- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance...
|
MONTHYEARND-21-0973, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of Item 2.3.06.05a.i (Index Number 361)2021-10-29029 October 2021 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of Item 2.3.06.05a.i (Index Number 361) Project stage: Request ML21342A2922021-11-0202 November 2021, 9 December 2021 Update to Targeted Inspections, Tests, Analyses, and Acceptance Criteria for Vogtle Electric Generating Plant Unit 3 and 4 Project stage: Request ND-21-0982, ITAAC Closure Notification on Completion of Item 2.3.13.05.1 (Index Number 462)2021-11-0303 November 2021 ITAAC Closure Notification on Completion of Item 2.3.13.05.1 (Index Number 462) Project stage: Request ND-21-0992, ITAAC Closure Notification on Completion of Item 3.3.00.10.i (Index Number 815)2021-11-0404 November 2021 ITAAC Closure Notification on Completion of Item 3.3.00.10.i (Index Number 815) Project stage: Request ND-21-0377, ITAAC Closure Notification on Completion of ITAAC Item 2.2.01.11a.iii (Index Number 116)2021-11-0505 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.2.01.11a.iii (Index Number 116) Project stage: Request ND-20-0801, ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759)2021-11-0808 November 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.01 (Index Number 759) Project stage: Request ND-21-0995, ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4)2021-11-10010 November 2021 ITAAC Closure Notification on Completion of ITAAC 2.1.01.04 (Index Number 4) Project stage: Request ND-21-0167, ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.10.ii (Index Number 816)2021-11-11011 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 3.3.00.10.ii (Index Number 816) Project stage: Request ND-21-0038, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763)2021-11-12012 November 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.d (Index Number 763) Project stage: Request ND-21-0713, ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 (Index Number 716)2021-11-17017 November 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.7.04.03 (Index Number 716) Project stage: Request ND-21-1010, ITAAC Closure Notification on Completion of ITAAC C.2.6.09.09 (Index Number 670)2021-11-18018 November 2021 ITAAC Closure Notification on Completion of ITAAC C.2.6.09.09 (Index Number 670) Project stage: Request ND-21-1025, Unit 4 - ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.02.i (Index Number 565)2021-11-24024 November 2021 Unit 4 - ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.02.i (Index Number 565) Project stage: Request ND-21-0757, ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220)2021-12-0202 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.04.02a (Index Number 220) Project stage: Request ND-21-0769, ITAAC Closure Notification on Completion of ITAAC 2.2.02.02a (Index Number 120)2021-12-0707 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.02.02a (Index Number 120) Project stage: Request ND-20-1378, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761)2021-12-0808 December 2021 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761) Project stage: Request ND-21-1084, ITAAC Closure Notification on Completion of ITAAC 2.3.03.03c (Index Number 322)2021-12-0909 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.3.03.03c (Index Number 322) Project stage: Request ND-21-1036, ITAAC Closure Notification on Completion of ITAAC Item 2.2.03.12a.i (Index Number 214)2021-12-0909 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.2.03.12a.i (Index Number 214) Project stage: Request ND-21-0779, ITAAC Closure Notification on Completion of ITAAC 2.3.13.02 (Index Number 459)2021-12-15015 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.3.13.02 (Index Number 459) Project stage: Request ND-21-1030, ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56)2021-12-15015 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.1.02.12a.iv (Index Number 56) Project stage: Request ND-21-1022, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.1 (Index Number 291)2021-12-16016 December 2021 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.02.05.1 (Index Number 291) Project stage: Request ND-21-0993, ITAAC Closure Notification on Completion of ITAAC Item 2.1.02.15 (Index Number 67)2021-12-16016 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.1.02.15 (Index Number 67) Project stage: Request ND-21-0270, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05a (Index Number 644)2021-12-17017 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05a (Index Number 644) Project stage: Request ND-21-0802, ITAAC Closure Notification on Completion of ITAAC 2.2.01.02a (Index Number 91)2021-12-21021 December 2021 ITAAC Closure Notification on Completion of ITAAC 2.2.01.02a (Index Number 91) Project stage: Request ND-21-1095, Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.1.03.06.1 (Index Number 75)2021-12-21021 December 2021 Resubmittal of Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.1.03.06.1 (Index Number 75) Project stage: Request ND-21-0956, ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78)2021-12-21021 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.1.03.07.i (Index Number 78) Project stage: Request ND-21-0990, ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.04 (Index Number 572)2021-12-27027 December 2021 ITAAC Closure Notification on Completion of ITAAC Item 2.5.05.04 (Index Number 572) Project stage: Request ND-21-0744, Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355)2022-01-21021 January 2022 Vogtie Electric Generating Plant, Unit 3, ITAAC Closure Notification on Completion of ITAAC 2.3.06.02a (Index Number 355) Project stage: Request ND-20-0582, ITAAC Closure Notification on Completion of ITAAC 2.3.29.04 (Index Number 491)2022-01-21021 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.29.04 (Index Number 491) Project stage: Request ND-22-0049, ITAAC Closure Notification on Completion of ITAAC 2.6.09.13c (Index Number 654)2022-01-21021 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.13c (Index Number 654) Project stage: Request ND-22-0052, ITAAC Closure Notification on Completion of ITAAC 2.6.09.15a (Index Number 655)2022-01-27027 January 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.15a (Index Number 655) Project stage: Request ND-22-0080, ITAAC Closure Notification on Completion of ITAAC 2.3.09.02b (Index Number 422)2022-02-0404 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.09.02b (Index Number 422) Project stage: Request ND-21-1026, ITAAC Closure Notification on Completion of ITAAC 2.6.01.02.i (Index Number 579)2022-02-14014 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.01.02.i (Index Number 579) Project stage: Request ND-22-0051, (Taac Closure Notification on Completion of ITAAC 2.6.09.13a Index Number 652)2022-02-16016 February 2022 (Taac Closure Notification on Completion of ITAAC 2.6.09.13a Index Number 652) Project stage: Request ND-21-0796, ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.03.03 (Index Number 72) Project stage: Request ND-22-0070, ITAAC Closure Notification on Completion of ITAAC 3.3.00.16 (Index Number 821)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.16 (Index Number 821) Project stage: Request ND-22-0103, ITAAC Closure Notification on Completion of ITAAC 2.6.09.08 (Index Number 6501)2022-02-16016 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.08 (Index Number 6501) Project stage: Request ND-22-1157, ITAAC Closure Notification on Completion of 2.7.02.03a (Index Number 703)2022-02-17017 February 2022 ITAAC Closure Notification on Completion of 2.7.02.03a (Index Number 703) Project stage: Request ND-22-0104, ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647)2022-02-18018 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.06 (Index Number 647) Project stage: Request ND-21-0271, ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646)2022-02-18018 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.09.05c (Index Number 646) Project stage: Request ND-21-0654, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02c (Index Number 595) Project stage: Request ND-22-0131, ITAAC Closure Notification on Completion of ITAAC 2.6.02.02a (Index Number 593)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.02.02a (Index Number 593) Project stage: Request ND-21-0795, ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13)2022-02-21021 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.1.02.02a (Index Number 13) Project stage: Request ND-21-0092, ITAAC Closure Notification on Completion of ITAAC 2.3.11.03b (Index Number 454)2022-02-22022 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.11.03b (Index Number 454) Project stage: Request ND-21-0723, ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159)2022-02-22022 February 2022 ITAAC Closure Notice on Completion of ITAAC 2.2.03.02a (Index Number 159) Project stage: Request ND-22-0046, ITAAC Closure Notification on Completion of ITAAC 2.3.10.11a (Index Number 878)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.10.11a (Index Number 878) Project stage: Request ND-22-0092, ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 3.3.00.02a.i.b (Index Number 761) Project stage: Request ND-22-0085, ITAAC Closure Notification on Completion of ITAAC 2.3.07.06a (Index Number 399)2022-02-23023 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.07.06a (Index Number 399) Project stage: Request ND-20-0880, ITAAC Closure Notification on Completion of ITAAC 2.3.11.03c (Index Number 455)2022-02-24024 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.3.11.03c (Index Number 455) Project stage: Request ND-22-0088, ITAAC Closure Notification on Completion of ITAAC 2.6.01.03a (Index Number 582)2022-02-24024 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.01.03a (Index Number 582) Project stage: Request ND-22-0148, ITAAC Closure Notification on Completion of ITAAC 2.6.03.07 (Index Number 616)2022-02-25025 February 2022 ITAAC Closure Notification on Completion of ITAAC 2.6.03.07 (Index Number 616) Project stage: Request 2021-12-21
[Table View] |
Text
A Southern Nuclear Docket No.: 52-025 MAY 1 0 2022 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Jamie M. Coleman Regulatory Affairs Director Vogtle 3 & 4 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 7825 River Road Waynesboro, GA 30830 706-848-6926 tel ND-22-0342 1 O CFR 52.99(c)(1)
Resubmittal of ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.xiii [Index Number 1981 Ladies and Gentlemen:
In accordance with 1 O CFR 52.99(c)(1 ), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant (VEGP) Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.2.03.08c.xiii [Index Number 1981 for verifying the surfaces in the vicinity of the containment recirculation screens in the Passive Core Cooling System (PXS) are stainless steel. The closure process for this ITAAC is based on the guidance described in NEI 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52," which was endorsed by the NRC in Regulatory Guide 1.215.
Southern Nuclear Operating Company (SNC) previously submitted ITAAC Closure Notification on Completion of ITAAC 2.2.03.08c.xiii [Index Number 1981, letter number ND-20-0653, dated April 19, 2022 [ML22109A1731. This resubmittal addresses changes to the Principal Closure Document (Reference 1 in the enclosure) to support the completion of the subject ITAAC and supercedes ND-20-0653 in its entirety.
This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 1 O CFR 52.99.
If there are any questions, please contact Kelli A. Roberts at 706-848-6991.
Respectfully submitted, J).~an~
Regulatory Affairs Director Vogtle 3 & 4
Enclosure:
JMC/CEM/sfr Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.2.03.08c.xiii [Index Number 1981
U.S. Nuclear Regulatory Commission ND-22-0342 Page 2 of 3 To:
Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena Ill Mr. D. L. McKinney Mr. H. Nieh Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. J.B. Williams Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Beilke Mr. S. Leighty Ms. A. C. Chamberlain Mr. J.C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 Nuclear Regulatory Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. 0. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Ms. K. Mccurry Mr. J. Parent Mr. B. Griman Mr. V. Hall
U.S. Nuclear Regulatory Commission ND-22-0342 Page 3 of 3 Oglethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson Dalton Utilities Mr. T. Bundros Westinghouse Electric Company, LLC Dr. L. Oriani Mr. D. C. Durham Mr. M. M. Corletti Mr. Z. S. Harper Ms. S.L. Zwack Other Mr. S. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.
Dr. W. R. Jacobs, Jr., Ph.D., GOS Associates, Inc.
Mr. S. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. S. Blanton, Balch Bingham
U.S. Nuclear Regulatory Commission ND-22-0342 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-22-0342 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 Completion of ITAAC 2.2.03.08c.xiii [Index Number 198]
U.S. Nuclear Regulatory Commission ND-22-0342 Enclosure Page 2 of 3 IT AAC Statement Design Commitment 8.c) The PXS provides RCS makeup, boration, and safety injection during design basis events.
Inspections, Tests, Analyses xiii) Inspections will be conducted of the surfaces in the vicinity of the containment recirculation screens. The surfaces in the vicinity of the containment recirculation screens are the surfaces located above the bottom of the recirculation screens up to and including the bottom surface of the plate discussed in Table 2.2.3-4, item 8.c.vii, out at least 8 ft, 3 in perpendicular to the front and at least 7 feet to the side of the face of the screens.
Acceptance Criteria xiii) These surfaces are stainless steel.
ITAAC Determination Basis Multiple ITAAC are performed to demonstrate that the Passive Core Cooling System (PXS) provides Reactor Coolant System (RCS) makeup, boration, and safety injection during design basis events. For this ITAAC, inspections are performed to verify that the surfaces in the vicinity of the containment recirculation screens in the PXS are stainless steel.
The surfaces in the vicinity of the containment recirculation screens in the PXS are defined as the surfaces located above the bottom of the containment recirculation screens up to and including the bottom surface of the plate discussed in Vogtle Electric Generating Plant (VEGP)
Combined License Appendix C, Table 2.2.3-4 item 8.c.vii, out at least 8 ft, 3 in perpendicular to the front and at least 7 feet to the side of the face of the screens.
The results of the inspections of the surfaces in the vicinity of the containment recirculation screens in the PXS as defined above are documented in the Unit 3 Principal Closure Document (Reference 1) supporting the Unit 3 ITAAC 2.2.03.0Sc.xiii Completion Package (Reference 2).
The inspection confirmed that the surfaces in the vicinity of the containment recirculation screens are stainless steel.
The Unit 3 Principal Closure Document (Reference 1) is available for NRC inspection as part of the Unit 3 ITAAC 2.2.03.0Sc.xiii Completion Package (Reference 2).
ITAAC Finding Review In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all lTAAC findings pertaining to the subject ITAAC and associated corrective actions. This review found that there are no relevant IT AAC findings associated with this ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 2.2.03.0Sc.xiii (Reference 2) and is available for NRC review.
U.S. Nuclear Regulatory Commission ND-22-0342 Enclosure Page 3 of 3 IT AAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.2.03.08c.xiii was petfor~
d for VEGP Unit 3 and that the prescribed acceptance criteria were met.
Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.
References (available for NRC inspection)
- 1. SV3-PXS-ITR-800198, Rev. 1,"Unit 3 PXS ITAAC Inspection of Room 11202: ITAAC 2.2.03.0Sc.xiii NRC Index Number 198"
- 2. 2.2.03.08c.xiii-U3-CP-Rev1, ITAAC Completion Package
- 3. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"