ND-20-0751, ITAAC Closure Notification on Completion of ITAAC 2.1.02.11c.i (Index Number 51)

From kanterella
(Redirected from ND-20-0751)
Jump to navigation Jump to search

ITAAC Closure Notification on Completion of ITAAC 2.1.02.11c.i (Index Number 51)
ML22133A243
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 05/13/2022
From: Coleman J
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ITAAC 2.1.02.11c.i, ND-20-0751
Download: ML22133A243 (7)


Text

Jamie M. Coleman 7825 River Road A Southern Nuclear Regulatory Affairs Director Waynesboro , GA 30830 Vogtle 3 & 4 706-848-6926 tel May 13, 2022 Docket No.: 52-025 ND-20-0751 10 CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington , DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC 2.1.02.11 c.i [Index Number 511 Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1 ), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 3 Inspections, Tests , Analyses , and Acceptance Criteria (ITAAC) Item 2.1.02.11 c.i [Index Number 511 which confirms that valves identified in Combined License (COL) Appendix C Table 2.1.2-1 as having Diverse Actuation System (DAS) control perform an active safety function after receiving a signal from DAS . The closure process for this ITAAC is based on the guidance described in NEI 08-01 , "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52 ," which was endorsed by the NRC in Regulatory Guide 1.215 .

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions , please contact Kelli Roberts at 706-848-6991 .

Respectfully submitted ,

/ ~

~eman Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.1 .02.11 c.i [Index Number 511 JMC/DLW/sfr

U.S . Nuclear Regulatory Commission ND-20-0751 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena Ill Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. J.B. Williams Mr. A S. Parton Ms. K. A Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beilke Mr. S. Leighty Ms . A C. Chamberlain Mr. J. C. Haswell Document Services RTYPE : VND .LI .L06 File AR.01 .02.06 Nuclear Regulatory Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. 0 . Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Ms. K. Mccurry Mr. J. Parent Mr. B. Griman Mr. V. Hall

U.S. Nuclear Regulatory Commission ND-20-0751 Page 3 of 3 Oglethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Dr. L. Oriani Mr. D. C. Durham Mr. M. M. Corletti Mr. Z. S. Harper Ms . S.L. Zwack Other Mr. S. W . Kline , Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr. , Ph.D ., GOS Associates, Inc.

Mr. S. Roetger, Georgia Public Service Commission Mr. R. L. Trokey , Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-20-0751 Enclosure Page 1 of 4 Southern Nuclear Operating Company ND-20-0751 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.1.02.11c.i [Index Number 51]

U.S. Nuclear Regulatory Commission ND-20-0751 Enclosure Page 2 of 4 ITAAC Statement Design Commitment 11 .c) The valves identified in Table 2.1.2-1 as having DAS control perform an active safety function after receiving a signal from DAS .

Inspections, Tests, Analyses i) Testing will be performed on the squib valves identified in Table 2.1.2-1 using real or simulated signals into the DAS without stroking the valve .

Acceptance Criteria i) The squib valves receive a signal at the valve electrical leads that is capable of actuating the squib valve.

ITAAC Determination Basis Multiple ITAAC were performed to verify that the valves identified in Combined License (COL)

Appendix C Table 2.1.2-1 as having Diverse Actuation System (DAS) control perform an active safety function after receiving a signal from DAS. The subject ITAAC performed testing on the squib valves listed in Attachment A.

Testing was performed in accordance with Unit 3 work order and preoperational test procedure listed in Reference 1 to verify that the valves identified in Attachment A as having DAS control perform an active safety function after receiving a signal from DAS. Testing was performed on the squib valves using real signals into the DAS without stroking the valve and ensured the squib valves received a signal at the valve electrical leads that was capable of actuating the valve .

Circuit resistance was measured and inside and outside containment temperatures were measured at multiple locations and were used to calculate the circuit resistance expected during accident conditions . During testing each squib valve identified in Attachment A had the squib valve igniters replaced with test resistor fixtures. Test resistance was modified to be greater than the calculated maximum resistance expected during accident conditions . The squib valves were armed using the manual controls on the DAS panel/cabinets and then actuated with the DAS actuation controls. A Data Acquisition (DAO) system was used to measure both firing current and signal duration .

The minimum signal necessary to actuate the squib valves was specified in valve design information as at least 3.7 amperes for 1O milliseconds . The information recorded during testing of duration and firing current was utilized to confirm that a sufficient test signal was received at each of the squib valves .

The completed test results (Reference 1), confirmed that each squib valve , identified in the Attachment A , received a signal at the valve electrical leads that was capable of actuating the squib valve.

Reference 1 is available for NRC inspection as part of the Unit 3 ITAAC Completion Package (Reference 2) .

U.S. Nuclear Regulatory Commission ND-20-0751 Enclosure Page 3 of 4 ITAAC Finding Review In accordance with plant procedures for ITAAC completion , Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there were no relevant findings associated with this ITAAC. The review is documented in the ITAAC Completion Package (Reference 2) and is available for NRC review.

ITAAC Completion Statement Based on the above information , SNC hereby notifies the NRC that ITAAC 2.1.02.11c.i was performed for VEGP Unit 3 and that the prescribed acceptance criteria were met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed , ITAAC compliant condition in accordance with approved plant programs and procedures.

References (available for NRC inspection)

1. SV3-RCS-ITR-800051 , Rev. 0, ITAAC Technical Report, "Unit 3 Testing Results of RCS Squib Valves : ITAAC 2.1.02 .11 c.i , NRC Index Number: 51 "
2. 2.1 .02.11 c.i-U3-CP-Rev 0, ITAAC Completion Package

U.S. Nuclear Regulatory Commission ND-20-0751 Enclosure Page 4 of 4 Attachment A

  • Excerpt from COL Appendix C Table 2.1.2-1
  • Control
  • Equipment Name *Tag No.

PMS/DAS Fourth-stage ADS Squib Valve RCS-PL-V004A Yes/Yes Fourth-stage ADS Squib Valve RCS-PL-V004B Yes/Yes Fourth-stage ADS Squib Valve RCS-PL-V004C Yes/Yes Fourth-stage ADS Squib Valve RCS-PL-V004D Yes/Yes