MONTHYEARML20211C2101986-10-17017 October 1986 Proposed Findings of Fact & Conclusions of Law Re Issue of Manpower Mobilization & Adequacy of Communication Sys to Be Used in Event of Emergency.Certificate of Svc Encl ML20211D7191986-10-17017 October 1986 Proposed Findings of Fact & Conclusions of Law in Form of Suppl to Fourth Partial Initial Decision on Offsite Emergency Planning Contentions Re Graterford.Certificate of Svc Encl ML20211D2301986-10-16016 October 1986 Proposed Findings of Fact & Conclusions of Law in Form of Suppl to Fourth Partial Initial Decision Re Remanded Contention Concerning Manpower Mobilization at Graterford. Certificate of Svc Encl ML20215H6091986-10-16016 October 1986 Proposed Findings of Fact & Conclusions of Law on Contention Re Manpower Mobilization.W/Certificate of Svc ML20212P3351986-08-29029 August 1986 Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decision Re Remanded Bus Driver Facility Offsite Emergency Planning Contention.Certificate of Svc Encl ML20212P5421986-08-29029 August 1986 Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decision Assuring That School Bus Drivers for Oj Roberts & Spring-Ford School Districts Sufficient to Respond to Facility Radiological Emergency Event ML20203M9141986-08-27027 August 1986 Proposed Findings of Fact & Conclusions of Law Concerning ASLB Remanded Issue in ALAB-836.Sufficient Number of School Bus Drivers Would Be Available in Event of Emergency. W/Certificate of Svc ML20212N0661986-08-26026 August 1986 Proposed Findings of Fact & Conclusions of Law in Form of Suppl to Third Partial Initial Decision Re Offsite Emergency Planning Contentions.Proposed Transcript Corrections & Certificate of Svc Encl ML20126M6111985-07-25025 July 1985 Submits Author/Friends of the Earth Proposed Findings & Conclusions Re Emergency Planning Contentions for Graterford Inmates.Graterford Emergency Plans Inadequate & Violate NRC & FEMA Regulations ML20132H1211985-07-17017 July 1985 Proposed Findings of Fact & Conclusions of Law in Form of Unsigned & Undated Fourth Partial Initial Decision Re Graterford Offsite Emergency Planning Contentions. Certificate of Svc Encl ML20099H3811985-03-14014 March 1985 Reply to Joint Intervenors 850219 Findings of Fact & Conclusions of Law Re Offsite Emergency Planning Contentions.Certificate of Svc Encl ML20108F2731985-03-0707 March 1985 Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decision Re Offsite Emergency Planning Contentions.Certificate of Svc Encl ML20111B6961985-03-0606 March 1985 Proposed Findings of Fact & Conclusions of Law on Limerick Ecology Action Contentions Re Offsite Emergency Planning. Plan Currently Being Developed Would Be Implemented in Event of Incident.Certificate of Svc Encl ML19269B1551985-03-0202 March 1985 Findings & Conclusions on Offsite Emergency Planning & Complaint That Rl Anthony/Friends of the Earth 850129 Motion to Revise Schedule Denied ML20107D0281985-02-19019 February 1985 Applicant Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decision Re Offsite Emergency Planning Contentions.Rev to Applicant Exhibit List Encl ML20094C1151984-08-0606 August 1984 Reply to City of Philadelphia & Limerick Ecology Action 840726 Proposed Findings of Fact & Conclusions of Law Re Severe Accident Risk Assessment Contentions.Certificate of Svc Encl ML20094A9521984-08-0101 August 1984 Second Errata to 840726 Proposed Findings of Fact & Conclusions of Law on Limerick Ecology Action Contentions DES-1,DES-2,DES-3 & DES-4.Certificate of Svc Encl ML20093N1261984-07-27027 July 1984 Errata to 840726 Proposed Findings of Fact & Conclusions of Law on Limerick Ecology Action Contentions DES-1, DES-2,DES-3 & DES-4.Proposed Transcript Corrections & Certificate of Svc Encl ML20093K9611984-07-26026 July 1984 Proposed Findings of Fact & Conclusions of Law on Limerick Ecology Action Contentions DES-1,-2,-3 & -4 Re Severe Accident Risk.Certificate of Svc Encl ML20093A5391984-07-0909 July 1984 Reply Findings of Fact & Conclusions of Law Re Limerick Ecology Action Onsite Emergency Planning Contentions. Certificate of Svc Encl ML20093A5321984-07-0909 July 1984 Reply Findings of Fact & Conclusions of Law to Limerick Ecology Findings Re Contention I-42 ML20092P5931984-07-0505 July 1984 Transmittal of Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decisions Re Severe Accident Risk Issues.Updated Exhibit & Witness Lists Encl ML20092K7281984-06-21021 June 1984 Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decision Re Limerick Ecology Action Onsite Emergency Planning Contentions.Certificate of Svc Encl ML20092J7631984-06-21021 June 1984 Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decision Re Limerick Ecology Action Contention I-42 Concerning Environ Qualification of Electrical Equipment ML20092J7461984-06-19019 June 1984 Proposed Findings of Fact Re Onsite Emergency Planning Contentions ML20091M9691984-06-0808 June 1984 Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decision Re Limerick Ecology Action Onsite Emergency Planning Contentions ML20091N0211984-06-0808 June 1984 Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decision Re Limerick Ecology Action Contention I-42.Certificate of Svc Encl ML20099G4581984-06-0606 June 1984 Rebuttal of Applicant 840518 Reply on Contentions V-3a & V-3b Re safety-related Structures.Six Remedies Listed in Finding Should Be Mitigated Re Hazards to safety-related Structures Set Forth in Record of Hearings on Contentions ML20091B3791984-05-21021 May 1984 Findings & Conclusions Re Contention VI-I ML20084Q9001984-05-18018 May 1984 Reply Findings of Fact & Conclusions of Law to Contentions V-3a & V-3b,in Response to Friends of the Earth 840502 Findings & Conclusions from Records of Evidentiary Hearings ML20084H5331984-05-0202 May 1984 Proposed Findings of Fact on Contentions V-3a & V-3b Re Effects on safety-related Structures on Postulated Ruptures in Arco Petroleum & Columbia Gas Pipelines That Run Near Site.Certificate of Svc Encl ML20083R6971984-04-20020 April 1984 Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decision Re Contentions V-3a & V-3b. Certificate of Svc Encl ML20081C8101984-03-12012 March 1984 Reply Findings of Fact & Conclusions of Law Re Contention V-4 in Response to Air & Water Pollution Patrol (Awpp) 840224 Proposed Findings.Awpp Findings Should Be Rejected.Certificate of Svc Encl ML20080N0491984-02-16016 February 1984 Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decision on Contention V-4 Re Carburetor Icing.Notice of Appearances & Certificate of Svc Encl ML20067A8471982-11-30030 November 1982 Reply Findings of Fact & Conclusions of Law in Form of Initial Decision ML20066L1811982-11-17017 November 1982 Pages 8D,8E & 9,inadvertently Omitted from 821117 Proposed Findings of Fact,Conclusions of Law & Opinion ML20066F9171982-11-16016 November 1982 Proposed Findings of Fact & Conclusions of Law & Opinion. Certificate of Svc Encl ML20066C6211982-11-0909 November 1982 Proposed Findings of Fact & Conclusions of Law in Form of Partial Initial Decision.Notice of Appearance & Certificate of Svc Encl 1986-08-29
[Table view] Category:LEGAL TRANSCRIPTS & ORDERS & PLEADINGS
MONTHYEARML20151L3671997-08-0505 August 1997 Order Prohibiting Involvement in NRC Licensed Activities (Effective Immediately).Orders That SA Blacklock Prohibited from Engaging in Activities Licensed by NRC for 5 Yrs from Date of Order ML20151L5181997-08-0505 August 1997 Order Prohibiting Involvement in NRC Licensed Activities (Effective Immediately) Re SL Nevin Deliberately Falsifying Records of RECW Sample Documentation on 960207 ML20203H6891997-06-0202 June 1997 Transcript of 970602 Enforcement Conference in King of Prussia,Pa ML20083N3971995-04-26026 April 1995 Comment Supporting Proposed GL, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves ML20081B3811995-03-0101 March 1995 Comment Supporting Proposed Suppl 5 to GL 88-20, IPEEE for Severe Accident Vulnerabilities ML20058K7381993-12-0303 December 1993 Memorandum & Order CLI-93-25.* Commission Denies State of Nj Petition for Leave to Intervene & Request for Adjudicatory Hearing Filed on 931008.W/Certificate of Svc.Served on 931203 ML20059B0301993-10-22022 October 1993 NRC Staff Response to Commission Questions Posed W/Respect to State of New Jersey Petition for Leave to Intervene & Request for Hearing.* Denies Petition to Intervene & Request for Hearing.W/Certificate of Svc & Notice of Appearance ML20059B1111993-10-20020 October 1993 Philadelphia Electric Co Response to NRC 931014 Order.* State Failed to Demonstrate Entitlement to Hearing to Challenge Util Amend to Permit Util to Receive Shoreham Fuel ML20057G2141993-10-14014 October 1993 Order.* Requests for Simultaneous Responses,Not to Exceed 10 Pages to Be Filed by State,Peco & Lipa & Served on Other Specified Responders by 931020.NRC May File by 931022. W/Certificate of Svc.Served on 931014 ML20059A4581993-10-14014 October 1993 Order Requesting Answers to Two Questions Re State of Nj Request for Immediate Action by NRC or Alternatively, Petition for Leave to Intervene & Request for Hearing. Operations Plans for Marine Transportation Withheld ML20059B1291993-09-14014 September 1993 Affidavit of Jh Freeman.* Discusses Transfer of Slightly Used Nuclear Fuel from Shoreham Nuclear Power Station to Limerick Generating Station.W/Certificate of Svc & Notice of Appearance ML20045D8121993-06-14014 June 1993 Comment Supporting Proposed Rules 10CFR50 & 54 Re FSAR Update Submittals. ML20126F2721992-12-21021 December 1992 Comment Endorsing Positions & Comments of NUMARC & BWROG Re Draft GL, Augmented Inservice Insp Requirments for Mark I & Mark II Steel Containments,Refueling Cavities & Associated Drainage Sys ML20062C6561990-10-22022 October 1990 Affidavit Requesting Withholding of Summary Rept on Evaluation of Recirculation Nozzle to Safe End Weld Indication & Proposed Disposition to Permit Unit 1 Cycle 4 Operation, from Public Disclosure,Per 10CFR2.790 ML20246J4521989-08-30030 August 1989 Memorandum & Order (Terminating Proceeding).* Terminates Proceeding Per Settlement Agreement Between Limerick Ecology Action,Inc & Licensee.W/Certificate of Svc.Served on 890831 ML20246F1471989-08-25025 August 1989 Settlement Agreement.* Certificate of Svc Encl ML20246F1011989-08-25025 August 1989 Joint Motion for Termination of Proceedings.* Board Moved to Accept Encl Settlement Agreement,Dismiss Limerick Ecology Action,Inc (Lea) Contention W/Prejudice,Dismiss Lea as Party to Proceeding & Terminate Proceeding ML20246F0121989-08-25025 August 1989 Memorandum & Order CLI-89-17.* Staff Authorizes Issuance of Full Power License to Licensee to Operate Unit 2 After Requisite Safety Findings Under 10CFR50.57 Completed. W/Certificate of Svc ML20246E3431989-08-22022 August 1989 Opposition of Intervenor Limerick Ecology Action,Inc to Motion by Licensee Philadelphia Electric Co to Set Schedule for Discovery & Hearing.* Requests That Schedule Be Replaced W/More Reasonable Schedule,As Proposed.W/Certificate of Svc ML20246C0271989-08-18018 August 1989 Notice of Appointment of Adjudicatory Employee.* Informs That D Nash Appointed as Commission Adjudicatory Employee to Advise Commission on Issues in Proceeding.W/Certificate of Svc.Served on 890818 ML20246B7721989-08-17017 August 1989 Correction of Memorandum & Order of 890815.* Advises That Refs to 49CFR2.730(c) on Page 1 & 49CFR2.710 & 49CFR2.711 on Page 2 Should Be Corrected to Read as 10CFR2.730(c),2.710 & 2.711,respectively.W/Certificate of Svc.Served on 890818 ML20246D7411989-08-17017 August 1989 Transcript of 890817 Meeting in Rockville,Md Re Discussion of Full Power OL for Facility.Pp 1-58.Supporting Documentation Encl ML20246B7571989-08-16016 August 1989 Order Responding to Limerick Ecology Action Motion for Reconsideration.* Denies Motion to Reconsider,Stay,Suspend or Revoke 890707 Order on Basis That Order Appropriate.W/ Certificate of Svc.Served on 890816.Re-served on 890818 ML20246B7751989-08-16016 August 1989 Memorandum & Order.* Denies Rl Anthony 890623 Request for Hearing for Intervention in Remand Proceeding & for Stay of Low Power Authorization.W/Certificate of Svc.Served on 890816 ML20246B7931989-08-15015 August 1989 Memorandum & Order (Request for Expedited Answer).* Denies Licensee 890811 Request for Expedited Answer from NRC & Limerick Ecology Action on Basis That Request Lacks Good Cause.W/Certificate of Svc.Served on 890816 ML20245H8061989-08-14014 August 1989 Supplemental Response of Intervenor Limerick Ecology Action, Inc to Memorandum & Order of Commission & to Memorandum & Order of 890807.* Requests Further Extension of Time in Which to Reply.Certificate of Svc Encl ML20245H8491989-08-14014 August 1989 Notice of Change of Address.* Advises of Council Change of Address for Svc of Documents ML20245H5991989-08-11011 August 1989 Memorandum & Order (Terminating Proceeding).* Dismisses Graterford Inmates Contention Re Adequacy of Training for Drivers Responsible for Evacuating Graterford & Terminates Proceeding.Certificate of Svc Encl.Served on 890814 ML20245H7341989-08-10010 August 1989 Motion by Licensee Philadelphia Electric Co to Set Schedule for Discovery & Hearing & Request for Expedited Answer to This Motion.* Divergence in Positions of Respective Parties Emphasizes Need to Conclude Proceeding.W/Certificate of Svc ML20245F7511989-08-0909 August 1989 Reply by Licensee Philadelphia Electric Co to NRC Staff Response to Commission Questions.* Commission Should Rely on Licensee Cost Analysis in Response to Question 5 & Rc Williams Affidavit.W/Certificate of Svc ML20245F7341989-08-0909 August 1989 NRC Staff Response to Commission Memorandum & Order of 890807.* Advises That NRC Will Provide Comments on Limerick Ecology Action 890814 Filing Prior to Commission Meeting Scheduled for 890817.W/Certificate of Svc ML20245F7161989-08-0909 August 1989 Reply by Licensee Philadelphia Electric Co to Response of Intervenor Limerick Ecology Action,Inc to Memorandum & Order of Commission Dtd 890726.* Environ Benefits for Operating Unit 2 Outweigh Small Risk of Severe Accident ML20245F7291989-08-0808 August 1989 Affidavit.* Discusses Costs Incurred While Plant Inoperable. Allowance for Funds Used During Const,Security,Maint & Operational Costs Considered Proper for Calculating Costs for Delay ML20248D9241989-08-0707 August 1989 Memorandum & Order.* Extends Limerick Ecology Action Response Deadline to 890814 to Respond to Five Questions Re Severe Accident Mitigation Design Alternatives.W/Certificate of Svc.Served on 890807 ML20248D7871989-08-0303 August 1989 Correction for NRC Staff Response to Commission Questions.* Forwards Corrected Page 5 to NRC Response to Questions Filed on 890802,deleting Phrase by Nearly Factor 2.5 in Next to Last Line.W/Certificate of Svc ML20248D5391989-08-0202 August 1989 Affidavit of MT Masnik.* Advises That Author Prepared Response to Question 3 ML20248D7111989-08-0202 August 1989 Response of Intervenor Limerick Ecology Action,Inc to Memorandum & Order of Commission Dtd 890726.* Commission Order Fails to Provide Intervenor Adequate Time for Response & Should Therefore Be Revoked.W/Certificate of Svc ML20248D5671989-08-0202 August 1989 Affidavit of SE Feld.* Advises That Author Prepared Response to Question 5.W/Certificate of Svc ML20248D4971989-08-0202 August 1989 Joint Affidavit of Gy Suh & CS Hinson.* Advises That Authors Prepared Responses to Questions 1 & 4 ML20248D6451989-08-0202 August 1989 Affidavit.* Advises That Author Read Responses to Request for Comments by NRC & Knows Contents.W/Certificate of Svc ML20248D4721989-08-0202 August 1989 NRC Staff Response to Commission Questions.* Provides Info for Use in Commission Effectiveness Review of Plant Full Power Operation,Per Commission 890726 Memorandum & Order. Supporting Affidavits Encl ML20248D5981989-08-0202 August 1989 Response by Licensee Philadelphia Electric Co to Commission Request for Comments by Memorandum & Order Dtd 890726.* Licensee Requests Commission Issue Full Power OL for Unit 2 Conditioned Upon Outcome of Pending Litigation ML20248D5311989-08-0202 August 1989 Affidavit of Rj Barrett.* Advises That Author Prepared Response to Question 2 ML20245J1321989-07-27027 July 1989 Transcript of 890727 Meeting in Rockville,Md Re Facility Severe Accident Mitigation Issues.Pp 1-130.Supporting Info Encl ML20247N3261989-07-26026 July 1989 Transcript of 890726 Affirmation/Discussion & Vote in Rockville,Md on SECY-89-220 Re Order Requesting Info from Parties for Immediate Effectiveness Review of Full Power Authorization for Limerick Unit 2.Pp 1-4 ML20248D7331989-07-24024 July 1989 Second Rept of Parties & Request for Dismissal of Graterford Inmates Contention & Termination of Proceeding.* Requests Board to Enter Order to Terminate Proceeding Based on Parties Agreeing to Dismissal of Remaining Contention ML20247Q4621989-07-23023 July 1989 Response of Intervenor Rl Anthony to Answer of Philadelphia Electric Co (PECO) to Request for Hearing on PECO Application for Low Power Operation of Unit 2 & Stay of Any Operation in Keeping W/Us Circuit Court Remand Of....* ML20247B7261989-07-20020 July 1989 Notice of Appointment of Adjudicatory Employee.* Advises That H Vandermole Appointed to Advise Commission on Issues in Proceeding Re Severe Accident Mitigation Design Alternatives.W/Certificate of Svc.Served on 890720 ML20247B3821989-07-18018 July 1989 Memorandum & Order.* Orders That Severe Accident Mitigation Alternatives,Per Nepa,To Be Considered Include Containment Heat Removal,Core Residue Capture & Venting.Certificate of Encl.Served on 890719 ML20247B7641989-07-13013 July 1989 Motion of Intervenor,Limerick Ecology Action Inc,To Reconsider/Stay/Suspend/Revoke Order Authorizing Issuance of Low Power OL for Limerick 2.* Consideration of Accident Mitigation Alternatives Imperative.Certificate of Svc Encl 1997-08-05
[Table view] |
Text
.
4 00LXETEC
'JSNRC UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION -
ATOMIC SAFETY AND LICENSING BOARD '86 0CT 17 Pl2:32 BEFORE ADMINISTRATIVE JUDGES:
Helen F. Hoyt, Chairperson
~
GFF' r --
Dr. Richard F. Cole DCCXEi ,
3 Jerry Harbour
)
In the Matter of )
)
PHILADELPHIA ELECTRIC COMPANY ) Docket Nos. 50-352-O L ^
) 50-353-O L (Limerick Generating Station, )
Units 1 and 2) ) ,
)
APPE A R A NCES Robert M. Rader, Esq., and Nils N. Nichols, Esq., of. Conner & Wetterhahn, P.C.,
Washington, D.C., for Philadelphia Electric Company.
Benjamin 11. Vogler, Esq., and Joseph Rutberg, Esq., Washington, D.C. for the Nuclears Regulatory Commission.
Theodore G. Otto, III, Esq., Harrisburg, Pennsylvania, for the Coramonwealth of Pennsylvania.
Angus R. Love, Esq., for the Graterford Correctional Institution inmates.
Michael B. Ilirsch, Esq., Office of the General Counsel, Federal Emergency Management Agency, hashington, D.C., for FEM A.
PROPOSED FINDINGS OF FACT AND CONCLUSIONS OF LAW
- l. INTRODUCTION By order dated August 28, 1986, the Atomic Safety and Licensing Appeal Board reversed the Atomic. Safety and Licensibg Board's (Licensing Board) order of June 12, 1986 and its Fourth Partial Initial Decision, LBP-85-25 to the extent that they excluded the inmates' manpower mobilization contention. Shortly thereafter, the Licensing Board 8610240049 861016 ,
PDR ADOCK 05000352 l
O PDR l-
scheduled a hearing on September 22, 1986 regarding the manpower mobilization contention. Discovery was conducted by all parties, with witness lists being exchanged on September 12, 1986.
At the hearing held on September 22, 198.6, the Commonwealth of Pennsylvania presented the testimony of Richard A. Buell, who is District Manager, Network Technical Services for the Bell Telephone Company of Pennsylvania, and Charles H. Zimmerman, Superintendent, State Correctional Institution at Graterford (SCl-Graterford). The Graterford inmates presented the testimony of Richard T. Brown, Comm.unications Technician, AT&T Communications and William Miller, Manager of Switching Services, Bell Telephone Company of Pennsylvania. The Federal Emergency Management Agency (FEM A) presented the testimony of James R. Asher of FEMA.
The testimony of these witnesses and the exhibits admitted into evidence at the hearing provide ample evidence upon which to make a decision on the admitted contention.
Accordingly, below are the Commonwealth's proposed findings of fact and conclusions of law.
- 11. FINDINGS OF FACT The inmates' manpower mobilization contention alleges that "[t]here is no reasonable assurance that the call-up system to be utilized in the event of a nuclear emergency in order to mobilize the entire work force of State Correctional Institute (sic) at Graterford will achieve its designated purpose" Proposed Revised Contentions (May 13, 1985) at Page 2.
- 1. If an evacuation of the institution was necessary between the hours of 6:00 a.m and 10:00 p.m., there would be enough manpower at the institution to evacuate the inmates without additional manpower (Zimmerman, Tr. 21451-2, 21469, 21495-6).
- 2. During the 10:00 p.m. to 6:00 a.m. shift, approximately fifteen percent (15%)
of the total off-duty staff would need to be called in (Zimmerman, Tr. 21451, 21453).
4
- 3. SCl-Graterford has four (4) shif ts, 6:00 a.m. to 2:00 p.m., 2:00 p.m. to 10:00 p.m. and 10:00 p.m. to 6:00 a.m. There is also a shift that begins anywhere between 7:00 a.m. and 9:00 a.m. through 5:00 p.m. (Zimmerman, Tr. 21450-3).
- 4. The institution is almost like a little city during the 6:00 a.m. to 10:00 p.m.
shifts; and if the institution was locked down during these time periods, the additional staff necessary to operate the institution would be available to evacuate the institution according to the plan (Zimmerman, Tr. 21452).
5.- If additional manpower is necessary to evacuate the institution, all off-duty staff are sufficiently trained to assist in the evacuation since they have been trained in the care, custody and control of inmates (Zimmerman, Tr. 21.453). ,
- 6. If additional manpower was needed, the institution has an established call '
in procedure, which relies on commercial telephone lines. This procedure has always provided the institution with sufficient manpower (Zimmerman, Tr. 21454, 21462-3).
- 7. SCl-Graterford has sixty-six (66) available phone lines, ten (10) of these lines being switched in Philadelphia and a hot-line to the Pennsylvania State Police At Limerick (Zimmerman, Tr. 21456-7).
- 8. SCl-Graterford also has other means of either calling in the additional manpower or having the manpower provided from cther institutions (Zimmerman, Tr. 21461-7).
- 9. The institution has nineteen (19) telephone lines that work in the event of a power failure (Commonwealth Exhibit No.1; Zimmerman, Tr. 21473-490).
- 10. The call-up procedure will hilow the institution to meet the one to two (1-2) hour estimate for calling off-duty personnel and the two to three (2-3) hour estimate in adverse weather (Zimmerman, Tr. 21468).
- 11. Mr. Richard A. Buell, District Manager, Network Technical Services, Bell of Pennsylvania, has a Bachelor of Science in Civil Engineering from Lehigh University.
He also provides technical support for various organizations in the company, as far as
d technical matters concerning telephone network. He .has been employed by Bell of Pennsylvania or its predecessors for a little over thirty (30) years, and has an awareness of the ' telephone switching stations in the Commonwealth (Buell, Tr. 21386-7).
- 12. Mr. Buell could identify twenty-one (21) telephone lines from SCI-Graterford that go into the Collegeville central office, which is a switching station for the telephone company (Buell, Tr. 21388, 21390-1).
- 13. Ten (10) telephone lines from SCI-Graterford are switched at the Collegeville central office, ten (10) lines from Graterford go through the Collegeville central office, -
but are switched in Philadelphia (Buell, Tr. 21390-1).
- 14. One telephone line is a private line from SCI-Graterford to the Pennsylvania ,,
State Police. This line is not effected by an overload (Buell, Tr. 21391).
- 15. There could be more telephone lines coming from SCI-Graterford into the Collegeville central office, which Mr. Buell could not identify (Buell, Tr. 21392).
- 16. The telephone company engineers its telephone service for a dialtone to be provided durin.g the business hour to ninety-seven percent (97%) of our customers '.vithin i three (3) seconds (Buell, Tr. 21392-3).
1 17. An overload condition exists when the telephone company does not get dialtone to ninety-seven percent (97%) of the customers within three (3) seconds (Buell, Tr. 21431-2).
- 18. Even in an overload situation, all calls would be completed (Buell, Tr. 21421).
- 19. Telephone usage between the hours of 10:00 p.m. and 6:00 a.m. is normally ,
much lower than the load the telephone company would expect during the busy hours
[
(Buell, Tr. 21409-10).
- 20. During Hurricane Agnes, there were equipment failures, lines down and a j eentral office under water (Buell, Tr. 21405).
I
- 21. The Collegeville central office, as well as many of the central offices immediately contiguous to the Collegeville central office (Trooper, Centerville, i
4 4
Harleysville) are either currently served by a 5 ESS System or will be so served in the near future. The 5 ESS System is the state of the art for the company (Buell, Tr. 21406-7).
111. CONCLUSIONS OF LAW The Board has considered all proposed findings of fact and conclusions of law filed by the parties. We have also considered all of the testimony and exhibits submitted I
by the parties. Based upon a review of the entire record in this proceeding, the Board concludes that: ,
- 22. That there is a reasonable assurance that the call-up system in place which will be utilized in the event of. a nuclear emergency in order to mobilize manpower -
necessary to evacuate SCI-Graterford will achieve its designated purpose and, thus, complies with NUREG-0654 and 10 CFR 0 50.47(aX1).
IV. ORDER Pursuant to 10 CFR Q 2.760(a) of the Commission's Rules of _ Practice, this decision will constitute the final decision of the Commission forty-five (45) days from the date of issuance, unless an appeal is taken in accordance with 10 CFR I 2.762 or the Commission directs otherwise. See also 10 CFR 69 2.764 and 2.785 and 2.786.
Any party may take an appeal from this decision by filing a . Notice of Appeal within ten .(10) days af ter service of this decision. Each appellant must file a brief supporting its position on appeal within thirty (30) days after filing its Notice of Appeal (forty (40) days if the Staff is the Appellant). Within thirty (30) days after the period has expired for the filing and service of the briefs of all appellants (forty (40) days in the case of the Staff), a party who is not an appellant may file a brief in support of or in opposition to the appeal of any other party. A responding party shall file a single, responsive brief regardless of the number of appellant briefs filed. See 10 CFR 6 2.762(c).
i
QL ?,L il '
liMi' CERTIFICATE OF SERVICE
'86 0CT 17 R2:32 1 hereby certify that I have this day served a copy of the foregping document 00CXf.iji,,. . ; ,'yj' ulon the following by overnight delivery service, except as otherwise indicdtedM Robert M. Rader, Esquire Angus R, Love, Esquire ,
Conner and Wetterhahn, P.C. Montgor..ery County Legal Aid 1747 Pennsylvania Avenue 107 East Main Street Washington, D.C. 20006 Norristown, Pennsylvania 19401 eBPI Benjamin H. Vogler,- Esquire
- John L. Patten, Director Counsel for NRC Staff Pennsylvania Emergency Management Office of the Executive Agency Legal Director B-151 Transportation and Safety Building U.S. NRC Harrisburg, Pennsylvania 17120 Washington, D.C. 20555 Docketing and Service Section Michael B. Hirsch, Esquire Office of the Secretary Office of General Counsel U.S. N R C Federal Emergency Management Agency i Washington, D.C. 20555 500 C. Street, S.W., Room E40 Washington, D.C. 20472 l
l heodore G. Otto,111
/ Chief Counsel Pennsylvania Department of Corrections l
Dated: October 16, 1986