NL-15-1096, Provides Follow-up Letter Regarding Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval

From kanterella
Jump to navigation Jump to search

Provides Follow-up Letter Regarding Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval
ML15170A192
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 06/18/2015
From: Pierce C
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-15-1096
Download: ML15170A192 (2)


Text

Charles R. Pierce Southern Nuclear Regulatory Affairs Director Operating Company, Inc.

40 Inverness Center Parkway Post Office Box 1295 Birmmgham, AL 35201 Tel 205.992.7872 s UTHERN << \

COMPANY Fax 205.992.7601 June 18,2015 Docket Nos.: 50-321 NL-15-1096 50-366 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant - Units 1 & 2 Follow-up Letter Regarding Submittal of the lnservice Testing Program Relief Requests and Alternatives for Pumps and Valves- Fifth Ten-Year Interval Ladies and Gentlemen:

By letter dated May 4, 2015, Southern Nuclear Operating Company (SNC) requested Nuclear Regulatory Commission (NRC) approval of various relief requests and alternatives for Edwin I. Hatch Nuclear Plant (HNP) Units 1 and 2 (SNC letter NL-15-0784}. These relief requests and alternatives are applicable to the Fifth Ten-Year lntervallnservice Testing Program which will start on January 1, 2016.

Upon further consideration, SNC no longer requests NRC approval of RR-V-3. In addition, SNC would like to request that NRC approval of RR-P-3 be granted pursuant to 10 CFR 50.55a(z)(1) instead of 10 CFR 50.55a(z)(2). Lastly, SNC requests NRC approval of RR-V-10 pursuant to 10 CFR 50.55a(z)(1}.

This letter contains no NRC commitments. If you have any questions, please contact Ken McElroy at (205) 992-7369.

Respectfully submitted, C,1{ ~

C. R. Pierce Regulatory Affairs Director CRP/RMJ

U.S. Nuclear Regulatory Commission NL-15-1096 Page2 cc: Southern Nuclear Operating Company Mr. S. E. Kuczynski, Chairman, President & CEO Mr. D. G. Best, Executive Vice President & Chief Nuclear Officer Mr. D. R. Vineyard, Vice President- Hatch Mr. M. D. Meier, Vice President- Regulatory Affairs Mr. D. R. Madison, Vice President- Fleet Operations Mr. B. J. Adams, Vice President- Engineering Mr. G. L. Johnson, Regulatory Affairs Manager- Hatch RTYPE: CHA02.004 U.S. Nuclear Regulatory Commission Mr. V. M. McCree, Regional Administrator Mr. R. E. Martin, NRR Senior Project Manager- Hatch Mr. D. H. Hardage, Senior Resident Inspector- Hatch