Other: ML19327A527, ML19327A533, ML19330B521, ML19330B523, ML19331B934, ML19336A759, ML19340B179, ML19344B508, ML19347C984, ML19347C997, ML19350A630, ML20053A188, ML20080J137, ML20080P638, ML20083D856, ML20083E087, ML20083H776, ML20084D339, ML20085B165, ML20092A427, ML20135G519, ML20137F772, ML20213G752, ML20214F390, ML20244B663, ML20244B666
|
MONTHYEARML19330B5211980-07-25025 July 1980 Responds to IE Bulletin 80-17,Suppl 2, Failure of 76 of 185 Control Rods to Fully Insert During Scram at Bwr. No Mod Required for Units 1 & 2 Vent Sys Since as-built Sys Satisfies Requirements of Bulletin Project stage: Other ML19330B5231980-07-25025 July 1980 Responds to IE Bulletin 80-14, Degradation of BWR Scram Discharge Vol Capability. Investigation to Determine How Frequently Scram Discharge Vol Vent & Drain Valves Should Be Tested Underway Project stage: Other ML19327A5331980-07-28028 July 1980 Responds to IE Bulletin 80-17.Provides Manual & Automatic Scram Test Results.Scram Discharge Vol Vent Lines Verified & Emergency Operating Procedure Changes Completed Project stage: Other ML19327A5271980-07-31031 July 1980 Responds to IE Bulletin 80-17 & Provides Manual Scram Test Results.Scram Discharge Vol Vents Lines Verified as Functional & Full Operator Training to Be Completed as of 800802.Recirculation Pump Trip Installed Project stage: Other ML19331B9341980-08-0505 August 1980 Responds to IE Bulletin 80-17, Failure of Control Rods to Insert During Scram at Bwr. Automatic Scram Performed & Scram Discharge Vol Responded Properly.Automatic Scram Test Results Enncl Project stage: Other ML19340B1791980-10-10010 October 1980 Responds to NRC Requesting Tech Spec Mods Re Scram Discharge Vol.Present Tech Specs Assume Control Drive Sys Operability & Scram Discharge Vol Piping Is Sized to Assure Complete Scram.Mods Will Not Increase Reliability Project stage: Other ML19344B5081980-10-14014 October 1980 Responds to Mar 1980 Comments Made at White House Issues Briefing session.NUREG-0625 Is Not Intended to Be Sole Basis for Judging Sites.Evacuation Plans Considered in Licensing Actions Leading to Cp.Foundation Will Be Evaluated Project stage: Other ML19336A7591980-10-24024 October 1980 Responds to 801001 Request Re Participation in Development of Scram Sys Design & Performance Criteria.Not Active Member in Subgroup Considering Criteria.Plans to Consolidate Reviews of Design Rather than Performing Separate Reviews Project stage: Other ML19341C7971981-02-26026 February 1981 Semiannual Rept,Plant Radioactive Effluent Releases,Jul-Dec 1980 Project stage: Request ML19347C9841981-02-26026 February 1981 Tech Spec Tables 3.6.3-1,3.7-1 & Page 3.7-20 for Primary Containment Isolation Valves Project stage: Other ML19347C9811981-02-26026 February 1981 Application for Amend to Licenses NPF-5 & DPR-57,submitted as Proposed Changes to Tech Specs Re BWR Scram Sys Design Project stage: Request ML19347C9971981-03-0404 March 1981 Submits Addl Info Re BWR Scram Discharge Sys Mods,Per 801001 Request.Mods Will Be Implemented as Needed to Result in Conformance to Owners Group Criteria by End of 1982 Provided Qualified Equipment Is Commercially Available Project stage: Other ML19350A6301981-03-0606 March 1981 Notifies That Util 801010 Commitments to BWR Scram Discharge Sys long-term Mods Do Not Satisfy NRC Criteria.Revised Tech Specs Must Be Proposed at Least 3 Months in Advance of Mod Completion Dates Project stage: Other ML20010E8921981-09-0101 September 1981 Forwards Franklin Research Ctr Request for Addl Info Re BWR Scram Discharge Vol long-term Mods.Info Requested within 45 Days of Receipt of Ltr Project stage: RAI ML19280B1321981-10-0101 October 1981 Responds to 810901 Request for Addl Info from Franklin Research Ctr Re Util 810226 Proposed Tech Spec Mods for Scram Discharge Vol.Util Will Submit Amend to Unit 1 Rod Block Setpoint & Surveillance Requirements Project stage: Request ML20244B6661982-01-13013 January 1982 BWR Scram Discharge Vol Long-Term Mods,Ga Power Co,Hatch Nuclear Plant,Unit 1, Technical Evaluation Rept Project stage: Other ML20244B6631982-01-13013 January 1982 BWR Scram Discharge Vol Long-Term Mods, Technical Evaluation Rept Project stage: Other ML20053A1881982-05-18018 May 1982 Requests Extension of 821231 Commitment Date for Installation of Qualified Level Transmitters in Scram Discharge Sys to 831231 Project stage: Other ML20085B1651983-06-24024 June 1983 Order Confirming Licensee Commitments to Install Mods to Scram Discharge Sys by 831231 Project stage: Other ML20080J1371983-09-19019 September 1983 Proposed Tech Spec Changes Re Scram Discharge Sys Project stage: Other ML20080J1161983-09-19019 September 1983 Application to Amend Licenses DPR-57 & NPF-5,changing Tech Specs to Reflect Mods to Scram Discharge Sys,As Required by NRC Project stage: Request ML20080P6381983-10-0303 October 1983 Requests That Re Proposed Tech Spec Changes Concerning Scram Discharge Sys Be Superseded by 830919 Submittal Project stage: Other ML20083E0061983-12-14014 December 1983 Suppl to 830919 Application to Amend Licenses DPR-57 & NPF-5,changing Tech Specs Re Scram Discharge Vol Closure Times Project stage: Request ML20083E0871983-12-14014 December 1983 Proposed Tech Spec Changes Re Scram Discharge Vol Closure Times Project stage: Other ML20083D8561983-12-20020 December 1983 Corrects Changing Tech Specs Re Scram Discharge Sys Operability.Outboard Scram Discharge Vol Vent & Drain Valves Close Vs Open within 5 After Closure of Inboard Valves Project stage: Other ML20083H7761983-12-22022 December 1983 Forwards Addl Info Re Requesting Substitution of Longer Values for Scram Discharge Vol Vent & Drain Valve Closure Times.Closure Times Proposed in Do Not Meet Acceptance Criteria in SER Project stage: Other ML20084D3391984-04-23023 April 1984 Submits Results of GE Review of 831222 Analysis of Scram Discharge Vol Vent & Drain Valve Closure Times in Excess of 30 S.Ge Does Not Concur W/Analysis.Closure Times Should Be Accepted as Is.Continued Plant Operation Justified Project stage: Other ML20092A4271984-06-14014 June 1984 Submits Schedule Requested in Re Implementation of Mods Resulting in Scram Discharge Vol Vent & Drain Valve Closure Times Which Meet GE Requirements of 30 S.Tests Will Be Performed to Determine Extent of Mods Project stage: Other ML20135G5191985-09-13013 September 1985 Proposed Tech Spec,Adding 60 Scram Discharge Vol Vent & Drain Valve Closure Time Requirement Project stage: Other ML20135G5101985-09-13013 September 1985 Application for Amends to Licenses DPR-57 & NPF-5,adding 60 Scram Discharge Vol Vent & Drain Valve Closure Time Requirement to Tech Specs.Fee Paid Project stage: Request ML20136J4051985-11-18018 November 1985 Responds to Request for Addl Info Re 850913 Application for Amends to Licenses DPR-57 & NPF-5,allowing 60 Closure Time Limit for Scram Discharge Vol Vent & Drain Valves.Figure 6.2.2 from GE NEDO-24342 Re Scram Sys Pipe Breaks Encl Project stage: Request ML20137F3011986-01-0606 January 1986 Rev to 850913 Application for Amend to Licenses DPR-57 & NPF-5,revising Tech Spec to Provide Value of 45 Closure Time Requirement for Scram Discharge Vol Vent & Drain Valves for Unit 1 Project stage: Request ML20137F7721986-01-0606 January 1986 Proposed Tech Spec Changes Providing Value of 45 Closure Time Requirement for Scram Discharge Vol Vent & Drain Valves Project stage: Other ML20204A2781986-04-28028 April 1986 Forwards Request for Addl Info Re Request for Rev to Tech Specs to Reflect Addition of Closure of Containment Purge & Vent Valves on High Containment Radiation Signal.Response Requested within 60 Days Project stage: RAI ML20211G6301986-06-12012 June 1986 Forwards Request for Addl Info Re Util Listed Requests to Amend Tech Specs to Provide Closure Time Requirements for Scram Discharge Vol Vent & Drain Valves.Info Requested within 45 Days of Ltr Receipt Project stage: RAI ML20210T7521986-09-23023 September 1986 Responds to NRC 860612 Request for Addl Info Re Scram Discharge Vol Vent & Drain Valve Closure Times Project stage: Request ML20213G7521986-11-11011 November 1986 Forwards Bechtel Calculation Sheets Re CRD Scram Discharge Header Drain Piping Project stage: Other ML20214F3901987-05-13013 May 1987 Amends 136 & 75 to Licenses DPR-57 & NPF-5,respectively, Providing Closure Time Requirements for Scram Discharge Vol Vent & Drain Valves Project stage: Other ML20214F3951987-05-13013 May 1987 Safety Evaluation Supporting Amends 136 & 75 to Licenses DPR-57 & NPF-5,respectively Project stage: Approval 1983-10-03
[Table View] |
Similar Documents at Hatch |
|---|
|
Text
i y
7,,
Jun2 12,' 1986 Docket Nos. 50-321/366
~
Mr. J. T. - Beckham, Jr.
Vice President - Nuclear Generation Georgia Power Company P.O. Box 4545.
Atlanta, Georgia - 30302
Dear Mr. Beckham:
We~are reviewing the request to revise the Hatch Unit l'and Unit 2 Technical Specifications to provide closure time requirements for scram ' discharge volume vent and drain valves as submitted by your letters of December _ 14, 1983 and
. supplemented or revised by letters dated December 20 and December 22, 1983, April 23 and June 14, 1984, September 13 and November 18, 1985 and January 6, 1986.
In order to complete this review, we need the additional information-described in the enclosure. You are requested to provide a written response, submitting the requested -information, within 45 days of receipt of this letter. -
The reporting and recordkeeping requirements of this letter affect fewer than ten respondents; therefore, OMB clearance is not required ~under P.L.96-511.
Sincerely, Original signed by/
George W. Rivenbark, Project Manager BWR Project Directorate #2 Division of BWR Licensing
Enclosure:
Request for Additional Information cc w/ enclosure:
See next page Distribution: Docket:FjliiG GRivenbark NRC& LPDRs EJordan JPartlow PD#2 File BGrimes RBernero ACRS(10)
SNorris OELD DMuller rk;eh 6/// /86
/ / ///86
(, / t V86 4 /p /86 8606200037 86'0612 PDR ADOCK 05000321 P
POR
i l
' Mr. J. T. Beckham, Jr.
Edwin 1. Hatch Nuclear Plant, Georgia Power Company Units Nos. I and 2 cc:
Bruce W. Churchill Esquire Shaw,Pittman,Potis&Trowbridge 1800 M Street, N.W.
Washington, D.C.
20036 Mr. L. T. Gucwa Engineering Department Georgia Power Company P. O. Box 4545 Atlanta, Georgia 30302
~
Mr. H. C. Nix, Jr., General Manager o
Edwin I. Hatch Nuclear Plant Georgia Power Company P. O. Box 442 Baxley, Georgia 31513 Mr. Louis B. Long Southern Company Services Inc.
~
P. O. Box 2625 Birmingham, Alabama 35202 Resident inspector U.S. Nuclear Regulatory Comission Route 1, P. O. Box 279 Baxley, Georgia 31513 Regional Administrator, Region II U.S. Nuclear Regulatory Comission, 101 Marietta Street, Suite 3100 Atlanta, Georiga 30303 Mr. Charles H. Badger Office of Planning and Budget Room 610 270 Washington Street, S.W.
Atlanta, Georgia 30334 Mr. J. Leonard Ledbetter, Comissioner Department of Natural Resources 270 Washington Street, N.W.
Atlanta, Georgia 30334 Chairman Appling County Comissioners County Courthouse Baxley, Georgia 31513
REQUEST FOR ADDITIONAL INFORMATION BY THE OFFICE OF NUCLEAR REACTOR REGUEATION SCRA N SC N OLUME VENT & DRAIN VALVE CLOSURES HATCH UNITS 1 & 2 GEORGIA POWER COMPANY 1.
Your letter of June 14, 1984 indicates that extensive modifications would be required to meet'a 30 second closure time for the Scram Discharge
' Volume (SDV) vent and drain valves. 'Your letter of September 13, 1985 seems to indicate that the necessary plant modifications have been made.
If they have been made, then we do not understand why you can't agree with the 30 second closure limit.
If they have not been made, quantify your estimate of " extensive modifications":
For example, approximate amount of additional piping, extent of modification labor (in man-hours or dollars), length of time for completing the modifications.
~
2.
Your andlysis of the valve closure times seems to be predicated on the assumption that the water level in the SDV during normal operation prior to a scram is zero, i.e., the volume does not contain water. However, considerations of drainage piping flow resistance due to friction, as well as a postulated single failure (such as a closed drain valve), could lead to a non-zero water level within the SDV.
In view of the above, indicate the maximum potential water level that could accumulate within
~
the SDV prior to a scram.
3.
Your letter of November 18, 1985 provides stall flow measurements made over two full cycles of operation. This information was used as a basis for establishing a maximum post-LOCA CRD leakage. Provide justification that the stall flow value and hence your estimate of maximum post-LOCA CRD seal leakage will'not be exceeded.
Include a discussion of the error bounds of the data that relates the sta11' flow to post-LOCA flow.
4.
The General Electric report " Relaxation of Scram Discharge Volume Vent and Drain Valve Closure Times" dated December 1984 and your letter of December 22, 1983 list the Unit 1 SDV capacity as 482 gallons. Your i
letter of January 6,1986 lists SDV capacities of 549 gallons for Unit 1 and 636 gallons for Unit 2.
Explain these differences and provide 1.
detailed information (e.g. calculations) that will permit verification of the "as built" volume of the SDV for each unit.
i L