Summary of Meeting with Constellation Energy Generation, LLC Regarding Digital Modernization License Amendment Request for Limerick Generating Station, Units 1 and 2
ML23156A247
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 06/09/2023
From: Marshall M
Plant Licensing Branch 1
To:
Constellation Energy Generation
Sreenivas V, NRR/DORL/LPLI, 415-2597
Shared Package
ML23156A417 List:
References
EPID L-2022-LLA-0140
Download: ML23156A247 (1)


Text

June 9, 2023 LICENSEE:

Constellation Energy Generation, LLC FACILITY:

Limerick Generating Station, Unit Nos. 1 and 2

SUBJECT:

SUMMARY

OF MAY 24, 2023, MEETING WITH CONSTELLATION ENERGY GENERATION, LLC REGARDING DIGITAL MODERNIZATION LICENSE AMENDMENT REQUEST FOR LIMERICK GENERATING STATION, UNITS 1 AND 2 (EPID L-2022-LLA-0140)

On May 24, 2023, a closed observation meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Constellation Energy Generation, LLC (the licensee) via video conference. The purpose of the open meeting was to discuss the digital instrumentation and control (I&C) license amendment request (LAR) for Limerick Generating Station Unit Nos. 1 and 2 (Limerick). The meeting notice and agenda are available in the Agencywide Documents Access and Management System (ADAMS) at Accession No. ML23136A139. The purpose of the meeting was to discuss outstanding audit questions related to the subject review. These questions were originally provided to the licensee in the audit process and are documented in ADAMS (ML22110A097 and ML22353A632). A list of attendees is provided as an enclosure.

During the meeting, a discussion of the following Audit Questions1 was held:

Audit Question 79 Audit Question 55 Audit Question 65 Audit Question 66 Audit Question 69 Audit Question 75 Audit Question 98 Audit Question 99 Audit Question 56 Audit Question 72 Audit Question 101 Audit Question 102 Audit Question 100 Audit Question 78 Audit Question 80 Audit Question 84 Audit Question 87 Audit Question 88 1 Audit Questions are listed in the order they were discussed.

Audit Question 89 Audit Question 97 Audit Question 82 Audit Question 86 Audit Question 91 Audit Question 92 Following the audit question discussion, NRC informed the licensee that they have not had time to look at the letter submitted on May 23, 2023, and that they should expect a letter back once the content could be assessed and what impacts the letter has to the review.

No regulatory decisions were made during the meeting.

Please direct any inquiries regarding this meeting to Nick Smith at 301-415-2509 or Nicholas.smith@nrc.gov or Michael Marshall at 301-415-2871 or Michael.marshall@nrc.gov.

Sincerely,

/RA/

Michael Marshall, Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353

Enclosure:

List of Attendees cc: Listserv

Enclosure LIST OF ATTENDEES MAY 24, 2023, MEETING WITH CONSTELLATION ENERGY GENERATION, LLC LIMERICK GENERATING STATION UNIT NOS. 1 AND 2 LICENSE AMENDMENT REQUEST INVOLVING PROPOSED DIGITAL INSTRUMENTATION AND CONTROL UPGRADE Name Organization Ed Miller U.S. Nuclear Regulatory Commission (NRC)

Michael Marshall NRC David Rahn NRC Nick Smith NRC Deanna Zhang NRC Jack Zhao NRC Michael Waters NRC Ming Li NRC Richard Stattel NRC Steven Alferink NRC Samir Darbali NRC Aaron Armstrong NRC Hang Vu NRC Carla Roque-Cruz NRC Todd Keene NRC Jesse Seymore NRC Frank Mascitelli Constellation Energy Group, LLC (CEG)

Michael Foote CEG Dave Molteni CEG Ashley Rickey CEG Mark Samselski CEG Zina Gavin CEG David Peiffer CEG Brian Devine CEG Scott Schumacher CEG James Berg CEG John Connelly CEG George Bonanni CEG Pareez Golub CEG John Schrage CEG Paul Krueger CEG Joseph Drahus CEG Dominic Mocello CEG Calvin Tang Westinghouse Electric Company (WEC)

Warren Odess-Gillett WEC Alison Hahn Department of Energy

Package: ML23156A417 Meeting Notice: ML23136A139 Meeting Summary: ML23156A247 OFFICE NRR/DORL/LLPB/PM NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DORL/LPL1/BC NAME NSmith MMarshall KZeleznock HGonzález DATE 06/02/2023 06/03/2023 06/06/2023 06/09/2023