DETAILS Division:
DD Name:
Exposed wood timber, piping and large Boulder in FSS Survey Unit 12204C
==
Description:==
When performing REMP TLD change on 12/29/19 noted erosion in two areas 200-300 yards south of the old Fore Bay in 12204C. See two attached pictures. One picture shows approximate 2 foot deep crevice with over 8 foot uncovered timber.
Second area near timber is another crevice with large exposed boulder,2 inch pipe and rebar sticking up from eroded area.
Start Date:
1/3/2020 12:25:00 PM End Date:
2/20/2020 12:00:00 AM Status:
Completed PROPERTIES SIG Level:
3 Date/Time Initiated:
1/3/2020 12:25:00 PM Brief
Description:
Exposed wood timber, piping and large Boulder in FSS Survey Unit 12204C
==
Description:==
When performing REMP TLD change on 12/29/19 noted erosion in two areas 200-300 yards south of the old Fore Bay in 12204C. See two attached pictures. One picture shows approximate 2 foot deep crevice with over 8 foot uncovered timber.
Second area near timber is another crevice with large exposed boulder,2 inch pipe and rebar sticking up from eroded area.
Immediate Actions:
Took Pictures.
Recommended Actions:
Schedule and perform a special surveillance IAW: ZS-LT-300-001-003 Isolation and Control for Final Status Survey, Section 5.4. Post FSS Routine & Special Surveillances-this action is completed Project Management to assess future erosion concerns and what (if any) actions are necessary to prevent or mitigate those FRQFHUQV
Date Discovered:
12/29/2019 Issue Identified By:
Initiator Related Documents:
Reviewed Date/Time:
1/3/2020 12:00:00 AM Maintenance Rule Applicable?
False Reportability Applicable?
False Operability Review Required?
False CAQ/NONCAQ?
Non-CAQ 50.75g Issue?
False Page 1 of 3 ES-ZION-CR-2020-0001 Page 1 of 3 Condition Report
~
ENERGYSOLUTIONS I
1 1
1 1
1
Action - ES-ZION-ACT-2020-0168 Action Type:
Due Date:
Date Completed:
2/20/2020 2/20/2020 Action:
Project Management to assess future erosion concerns and what (if any) actions are QHFHVVDU\\WRSUHYHQWRUPLWLJDWHWKRVHFRQFHUQV3RWHQWLDOO\\ORRNDWDGGLQJWKLVWRWKH
surveillance schedule.
1st extension granted by the GM on 2/6/2020.
Results:
The area was resurveyed to validate FSS status had not changed. Survey showed no change to FSS. The normal surveillace of FSS areas added observing areas for any errosion issues.The areas identified in this CR are scheduled to be backfilled during final site grading.
This issue can be closed Assigned To:
Jerry X. Houff Corrective Action Trends Cause Codes:
A7-B1-C04-Other natural phenomena LTA Event Codes:
$6LWH&ORVXUH)66VXUYH\\LVVXH 7230D Issue?
False MRC Review Meeting Date:
MRC Approval:
False MRC Comments:
Responsibilities Initator:
Roger W. Boyce Shift Manager:
Jason P. Pacheco-ext CR Owner:
Shannon L. Quilling-ext Events Step Person Start Date End Date Initiation:
Roger W. Boyce 1/3/2020 1/3/2020 OP Review:
Jason P. Pacheco-ext 1/3/2020 1/3/2020 Screening:
Shannon L. Quilling-ext 1/3/2020 1/9/2020 MRC Review:
Shannon L. Quilling-ext Pending CA Completion:
Shannon L. Quilling-ext 1/9/2020 2/20/2020 Verify and Closure:
Shannon L. Quilling-ext 1/9/2020 2/20/2020 Page 2 of 3 ES-ZION-CR-2020-0001 Page 2 of 3 Condition Report
~
ENERGYSOLUTIONS f
Verification Verification:
Shannon L. Quilling-ext 2/20/2020 Verification Comments The action has been satisfied.