ML20211B105

From kanterella
Jump to navigation Jump to search

Informs That Organizational Chart in Revised Security Plan Is Inaccurate Due to Realignment of Nuclear Operating Div Organizational Structure on 970903.Will Submit Current Structure by 971103
ML20211B105
Person / Time
Site: Byron  Constellation icon.png
Issue date: 09/12/1997
From: Johnson I
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
TAC-M65282, TAC-M65283, NUDOCS 9709250064
Download: ML20211B105 (1)


Text

Commonweahh 1.dmn Company 125 South Clark Strcct P O (kix 767 y hicah,11.606900767 Saptember 12,1997 CERTIFIED MAIL U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington DC 20555

Subject:

Byron Nuclear Power Stations Units 1 and 2 Byron Sta tion Security Plan NRC Docket Nos. 50-454 & 50-455 TAC Nos. 65282/65283 in July of this year, Comed revised its Security Organization to reflect a change from an on-site reporting function to an off site centralized organization.

The Security Plan was revised and was in the process of being submitted to the NRC per the requirements of 10CFR 50.54(p). On September 3,1997 Comed realigned its Nuclear Operating Division's organizational structure to continue its focus on operational safety and performance improvements.

As a result, the Organizational Chart in the Security Plan was inaccurate and required a revision to properly depict this new realignment. While the July 1997 revision identified an "off-site" reporting structure, the September realignment will require a " title block" char:ge only, We have concluded that both these changes do not decrease the Safeguards effectiveness of the Security Plan and to submit an Organizational Structure that was incorrect would not be prudent. Therefore, we will submit the current structure to you by November 3,1997.

Additionally, the Vehicle Barrier Systems (VBS) drawing, #5A that was revised to depict the "as built" configuration which had been reviewed and approved by NRC Regional and NRR person:tel was scheduled to be submitted with the July Revision.

This drawing will also be included with the submittal that will be sent to you by November 3,1997.

Sincerely,

//dd eU mc

()

Irene M. Johnsol Licensing Operations Director cc:

A. B. Beach g' ';P],ggliJillig'glg f

lgl

,l.

lill.Il 9709250064 970912 PDR ADOCK 05000454 F

PDR A Unkom Company

_