Request for Withholding Info from Public Disclosure LAR and Exemptions to Allow Use of LTAs for ATF - Enclosure 1, Evaluation of the Proposed Change (Proprietary) EPID L-2022-LLA-0097, LLE-0020, LLE-0021, LLE-0022
ML22234A069
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 09/15/2022
From: John Lamb
Plant Licensing Branch II
To: Gayheart C
Southern Nuclear Operating Co
Lamb J
References
EPID L-2022-LLA-0097, EPID L-2022-LLE-0020, EPID L-2022-LLE-0021, EPID L-2022-LLE-0022
Download: ML22234A069 (3)


Text

September 15, 2022 Ms. Cheryl A. Gayheart Regulatory Affairs Director Southern Nuclear Operating Co., Inc.

3535 Colonnade Parkway Birmingham, AL 35243

SUBJECT:

VOGTLE ELECTRIC GENERATING PLANT, UNITS 1 AND 2 - REQUEST FOR WITHHOLDING INFORMATION FROM PUBLIC DISCLOSURE RE: LICENSE AMENDMENT REQUEST AND EXEMPTIONS TO ALLOW USE OF LEAD TEST ASSEMBLIES FOR ACCIDENT TOLERANT FUEL - ENCLOSURE 1, EVALUATION OF THE PROPOSED CHANGE (PROPRIETARY)

(EPID L-2022-LLA-0097, L-2022-LLE-0020, L-2022-LLE-0021, and L-2022-LLE-0022)

Dear Ms. Gayheart:

By letter dated June 30, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22181B155), Southern Nuclear Operating Company (SNC) submitted a license amendment request and exemption requests to allow the use of lead test assemblies (LTAs) for accident tolerant fuel (ATF). In Enclosure 5 of the letter dated June 30, 2022, SNC submitted an affidavit dated August 27, 2021, executed by Zachary Harper, Manager, Licensing Engineering, Westinghouse Electric Company LLC (Westinghouse),

requesting that the information contained in the following document be withheld from public disclosure pursuant to Section 2.390 of Title 10 of the Code of Federal Regulations (10 CFR):

- Evaluation of the Proposed Change (Proprietary)

A nonproprietary copy of this document contained in Enclosure 2 of the letter dated June 30, 2022, has been placed in the U.S. Nuclear Regulatory Commissions (NRCs) Public Document Room and added to the NRC Library at the above-referenced ADAMS Accession No. ML22181B156.

The affidavit stated that the submitted information should be considered exempt from mandatory public disclosure for the following reasons:

(5)(a) The information reveals the distinguishing aspects of a process (or component, structure, tool, method, etc.) where prevention of its use by any of Westinghouses competitors without license from Westinghouse constitutes a competitive economic advantage over other companies.

(5)(c) Its use by a competitor would reduce his expenditure of resources or improve his competitive position in the design, manufacture, shipment, installation, assurance of quality, or licensing a similar product.

The NRC staff has reviewed your application and the material in accordance with the requirements of 10 CFR 2.390 and, on the basis of the statements in the affidavit, have determined that the submitted information sought to be withheld contains proprietary commercial information and should be withheld from public disclosure.

Therefore, the version of the submitted information marked as proprietary will be withheld from public disclosure pursuant to 10 CFR 2.390(b)(5) and Section 103(b) of the Atomic Energy Act of 1954, as amended.

Withholding from public inspection shall not affect the right, if any, of persons properly and directly concerned to inspect the documents. If the need arises, we may send copies of this information to our consultants working in this area. The NRC staff will, of course, ensure that the consultants have signed the appropriate agreements for handling proprietary information.

If the basis for withholding this information from public inspection should change in the future such that the information could then be made available for public inspection, you should promptly notify the NRC. You also should understand that the NRC may have cause to review this determination in the future, for example, if the scope of a Freedom of Information Act request includes your information. In all review situations, if the NRC makes a determination adverse to the above, you will be notified in advance of any public disclosure.

If you have any questions regarding this matter, please contact me at 301-415-3100 or John.Lamb@nrc.gov.

Sincerely,

/RA/

John G. Lamb, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: 50-424 and 50-425 cc: Camille T. Zozula Manager, Regulatory Compliance &

Corporate Licensing Ref. CAW-21-5215 Westinghouse Electric Company 1000 Westinghouse Drive Cranberry Township, PA 16066 Listserv

ML22234A069 OFFICE DORL/LPL2-1/PM DORL/LPL2-1/LA DSS/SFNB/BC DORL/LPL2-1/BC DORL/LPL2-1/PM NAME JLamb KGoldstein Krepel (A)

MMarkley JLamb DATE 09/13/2022 08/22/2022 09/14/2022 09/14/2022 09/15/2022