CR-2019-0177, DRP Detected by Orise HPs in SU12204A
ML21067A221
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 02/10/2021
From:
ZionSolutions
To:
Office of Nuclear Material Safety and Safeguards
Shared Package
ML21067A225 List:
References
ZS-2021-0001
Download: ML21067A221 (3)


Text

DETAILS Division:

RP Name:

DRP Detected by ORISE HPs in SU12204A

==

Description:==

On 12/05/19, at approximately 1455, ORISE HPs detected activity greater than the background in Survey Unit (SU) 12204A while performing gamma scans. The material was excavated, and a discrete radioactive particle was identified. The particle was collected in a bag with soil. The initial reading using a 2350 meter and a 4410-gamma detector showed 503K CPM; using an M3/GM detector showed 600K CPM, and using a Telepole, dose rates showed 6.5 mrem/hr at contact and <0.1 mrem/hr at 30 cm.

The DRP was taken to Chemistry for isotopic analysis. qualitative results showed Co 60 9.87E+05 pCi/unit.

Start Date:

12/6/2019 1:38:00 PM End Date:

12/12/2019 12:00:00 AM Status:

Completed PROPERTIES SIG Level:

3 Date/Time Initiated:

12/6/2019 1:38:00 PM Brief

Description:

DRP Detected by ORISE HPs in SU12204A

==

Description:==

On 12/05/19, at approximately 1455, ORISE HPs detected activity greater than the background in Survey Unit (SU) 12204A while performing gamma scans. The material was excavated, and a discrete radioactive particle was identified. The particle was collected in a bag with soil. The initial reading using a 2350 meter and a 4410-gamma detector showed 503K CPM; using an M3/GM detector showed 600K CPM, and using a Telepole, dose rates showed 6.5 mrem/hr at contact and <0.1 mrem/hr at 30 cm.

The DRP was taken to Chemistry for isotopic analysis. qualitative results showed Co 60 9.87E+05 pCi/unit.

Immediate Actions:

DRP was captured and assessed using portable instrumentation then sent to chemistry for qualitative isotopic analysis.

Recommended Actions:

Review for 10CFR50.75g.

The DRP was removed leaving no residual contamination and is considered remediated; therefore, does not meet the intent of 10CFR50.75g(1).

1RIXUWKHUDFWLRQVDUHUHTXLUHG

Date Discovered:

12/5/2019 Issue Identified By:

NRC Related Documents:

Page 1 of 3 ES-ZION-CR-2019-0177 Page 1 of 3 Condition Report

~

ENERGYSOLUTIONS I

1 I

I I

I

Trends Cause Codes:

A7-B2-C01-Legacy contamination C02 Source unknown Event Codes:

$6LWH&ORVXUH)66VXUYH\\LVVXH Reviewed Date/Time:

12/6/2019 12:00:00 AM Maintenance Rule Applicable?

False Reportability Applicable?

False Operability Review Required?

False CAQ/NONCAQ?

Non-CAQ 50.75g Issue?

False 7230D Issue?

False MRC Review Meeting Date:

MRC Approval:

False MRC Comments:

Responsibilities Initator:

David S. Villicana Shift Manager:

Jason P. Pacheco-ext CR Owner:

Timothy W. Plutchak Events Step Person Start Date End Date Initiation:

David S. Villicana 12/6/2019 12/6/2019 OP Review:

Jason P. Pacheco-ext 12/6/2019 12/6/2019 Screening:

Timothy W. Plutchak 12/6/2019 12/12/2019 MRC Review:

Timothy W. Plutchak Pending CA Completion:

Timothy W. Plutchak 12/12/2019 12/12/2019 Verify and Closure:

Timothy W. Plutchak 12/12/2019 12/12/2019 Verification Verification:

Timothy W. Plutchak 12/12/2019 Verification Comments Close to actions taken as agreed by MRC members during 12/12/19 meeting.

Page 2 of 3 ES-ZION-CR-2019-0177 Page 2 of 3 Condition Report

~

ENERGYSOLUTIONS

Page 3 of 3 ES-ZION-CR-2019-0177 Page 3 of 3 Condition Report

~

ENERGYSOLUTIONS