MONTHYEARML24016A1902024-01-30030 January 2024 International, Inc. - Notice of Violation; the U.S. Nuclear Regulatory Commission Inspection Report 07201014/2022201 IR 05000498/20230042024-01-29029 January 2024 Integrated Inspection Report 05000498/2023004 and 05000499/2023004 ML24029A2752024-01-29029 January 2024 Request to Reschedule Evaluated Force-on-Force Drill ML24024A1162024-01-24024 January 2024 STP Unit 2 Request for Information ML24018A1992024-01-18018 January 2024 International, Administrative Change to HI-2200343-A IR 05000498/20244042024-01-18018 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000498/2024404; 05000499/2024404 ML23361A1622024-01-0404 January 2024 Application for HI-STORM Flood/Wind Multipurpose Storage System, Amendment No. 9 - Acknowledgement of Withdrawal and Notification of the U.S. Nuclear Regulatory Commission Staff Efforts Closure IR 05000498/20230032023-12-28028 December 2023 Acknowledgment of Reply to a Notice of Violation (NRC Inspection Report 05000498/2023003 and 05000499/2023003) ML23360A1692023-12-26026 December 2023 FEMA, Submittal of Radiological Emergency Preparedness Final Report for the South Texas Project Medical Services Drill Evaluated on August 31, 2023 ML23355A0812023-12-21021 December 2023 International - Withdrawal of HI-STORM FW Multipurpose Canister Storage System Amendment 9 NOC-AE-230040, Supplement to Proposed Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (Relief Request RR-ENG-4-06)2023-12-14014 December 2023 Supplement to Proposed Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (Relief Request RR-ENG-4-06) NOC-AE-230039, Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/20230032023-12-12012 December 2023 Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/2023003 ML23339A1902023-12-0505 December 2023 Update Foreign Ownership, Control, or Influence (FOCI) ML23326A2592023-12-0505 December 2023 Review of the Fall 2022 Steam Generator Tube Inspection Report IR 05000498/20234012023-12-0404 December 2023 Security Baseline Inspection Report 05000498/2023401 and 05000499/2023401 ML23321A2462023-11-17017 November 2023 HI-STORM FW Amendment 7 RAI Response Clarifications (Part 3) ML23324A0102023-11-16016 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23310A2282023-11-13013 November 2023 Integrated Inspection Report 05000498/2023003 and 05000499/2023003, and Notice of Violation ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23298A0002023-11-0101 November 2023 the Associated Independent Spent Fuel Storage Installation - Issuance of Amendment Nos. 226 and 211 Related to Order Approving Indirect Transfer of Licenses and Conforming License Amendments ML23303A0782023-10-30030 October 2023 Submittal of Supplemental Information in Response to Order Consenting to License Transfers and Approval of Draft Conforming License Amendments ML23279A0342023-10-30030 October 2023 Associated Independent Spent Fuel Storage Installation - Order Approving Indirect Transfer of Licenses and Draft Conforming License Amendments (EPID L-2023-LLM-0004) (Letter) IR 05000498/20234032023-10-26026 October 2023 Material Control and Accounting Program Inspection Report 05000498/2023403 and 05000499/2023403 (Cover Letter) ML23289A2132023-10-16016 October 2023 International - Schedule for Responses to HI-STORM FW Amendment 9 Requests for Additional Information ML23317A1262023-10-12012 October 2023 South. Texas Project Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program Revision 26 ML23279A1382023-10-0505 October 2023 Responses to Requests for Additional Information Related to Application for Order Approving Indirect Transfer of Control of Licenses ML23229A5172023-10-0404 October 2023 Amendment No. 9 to Certificate of Compliance No. 1032 for the HI-STORM Flood/Wind Multipurpose Canister Storage System - Request for Additional Information ML23271A1942023-10-0303 October 2023 Notification of Commercial Grade Dedication Inspection (05000498/2024013 and 05000499/2024013) and Request for Information ML23271A1662023-09-28028 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) ML23270B2592023-09-27027 September 2023 Update Foreign Ownership, Control, or Influence ML23263B1132023-09-20020 September 2023 Operator Licensing Examination Schedule Revision 1 ML23145A1752023-09-12012 September 2023 NRC Choice Letter to Holtec International with Attached Safety Inspection Report, IR 72-1014/2022-201, December 12-15, 2022, Inspection of Holtec International in Camden, New Jersey (Docket Nos.: 72-1014, 72-1032) ML23254A0652023-09-0707 September 2023 Registration of Spent Fuel Storage Cask Pursuant to 10 CFR 72.212(b)(2) IR 05000498/20243012023-09-0707 September 2023 Notification of NRC Initial Operator Licensing Examination 05000498/2024301; 05000499/2024301 ML23254A0012023-09-0505 September 2023 Registration of Use of Casks to Store Spent Fuel IR 05000498/20233012023-09-0101 September 2023 NRC Examination Report 05000498/2023301 and 05000499/2023301 ML23243B0562023-08-31031 August 2023 Supplemental Information to Application for Order Approving Indirect Transfer of Control of Licenses ML23236A6042023-08-24024 August 2023 Annual Dose Report for 2022 IR 05000498/20230052023-08-22022 August 2023 Updated Inspection Plan for South Texas Project Electric Generating Station, Units 1 and 2 (Report 05000498/2023005 and 05000499/2023005) - Mid Cycle Letter ML23229A4992023-08-17017 August 2023 Supplement to Proposed Alternate Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (Relief Request RR-ENG-4-06) ML23229A5892023-08-17017 August 2023 Voluntary Response to Regulatory Issue Summary (RIS) 2023-02, Scheduling Information for the Licensing of Accident Tolerant, Increased Enrichment, and Higher Burnup Fuels ML23229A5262023-08-17017 August 2023 Inservice Inspection Summary Report - 1 RE24, ML23228A2102023-08-15015 August 2023 Closure of Investigation (OI 4-22-19) ML23227A2492023-08-15015 August 2023 International, HI-STORM FW Amendment 7 RAI 3-10 Response Clarification Call Action Items 2024-01-04
[Table view] |
Text
.......
Nuclear Operating Company IIIIJ. - -
South Texas Project Electric Ge11erat/11g Station P.O. Box 289 Wadsworth, Texas 77483 July 18, 2022 NOC-AE-22003903 10 CFR 72.212(b)(2)
STI: 35339210 ATTN: Document Control Desk Director, Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 South Texas Project Units 1 and 2 Docket Nos. 50-498; 50-499; 72-1041 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask In accordance with 10 CFR 72.212(b)(2), STP Nuclear Operating Company (STPNOC) is registering the use of three spent fuel storage casks to store spent fuel at the South Texas Project Units 1 and 2 Independent Spent Fuel Storage Installation (ISFSI). The first cask was placed on the ISFSI pad June 24, 2022, the second cask was placed on the ISFSI pad July 1, 2022, and the third cask was placed on the ISFSI pad July 8, 2022.
The following information is provided as required by 10 CFR 72.212(b)(2):
Licensee Name: STP Nuclear Operating Company Licensee Address: South Texas Project Electric Generating Station, P.O. Box 289 Wadsworth, Texas 77483 Reactor Renewed License Numbers: NPF-76 and NPF-80 Reactor Docket Numbers: 50-498 and 50-499 ISFSI Docket Number: 72-1041 Contact Name and
Title:
Michael Schaefer, Senior Vice President, Projects Cask Certificate Number: 1032, Amendment 2 Cask Model Number: HI-STORM FW Version XL using MPC-37 Cask 1 Identification Number: DBO019CCK0022 Cask 2 Identification Number: DBO019CCK0023 Cask 3 Identification Number: DBO019CCK0024 There are no commitments in this letter.
If there are any questions regarding this matter, please contact Derrick Johnson at (361) 972-7088 or me at (361) 972-7888.
U'--,,/....,.~--,J?---
M. A. Schaefer Projects, Senior VP
NOC-AE-22003903 Page 2 of 2 cc:
Regional Administrator, Region IV U.S. Nuclear Regulatory Commission 1600 E. Lamar Boulevard Arlington, TX 76011-4511