- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance...
|
MONTHYEARND-21-0973, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of Item 2.3.06.05a.i (Index Number 361)2021-10-29029 October 2021 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of Item 2.3.06.05a.i (Index Number 361) Project stage: Request ML21342A2922021-11-0202 November 2021, 9 December 2021 Update to Targeted Inspections, Tests, Analyses, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 3 and 4 Project stage: Request ND-21-0982, ITAAC Closure Notification on Completion of Item 2.3.13.05.1 (Index Number 462)2021-11-0303 November 2021 ITAAC Closure Notification on Completion of Item 2.3.13.05.1 (Index Number 462) Project stage: Request ND-21-0992, ITAAC Closure Notification on Completion of Item 3.3.00.10.i (Index Number 815)2021-11-0404 November 2021 ITAAC Closure Notification on Completion of Item 3.3.00.10.i (Index Number 815) Project stage: Request ND-21-0377, ITAAC Closure Notification on Completion of ITAAC Item 2.2.01.11a.iii (Index Number 116)2021-11-0505 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.2.01.11a.iii (Index Number 116) Project stage: Request ND-20-0801, ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759)2021-11-0808 November 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759) Project stage: Request ND-21-0995, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2021-11-10010 November 2021 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) Project stage: Request ND-21-0167, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.10.ii (Index Number 816)2021-11-11011 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.10.ii (Index Number 816) Project stage: Request ND-21-0038, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763)2021-11-12012 November 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763) Project stage: Request ND-21-0713, ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 (Index Number 716)2021-11-17017 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 (Index Number 716) Project stage: Request ND-21-1010, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.09 (Index Number 670)2021-11-18018 November 2021 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.09 (Index Number 670) Project stage: Request ND-21-1025, Unit 4 - ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.02.i (Index Number 565)2021-11-24024 November 2021 Unit 4 - ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.02.i (Index Number 565) Project stage: Request ND-21-0757, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2021-12-0202 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) Project stage: Request ND-21-0769, ITAAC Closure Notification on Completion of ITAAC 2.2.02.02a (Index Number 120)2021-12-0707 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.02.02a (Index Number 120) Project stage: Request ND-20-1378, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761)2021-12-0808 December 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761) Project stage: Request ND-21-1084, ITAAC Closure Notification on Completion of ITAAC 2.3.03.03c (Index Number 322)2021-12-0909 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.3.03.03c (Index Number 322) Project stage: Request ND-21-1036, ITAAC Closure Notification on Completion of ITAAC Item 2.2.03.12a.i (Index Number 214)2021-12-0909 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.2.03.12a.i (Index Number 214) Project stage: Request ND-21-0779, ITAAC Closure Notification on Completion of ITAAC 2.3.13.02 (Index Number 459)2021-12-15015 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.3.13.02 (Index Number 459) Project stage: Request ND-21-1030, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56)2021-12-15015 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56) Project stage: Request ND-21-1022, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.1 (Index Number 291)2021-12-16016 December 2021 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.1 (Index Number 291) Project stage: Request ND-21-0993, ITAAC Closure Notification on Completion of ITAAC Item 2.1.02.15 (Index Number 67)2021-12-16016 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.1.02.15 (Index Number 67) Project stage: Request ND-21-0270, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05a (Index Number 644)2021-12-17017 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05a (Index Number 644) Project stage: Request ND-21-0802, ITAAC Closure Notification on Completion of ITAAC 2.2.01.02a (Index Number 91)2021-12-21021 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.01.02a (Index Number 91) Project stage: Request ND-21-1095, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.1.03.06.1 (Index Number 75)2021-12-21021 December 2021 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.1.03.06.1 (Index Number 75) Project stage: Request ND-21-0956, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2021-12-21021 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) Project stage: Request ND-21-0990, ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.04 (Index Number 572)2021-12-27027 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.04 (Index Number 572) Project stage: Request ND-21-0744, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2022-01-21021 January 2022 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) Project stage: Request ND-20-0582, ITAAC Closure Notification on Completion of ITAAC 2.3.29.04 (Index Number 491)2022-01-21021 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.29.04 (Index Number 491) Project stage: Request ND-22-0049, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13c (Index Number 654)2022-01-21021 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13c (Index Number 654) Project stage: Request ND-22-0052, ITAAC Closure Notification on Completion of ITAAC 2.6.09.15a (Index Number 655)2022-01-27027 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.15a (Index Number 655) Project stage: Request ND-22-0080, ITAAC Closure Notification on Completion of ITAAC 2.3.09.02b (Index Number 422)2022-02-0404 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.09.02b (Index Number 422) Project stage: Request ND-21-1026, ITAAC Closure Notification on Completion of ITAAC 2.6.01.02.i (Index Number 579)2022-02-14014 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.01.02.i (Index Number 579) Project stage: Request ND-22-0051, (Taac Closure Notification on Completion of ITAAC 2.6.09.13a Index Number 652)2022-02-16016 February 2022 (Taac Closure Notification on Completion of ITAAC 2.6.09.13a Index Number 652) Project stage: Request ND-21-0796, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) Project stage: Request ND-22-0070, ITAAC Closure Notification on Completion of ITAAC 3.3.00.16 (Index Number 821)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.16 (Index Number 821) Project stage: Request ND-22-0103, ITAAC Closure Notification on Completion of ITAAC 2.6.09.08 (Index Number 6501)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.08 (Index Number 6501) Project stage: Request ND-22-1157, ITAAC Closure Notification on Completion of 2.7.02.03a (Index Number 703)2022-02-17017 February 2022 ITAAC Closure Notification on Completion of 2.7.02.03a (Index Number 703) Project stage: Request ND-22-0104, ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647)2022-02-18018 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647) Project stage: Request ND-21-0271, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2022-02-18018 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) Project stage: Request ND-21-0654, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) Project stage: Request ND-22-0131, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02a (Index Number 593)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02a (Index Number 593) Project stage: Request ND-21-0795, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) Project stage: Request ND-21-0092, ITAAC Closure Notification on Completion of ITAAC 2.3.11.03b (Index Number 454)2022-02-22022 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.11.03b (Index Number 454) Project stage: Request ND-21-0723, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2022-02-22022 February 2022 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) Project stage: Request ND-22-0046, ITAAC Closure Notification on Completion of ITAAC 2.3.10.11a (Index Number 878)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.10.11a (Index Number 878) Project stage: Request ND-22-0092, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761) Project stage: Request ND-22-0085, ITAAC Closure Notification on Completion of ITAAC 2.3.07.06a (Index Number 399)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.07.06a (Index Number 399) Project stage: Request ND-20-0880, ITAAC Closure Notification on Completion of ITAAC 2.3.11.03c (Index Number 455)2022-02-24024 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.11.03c (Index Number 455) Project stage: Request ND-22-0088, ITAAC Closure Notification on Completion of ITAAC 2.6.01.03a (Index Number 582)2022-02-24024 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.01.03a (Index Number 582) Project stage: Request ND-22-0148, ITAAC Closure Notification on Completion of ITAAC 2.6.03.07 (Index Number 616)2022-02-25025 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.03.07 (Index Number 616) Project stage: Request 2021-12-21
[Table View] |
Text
.A Southern Nuclear Docket No.:
52-025 APR 1 8 2022 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 7825 River Road Waynesboro, GA 30830 706-848-6926 tel ND-22-0139 10 CFR 52.99(c)(1)
ITAAC Closure Notification on Completion of ITAAC 3.3.00.05b (Index Number 785]
Ladies and Gentlemen:
In accordance with 1 O CFR 52.99(c)(1 ), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP)
Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 3.3.00.05b [Index Number 785]. An inspection of the boundaries between the rooms identified in VEGP Unit 3 Combined License (COL) Appendix C Table 3.3-2 was performed to demonstrate that the boundaries between these rooms were designed and constructed to prevent flooding of rooms that contain safety-related equipment. The closure process for this ITAAC is based on the guidance described in NEl-08-01, "Industry Guideline for the ITAAC Closure Process under 1 O CFR Part 52", which is endorsed by the NRC in Regulatory Guide 1.215.
This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 1 O CFR 52.99.
If there are any questions, please contact Kelli A. Roberts at 706-848-6991.
Respectfully submitted, Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4
Enclosure:
JMC/JRV/sfr Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 3.3.00.05b [Index Number 785]
U.S. Nuclear Regulatory Commission ND-22-0139 Page 2 of 3 To:
Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena Ill Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. J.B. Williams Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beilke Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:
Nuclear Regulatory Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. 0. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Mr. T. Fanelli Ms. K. Mccurry Mr. J. Parent Mr. B. Griman Mr. V. Hall
U.S. Nuclear Regulatory Commission ND-22-0139 Page 3 of 3 Oglethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Dr. L. Oriani Mr. D. C. Durham Mr. M. M. Corletti Mr. Z. S. Harper Ms. S.L. Zwack Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GOS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham
U.S. Nuclear Regulatory Commission ND-22-0139 Enclosure Page 1 of 4 Southern Nuclear Operating Company ND-22-0139 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 3.3.00.05b [Index Number 785]
U.S. Nuclear Regulatory Commission ND-22-0139 Enclosure Page 2 of 4 ITAAC Statement Design Commitment:
5.b) The boundaries between rooms identified in Table 3.3-2 of the auxiliary building are designed to prevent flooding of rooms that contain safety-related equipment.
Inspections, Tests, Analyses:
An inspection of the auxiliary building rooms will be performed.
Acceptance Criteria:
A report exists that confirms floors and walls as identified on Table 3.3-2 have provisions to prevent flooding between rooms up to the maximum flood levels for each room defined in Table 3.3-2.
ITAAC Determination Basis An inspection of the boundaries between the rooms identified in Vogtle Electric Generating Plant (VEGP) Unit 3 Combined License (COL) Appendix C Table 3.3-2 (Attachment A), was performed to demonstrate that the boundaries between these rooms were designed and constructed to prevent flooding of rooms that contain safety-related equipment.
Inspections were performed of auxiliary building rooms to demonstrate that floors and walls as identified in Table 3.3-2 have provisions to prevent flooding between rooms up to the maximum flood levels for each room defined in COL Appendix C Table 3.3-2 (Attachment A). An inspection plan was prepared to identify all openings and penetrations on the floors and walls up to the maximum flood levels of the rooms. Each as-built opening or penetration observed and measured to be below the corresponding maximum flood level was inspected to ensure that the openings and penetrations were sealed as specified in the design documents. A final walkdown of the floors and walls was performed to ensure that all openings and penetrations were identified and inspected.
The inspection plan and results of the visual inspection of the floors and walls are documented in the Unit 3 Principal Closure Document (PCD) (Reference 1 ), and confirms floors and walls as identified on COL Appendix C Table 3.3-2 have provisions to prevent flooding between rooms up to the maximum flood levels for each room defined in COL Appendix C Table 3.3-2 (Attachment A).
Reference 1 is available for NRC inspection as part of the Unit 3 ITAAC 3.3.00.0Sb Completion Package (Reference 2).
ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This review found that there are no relevant IT AAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 3.3.00.0Sb (Reference 2) and is available for NRC review.
U.S. Nuclear Regulatory Commission ND-22-0139 Enclosure Page 3 of 4 IT AAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 3.3.00.05b was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met.
Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
References (available for NRC inspection)
- 1. SV3-1000-ITR-800785, Rev. 1, "Unit 3 Inspections of Aux Bldg. Safety-Related Equipment Rooms Flood Prevention: ITAAC 3.3.00.05b, NRC Index Number: 785"
- 2. 3.3.00.05b-U3-CP-Rev0, ITAAC Completion Package
- 3. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 1 0 CFR Part 52"
U.S. Nuclear Regulatory Commission ND-22-0139 Enclosure Page 4 of 4 Attachment A COL Appendix C Table 3.3-2 Table 3.3-2 Nuclear Island Building Room Boundaries Required to Have Flood Barrier Aoors and Walls Between Room Number to Room Number Boundary/
Room with Postulated Maximum Flood Level (Inches)
Flooding Source Adjacent Room Floor/36 12306 12211 Floor/3 12303 12203/12207 Floor/3 12313 12203/12207 Floor/1 12300 12201/12202/12207 12203/12204/12205 Floor/3 12312 12212 Wa1V36 12306 12305 Floor/1 12401 12301 /12302/12303 12312/12313 Wa1V1 12401 12411/12412 Floor/36 12404 12304 Ftoor/4 12405 12305 Floor/36 12406 12306 Wall/36 12404 12401 Wall/30 12452 12421 Ftoor/3 12501 12401/12411/12412 Aoor/3 12555 12421/12423/12422 Wall/168 12156 12111/12112 Wa1V76.5 12158 12111 Wa1V132 12258 12211/12212