- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance...
|
MONTHYEARND-21-0973, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of Item 2.3.06.05a.i (Index Number 361)2021-10-29029 October 2021 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of Item 2.3.06.05a.i (Index Number 361) Project stage: Request ML21342A2922021-11-0202 November 2021, 9 December 2021 Update to Targeted Inspections, Tests, Analyses, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 3 and 4 Project stage: Request ND-21-0982, ITAAC Closure Notification on Completion of Item 2.3.13.05.1 (Index Number 462)2021-11-0303 November 2021 ITAAC Closure Notification on Completion of Item 2.3.13.05.1 (Index Number 462) Project stage: Request ND-21-0992, ITAAC Closure Notification on Completion of Item 3.3.00.10.i (Index Number 815)2021-11-0404 November 2021 ITAAC Closure Notification on Completion of Item 3.3.00.10.i (Index Number 815) Project stage: Request ND-21-0377, ITAAC Closure Notification on Completion of ITAAC Item 2.2.01.11a.iii (Index Number 116)2021-11-0505 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.2.01.11a.iii (Index Number 116) Project stage: Request ND-20-0801, ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759)2021-11-0808 November 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759) Project stage: Request ND-21-0995, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2021-11-10010 November 2021 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) Project stage: Request ND-21-0167, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.10.ii (Index Number 816)2021-11-11011 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.10.ii (Index Number 816) Project stage: Request ND-21-0038, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763)2021-11-12012 November 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763) Project stage: Request ND-21-0713, ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 (Index Number 716)2021-11-17017 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 (Index Number 716) Project stage: Request ND-21-1010, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.09 (Index Number 670)2021-11-18018 November 2021 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.09 (Index Number 670) Project stage: Request ND-21-1025, Unit 4 - ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.02.i (Index Number 565)2021-11-24024 November 2021 Unit 4 - ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.02.i (Index Number 565) Project stage: Request ND-21-0757, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2021-12-0202 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) Project stage: Request ND-21-0769, ITAAC Closure Notification on Completion of ITAAC 2.2.02.02a (Index Number 120)2021-12-0707 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.02.02a (Index Number 120) Project stage: Request ND-20-1378, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761)2021-12-0808 December 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761) Project stage: Request ND-21-1084, ITAAC Closure Notification on Completion of ITAAC 2.3.03.03c (Index Number 322)2021-12-0909 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.3.03.03c (Index Number 322) Project stage: Request ND-21-1036, ITAAC Closure Notification on Completion of ITAAC Item 2.2.03.12a.i (Index Number 214)2021-12-0909 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.2.03.12a.i (Index Number 214) Project stage: Request ND-21-0779, ITAAC Closure Notification on Completion of ITAAC 2.3.13.02 (Index Number 459)2021-12-15015 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.3.13.02 (Index Number 459) Project stage: Request ND-21-1030, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56)2021-12-15015 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56) Project stage: Request ND-21-1022, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.1 (Index Number 291)2021-12-16016 December 2021 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.1 (Index Number 291) Project stage: Request ND-21-0993, ITAAC Closure Notification on Completion of ITAAC Item 2.1.02.15 (Index Number 67)2021-12-16016 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.1.02.15 (Index Number 67) Project stage: Request ND-21-0270, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05a (Index Number 644)2021-12-17017 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05a (Index Number 644) Project stage: Request ND-21-0802, ITAAC Closure Notification on Completion of ITAAC 2.2.01.02a (Index Number 91)2021-12-21021 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.01.02a (Index Number 91) Project stage: Request ND-21-1095, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.1.03.06.1 (Index Number 75)2021-12-21021 December 2021 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.1.03.06.1 (Index Number 75) Project stage: Request ND-21-0956, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2021-12-21021 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) Project stage: Request ND-21-0990, ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.04 (Index Number 572)2021-12-27027 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.04 (Index Number 572) Project stage: Request ND-21-0744, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2022-01-21021 January 2022 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) Project stage: Request ND-20-0582, ITAAC Closure Notification on Completion of ITAAC 2.3.29.04 (Index Number 491)2022-01-21021 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.29.04 (Index Number 491) Project stage: Request ND-22-0049, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13c (Index Number 654)2022-01-21021 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13c (Index Number 654) Project stage: Request ND-22-0052, ITAAC Closure Notification on Completion of ITAAC 2.6.09.15a (Index Number 655)2022-01-27027 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.15a (Index Number 655) Project stage: Request ND-22-0080, ITAAC Closure Notification on Completion of ITAAC 2.3.09.02b (Index Number 422)2022-02-0404 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.09.02b (Index Number 422) Project stage: Request ND-21-1026, ITAAC Closure Notification on Completion of ITAAC 2.6.01.02.i (Index Number 579)2022-02-14014 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.01.02.i (Index Number 579) Project stage: Request ND-22-0051, (Taac Closure Notification on Completion of ITAAC 2.6.09.13a Index Number 652)2022-02-16016 February 2022 (Taac Closure Notification on Completion of ITAAC 2.6.09.13a Index Number 652) Project stage: Request ND-21-0796, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) Project stage: Request ND-22-0070, ITAAC Closure Notification on Completion of ITAAC 3.3.00.16 (Index Number 821)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.16 (Index Number 821) Project stage: Request ND-22-0103, ITAAC Closure Notification on Completion of ITAAC 2.6.09.08 (Index Number 6501)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.08 (Index Number 6501) Project stage: Request ND-22-1157, ITAAC Closure Notification on Completion of 2.7.02.03a (Index Number 703)2022-02-17017 February 2022 ITAAC Closure Notification on Completion of 2.7.02.03a (Index Number 703) Project stage: Request ND-22-0104, ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647)2022-02-18018 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647) Project stage: Request ND-21-0271, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2022-02-18018 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) Project stage: Request ND-21-0654, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) Project stage: Request ND-22-0131, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02a (Index Number 593)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02a (Index Number 593) Project stage: Request ND-21-0795, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) Project stage: Request ND-21-0092, ITAAC Closure Notification on Completion of ITAAC 2.3.11.03b (Index Number 454)2022-02-22022 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.11.03b (Index Number 454) Project stage: Request ND-21-0723, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2022-02-22022 February 2022 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) Project stage: Request ND-22-0046, ITAAC Closure Notification on Completion of ITAAC 2.3.10.11a (Index Number 878)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.10.11a (Index Number 878) Project stage: Request ND-22-0092, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761) Project stage: Request ND-22-0085, ITAAC Closure Notification on Completion of ITAAC 2.3.07.06a (Index Number 399)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.07.06a (Index Number 399) Project stage: Request ND-20-0880, ITAAC Closure Notification on Completion of ITAAC 2.3.11.03c (Index Number 455)2022-02-24024 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.11.03c (Index Number 455) Project stage: Request ND-22-0088, ITAAC Closure Notification on Completion of ITAAC 2.6.01.03a (Index Number 582)2022-02-24024 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.01.03a (Index Number 582) Project stage: Request ND-22-0148, ITAAC Closure Notification on Completion of ITAAC 2.6.03.07 (Index Number 616)2022-02-25025 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.03.07 (Index Number 616) Project stage: Request 2021-12-21
[Table View] |
Text
^
1 I K I I
Michael J. Yox 7825 River Road iSk Southern Nuclear Regulatory Affairs Director Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel ND-22-0070 10 CFR 52.99(c)(1)
FEB 1 6 2022 Docket No.:
52-025 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC 3.3.00.16 [Index Number 8211 Ladies and Gentlemen:
In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 3.3.00.16 [Index Number 821].
This ITAAC confirms that secondary security power supply equipment for alarm annunciator equipment and non-portable communication equipment is located within a vital area. The closure process for this ITAAC is based on the guidance described in Nuclear Energy Institute (NEI) 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.
This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.
If there are any questions, please contact Kelli Roberts at 706-848-6991.
Respectfully submitted, Michael J. Yo>
Regulatory Affairs Dj/ector Vogtle 3 & 4
Enclosure:
Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 3.3.00.16 [Index Number 821]
MJY/RLB/sfr
U.S. Nuclear Regulatory Commission ND-22-0070 Page 2 of 3 To:
Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. J. B. Williams Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beiike Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc; Nuclear Reoulatorv Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. O. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Mr. T. Fanelli Ms. K. McCurry Mr. J. Parent Mr. B. Griman Mr. V. Hall
U.S. Nuclear Regulatory Commission ND-22-0070 Page 3 of 3 Oqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Daiton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Oriani Mr. D. C. Durham Mr. M. M. Corletti Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. 8. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, inc.
Mr. 8. Roetger, Georgia Pubiic Service Commission Mr. R. L. Trokey, Georgia Pubiic Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham
U.S. Nuclear Regulatory Commission ND-22-0070 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-22-0070 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 3.3.00.16 [Index Number 821]
U.S. Nuclear Regulatory Commission ND-22-0070 Enclosure Page 2 of 3 ITAAC Statement Desion Commitment
- 16. Secondary security power supply system for alarm annunciator equipment and non-portable communications equipment is located within a vital area.
Inspections/Tests/Analvses An inspection will be performed to ensure that the location of the secondary security power supply equipment for alarm annunciator equipment and non-portable communications equipment is within a vital area.
Acceptance Criteria Secondary security power supply equipment for alarm annunciator equipment and non-portable communication equipment is located within a vital area.
ITAAC Determination Basis An inspection of the secondary security power supply system for alarm annunciator equipment and non-portable communications equipment was performed to confirm the Vogtle Electric Generating Plant (VEGP) Unit 3 secondary security power supply equipment for alarm annunciator equipment and non-portable communication equipment is located within a vital area and satisfies the applicable secondary security power supply system location requirements of the VEGP Unit 3 and Unit 4 Physical Security Plan associated with 10 CFR 73.55(e)(9)(vi). The VEGP Unit 3 Plant Security System ITAACs only cover the Unit 3 plant security system design commitment scope.
The secondary security power supply equipment for alarm annunciator equipment and non portable communications equipment is installed in accordance with approved installation specifications and drawings issued for construction. An inspection was performed to verify that the secondary security power supply system for alarm annunciator equipment and non-portable communications equipment is located within a vital area. The inspection was performed as described in ITAAC Technical Report SV3-SES-ITR-800821 (Reference 1) and documented performance of visual observations to compare the installed secondary security power supply equipment locations to the approved drawings. The results of the inspection are documented in Reference 1.
Reference 1 exists, and concludes that inspections confirm that the secondary security power supply system for alarm annunciator equipment and non-portable communication equipment is located within a vital area.
Reference 1 is available for NRG inspection as part of the Unit 3 ITAAC 3.3.00.16 Completion Package (Reference 2).
ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there were no relevant ITAAC findings
U.S. Nuclear Regulatory Commission ND-22-0070 Enclosure Page 3 of 3 associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 3.3.00.16 (Reference 2) and is available for NRC review.
ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 3.3.00.16 was performed for VEGP Unit 3 and that the prescribed acceptance criteria was met.
Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
References (available for NRC inspection)
- 1. SV3-SES-ITR-800821, Walkdown Inspection for Secondary Security Power Supply Locations: ITAAC 3.3.00.16, Rev 0 (SRI)
- 2. 3.3.00.16-U3-CP-RevO, ITAAC Completion Package