energy, Inc.

Richard A. Ratliff A. Ramirez Bureau of Radiation Control City of Austin Texas Department of Health 1100 West 49th Street C. A. Johnson/A. C. Bakken III Austin, TX 78756-3189 AEP - Central Power and Light Company Cornelius F. O'Keefe Jon C. Wood U. S. Nuclear Regulatory Commission Matthews & Branscomb P. 0. Box 289, Mail Code: MN1 16 Wadsworth, TX 77483 C. M. Canady City of Austin Electric Utility Department 721 Barton Springs Road Austin, TX 78704

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 1 MONTHLY OPERATING REPORT SEPTEMBER 2002 STP NUCLEAR OPERATING COMPANY NRC DOCKET NO. 50-498 LICENSE NO. NPF-76 Approved By: -__,__ /0/7 /c E.D. VLPIN Date

MONTHLY

SUMMARY

South Texas Project Unit 1 operated during the reporting period at full power with no unit shutdowns or significant power reductions.

OPERATING DATA REPORT DOCKET NO. 50-498 UNIT I DATE Oct 7, 2002 COMPLETED BY R.L Hill TELEPHONE 361.972.7667 OPERATING STATUS

1. REPORTING PERIOD. 09/1/02-09/30/02 GROSS HOURS IN REPORTING PERIOD: 720
2. CURRENTLY AUTHORIZED POWER LEVEL (Mwt). 3,853 MAXIMUM DEPENDABLE CAPACITY (MWe-Net). 12506 DESIGN ELECTRICAL RATING (MWe-Net).1,250 6
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net): None
4. REASONS FOR RESTRICTION (IF ANY). N/A THIS MONTH YR TO DATE CUMULATIVE
5. NUMBER OF HOURS REACTOR CRITICAL 720.0 6,5510 96,500.9
6. REACTOR RESERVE SHUTDOWN HOURS 0 0 0
7. HOURS GENERATOR ON LINE 720.0 6,5510o 94,870.8
8. UNIT RESERVE SHUTDOWN HOURS 0 0 0 2,746,600 354,268,491
9. GROSS THERMAL ENERGY GENERATED (MWH) 24,970,151 10 NET ELECTRICAL ENERGY GENERATED (MWH) 917,216 8,300,015 115,648,129
11. REACTOR SERVICE FACTOR (%) 100.0 100.0 78.1
12. REACTOR AVAILABILITY FACTOR (%) 100.0 100.0 78.1
13. UNIT SERVICE FACTOR (%) 1000 100.0 76.8
14. UNIT AVAILABILITY FACTOR (%) 1000 1000 76 8
15. UNIT CAPACITY FACTOR- Using MDC (%) 101.9 101.3 74 8
16. UNIT CAPACITY FACTOR - Using DER (%) 101.9 101.3 74.8
17. UNIT FORCED OUTAGE RATE (%) 00 0.0 13.5
18. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION OF EACH):

Scheduled 21-day outage to allow scheduled refueling to begin on March 26, 2003.

19. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO 50-498 UNIT I DATE Oct. 7, 2002 COMPLETED BY R.L. Hill TELEPHONE 361.972 7667 MONTH SEPTEMBER DAY AVERAGE DAILY POWER DAY AVERAGE DAILY POWER LEVEL LEVEL (MWe-Net) (MWe-Net) 1 1270 17 1273 2 1271 18 1273 3 1271 19 1274 4 1272 20 1272 5 1274 21 1258 6 1274 22 1277 7 1273 23 1277 8 1273 24 1276 9 1274 25 1271 10 1275 26 1280 11 1275 27 1282 12 1277 28 1280 13 1275 29 1278 14 1272 30 1277 15 1271 16 1272

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-498 UNIT 1 DATE Oct 7, 2002 COMPLETED BY R L Hill TELEPHONE 361 972 7667 REPORT MONTH SEPTEMBER 1 2 3 4 5 No. Date Type Duration Reason Method of Licensee System Component Cause & Corrective Action to Prevent Recurrence (Hours) Shutting Event Code Code Down Report #

Reactor THERE WERE NO UNIT SHUTDOWNS OR SIGNIFICANT POWER REDUCTIONS DURING THE REPORTING PERIOD 1 2 3 4 5 F: Forced Reason: Method: IEEE 805-1983 IEEE 803-1983 S' Scheduled A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Cont of Existing E-Operator Training & License Exam Outage F-Adirmnstrative 5-Reduction G-Operational Error (Explain) 9-Other H-Other (Explain)

PORVS AND SAFETY VALVE

SUMMARY

There were no PORV or Safety Valves challenged dunng the reporting period.

SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION UNIT 2 MONTHLY OPERATING REPORT SEPTEMBER 2002 STP NUCLEAR OPERATING COMPANY NRC DOCKET NO. 50-499 LICENSE NO. NPF-80 Approved By.

E.D. II II -Date

MONTHLY

SUMMARY

South Texas Project Unit 2 operated during the reporting period at full power with no unit shutdowns or significant power reductions.

OPERATING DATA REPORT DOCKETNO. 50-499 UNIT 2 DATE Oct 7, 2002 COMPLETED BY R L. Hill TELEPHONE 361.972.7667 OPERATING STATUS 1 REPORTING PERIOD. 09/1/02-09/39/02 GROSS HOURS IN REPORTING PERIOD: 720

2. CURRENTLY AUTHORIZED POWER LEVEL (MWt). 3800 MAXIMUM DEPENDABLE CAPACITY (MWe-Net): 1,250.6 DESIGN ELECTRICAL RATING (MWe-Net): 1,250 6
3. POWER LEVEL TO WHICH RESTRICTED (IF ANY) (MWe-Net) None
4. REASONS FOR RESTRICTION (IF ANY): N/A THIS MONTH YR TO DATE CUMULATIVE
5. NUMBER OF HOURS REACTOR CRITICAL 7200 6,4561 94*270.1
6. REACTOR RESERVE SHUTDOWN HOURS 0 0 0
7. HOURS GENERATOR ON LINE 720 0 6,402 8 92,_030.5
8. UNIT RESERVE SHUTDOWN HOURS 0 0 0
9. GROSS THERMAL ENERGY GENERATED (MWH) 2,747,965 24,378,080 343,538,611
10. NET ELECTRICAL ENERGY GENERATED (MWH) 891,864 7,936,972 111,895,093
11. REACTOR SERVICE FACTOR (%) 100.0 986 81.0 12 REACTOR AVAILABILITY FACTOR (%) 100.0 986 81.0 13 UNIT SERVICE FACTOR (%) 100.0 97.7 79.0
14. UNIT AVAILABILITY FACTOR (%) 100.0 97.7 79.0
15. UNIT CAPACITY FACTOR - Using MDC (%) 99.0 96.9 76.8
16. UNIT CAPACITY FACTOR - Using DER (%) 99.0 969 76.8
17. UNIT FORCED OUTAGE RATE (%) 0.0 2.3 13.2
18. SHUTDOWNS SCHEDULED OVER NEXT 6 MONTHS (TYPE, DATE, & DURATION OF EACH):

Scheduled 65-day outage to allow refueling and steam generator replacement to begin on October 2, 2002

19. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP N/A

AVERAGE DAILY UNIT POWER LEVEL DOCKETNO 50-499 UNIT 2 DATE Oct 7, 2002 COMPLETED BY R.L Hill TELEPHONE 361.972.7667 MONTH SEPTEMBER DAY AVERAGE DAILY POWER DAY AVERAGE DAILY POWER LEVEL LEVEL (MWe-Net) (MWe-Net) 1237 17 1234 1237 18 1234 1237 19 1237 1237 20 1239 1237 21 1240 1238 22 1241 1238 23 1241 1240 24 1242 1242 25 1242 1241 26 1242 1241 27 1243 1242 28 1241 1237 29 1240 1234 30 1239 1233 1234

UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO. 50-499 UNIT 2 DATE Oct. 7, 2002 COMPLETED BY R.L. Hill TELEPHONE 361.972.7667 REPORT MONTH SEPTEMBER 1 2 3 4 5 No. Date Type Duration Reason Method of Licensee System Component Cause & Corrective Action to Prevent Recurrence (Hours) Shutting Event Code Code Down Report #

Reactor THERE WERE NO UNIT SHUTDOWNS OR SIGNIFICANT POWER REDUCTIONS DURING THE REPORTING PERIOD 1 2 3 4 5 F. Forced Reason Method: IEEE 805-1983 IEEE 803-1983 S. Scheduled A-Equipment Failure (Explain) 1-Manual B-Maintenance or Test 2-Manual Scram C-Refueling 3-Automatic Scram D-Regulatory Restriction 4-Cont. of Existing E-Operator Training & License Exam Outage F-Administrative 5-Reduction G-Operational Error (Explain) 9-Other H-Other (Explain)

PORVS AND SAFETY VALVE

SUMMARY

There were no PORV or Safety Valves challenged during the reporting period.