Letter Sequence Approval |
|---|
TAC:43754, (Approved, Closed) TAC:43755, (Approved, Closed) TAC:47143, (Approved, Closed) TAC:48071, (Approved, Closed) TAC:48072, (Approved, Closed) TAC:48748, (Approved, Closed) TAC:48749, (Approved, Closed) TAC:57415, (Approved, Closed) TAC:57416, (Approved, Closed) TAC:61626, (Approved, Closed) TAC:61627, (Approved, Closed) |
Results
Other: ML19343C564, ML20033D130, ML20054E507, ML20071H924, ML20079P712, ML20082J783, ML20091B733, ML20093E411, ML20096F812, ML20096F838, ML20106D353, ML20114B418, ML20262H555, ML20262H558, ML20262H561, ML20262H563, ML20262H567, ML20262H569, ML20262H571, ML20263B925, ML20263B927, ML20263B930, ML20263B932
|
MONTHYEARML20262H5581973-12-14014 December 1973 Details:1,2,17 & 21 Thru 27,32,33 & 34. Sheet 2 of 3 Project stage: Other ML20262H5611973-12-14014 December 1973 Details:3,13,19,24,28,35 & 36. Sheet 3 of 3 Project stage: Other ML20262H5551973-12-14014 December 1973 Watertight Door Assy. Sheet 1 of 3 Project stage: Other ML20262H5671975-06-18018 June 1975 4 Ft X 8 Ft Opening Lhrb Door & Frame Assembly. Sheet 1 of 3 Project stage: Other ML20262H5691975-06-18018 June 1975 Details 1 & 6. Sheet 2 of 3 Project stage: Other ML20262H5711975-06-18018 June 1975 Details 2,3,4 & 5. Sheet 3 of 3 Project stage: Other ML19343C5641981-03-19019 March 1981 Submits Comments & Requests for Certain Exemptions from Final Version of 10CFR50.48,App R,Per 810220 Request Project stage: Other ML20037D0201981-05-18018 May 1981 Forwards Supplemental Response to 10CFR50.48,App R Re Fire Protection Rule,Per NRC 810220 Request.Also Forwards Electrical Circuit Schedules,Circuit & Raceway Data & 210 Oversize Drawings.Aperture Cards Are Available in PDR Project stage: Supplement ML20038A9581981-11-12012 November 1981 Requests Extension of Schedule for Emergency Lighting Installation Until 811204.Class II Fee Encl Project stage: Other ML20033D1301981-11-18018 November 1981 Forwards Amend 9 to Evaluation of Fire Protection Plan. Control Rooms Have Been Modified to Enhance Operator Environ & Reduce Operator Stress & Fatigue Project stage: Other ML20039B8431981-12-0707 December 1981 Exemption Granting Extension of Completion Date of Emergency Lighting Installation from 811117 to 1204 Project stage: Other ML20049J3291982-03-0303 March 1982 Requests Extension to 820701 for Submitting Design Info Re Implementation Schedule of 10CFR50.48 & Encl 2 of NRC Project stage: Other ML20052F4801982-05-0303 May 1982 Exemption from Fire Protection Rule Schedular Requirements of 10CFR50.48(c).Exemption Subj to Listed Conditions. Clarification of Generic Ltr 81-12 & Criteria for Evaluating Exemption Requests Encl Project stage: Approval ML20054E5071982-06-0202 June 1982 Requests Verification of Exemption of Station Battery Room water-tight Doors from Having 3-h Fire Rating Project stage: Other ML20054L8131982-07-0101 July 1982 Forwards Supplemental Responses to 10CFR50.48 & App R to 10CFR50 & Engineering Planning & Mgt,Inc Rept, DC Essential Cabinet Analysis, Per NRC 810220 Request (Generic Ltr 81-12) Project stage: Supplement ML20262H5631982-08-20020 August 1982 Installation of PR2905-4 3 Ft 9 & 1/2 Inches X 7 Ft 1/2 Inch Door & Frame Assy. Sheet 1 of 1.No Revision Date Project stage: Other ML20265A8161982-09-22022 September 1982 Edwin I Hatch Nuclear Plant - 1 & 2 Fire Protection Piping River Intake Structure Project stage: Other ML20070V7991983-02-14014 February 1983 Requests Meeting on or After 830329 W/Nrr to Appeal for Reconsideration of NRC Proposed Denial of App R Exemption Request.Addl Info Forthcoming to Clarify 820701 Submittal Project stage: Meeting ML20073S1721983-04-28028 April 1983 Clarifies Requests for Exemptions from 10CFR50.48 & App R Requirements in Response to NRC Request at 830330 Meeting. Rev to 820701 Response to Be Submitted by 830530 Project stage: Meeting ML20071H9241983-05-19019 May 1983 Submits Info on Compliance W/Branch Technical Position 9.5-1 Re Qualification of Fire Protection Engineers. Qualification Requirements Met Through Maint of Staff at Affiliated Svc Company,Southern Co Svcs,Inc Project stage: Other ML20023D7611983-05-27027 May 1983 Forwards Revised Response to 820701 Requests for Exemption from 10CFR50.48 & App R Requirements,Per 830330 Request.Rev Reflects Compliance w/10CFR50.48 & App R Requirements & Responds to 830120 Draft SER Concerns Project stage: Draft Other ML20024A3861983-06-14014 June 1983 Forwards Addl Info to Justify 820701 10CFR50.48 & App R Schedule Exemption Requests Discussed at 830330 Meeting. Plan Being Developed to Complete Maint & Design Changes. W/Two Oversize Drawings.Aperture Cards Available in PDR Project stage: Meeting ML20263B9301983-08-18018 August 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 2 of 5 Project stage: Other ML20263B9251983-11-0707 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 4 of 5 Project stage: Other ML20263B9271983-11-0707 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 3 of 5 Project stage: Other ML20263B9321983-11-14014 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 1 of 5 Project stage: Other ML20082D3421983-11-16016 November 1983 Forwards Addl Info Justifying Three Requests for Exemption from 10CFR50.48 & App R as Discussed in 830330 Meeting.Rev to 820701 Response Will Be Submitted by 831130 Project stage: Meeting ML20082J7831983-11-30030 November 1983 Forwards Replacement Pages to Re Clarification of App R Exemption Requests,Reflecting Revised Sections of 820701 Response to 10CFR50.48 Project stage: Other ML20083D7541983-12-20020 December 1983 Forwards Revised Pages for Insertion Into 830701 Request for Exemption from 10CFR50.48 & 10CFR50,App R Requirements Re Sprinkler Head/Nozzle & Detector Placement Project stage: Request ML20083D7721983-12-21021 December 1983 Forwards Payment of Fee Required for Review of 810319 Submittal on Safe Alternate Shutdown & Request for Schedular Exemption from Installation of Emergency Lighting Project stage: Request ML17255A6241984-01-16016 January 1984 Forwards App R Alternative Shutdown Sys. New Shutdown Approach Provides Fewer Mods & Allows Phased Implementation as Opposed to Installation of Required Dedicated Shutdown Sys Project stage: Request ML20079P7121984-01-24024 January 1984 Submits Info Documenting Addl Considerations of Projected Phased Improvement in Fire Protection & Mitigating Factors for Areas Unmodified During Extended Implementation Period. Tentative Completion Dates for App R Mods Encl Project stage: Other ML17255A6941984-02-29029 February 1984 Summary of 840222 Meeting W/Util & Bechtel Re Proposed App R Exemption Requests & Alternative Shutdown Sys.Meeting Agenda & List of Attendees Encl Project stage: Meeting ML20084L4461984-04-18018 April 1984 Safety Evaluation Supporting Util 820701 Requests for Exemption from Requirements of App R to 10CFR50 & Approval of Deviations from Several NFPA Codes Per Installation & Maint of Fire Protection Sys Project stage: Approval ML20084L4301984-04-18018 April 1984 Exemption from Requirements of App R to 10CFR50 Re Licensee Alternate Fire Protection Configuration for East Corridor, Control & Turbine Bldgs & Condensate Pump Area Project stage: Approval ML17254A7601984-05-10010 May 1984 Exemption from Schedular Requirements of 10CFR50.48(c)(4) to Extend Implementation of Alternative Shutdown Sys Until Startup from 1986 Refueling Outage Project stage: Approval ML20091B7331984-05-25025 May 1984 Notifies of Commitment to Meet on fire-area-by-fire-area Basis,Either Item 1 or 2 & 3 for Period of Time from Expiration of 10CFR50.48 Schedule Allowance Until Area Complies W/Paragraphs III.G.2 & III.G.3 of 10CFR50,App R Project stage: Other ML20197G5581984-06-0808 June 1984 Requests Addl Info on App R Implementation,Needed to Respond to 840525 Request for Schedular Exemption.Proposed Schedules Appear Acceptable Project stage: Approval ML20096F8121984-09-0404 September 1984 Requests Notification of Determination Re Acceptability of Kaowool as Fire Barrier Project stage: Other ML20096F8381984-09-0404 September 1984 Forwards Proposed Specific Compensatory Measures to Support 840525 Requested 10CFR50.48 Schedular Exemptions for nonoutage-related App R Mods,Per 840608 Request Project stage: Other ML20093E4111984-10-0202 October 1984 Proposes Establishment of Roving Fire Watch to Pass Through Listed Sections of Control & Reactor Bldgs as Compensatory Measures to Support Schedular Extension of App R Mods Project stage: Other ML20265A8211984-10-0404 October 1984 Intake Structure Pumps Project stage: Other ML20265A8261984-10-0404 October 1984 As Built Isometrics for Intake Structure Pumps Project stage: Other ML20106D3531984-10-19019 October 1984 Requests Exemption from 10CFR50.48(c) to Allow Extension Until 861130 of Implementation Schedule for Listed App R Related Mods Which Can Be Implemented During Nonoutage Period Project stage: Other ML20107F1811984-10-26026 October 1984 Provides Basis for Request for Exemption from 10CFR50.48 Requirements Re Implementation of non-outage Related 10CFR50,App R Mods.Fire Protection Enhancement Program Cannot Be Implemented within Expected Time Frame Project stage: Request ML20101E3731984-12-20020 December 1984 Submits Specific Info Re Compensatory Measures for nonoutage-related App R Mods Not Completed within 10CFR50.48 Time Frame,In Support of 841002 Request for Extension of Schedule to Complete Listed Mods Project stage: Request ML20215F7371984-12-26026 December 1984 Rev 1 to Administrative Control Procedure 40AC-FPX01-0, Fire Protection Program. Portions of Procedures 34AB-OPS-056-1S & 34AB-OPS-056-2S Encl Project stage: Other ML20114C0021985-01-10010 January 1985 Environ Assessment & Finding of No Significant Impact Re Util 840904 Request for Schedular Deferment from 10CFR50, App R,Section Iii.G for Fire Protection Equipment Used for Safe Shutdown to 861130.EIS Unwarranted Project stage: Approval ML20114B8481985-01-16016 January 1985 Exemption from Requirements of 10CFR50.48(c) to Extend Deadline for Completion of Fire Protection Mods Not Requiring Plant Shutdown Until 861130 Project stage: Approval ML20114B4181985-01-17017 January 1985 Responds to 850116 Order & Provides Rev to Interim Mitigation Factors for Nonoutage Related App R Mods,Per 850117 Telcon Project stage: Other 1983-04-28
[Table View] |
Exemption from Requirements of 10CFR50.48(c) to Extend Deadline for Completion of Fire Protection Mods Not Requiring Plant Shutdown Until 861130| ML20114B848 |
| Person / Time |
|---|
| Site: |
Hatch  |
|---|
| Issue date: |
01/16/1985 |
|---|
| From: |
Case E Office of Nuclear Reactor Regulation |
|---|
| To: |
GEORGIA POWER CO. |
|---|
| Shared Package |
|---|
| ML20114B850 |
List: |
|---|
| References |
|---|
| TAC-43754, TAC-43755, TAC-47143, TAC-48071, TAC-48072, TAC-48748, TAC-48749, TAC-57415, TAC-57416, TAC-61626, TAC-61627, NUDOCS 8501290561 |
| Download: ML20114B848 (5) |
|
Similar Documents at Hatch |
|---|
|
Text
-
1 7590-01 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of
)
)
GEORGIA POWER COMPANY, ET AL
)
Dockets Nos. 50-321
)
and 50-366 (Edwin I. Hatch Nuclear Plant,
)
Units Nos. I and 2)
)
EXEMPTION-I.
The Georgia Power Company (GPC or the licensee) and three other co-owners are the holders of Facility Operating Licenses Nos. DPR-57 and NPF-5 which authorize operation of the Edwin I. Hatch Nuclear Plant, Units 1 and 2 (Hatch or the facilities) at steady state reactor power levels not in excess of 2436 magawatts thermal for each unit. The facilities are boiling i
water reactors located at the licensee's site in Appling County, Georgia.
The licenses are subject to all rules and regulations of the Nuclear Regulatory Comission (the Commission).
I II.
Subsection (c) of 10 CFR 50.48 requires that fire protection modifications for which plant shutdown is not required (other than alternate l
shutdown capability) be completed nine months after the effective date of i
l Appendix R.
For the items covered by this exemption, the licensee was able totakeadvantageofthe"tollingprovision," subsection (c)(6),thereby commencing the nine-month period upon issuance of the staff Safety Evaluation dated April 18, 1984. The deadline for these modifications was therefore January 18, 1985.
85012go561850116 DR A OCK 0500032 p
7590-01 In a submittal dated September 4, 1984, supplemented by letters dated October 2, 1984, October 19, 1984, October 26, 1984, and December 20, 198a, the licensee requested an exemption from the schedular requirements of 10 CFR 50.48(c) which would extend the deadline from January 18, 1985, to November 30, 1986, for installation of fire protection modifications in certain areas of Units 1 and 2 for which plant shutdown is not required in order to install the modifications. The proposed exemption is needed since the licensee has ine'!cated that the installation of the non-outage related fire protection modifications in these areas of Units 1 and 2 cannot be completed on the schedule stated in 10 CFR 50.48(c) for the following reasons:
(1) The magnitude of the overall fire protection enhancement program at plant Hatch is large and has a projected cost of 25 million dollars (excluding the alternate shutdown system for the control room / cable spreading room fire).
(2) Currently, extensive redesign and modifications of safe shutdown related equipment and cables is underway in response to equipment qualification, operational safety enhancement and plant reliability i
improvement projects. These projects are interdependent with the fire protection program and the design for Appendix R cableway barriers must, in many cases, follow the final design of the equipment qualification project.
(3) Design sequences of the Appendix R modifications are complex and the final bill of materials and specifications for the bidding of installation contracts cannot proceed until the design is near its l
l I
7590-01
- final stages.
Following design, implementation must await rerouting of cables from Appendix R or equipment qualification modifications.
The first of these reasons, the overall extent and cost of the fire protection program at Hatch, is not by itself an acceptable basis for extension of the schedule. Based on the information provided, the Hatch program is comensurate with programs at other facilities both in extent and cost. This Exemption is therefore not based on this factor. The second and third reasons, having to do with the interrelationship between non-outage-related and outage-related work and the inability to perfonn certain tasks before a final design has been completed, are acceptable bases on which a schedule
~
extension can be granted.
The licensee indicated that in each area for which schedular exemptions are requested, the vulnerable systems will be protected by one of the following means:
(1) a fire watch; (2) automatic fire detection and fire suppression systems; (3) complete, nonrombustible fire barriers or e combination of (2) and (3).
In those locations where a fire watch will be provided, an individual will be present to detect and respond to any fire emergency. This provides reasonable assurance that a fire will be discovered in its initial stages before significant damage occurs and will be suppressed manually by either the fire watch or the plant fire brigade. Under these circumstances, fire damage will be limited, and no loss of safe shutdown capability should occur.
l
7590-01,
In several locations, the licensee has proposed to install a complete
. noncombustible fire barrier to protect one shutdown division.
If a fire were to occur,.the existing fire detection systems or a plant operator would
+
detect a fire and summon the fire brigade. One shutdown division would be 1
protected by the barrier until fire extinguishment was effected.
Consequently, the Comission's staff has reasonable assurance that safe shutdown could be achieved and maintained via the undamaged shutdown division.
i Based on the considerations discussed above, the Comission concludes that the licensee has provided reasonable and acceptable interim post-fire safe shutdown capability or interim fire protection measures to support the exemption request.
,III.
Accordingly, the Comission has determined that, pursuant to 10 CFR 50.12(a), an exemption as requested by the licensee's letter of September 4, i
1984, and supplemented by letters dated October 2, 1984, October 19, 1984, October 26, 1984, and December 20, 1984,' is authorized by law and will not endanger life or property or the common defense and security and is otherwise l
in the public interest. The Comission hereby grants an exemption from the i
requirements of 10 CFR 50.48(c) to extend the deadline for completion of fire protection modifications not requiring plant shutdown at the Edwin I.
Hatch Nuclear Plant, Units 1 and 2, until November 30, 1986, for each Unit.
i
7590-01
, Pursuant to 10 CFR 51.32, the Commission has determined that the issuance of the exemption will have no significant impact on the environment (50 FR 2113).
This Exemption is effective upon issuance.
FOR NUCLEAR REGU RY COMMISSION
'0%
Edson G. Case, Acting Director Office of Nuclear Reactor Regulation Dated at Bethesda, Maryland this 16th day of January 1985.
4 f
e v
w