Requests Exemption from 10CFR50.48(c) to Allow Extension Until 861130 of Implementation Schedule for Listed App R Related Mods Which Can Be Implemented During Nonoutage Period
ML20106D353
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 10/19/1984
From: Gucwa L
GEORGIA POWER CO.
To: Stolz J
Office of Nuclear Reactor Regulation
References
NED-84-523, TAC-43754, TAC-43755, TAC-47143, TAC-48071, TAC-48072, TAC-48748, TAC-48749, TAC-57415, TAC-57416, NUDOCS 8410250105
Download: ML20106D353 (4)


Text

-

e.*

g

Georgia Power Company 333 Piedmont Avenue

' Atlanta, Georgia 30308 -

Telephone 404 5264526 Mail.ng Address:

Post Oftce Box 4545 Atlanta, Georgia 30302 h

GeorgiaPower L T. Gucwa the southem electre system i~

. Manager Nuclear Engineenng and Chief Nuclear Engineer October 19, 1984 Director of Nuclear Reactor. Regulation Attentica: Mr.-John F. Stolz, Chief Operating Reactors Branch No. 4 Division of Licensing U. S. Nuclear Regulatory Ccratission Washington, D. C.

20555 NRC DOCKERS 50-321, 50-366

' OPEPATING LICENSES DPR-57, NPF-5 EDWIN I. HATCH NUCLEAR PIANT UNITS 1, 2 SCHEDULER EXDFFIONS FOR NON-OUTAGE-REIATED APPENDIX R MODIFICATIONS Gentlemen In previous ~ correspondence Georgia Power Company (GPC) has discussed a proposed scheduler exemption for implementation of Appendix R non-outage related modifications.

In that correspondence we proposed to meet, on a

~

fire area' by-fire area basis, items of mitigation for the period of time from expiration of the 10 CFR 50.48 schedule allowance until the specific modifications in fire areas are complete. GPC herein restates our scheduler exemption request in order to provide a more clear definition of our need.

GPC requests an exemption to the provisions of 10, CFR 50.48(c) to allow an extension to November 30, 1986, of the implementation schedule for the Appendix R-related modifications identified in the "Edwin I.

Hatch Nuclear Plant Response to 10 CFR 50.48 and Appendix R" listed below which can be implemented 'during a non-outage period but which, as part of the total integrated Appendix R modification schedule, can not be completed in the time frame allowed by regulation.

These modifications are grouped by fire areas as identified in our July 1,

1932 suhnittal and subsequent amendments.

Fbr clarity, other modifications identified in that submittal which have been determined to require a plant outage to complete are not listed:

4.1.1 4160-V Transformer Room - Unit 1 o

Wrap conduit ESS-II-477 with 1-h barrier 8410250105 841019 PDR ADOCK 05000321 gh F

PDR

- - 'll

u -

n 1.

Director of-Nuclear Reactor Regulation-U. S. Nuclear' Regulatory Commission

, Washington, D. C.-

20555-October 19, 1984 Page 2 4.1.2 West 600-V Switchgear Ibom - Unit 1 o

-Wrap conduit ESS-II-477 with 1-h barrier o -

Upgrade west wall to 3-h barrier 4.1.4

- Control' Building Working Floor el 112 ft - Unit 1 Wrap raceway R25-S037-ES4-M14 with 3-h barrier o-4.1.5 Reactor Building North of Column Line R7 - Unit 1 o

. Install detection on 158 ft elevation and additional

. detectors associated with the water curtain on-the 130 ft elevation Wrap safe shutdown-related cables in 20 ft sprinkler zone o

along R7 on elevations 130 ft and 158 ft

~

4.1.6 Reactor Building South of Colunn Line' R7 - Unit 1 Wrap cxmduit ESS-II-3645 ~with 1-h barrier o

Wrap conduit ESS-II-3648 with 1-h barrier o

Wrap conduit ESS-I-3838 with 1-h barrier o

4.1.7.

. West DC Switchgear Room - Unit 1 Upgrade wall between switchgear room.and oil conditioner i

o rocan to 3-h barrier A

4.2.2 Control Building Health Physics Area - Unit 2 o

Extension of sprinkler systems to cover trays 200A801, 2CRA801, and 2CUA701

-4.2.4 Control Building Oil Conditioner Room - Unit 2 o

Wrap raceway 2E22063 with 1-h barrier Wrap-raceway 2E22064 with 1-h barrier o

Upgrade wall to 3-h fire rating o

- _,. - - _ _... -. _ _ _.. _ _ _ _. ~ _, _ _. _ _. _.

n

~..

5

-Director of Nuclear Reactor Regulation U. S. Nuclear Regulatory Comission Washington, D. C.

20555 October 19, 1984 Page 3 4.2.6 Reactor Building North of Column Line R19 - Unit 2 o'

Install sprinkler system on elevation 158 ft o

Install detection system on elevation 158 ft 4.2.9 Turbine Building East Cableway - Unit 2 o

Wrap the following conduits with 1-h barrier

2CKA701, 2CLA701, 2CMA701, 2E12076, 2E12082, 2E12084,
2E12085, 2E22824, 2MR2543, 2MR2544, and 2CDAB01 4.2.10 Diesel Building Switchgear Ibom 2G - Unit 2 o

Wrap raceway 2ESB170 with.1-h barrier o

wrap raceway 2ESB168 with 1-h barrier o

Wrap raceway 2ESB167 with 1-h barrier 4.3.2 Control Building Corridor - Common o

' Wrap the following raceways with 1-h barrier:

Unit 1 Unit 2

'n08-01 TEJ8-02 TEAB-03 2CFA801 TEA 8-04 TEIB-01 T m8-03 2CZA801 TML8-01 TEB8-02 TEH8-01 2CZB801 Ts8-03 TEB8-04 T mB-02 ESS II-477 TEB8-01 o

Extend sprinkler system to provide full coverage 4.3.3 RPS and Vertical Cable Chase Ibms - Common o

Wrap raceway ESS-I-499 with 1-h barrier o

Install 3-h fire-rated doors to separate RPS rooms from cable chase i

l

a

-Director of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C.

. 20555 October 19, 1984 Page 4 In our letter NED-84-444 (dated September 4,1984) implementation dates of October 15, 1984 for Unit 2 and the end of the current refueling outage for Unit 1 were specified for the proposed interim compensatory measurcs.

However, 10 CFR 50.48 allows nine conths for implementation of non-outage related. modifications.

Therefore, GPC.hereby revises the planned implementation date for the interim compensatory measures cited in that letter and in NEIN34-518 (dated October 2, 1984) to nine months following

the issuance of the NRC approval of our requested technical exemptions, that is January 14, 1985.

With this subnittal, GPC requests that our proposed scheduler exemption be granted by NRC. The staffs of GPC and its consultants are available for additicmal discussion of this exemption, should the NRC so desire.

Should you have any questions in this regard, please contact this office.

Yours very truly,

[ " Q -= =

L. T. Gucwa WE:eb Enclosure xc: