NL-15-1096, Provides Follow-up Letter Regarding Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval
Letter Sequence Request | |
---|---|
CAC:MF6238, (Withdrawn, Closed) | |
Administration | |
MONTHYEARNL-15-0784, Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval2015-05-0404 May 2015
[Table View]Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval Project stage: Request NL-15-1096, Provides Follow-up Letter Regarding Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval2015-06-18018 June 2015 Provides Follow-up Letter Regarding Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval Project stage: Request NL-15-1221, Withdrawal of RR-V-2 and Response to Request for Additional Information on RR-V-12015-07-16016 July 2015 Withdrawal of RR-V-2 and Response to Request for Additional Information on RR-V-1 Project stage: Withdrawal NL-15-1114, Response to Request for Additional Information for Alternative Requests RR-P-11 and RR-P-132015-07-16016 July 2015 Response to Request for Additional Information for Alternative Requests RR-P-11 and RR-P-13 Project stage: Response to RAI NL-15-1997, Revision to Relief Request P-5 and P-92015-10-26026 October 2015 Revision to Relief Request P-5 and P-9 Project stage: Request ML15310A4062015-12-30030 December 2015 Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval Project stage: Other 2015-05-04 |
ML15170A192 | |
Person / Time | |
---|---|
Site: | Hatch |
Issue date: | 06/18/2015 |
From: | Pierce C Southern Nuclear Operating Co |
To: | Document Control Desk, Office of Nuclear Reactor Regulation |
References | |
NL-15-1096 | |
Download: ML15170A192 (2) | |
Similar Documents at Hatch | |
---|---|
Category:Code Relief or Alternative
MONTHYEARML20143A2332020-06-0303 June 2020
[Table view]Relief Request for Deferral of ASME Boiler and Pressure Vessel Code, Section XI, Required Summary Report Submittal (EPID L-2020-LLR-0074 (COVID-19)) ML20034E8942020-02-11011 February 2020 Relief Request Gen-ISI-ALT-2019-01 for Proposed Alternative to Use of ASME Code Case N-831-1, Ultrasonic Examination in Lieu of Radiography for Welds in Ferritic or Austenitic Pipe Section XI, Division 1 ML19361A0562020-01-0909 January 2020 Proposed Alternative HNP-ISI-ALT-05-10 for the Implementation of BWRVIP 38 and -76 in Lieu of B-N-2 Examinations for Core Support Structures NL-19-1336, Implementation of BWRVIP-38 and -76 in Lieu of B-N-2 Examinations for Core Support Structures2019-11-0404 November 2019 Implementation of BWRVIP-38 and -76 in Lieu of B-N-2 Examinations for Core Support Structures ML18320A0572018-11-30030 November 2018 Plant, Units 1 and 2 - Proposed Inservice Inspection Alternative GEN-ISI-ALT-2017-03, Code Case N-513-4 for Moderate Pressure NL-18-0713, Request for Alternative HNP-ISI-ALT-05-08 to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping for Hatch Unit 1 Plant Service Water2018-05-17017 May 2018 Request for Alternative HNP-ISI-ALT-05-08 to Implement Code Case N-513-4, Evaluation Criteria for Temporary Acceptance of Flaws in Moderate Energy Class 2 or 3 Piping for Hatch Unit 1 Plant Service Water NL-18-0408, Proposed Alternative RR-V-12 Regarding Main Steam Safety Relief Valve Testing2018-04-0909 April 2018 Proposed Alternative RR-V-12 Regarding Main Steam Safety Relief Valve Testing NL-18-0428, Withdrawal of Proposed Alternative GEN-ISI-ALT-2017-001 Implementation of Code Case N-786-12018-04-0909 April 2018 Withdrawal of Proposed Alternative GEN-ISI-ALT-2017-001 Implementation of Code Case N-786-1 ML17279A0452017-10-26026 October 2017 Relief Requests ISI-RR-13, -14, -18, -19, -23, and -24 for Relief from Inservice Inspection Requirements ML17268A0442017-10-20020 October 2017 Relief Requests ISI RR 16, ISI-RR-17, ISI-44-21, and ISI-RR-22 for Relief from Inservice Inspection Requirements ML17205A3452017-08-10010 August 2017 Relief Request HNP-ISI-RR- 05-01 Regarding Reactor Pressure Vessel Head Stud Inservice Inspection Requirements ML17062A8322017-03-29029 March 2017 Relief Request ISI RR-15 Regarding Control Rod Drive Housing Welds Inservice Inspection Requirements ML16314A1322016-11-23023 November 2016 Request for Alternative HNP-ISI-ALT-05-03, Version 1.0, Regarding Reactor Pressure Vessel Flange Leak-Off Piping ML15310A4062015-12-30030 December 2015 Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval ML15352A2942015-12-28028 December 2015 Relief from the Requirements of the ASME Code ML15349A9732015-12-18018 December 2015 Relief from the Requirements of the ASME Code NL-15-1221, Withdrawal of RR-V-2 and Response to Request for Additional Information on RR-V-12015-07-16016 July 2015 Withdrawal of RR-V-2 and Response to Request for Additional Information on RR-V-1 NL-15-1265, E.I Hatch, Units 1 and 2 - 10CFR 50.55a Request No. HNP-ISI-ALT-5-01, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Maintaining Isi/Cii Related Activities on the 2001 E/2003A ASME Section XI Code2015-07-16016 July 2015 E.I Hatch, Units 1 and 2 - 10CFR 50.55a Request No. HNP-ISI-ALT-5-01, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) Maintaining Isi/Cii Related Activities on the 2001 E/2003A ASME Section XI Code NL-15-1096, Provides Follow-up Letter Regarding Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval2015-06-18018 June 2015 Provides Follow-up Letter Regarding Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval NL-11-0162, Submittal of Revision to Relief Request RR-V-4 Fourth 10-Year Interval Inservice Testing Program2011-01-26026 January 2011 Submittal of Revision to Relief Request RR-V-4 Fourth 10-Year Interval Inservice Testing Program ML1100504942011-01-14014 January 2011 Safety Evaluation of Relief Request HNP-ISI-ALT-10, Version 1, for the Fourth 10-Year Inservice Inspection Interval Temporary Non-Code Repair of Service Water Piping, TAC ME4253 ML1020304442010-07-22022 July 2010 E-mail from Robert Martin, Regarding Verbal Authorixation of Relief - Note to File ML1020304522010-07-21021 July 2010 Verbal Authorization for Relief Request HNP-ISI-ALT-10 Temporary Non-code Repair of Service Water Piping ML1009802142010-04-0808 April 2010 Safety Evaluation of Relief Request HNP-ISI-ALT-09, Version 2.0, for the Fourth 10-year Inservice Inspection Interval ML0731301882007-12-0606 December 2007 Safety Evaluation for Alternative ISI-ALT-08 ML0713602972007-06-0505 June 2007 Relief, Evaluation of Third 10-Year Interval Inservice Inspection Program Plan Request to Relief Nos. RR-42 Through RR-45, RR- 51, RR-58, RR-59, RR-60, & RR-62 ML0604502862006-02-14014 February 2006 Request for Relief from the Requirements of the American Society of Mechanical Engineered Boiler and Vessel Code (ASME Code) ML0534700912006-01-0303 January 2006 Relief, Boiler and Pressure Vessel Code, MC6528 and MC6529 ML0533303392005-12-22022 December 2005 Request for Relief from the Requirements of the American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Code) ML0529700082005-11-0909 November 2005 Relief, Proposed Alternative RR-41 for Third and Fourth 10-Year Inservice Inspection Interval NL-05-1372, Third and Fourth 10-Year Interval Inservice Inspection Programs, Submittal of Revised Exemption Request2005-08-0202 August 2005 Third and Fourth 10-Year Interval Inservice Inspection Programs, Submittal of Revised Exemption Request ML0510301992005-04-25025 April 2005 RR, ISI Program Intervals for Alternative Alignment of Iwe/Iwl Inspection Program (Tac No. MC4870, MC4871, MC4872, MC4873, MC4874, MC4875) NL-05-0726, Fourth 10-Year Interval IST Program Update2005-04-20020 April 2005 Fourth 10-Year Interval IST Program Update ML0501303172005-01-28028 January 2005 Ltr, RR No. 38 NL-04-1764, Third 10-Year Interval Inservice Inspection Program Submittal of Revised Relief Request RR-382004-09-13013 September 2004 Third 10-Year Interval Inservice Inspection Program Submittal of Revised Relief Request RR-38 ML0332800372003-11-21021 November 2003 Safety Evaluation Re. Request to Use ASME Code Case N-661 NL-03-1744, Third 10-Year Interval Inservice Testing Program Submittal of Revised Relief Request RR-V-18 and Response to Request for Additional Information (RAI)2003-09-12012 September 2003 Third 10-Year Interval Inservice Testing Program Submittal of Revised Relief Request RR-V-18 and Response to Request for Additional Information (RAI) ML0304100732003-02-10010 February 2003 Relief Request, Third 10-year Inservice Inspection Program ML0301404462003-01-14014 January 2003 Relief Request, Third 10-Year Inservice Inspection Program ML0230903232002-10-30030 October 2002 Third 10-Year Interval Inservice Testing Program, Revision to Existing Relief Request RR-V-11 ML0218305772002-07-0202 July 2002 Relief Requests for the Second 10-Year Inservice Inspection (ISI) Interval 2020-06-03 Category:Inservice/Preservice Inspection and Test Report MONTHYEARNL-24-0260, Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R312024-07-0909 July 2024
[Table view]Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R31 NL-22-0365, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R302022-05-31031 May 2022 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R30 NL-21-0905, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R292022-01-26026 January 2022 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R29 NL-19-1491, Update to the Snubber Program Plan for the Fifth Ten-Year Inservice Testing Interval2019-12-0909 December 2019 Update to the Snubber Program Plan for the Fifth Ten-Year Inservice Testing Interval NL-19-0726, Inservice Inspection Program Owner'S Activity Report for Outage 2R252019-06-17017 June 2019 Inservice Inspection Program Owner'S Activity Report for Outage 2R25 NL-19-0317, Submittal of Fifth Ten-Year Interval Lnservice Testing Program Update2019-04-0202 April 2019 Submittal of Fifth Ten-Year Interval Lnservice Testing Program Update NL-17-1194, Submittal of Response to Request for Information Fourth Interval Relief Requests RR-13, RR-14, RR-18, RR19, RR-23, and RR-242017-07-10010 July 2017 Submittal of Response to Request for Information Fourth Interval Relief Requests RR-13, RR-14, RR-18, RR19, RR-23, and RR-24 NL-17-0951, Inservice Inspection Program, Owner'S Activity Report for Outage 2R242017-05-30030 May 2017 Inservice Inspection Program, Owner'S Activity Report for Outage 2R24 NL-16-2707, Units 1 and 2; Fourth 10-year Interval In-service Inspection Program ISI Program Update: Notification of Impractical ASME Code Requirements (NL-16-2707)2016-12-27027 December 2016 Units 1 and 2; Fourth 10-year Interval In-service Inspection Program ISI Program Update: Notification of Impractical ASME Code Requirements (NL-16-2707) ND-16-1437, Snubber Program Plan for the Fifth Ten-Year Inservice Testing Interval2016-08-24024 August 2016 Snubber Program Plan for the Fifth Ten-Year Inservice Testing Interval NL-16-0795, Inservice Inspection Program - Owner'S Activity Report for Outage IR272016-06-0101 June 2016 Inservice Inspection Program - Owner'S Activity Report for Outage IR27 NL-16-0421, Full Structural Weld Overlays on Reactor Recirculation and Residual Heat Removal Systems, Nondestructive Examination Results - Spring 2016 Outage (1R27)2016-03-17017 March 2016 Full Structural Weld Overlays on Reactor Recirculation and Residual Heat Removal Systems, Nondestructive Examination Results - Spring 2016 Outage (1R27) NL-15-1096, Provides Follow-up Letter Regarding Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval2015-06-18018 June 2015 Provides Follow-up Letter Regarding Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval NL-15-1032, E. I. Hatch, Unit 2 - Inservice Inspection Program Owner'S Activity Report for Outage 2R232015-06-12012 June 2015 E. I. Hatch, Unit 2 - Inservice Inspection Program Owner'S Activity Report for Outage 2R23 NL-15-0784, Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval2015-05-0404 May 2015 Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval NL-14-1821, Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 2.0 - Supplemental Information2014-11-13013 November 2014 Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 2.0 - Supplemental Information NL-14-1276, Snubber Inspection Plan Submittal in Accordance with ASME OM Code2014-10-31031 October 2014 Snubber Inspection Plan Submittal in Accordance with ASME OM Code NL-14-1250, Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 2.02014-09-19019 September 2014 Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 2.0 NL-14-0840, Lnservice Inspection Program Owner'S Activity Report for Outage 1R262014-06-0303 June 2014 Lnservice Inspection Program Owner'S Activity Report for Outage 1R26 NL-14-0231, Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 1.02014-03-0606 March 2014 Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 1.0 NL-12-1266, Inservice Inspection Program, Owner'S Activity Report for Outage 1R252012-06-14014 June 2012 Inservice Inspection Program, Owner'S Activity Report for Outage 1R25 NL-10-0989, Fourth 10-Year Interval Lnservice Inspection Program Submittal of Relief Requests2010-07-0808 July 2010 Fourth 10-Year Interval Lnservice Inspection Program Submittal of Relief Requests NL-10-1023, Inservice Inspection Program, Owner'S Activity Report for Outage 1R242010-06-11011 June 2010 Inservice Inspection Program, Owner'S Activity Report for Outage 1R24 NL-08-1798, Fourth 10-Year Interval Lnservice Inspection Program Submittal of Relief Request RR-012008-12-19019 December 2008 Fourth 10-Year Interval Lnservice Inspection Program Submittal of Relief Request RR-01 NL-08-0901, Unit 1, Inservice Inspection Program Owner'S Activity Report for Outage 1R23 and Structural Integrity Design Report for the N9 CRD Nozzle-to-Cap Full Structural Weld Overlay2008-06-13013 June 2008 Unit 1, Inservice Inspection Program Owner'S Activity Report for Outage 1R23 and Structural Integrity Design Report for the N9 CRD Nozzle-to-Cap Full Structural Weld Overlay NL-07-0987, Fourth Interval Inspection (ISI) Plan Correction2007-05-0909 May 2007 Fourth Interval Inspection (ISI) Plan Correction NL-07-0802, Response to Request for Additional Information Regarding the Third 10-Year Interval Inservice Inspection (ISI) Relief Requests2007-04-13013 April 2007 Response to Request for Additional Information Regarding the Third 10-Year Interval Inservice Inspection (ISI) Relief Requests ML0704300922006-11-20020 November 2006 E. I. Hatch, Unit 2, Volume 1, Revision 2, Introduction Fourth Ten-Year Examination Plan. ML0704301002006-11-20020 November 2006 E. I. Hatch, Unit 2, Volume 3, Revision 1.0, Class 1, 2 and 3 Figures Fourth Ten-Year Inservice Inspection Plan. ML0704300942006-11-20020 November 2006 E. I. Hatch, Unit 2, Volume 2, Revision 1, Class 1, 2 and 3 Components Fourth Ten-Year Examination Plan. ML0704301012006-08-10010 August 2006 E. I. Hatch, Unit 2, Version 1.0, Pressure Test Section Fourth Ten-Year Examination Plan. NL-06-1358, Inservice Inspection Program, Owner'S Activity Report for Outage 1R222006-06-29029 June 2006 Inservice Inspection Program, Owner'S Activity Report for Outage 1R22 ML0704300812006-02-0606 February 2006 E. I. Hatch, Unit 1, Volume 1, Revision 1, Introduction Fourth Ten-Year Inservice Inspection Plan. ML0704300832006-02-0606 February 2006 E. I. Hatch, Unit 1, Volume 2, Revision 1, Class 1, 2 and 3 Components Fourth Ten-Year Inservice Inspection Plan. ML0704300872006-02-0606 February 2006 E. I. Hatch, Unit 1, Volume 3, Revision 1, Class 1, 2 and 3 Figures, Fourth Ten-Year Inservice Inspection Plan. ML0704300962005-08-31031 August 2005 E. I. Hatch, Unit 1, Version 1.0, Pressure Test Section Fourth Ten-Year Examination Plan. NL-05-1190, Fourth 10-Year Interval Inservice Testing (Ist)Program Updates Submittal for Edwin I. Hatch Nuclear Plant2005-07-11011 July 2005 Fourth 10-Year Interval Inservice Testing (Ist)Program Updates Submittal for Edwin I. Hatch Nuclear Plant ML0516403852005-06-0707 June 2005 Third 10-Year Interval Inservice Inspection Program Owner'S Activity Report NL-04-0813, Third 10-Year Interval Inservice Inspection Program Owner'S Activity Report2004-06-0707 June 2004 Third 10-Year Interval Inservice Inspection Program Owner'S Activity Report NL-04-0478, Third 10-Year Interval Inservice Inspection Program Submittal of Relief Requests (RR) RR-38, RR-39, and RR-402004-03-29029 March 2004 Third 10-Year Interval Inservice Inspection Program Submittal of Relief Requests (RR) RR-38, RR-39, and RR-40 NL-03-1380, Third 10-Year Interval Inservice Testing Program, Submittal of Relief Requests RR-V-182003-07-11011 July 2003 Third 10-Year Interval Inservice Testing Program, Submittal of Relief Requests RR-V-18 ML0230903562002-11-0101 November 2002 Third 10-Year Interval Inservice Inspection (ISI) Program, Revision of Relief Request RR-11 ML0228200262002-10-0404 October 2002 Third 10-Year Interval Inservice Inspection Program, Response to Request for Additional Information (RAI) ML0226604362002-09-17017 September 2002 Third 10-Year Interval Inservice Inspection Program Owner'S Activity Report 2024-07-09 Category:Letter type:NL MONTHYEARNL-23-0930, Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-09-11011 September 2024
[Table view]Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program NL-24-0337, Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program2024-09-0909 September 2024 Interim 10 CFR 21.21(a)(2) Report Regarding Operation Technology, Inc., ETAP Software Error in Transient Stability Program NL-24-0334, 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc2024-09-0303 September 2024 0 to the Updated Final Safety Analysis Report, Technical Specifications Bases Changes, Technical Requirements Manual Changes, License Renewal 10 CFR 54 .37(b) Changes, 10 CFR 50.59 Summary Report & Revised Nrc NL-24-0313, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information2024-08-23023 August 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint Response to Request for Additional Information NL-24-0290, Response to Request for Additional Information Related to Request for Specific Exemption2024-07-26026 July 2024 Response to Request for Additional Information Related to Request for Specific Exemption NL-24-0276, Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-07-26026 July 2024 Post-Audit Supplement to License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0261, 10 CFR 50.46 ECCS Evaluation Model Annual Report for 20232024-07-19019 July 2024 10 CFR 50.46 ECCS Evaluation Model Annual Report for 2023 NL-24-0260, Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R312024-07-0909 July 2024 Inservice Inspection Program Owner’S Activity Report (OAR-1) for Refueling Outage 1R31 NL-24-0240, Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link2024-07-0303 July 2024 Reactor Core Isolation Cooling (RCIC) System Inoperable Due to Mispositioned Link NL-24-0237, Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications2024-07-0303 July 2024 Incorrectly Installed Temporary Modification Results in Multiple Conditions Prohibited by Plant Technical Specifications NL-24-0143, Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in2024-06-27027 June 2024 Proposed Alternative to Use ASME Code Case N-752, Risk-Informed Categorization and Treatment for Repair/ Replacement Activities in NL-24-0239, Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-1392024-06-17017 June 2024 Response to Apparent Violation in NRC Inspection Report 05000321, 366/2024090: EA-23-139 NL-24-0148, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-06-0404 June 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0202, SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations2024-05-24024 May 2024 SNC Response to Regulatory Issue Summary 2024-01: Preparation and Scheduling of Operator Licensing Examinations NL-24-0191, Annual Radiological Environmental Operating Reports for 20232024-05-10010 May 2024 Annual Radiological Environmental Operating Reports for 2023 NL-24-0166, Manual Reactor Trip Due to Loss of Feedwater2024-05-0909 May 2024 Manual Reactor Trip Due to Loss of Feedwater NL-24-0195, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water.2024-05-0707 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water. NL-24-0064, Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.52024-05-0303 May 2024 Units 1 & 2 and Hatch Nuclear Plant - Units 1 & 2 License Amendment Request to Revise Technical Specification 1.1 and Add Online Monitoring Program to Technical Specification 5.5 NL-24-0165, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20232024-04-25025 April 2024 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2023 NL-24-0157, Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications2024-04-24024 April 2024 Incorrectly Installed Temporary Modification Results in a Condition Prohibited by Plant Technical Specifications NL-24-0026, Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint2024-04-19019 April 2024 Application to Revise Technical Specifications Surveillance Requirements to Increase Safety/Relief Valves Setpoint NL-24-0144, Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La)2024-04-0909 April 2024 Primary Containment Penetration Exceeded Maximum Allowable Primary Containment Leakage Rate (La) NL-24-0115, Response to Request for Additional Information Exemption Requests for Physical.2024-04-0404 April 2024 Response to Request for Additional Information Exemption Requests for Physical. NL-24-0116, Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred.2024-03-29029 March 2024 Nuclear Property Insurance Coverage as of April 1, 2024 and Licensee Guarantees of Payment of Deferred. NL-24-0062, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2024-03-12012 March 2024 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-24-0089, Correction of Technical Specification Omission2024-03-0909 March 2024 Correction of Technical Specification Omission NL-24-0061, Cycle 32 Core Operating Limits Report Version 12024-03-0101 March 2024 Cycle 32 Core Operating Limits Report Version 1 NL-24-0067, 10 CFR 72.48(d)(2) Biennial Report2024-02-26026 February 2024 10 CFR 72.48(d)(2) Biennial Report NL-24-0051, License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components2024-02-20020 February 2024 License Amendment Request to Revise Renewed Facility Operating Licenses to Adopt an Alternative Seismic Method for Categorization of Structures, Systems, and Components NL-24-0042, Response to Request for Additional Information Exemption Requests for Physical Barriers2024-02-13013 February 2024 Response to Request for Additional Information Exemption Requests for Physical Barriers NL-24-0033, Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers2024-02-0505 February 2024 Response to Question for Withholding Information from Public Disclosure Exemption Requests for Physical Barriers NL-24-0014, Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical.2024-01-30030 January 2024 Revised Response to Request for Additional Information Regarding License Amendment Request to Relax the Required Number of Fully Tensioned Reactor Pressure Vessel Head Closure Studs in Technical. NL-23-0889, Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems2023-12-0606 December 2023 Units 1 and 2 - License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times for Residual Heat Removal Service Water (RHRSW) and Plant Service Water (Psw) Systems NL-23-0879, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation NL-23-0841, Update to Notice of Intent to Pursue Subsequent License Renewal2023-11-20020 November 2023 Update to Notice of Intent to Pursue Subsequent License Renewal NL-23-0658, Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal2023-08-11011 August 2023 Southern Nuclear Operating Company - Response to Request for Additional Information Regarding Quality Assurance Topical Report Submittal NL-23-0542, CFR 50.46 ECCS Evaluation Model Annual Report for 20222023-08-0909 August 2023 CFR 50.46 ECCS Evaluation Model Annual Report for 2022 NL-23-0624, Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis2023-08-0404 August 2023 Report of Changes to Emergency Plan and Summary of 50.54(q) Analysis NL-23-0566, ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use2023-07-13013 July 2023 ISFSI and Edwin I. Hatch Nuclear Plant ISFSI - Registration of Spent Fuel Cask Use NL-23-0555, Request for Exemption from Physical Barrier Requirement2023-07-0707 July 2023 Request for Exemption from Physical Barrier Requirement NL-23-0444, Quality Assurance Topical Report Submittal2023-06-15015 June 2023 Quality Assurance Topical Report Submittal NL-23-0457, ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use2023-06-12012 June 2023 ISFSI, and Edwin I. Hatch Nuclear Plant, ISFSI - Registration of Spent Fuel Cask Use NL-23-0422, Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R272023-05-30030 May 2023 Inservice Inspection Program Owner'S Activity Report for Refueling Outage 2R27 NL-23-0383, SNC Response to Regulatory Issue Summary 2023-01:Preparation And.2023-05-19019 May 2023 SNC Response to Regulatory Issue Summary 2023-01:Preparation And. NL-23-0372, Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 20222023-05-10010 May 2023 Units 1 & 2, Joseph M. Farley Nuclear Plant - Units 1 & 2, Vogtle Electric Generating Plant - Units 1 & 2, Annual Radiological Environmental Operating Reports for 2022 NL-23-0310, Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 20222023-04-25025 April 2023 Annual Non-Radiological Environmental Operating Reports and Annual Radioactive Effluent Release Reports for 2022 NL-23-0019, GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2023-04-12012 April 2023 GEN-ISI-ALT-2023-01, Request to Use Provision of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI NL-23-0263, Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report2023-04-0505 April 2023 Southern Nuclear Company Submittal of Drug and Alcohol Testing Errors Identified 10 CFR 26.719(c) 30-Day Report NL-23-0014, Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding2023-03-29029 March 2023 Southern Nuclear Operating Co Submittal of Report on Status of Decommissioning Funding NL-23-0208, Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update2023-03-29029 March 2023 Independent Spent Fuel Storage Installation ISFSI, Decommissioning Funding Plan Triennial Update 2024-09-09 |
Text
Charles R. Pierce Southern Nuclear Regulatory Affairs Director Operating Company, Inc.
40 Inverness Center Parkway Post Office Box 1295 Birmmgham, AL 35201 Tel 205.992.7872 s UTHERN << \
COMPANY Fax 205.992.7601 June 18,2015 Docket Nos.: 50-321 NL-15-1096 50-366 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant - Units 1 & 2 Follow-up Letter Regarding Submittal of the lnservice Testing Program Relief Requests and Alternatives for Pumps and Valves- Fifth Ten-Year Interval Ladies and Gentlemen:
By letter dated May 4, 2015, Southern Nuclear Operating Company (SNC) requested Nuclear Regulatory Commission (NRC) approval of various relief requests and alternatives for Edwin I. Hatch Nuclear Plant (HNP) Units 1 and 2 (SNC letter NL-15-0784}. These relief requests and alternatives are applicable to the Fifth Ten-Year lntervallnservice Testing Program which will start on January 1, 2016.
Upon further consideration, SNC no longer requests NRC approval of RR-V-3. In addition, SNC would like to request that NRC approval of RR-P-3 be granted pursuant to 10 CFR 50.55a(z)(1) instead of 10 CFR 50.55a(z)(2). Lastly, SNC requests NRC approval of RR-V-10 pursuant to 10 CFR 50.55a(z)(1}.
This letter contains no NRC commitments. If you have any questions, please contact Ken McElroy at (205) 992-7369.
Respectfully submitted, C,1{ ~
C. R. Pierce Regulatory Affairs Director CRP/RMJ
U.S. Nuclear Regulatory Commission NL-15-1096 Page2 cc: Southern Nuclear Operating Company Mr. S. E. Kuczynski, Chairman, President & CEO Mr. D. G. Best, Executive Vice President & Chief Nuclear Officer Mr. D. R. Vineyard, Vice President- Hatch Mr. M. D. Meier, Vice President- Regulatory Affairs Mr. D. R. Madison, Vice President- Fleet Operations Mr. B. J. Adams, Vice President- Engineering Mr. G. L. Johnson, Regulatory Affairs Manager- Hatch RTYPE: CHA02.004 U.S. Nuclear Regulatory Commission Mr. V. M. McCree, Regional Administrator Mr. R. E. Martin, NRR Senior Project Manager- Hatch Mr. D. H. Hardage, Senior Resident Inspector- Hatch