ITAAC Closure Notification on Completion of ITAAC 3.3.00.05c (Index Number 786)
ML22059B067
Person / Time
Site: Vogtle 
Issue date: 02/28/2022
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ITAAC 3.3.00.05c, ND-21-1115
Download: ML22059B067 (6)


Text

>- Southern Nuclear FEB 2 8 2022 Docket No.:

52-025 Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4 7825 River Road Waynesboro, GA 30830 706-848-6459 tel ND-21-1115 10 CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC 3.3.00.05c [Index Number 7861 Ladies and Gentlemen:

In accordance with 1 O CFR 52.99(c)(1 ), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 3.3.00.05c [Index Number 786). This ITAAC requires inspections be performed of the boundaries between the following rooms which contain safety-related equipment - Passive Core Cooling System (PXS)

Valve/Accumulator Room A (11206), PXS Valve/Accumulator Room B (11207), and Chemical and Volume Control System (CVS) Room (11209) - to demonstrate that the boundaries between these rooms are designed to prevent flooding between these rooms. The closure process for this ITAAC is based on the guidance described in Nuclear Energy Institute (NEI) 08-01, Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 1 O CFR 52.99.

If there are any questions, please contact Kelli A. Roberts at 706-848-6991.

Respectfully submitted, Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

MJY/JRV/sfr Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 3.3.00.05c [Index Number 786)

U.S. Nuclear Regulatory Commission ND-21-1115 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena Ill Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. J.B. Williams Mr. M. J. Yax Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beilke Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Regulatory Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. 0. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Mr. T. Fanelli Ms. K. Mccurry Mr. J. Parent Mr. B. Griman Mr. V. Hall

U.S. Nuclear Regulatory Commission ND-21-1115 Page 3 of 3 Oglethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Dr. L. Oriani Mr. D. C. Durham Mr. M. M. Corletti Mr. Z.S. Harper Mr. J. L. Coward Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GOS Associates, Inc.

Mr. S. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-21-1115 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-21-1115 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 3.3.00.0Sc [Index Number 786]

U.S. Nuclear Regulatory Commission ND-21-1115 Enclosure Page 2 of 3 ITAAC Statement Design Commitment 5.c) The boundaries between the following rooms, which contain safety-related equipment -

PXS valve/accumulator room A (11206), PXS valve/accumulator room B (11207), and CVS room (11209) - are designed to prevent flooding between these rooms.

Inspections/Tests/ Analyses An inspection of the boundaries between the following rooms which contain safety-related equipment - PXS Valve/Accumulator Room A (11206), PXS Valve/Accumulator Room B (11207), and CVS Room (11209) - will be performed.

Acceptance Criteria A report exists that confirms that flooding of the PXS Valve/Accumulator Room A (11206), and the PXS Valve/Accumulator Room B (11207) is prevented to a maximum flood level as follows:

PXS A 110'-2", PXS B 110'-1 "; and of the CVS room (11209) to a maximum flood level of 110'-0".

ITAAC Determination Basis An inspection of the boundaries between the following rooms which contain safety-related equipment - Passive Core Cooling System (PXS) Valve/Accumulator Room A (11206), PXS Valve/Accumulator Room B (11207), and Chemical and Volume Control System (CVS) Room (11209) - was performed to derr.o:1strate that the boundaries between these rooms a:-e designed to prevent flooding between these rooms.

The inspection was performed to document the existence of provisions to prevent flooding between rooms via openings or penetrations below the maximum flood levels of 110'-2" for PXS A, 110'-1" for PXS B (including adjacent room 11208), and 110'-0" for the CVS room. A visual inspection was performed of the floors, walls, and ceilings of each room indicated above. As part of this visual inspection, all openings, and penetrations through these boundaries below the maximum flood levels were documented. Each opening or penetration located below the maximum flood levels was inspected to ensure that watertight hatches, curbs (flood weirs), and penetration seals specified in the design documents to prevent flooding from the flooding source to the adjacent rooms are installed as required. In addition, the height of each curb (flood weir) was verified to ensure flooding between the rooms is prevented.

The inspection plan and results of the visual inspection of the floors, walls and ceiling were documented in the Unit 3 inspection report (Reference 1 ). The inspection results compiled in Reference 1 confirm that floors, walls, and ceilings have provisions to prevent flooding between the PXS Valve/ Accumulator Room A (11206), PXS Valve/Accumulator Room B (11207), and the CVS room (11209) up to the maximum flood levels for each room (i.e., PXS A 110'-2", PXS B 110'-1 "; and CVS room 110'-0").

Reference 1 is available for NRC inspection as part of the Unit 3 ITAAC 3.3.00.0Sc Completion Package (Reference 2).

U.S. Nuclear Regulatory Commission ND-21-1115 Enclosure Page 3 of 3 ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 3.3.00.05c (Reference 2) and is available for NRC review.

ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 3.3.00.05c was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as designed, ITAAC compliant condition in accordance with approved plant programs and procedures.

References (available for NRC inspection)

1. SV3-11 00-ITR-800786, Rev. 1, "Accumulator Rooms and CVS Room Flood Prevention"
2. 3.3.00.05c -U3-CP-Rev0, ITAAC Completion Package
3. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 1 0 CFR Part 52"