- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance...
|
MONTHYEARND-21-0973, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of Item 2.3.06.05a.i (Index Number 361)2021-10-29029 October 2021 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of Item 2.3.06.05a.i (Index Number 361) Project stage: Request ML21342A2922021-11-0202 November 2021, 9 December 2021 Update to Targeted Inspections, Tests, Analyses, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 3 and 4 Project stage: Request ND-21-0982, ITAAC Closure Notification on Completion of Item 2.3.13.05.1 (Index Number 462)2021-11-0303 November 2021 ITAAC Closure Notification on Completion of Item 2.3.13.05.1 (Index Number 462) Project stage: Request ND-21-0992, ITAAC Closure Notification on Completion of Item 3.3.00.10.i (Index Number 815)2021-11-0404 November 2021 ITAAC Closure Notification on Completion of Item 3.3.00.10.i (Index Number 815) Project stage: Request ND-21-0377, ITAAC Closure Notification on Completion of ITAAC Item 2.2.01.11a.iii (Index Number 116)2021-11-0505 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.2.01.11a.iii (Index Number 116) Project stage: Request ND-20-0801, ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759)2021-11-0808 November 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759) Project stage: Request ND-21-0995, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2021-11-10010 November 2021 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) Project stage: Request ND-21-0167, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.10.ii (Index Number 816)2021-11-11011 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.10.ii (Index Number 816) Project stage: Request ND-21-0038, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763)2021-11-12012 November 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763) Project stage: Request ND-21-0713, ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 (Index Number 716)2021-11-17017 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 (Index Number 716) Project stage: Request ND-21-1010, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.09 (Index Number 670)2021-11-18018 November 2021 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.09 (Index Number 670) Project stage: Request ND-21-1025, Unit 4 - ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.02.i (Index Number 565)2021-11-24024 November 2021 Unit 4 - ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.02.i (Index Number 565) Project stage: Request ND-21-0757, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2021-12-0202 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) Project stage: Request ND-21-0769, ITAAC Closure Notification on Completion of ITAAC 2.2.02.02a (Index Number 120)2021-12-0707 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.02.02a (Index Number 120) Project stage: Request ND-20-1378, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761)2021-12-0808 December 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761) Project stage: Request ND-21-1084, ITAAC Closure Notification on Completion of ITAAC 2.3.03.03c (Index Number 322)2021-12-0909 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.3.03.03c (Index Number 322) Project stage: Request ND-21-1036, ITAAC Closure Notification on Completion of ITAAC Item 2.2.03.12a.i (Index Number 214)2021-12-0909 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.2.03.12a.i (Index Number 214) Project stage: Request ND-21-0779, ITAAC Closure Notification on Completion of ITAAC 2.3.13.02 (Index Number 459)2021-12-15015 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.3.13.02 (Index Number 459) Project stage: Request ND-21-1030, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56)2021-12-15015 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56) Project stage: Request ND-21-1022, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.1 (Index Number 291)2021-12-16016 December 2021 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.1 (Index Number 291) Project stage: Request ND-21-0993, ITAAC Closure Notification on Completion of ITAAC Item 2.1.02.15 (Index Number 67)2021-12-16016 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.1.02.15 (Index Number 67) Project stage: Request ND-21-0270, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05a (Index Number 644)2021-12-17017 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05a (Index Number 644) Project stage: Request ND-21-0802, ITAAC Closure Notification on Completion of ITAAC 2.2.01.02a (Index Number 91)2021-12-21021 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.01.02a (Index Number 91) Project stage: Request ND-21-1095, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.1.03.06.1 (Index Number 75)2021-12-21021 December 2021 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.1.03.06.1 (Index Number 75) Project stage: Request ND-21-0956, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2021-12-21021 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) Project stage: Request ND-21-0990, ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.04 (Index Number 572)2021-12-27027 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.04 (Index Number 572) Project stage: Request ND-21-0744, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2022-01-21021 January 2022 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) Project stage: Request ND-20-0582, ITAAC Closure Notification on Completion of ITAAC 2.3.29.04 (Index Number 491)2022-01-21021 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.29.04 (Index Number 491) Project stage: Request ND-22-0049, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13c (Index Number 654)2022-01-21021 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13c (Index Number 654) Project stage: Request ND-22-0052, ITAAC Closure Notification on Completion of ITAAC 2.6.09.15a (Index Number 655)2022-01-27027 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.15a (Index Number 655) Project stage: Request ND-22-0080, ITAAC Closure Notification on Completion of ITAAC 2.3.09.02b (Index Number 422)2022-02-0404 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.09.02b (Index Number 422) Project stage: Request ND-21-1026, ITAAC Closure Notification on Completion of ITAAC 2.6.01.02.i (Index Number 579)2022-02-14014 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.01.02.i (Index Number 579) Project stage: Request ND-22-0051, (Taac Closure Notification on Completion of ITAAC 2.6.09.13a Index Number 652)2022-02-16016 February 2022 (Taac Closure Notification on Completion of ITAAC 2.6.09.13a Index Number 652) Project stage: Request ND-21-0796, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) Project stage: Request ND-22-0070, ITAAC Closure Notification on Completion of ITAAC 3.3.00.16 (Index Number 821)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.16 (Index Number 821) Project stage: Request ND-22-0103, ITAAC Closure Notification on Completion of ITAAC 2.6.09.08 (Index Number 6501)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.08 (Index Number 6501) Project stage: Request ND-22-1157, ITAAC Closure Notification on Completion of 2.7.02.03a (Index Number 703)2022-02-17017 February 2022 ITAAC Closure Notification on Completion of 2.7.02.03a (Index Number 703) Project stage: Request ND-22-0104, ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647)2022-02-18018 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647) Project stage: Request ND-21-0271, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2022-02-18018 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) Project stage: Request ND-21-0654, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) Project stage: Request ND-22-0131, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02a (Index Number 593)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02a (Index Number 593) Project stage: Request ND-21-0795, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) Project stage: Request ND-21-0092, ITAAC Closure Notification on Completion of ITAAC 2.3.11.03b (Index Number 454)2022-02-22022 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.11.03b (Index Number 454) Project stage: Request ND-21-0723, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2022-02-22022 February 2022 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) Project stage: Request ND-22-0046, ITAAC Closure Notification on Completion of ITAAC 2.3.10.11a (Index Number 878)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.10.11a (Index Number 878) Project stage: Request ND-22-0092, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761) Project stage: Request ND-22-0085, ITAAC Closure Notification on Completion of ITAAC 2.3.07.06a (Index Number 399)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.07.06a (Index Number 399) Project stage: Request ND-20-0880, ITAAC Closure Notification on Completion of ITAAC 2.3.11.03c (Index Number 455)2022-02-24024 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.11.03c (Index Number 455) Project stage: Request ND-22-0088, ITAAC Closure Notification on Completion of ITAAC 2.6.01.03a (Index Number 582)2022-02-24024 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.01.03a (Index Number 582) Project stage: Request ND-22-0148, ITAAC Closure Notification on Completion of ITAAC 2.6.03.07 (Index Number 616)2022-02-25025 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.03.07 (Index Number 616) Project stage: Request 2021-12-21
[Table View] |
Text
A Southern Nuclear May 13, 2022 Docket No.:
52-025 Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6926 tel ND-20-0751 10 CFR 52.99(c)(1)
U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC 2.1.02.11 c.i [Index Number 511 Ladies and Gentlemen:
In accordance with 10 CFR 52.99(c)(1 ), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.1.02.11 c.i [Index Number 511 which confirms that valves identified in Combined License (COL) Appendix C Table 2.1.2-1 as having Diverse Actuation System (DAS) control perform an active safety function after receiving a signal from DAS. The closure process for this ITAAC is based on the guidance described in NEI 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.
This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.
If there are any questions, please contact Kelli Roberts at 706-848-6991.
Respectfully submitted,
/ ~
~eman Regulatory Affairs Director Vogtle 3 & 4
Enclosure:
JMC/DLW/sfr Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.1.02.11 c.i [Index Number 511
U.S. Nuclear Regulatory Commission ND-20-0751 Page 2 of 3 To:
Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena Ill Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. J.B. Williams Mr. A S. Parton Ms. K. A Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beilke Mr. S. Leighty Ms. A C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 Nuclear Regulatory Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. 0. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Ms. K. Mccurry Mr. J. Parent Mr. B. Griman Mr. V. Hall
U.S. Nuclear Regulatory Commission ND-20-0751 Page 3 of 3 Oglethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Dr. L. Oriani Mr. D. C. Durham Mr. M. M. Corletti Mr. Z. S. Harper Ms. S.L. Zwack Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GOS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham
U.S. Nuclear Regulatory Commission ND-20-0751 Enclosure Page 1 of 4 Southern Nuclear Operating Company ND-20-0751 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.1.02.11c.i [Index Number 51]
U.S. Nuclear Regulatory Commission ND-20-0751 Enclosure Page 2 of 4 ITAAC Statement Design Commitment 11.c) The valves identified in Table 2.1.2-1 as having DAS control perform an active safety function after receiving a signal from DAS.
Inspections, Tests, Analyses i) Testing will be performed on the squib valves identified in Table 2.1.2-1 using real or simulated signals into the DAS without stroking the valve.
Acceptance Criteria i) The squib valves receive a signal at the valve electrical leads that is capable of actuating the squib valve.
ITAAC Determination Basis Multiple ITAAC were performed to verify that the valves identified in Combined License (COL)
Appendix C Table 2.1.2-1 as having Diverse Actuation System (DAS) control perform an active safety function after receiving a signal from DAS. The subject ITAAC performed testing on the squib valves listed in Attachment A.
Testing was performed in accordance with Unit 3 work order and preoperational test procedure listed in Reference 1 to verify that the valves identified in Attachment A as having DAS control perform an active safety function after receiving a signal from DAS. Testing was performed on the squib valves using real signals into the DAS without stroking the valve and ensured the squib valves received a signal at the valve electrical leads that was capable of actuating the valve.
Circuit resistance was measured and inside and outside containment temperatures were measured at multiple locations and were used to calculate the circuit resistance expected during accident conditions. During testing each squib valve identified in Attachment A had the squib valve igniters replaced with test resistor fixtures. Test resistance was modified to be greater than the calculated maximum resistance expected during accident conditions. The squib valves were armed using the manual controls on the DAS panel/cabinets and then actuated with the DAS actuation controls. A Data Acquisition (DAO) system was used to measure both firing current and signal duration.
The minimum signal necessary to actuate the squib valves was specified in valve design information as at least 3.7 amperes for 1 O milliseconds. The information recorded during testing of duration and firing current was utilized to confirm that a sufficient test signal was received at each of the squib valves.
The completed test results (Reference 1 ), confirmed that each squib valve, identified in the Attachment A, received a signal at the valve electrical leads that was capable of actuating the squib valve.
Reference 1 is available for NRC inspection as part of the Unit 3 ITAAC Completion Package (Reference 2).
U.S. Nuclear Regulatory Commission ND-20-0751 Enclosure Page 3 of 4 ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there were no relevant findings associated with this ITAAC. The review is documented in the ITAAC Completion Package (Reference 2) and is available for NRC review.
ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.1.02.11c.i was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met.
Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
References (available for NRC inspection)
- 1. SV3-RCS-ITR-800051, Rev. 0, ITAAC Technical Report, "Unit 3 Testing Results of RCS Squib Valves: ITAAC 2.1.02.11 c.i, NRC Index Number: 51 "
- 2. 2.1.02.11 c.i-U3-CP-Rev 0, ITAAC Completion Package
U.S. Nuclear Regulatory Commission ND-20-0751 Enclosure Page 4 of 4 Attachment A
- Excerpt from COL Appendix C Table 2.1.2-1
Fourth-stage ADS Squib Valve RCS-PL-V004A Fourth-stage ADS Squib Valve RCS-PL-V004B Fourth-stage ADS Squib Valve RCS-PL-V004C Fourth-stage ADS Squib Valve RCS-PL-V004D
- Control PMS/DAS Yes/Yes Yes/Yes Yes/Yes Yes/Yes