Cheryl A. Gayheart Regulatory Affairs Director 3535 Colonnade Parkway Birmingham, AL 35243 205-992-5316 cagayhea@southernco.com April 19, 2022 Docket Nos.: 50-321 NL-22-0271 50-366 10 CFR 50.54(p)(2)
ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Edwin I. Hatch Nuclear Plant - Units 1 and 2 Report of Changes to the Physical Security Plan Ladies and Gentlemen:
In accordance with the provisions of 10 CFR 50.54(p), Southern Nuclear Operating Company (SNC) hereby reports that the Edwin I. Hatch Nuclear Plant Units 1 and 2 (HNP) Physical Security Plan (PSP) has been revised to Version 18-HNP-2.1. provides a summary description of the changes incorporated into the HNP PSP, Version 18-HNP-2.1. SNC has reviewed the changes in accordance with the provisions of 10 CFR 50.54(p)(2) and determined that this revision does not decrease the safeguards effectiveness of the HNP PSP.
This letter contains no NRC commitments. If you have any questions, please contact Ryan Joyce at 205-992-6468.
Respectfully submitted, Cheryl A. Gayheart Regulatory Affairs Director CAG/tle
Enclosure:
Description of Changes to the Physical Security Plan cc:
NRC Regional Administrator, Region II NRC NRR Project Manager - Hatch NRC Senior Resident Inspector - Hatch SNC Records Rtype: CHA02.004
Edwin I. Hatch Nuclear Plant - Units 1 and 2 Report of Changes to the Physical Security Plan Enclosure Description of Changes to the Physical Security Plan
Enclosure to NL-22-0271 Description of Changes to the Physical Security Plan Page E-1 Description of Changes The Edwin I. Hatch Nuclear Plant Units 1 and 2 (HNP) Physical Security Plan (PSP) has been revised to Version 18-HNP-2.1.
Specifically, HNP PSP Section 11.2.3, Waterborne Threat Measures, has been edited to change the description of the intake boom from a barrier to a demarcation.
Effective Date March 26, 2022.
Conclusion SNC evaluated these changes in accordance with 10 CFR 50.54(p)(2) and determined that the changes do not reduce the effectiveness of the PSP for HNP. The 10 CFR 50.54(p) evaluation and PSP are available for inspection at the NRCs request.