Other: ML19343C564, ML20033D130, ML20054E507, ML20071H924, ML20079P712, ML20082J783, ML20091B733, ML20093E411, ML20096F812, ML20096F838, ML20106D353, ML20114B418, ML20262H555, ML20262H558, ML20262H561, ML20262H563, ML20262H567, ML20262H569, ML20262H571, ML20263B925, ML20263B927, ML20263B930, ML20263B932
|
MONTHYEARML20262H5581973-12-14014 December 1973 Details:1,2,17 & 21 Thru 27,32,33 & 34. Sheet 2 of 3 Project stage: Other ML20262H5611973-12-14014 December 1973 Details:3,13,19,24,28,35 & 36. Sheet 3 of 3 Project stage: Other ML20262H5551973-12-14014 December 1973 Watertight Door Assy. Sheet 1 of 3 Project stage: Other ML20262H5671975-06-18018 June 1975 4 Ft X 8 Ft Opening Lhrb Door & Frame Assembly. Sheet 1 of 3 Project stage: Other ML20262H5691975-06-18018 June 1975 Details 1 & 6. Sheet 2 of 3 Project stage: Other ML20262H5711975-06-18018 June 1975 Details 2,3,4 & 5. Sheet 3 of 3 Project stage: Other ML19343C5641981-03-19019 March 1981 Submits Comments & Requests for Certain Exemptions from Final Version of 10CFR50.48,App R,Per 810220 Request Project stage: Other ML20037D0201981-05-18018 May 1981 Forwards Supplemental Response to 10CFR50.48,App R Re Fire Protection Rule,Per NRC 810220 Request.Also Forwards Electrical Circuit Schedules,Circuit & Raceway Data & 210 Oversize Drawings.Aperture Cards Are Available in PDR Project stage: Supplement ML20038A9581981-11-12012 November 1981 Requests Extension of Schedule for Emergency Lighting Installation Until 811204.Class II Fee Encl Project stage: Other ML20033D1301981-11-18018 November 1981 Forwards Amend 9 to Evaluation of Fire Protection Plan. Control Rooms Have Been Modified to Enhance Operator Environ & Reduce Operator Stress & Fatigue Project stage: Other ML20039B8431981-12-0707 December 1981 Exemption Granting Extension of Completion Date of Emergency Lighting Installation from 811117 to 1204 Project stage: Other ML20049J3291982-03-0303 March 1982 Requests Extension to 820701 for Submitting Design Info Re Implementation Schedule of 10CFR50.48 & Encl 2 of NRC Project stage: Other ML20052F4801982-05-0303 May 1982 Exemption from Fire Protection Rule Schedular Requirements of 10CFR50.48(c).Exemption Subj to Listed Conditions. Clarification of Generic Ltr 81-12 & Criteria for Evaluating Exemption Requests Encl Project stage: Approval ML20054E5071982-06-0202 June 1982 Requests Verification of Exemption of Station Battery Room water-tight Doors from Having 3-h Fire Rating Project stage: Other ML20054L8131982-07-0101 July 1982 Forwards Supplemental Responses to 10CFR50.48 & App R to 10CFR50 & Engineering Planning & Mgt,Inc Rept, DC Essential Cabinet Analysis, Per NRC 810220 Request (Generic Ltr 81-12) Project stage: Supplement ML20262H5631982-08-20020 August 1982 Installation of PR2905-4 3 Ft 9 & 1/2 Inches X 7 Ft 1/2 Inch Door & Frame Assy. Sheet 1 of 1.No Revision Date Project stage: Other ML20265A8161982-09-22022 September 1982 Edwin I Hatch Nuclear Plant - 1 & 2 Fire Protection Piping River Intake Structure Project stage: Other ML20070V7991983-02-14014 February 1983 Requests Meeting on or After 830329 W/Nrr to Appeal for Reconsideration of NRC Proposed Denial of App R Exemption Request.Addl Info Forthcoming to Clarify 820701 Submittal Project stage: Meeting ML20073S1721983-04-28028 April 1983 Clarifies Requests for Exemptions from 10CFR50.48 & App R Requirements in Response to NRC Request at 830330 Meeting. Rev to 820701 Response to Be Submitted by 830530 Project stage: Meeting ML20071H9241983-05-19019 May 1983 Submits Info on Compliance W/Branch Technical Position 9.5-1 Re Qualification of Fire Protection Engineers. Qualification Requirements Met Through Maint of Staff at Affiliated Svc Company,Southern Co Svcs,Inc Project stage: Other ML20023D7611983-05-27027 May 1983 Forwards Revised Response to 820701 Requests for Exemption from 10CFR50.48 & App R Requirements,Per 830330 Request.Rev Reflects Compliance w/10CFR50.48 & App R Requirements & Responds to 830120 Draft SER Concerns Project stage: Draft Other ML20024A3861983-06-14014 June 1983 Forwards Addl Info to Justify 820701 10CFR50.48 & App R Schedule Exemption Requests Discussed at 830330 Meeting. Plan Being Developed to Complete Maint & Design Changes. W/Two Oversize Drawings.Aperture Cards Available in PDR Project stage: Meeting ML20263B9301983-08-18018 August 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 2 of 5 Project stage: Other ML20263B9251983-11-0707 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 4 of 5 Project stage: Other ML20263B9271983-11-0707 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 3 of 5 Project stage: Other ML20263B9321983-11-14014 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 1 of 5 Project stage: Other ML20082D3421983-11-16016 November 1983 Forwards Addl Info Justifying Three Requests for Exemption from 10CFR50.48 & App R as Discussed in 830330 Meeting.Rev to 820701 Response Will Be Submitted by 831130 Project stage: Meeting ML20082J7831983-11-30030 November 1983 Forwards Replacement Pages to Re Clarification of App R Exemption Requests,Reflecting Revised Sections of 820701 Response to 10CFR50.48 Project stage: Other ML20083D7541983-12-20020 December 1983 Forwards Revised Pages for Insertion Into 830701 Request for Exemption from 10CFR50.48 & 10CFR50,App R Requirements Re Sprinkler Head/Nozzle & Detector Placement Project stage: Request ML20083D7721983-12-21021 December 1983 Forwards Payment of Fee Required for Review of 810319 Submittal on Safe Alternate Shutdown & Request for Schedular Exemption from Installation of Emergency Lighting Project stage: Request ML17255A6241984-01-16016 January 1984 Forwards App R Alternative Shutdown Sys. New Shutdown Approach Provides Fewer Mods & Allows Phased Implementation as Opposed to Installation of Required Dedicated Shutdown Sys Project stage: Request ML20079P7121984-01-24024 January 1984 Submits Info Documenting Addl Considerations of Projected Phased Improvement in Fire Protection & Mitigating Factors for Areas Unmodified During Extended Implementation Period. Tentative Completion Dates for App R Mods Encl Project stage: Other ML17255A6941984-02-29029 February 1984 Summary of 840222 Meeting W/Util & Bechtel Re Proposed App R Exemption Requests & Alternative Shutdown Sys.Meeting Agenda & List of Attendees Encl Project stage: Meeting ML20084L4461984-04-18018 April 1984 Safety Evaluation Supporting Util 820701 Requests for Exemption from Requirements of App R to 10CFR50 & Approval of Deviations from Several NFPA Codes Per Installation & Maint of Fire Protection Sys Project stage: Approval ML20084L4301984-04-18018 April 1984 Exemption from Requirements of App R to 10CFR50 Re Licensee Alternate Fire Protection Configuration for East Corridor, Control & Turbine Bldgs & Condensate Pump Area Project stage: Approval ML17254A7601984-05-10010 May 1984 Exemption from Schedular Requirements of 10CFR50.48(c)(4) to Extend Implementation of Alternative Shutdown Sys Until Startup from 1986 Refueling Outage Project stage: Approval ML20091B7331984-05-25025 May 1984 Notifies of Commitment to Meet on fire-area-by-fire-area Basis,Either Item 1 or 2 & 3 for Period of Time from Expiration of 10CFR50.48 Schedule Allowance Until Area Complies W/Paragraphs III.G.2 & III.G.3 of 10CFR50,App R Project stage: Other ML20197G5581984-06-0808 June 1984 Requests Addl Info on App R Implementation,Needed to Respond to 840525 Request for Schedular Exemption.Proposed Schedules Appear Acceptable Project stage: Approval ML20096F8121984-09-0404 September 1984 Requests Notification of Determination Re Acceptability of Kaowool as Fire Barrier Project stage: Other ML20096F8381984-09-0404 September 1984 Forwards Proposed Specific Compensatory Measures to Support 840525 Requested 10CFR50.48 Schedular Exemptions for nonoutage-related App R Mods,Per 840608 Request Project stage: Other ML20093E4111984-10-0202 October 1984 Proposes Establishment of Roving Fire Watch to Pass Through Listed Sections of Control & Reactor Bldgs as Compensatory Measures to Support Schedular Extension of App R Mods Project stage: Other ML20265A8211984-10-0404 October 1984 Intake Structure Pumps Project stage: Other ML20265A8261984-10-0404 October 1984 As Built Isometrics for Intake Structure Pumps Project stage: Other ML20106D3531984-10-19019 October 1984 Requests Exemption from 10CFR50.48(c) to Allow Extension Until 861130 of Implementation Schedule for Listed App R Related Mods Which Can Be Implemented During Nonoutage Period Project stage: Other ML20107F1811984-10-26026 October 1984 Provides Basis for Request for Exemption from 10CFR50.48 Requirements Re Implementation of non-outage Related 10CFR50,App R Mods.Fire Protection Enhancement Program Cannot Be Implemented within Expected Time Frame Project stage: Request ML20101E3731984-12-20020 December 1984 Submits Specific Info Re Compensatory Measures for nonoutage-related App R Mods Not Completed within 10CFR50.48 Time Frame,In Support of 841002 Request for Extension of Schedule to Complete Listed Mods Project stage: Request ML20215F7371984-12-26026 December 1984 Rev 1 to Administrative Control Procedure 40AC-FPX01-0, Fire Protection Program. Portions of Procedures 34AB-OPS-056-1S & 34AB-OPS-056-2S Encl Project stage: Other ML20114C0021985-01-10010 January 1985 Environ Assessment & Finding of No Significant Impact Re Util 840904 Request for Schedular Deferment from 10CFR50, App R,Section Iii.G for Fire Protection Equipment Used for Safe Shutdown to 861130.EIS Unwarranted Project stage: Approval ML20114B8481985-01-16016 January 1985 Exemption from Requirements of 10CFR50.48(c) to Extend Deadline for Completion of Fire Protection Mods Not Requiring Plant Shutdown Until 861130 Project stage: Approval ML20114B4181985-01-17017 January 1985 Responds to 850116 Order & Provides Rev to Interim Mitigation Factors for Nonoutage Related App R Mods,Per 850117 Telcon Project stage: Other 1983-04-28
[Table View] |
Requests Exemption from 10CFR50.48(c) to Allow Extension Until 861130 of Implementation Schedule for Listed App R Related Mods Which Can Be Implemented During Nonoutage Period| ML20106D353 |
| Person / Time |
|---|
| Site: |
Hatch  |
|---|
| Issue date: |
10/19/1984 |
|---|
| From: |
Gucwa L GEORGIA POWER CO. |
|---|
| To: |
Stolz J Office of Nuclear Reactor Regulation |
|---|
| References |
|---|
| NED-84-523, TAC-43754, TAC-43755, TAC-47143, TAC-48071, TAC-48072, TAC-48748, TAC-48749, TAC-57415, TAC-57416, NUDOCS 8410250105 |
| Download: ML20106D353 (4) |
|
Similar Documents at Hatch |
|---|
|
Text
-
e.*
g
- Georgia Power Company 333 Piedmont Avenue
' Atlanta, Georgia 30308 -
- Telephone 404 5264526 Mail.ng Address:
Post Oftce Box 4545 Atlanta, Georgia 30302 h
GeorgiaPower L T. Gucwa the southem electre system i~
. Manager Nuclear Engineenng and Chief Nuclear Engineer October 19, 1984 Director of Nuclear Reactor. Regulation Attentica: Mr.-John F. Stolz, Chief Operating Reactors Branch No. 4 Division of Licensing U. S. Nuclear Regulatory Ccratission Washington, D. C.
20555 NRC DOCKERS 50-321, 50-366
' OPEPATING LICENSES DPR-57, NPF-5 EDWIN I. HATCH NUCLEAR PIANT UNITS 1, 2 SCHEDULER EXDFFIONS FOR NON-OUTAGE-REIATED APPENDIX R MODIFICATIONS Gentlemen In previous ~ correspondence Georgia Power Company (GPC) has discussed a proposed scheduler exemption for implementation of Appendix R non-outage related modifications.
In that correspondence we proposed to meet, on a
~
fire area' by-fire area basis, items of mitigation for the period of time from expiration of the 10 CFR 50.48 schedule allowance until the specific modifications in fire areas are complete. GPC herein restates our scheduler exemption request in order to provide a more clear definition of our need.
GPC requests an exemption to the provisions of 10, CFR 50.48(c) to allow an extension to November 30, 1986, of the implementation schedule for the Appendix R-related modifications identified in the "Edwin I.
Hatch Nuclear Plant Response to 10 CFR 50.48 and Appendix R" listed below which can be implemented 'during a non-outage period but which, as part of the total integrated Appendix R modification schedule, can not be completed in the time frame allowed by regulation.
These modifications are grouped by fire areas as identified in our July 1,
1932 suhnittal and subsequent amendments.
Fbr clarity, other modifications identified in that submittal which have been determined to require a plant outage to complete are not listed:
4.1.1 4160-V Transformer Room - Unit 1 o
Wrap conduit ESS-II-477 with 1-h barrier 8410250105 841019 PDR ADOCK 05000321 gh F
PDR
- - 'll
u -
n 1.
Director of-Nuclear Reactor Regulation-U. S. Nuclear' Regulatory Commission
, Washington, D. C.-
20555-October 19, 1984 Page 2 4.1.2 West 600-V Switchgear Ibom - Unit 1 o
-Wrap conduit ESS-II-477 with 1-h barrier o -
Upgrade west wall to 3-h barrier 4.1.4
- Control' Building Working Floor el 112 ft - Unit 1 Wrap raceway R25-S037-ES4-M14 with 3-h barrier o-4.1.5 Reactor Building North of Column Line R7 - Unit 1 o
. Install detection on 158 ft elevation and additional
. detectors associated with the water curtain on-the 130 ft elevation Wrap safe shutdown-related cables in 20 ft sprinkler zone o
along R7 on elevations 130 ft and 158 ft
~
4.1.6 Reactor Building South of Colunn Line' R7 - Unit 1 Wrap cxmduit ESS-II-3645 ~with 1-h barrier o
Wrap conduit ESS-II-3648 with 1-h barrier o
Wrap conduit ESS-I-3838 with 1-h barrier o
4.1.7.
. West DC Switchgear Room - Unit 1 Upgrade wall between switchgear room.and oil conditioner i
o rocan to 3-h barrier A
4.2.2 Control Building Health Physics Area - Unit 2 o
Extension of sprinkler systems to cover trays 200A801, 2CRA801, and 2CUA701
-4.2.4 Control Building Oil Conditioner Room - Unit 2 o
Wrap raceway 2E22063 with 1-h barrier Wrap-raceway 2E22064 with 1-h barrier o
Upgrade wall to 3-h fire rating o
- _,. - - _ _... -. _ _ _.. _ _ _ _. ~ _, _ _. _ _. _.
n
~..
5
-Director of Nuclear Reactor Regulation U. S. Nuclear Regulatory Comission Washington, D. C.
20555 October 19, 1984 Page 3 4.2.6 Reactor Building North of Column Line R19 - Unit 2 o'
Install sprinkler system on elevation 158 ft o
Install detection system on elevation 158 ft 4.2.9 Turbine Building East Cableway - Unit 2 o
Wrap the following conduits with 1-h barrier
- 2CKA701, 2CLA701, 2CMA701, 2E12076, 2E12082, 2E12084,
- 2E12085, 2E22824, 2MR2543, 2MR2544, and 2CDAB01 4.2.10 Diesel Building Switchgear Ibom 2G - Unit 2 o
Wrap raceway 2ESB170 with.1-h barrier o
wrap raceway 2ESB168 with 1-h barrier o
Wrap raceway 2ESB167 with 1-h barrier 4.3.2 Control Building Corridor - Common o
' Wrap the following raceways with 1-h barrier:
Unit 1 Unit 2
'n08-01 TEJ8-02 TEAB-03 2CFA801 TEA 8-04 TEIB-01 T m8-03 2CZA801 TML8-01 TEB8-02 TEH8-01 2CZB801 Ts8-03 TEB8-04 T mB-02 ESS II-477 TEB8-01 o
Extend sprinkler system to provide full coverage 4.3.3 RPS and Vertical Cable Chase Ibms - Common o
Wrap raceway ESS-I-499 with 1-h barrier o
Install 3-h fire-rated doors to separate RPS rooms from cable chase i
l
a
-Director of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C.
. 20555 October 19, 1984 Page 4 In our letter NED-84-444 (dated September 4,1984) implementation dates of October 15, 1984 for Unit 2 and the end of the current refueling outage for Unit 1 were specified for the proposed interim compensatory measurcs.
However, 10 CFR 50.48 allows nine conths for implementation of non-outage related. modifications.
Therefore, GPC.hereby revises the planned implementation date for the interim compensatory measures cited in that letter and in NEIN34-518 (dated October 2, 1984) to nine months following
- the issuance of the NRC approval of our requested technical exemptions, that is January 14, 1985.
With this subnittal, GPC requests that our proposed scheduler exemption be granted by NRC. The staffs of GPC and its consultants are available for additicmal discussion of this exemption, should the NRC so desire.
Should you have any questions in this regard, please contact this office.
Yours very truly,
[ " Q -= =
L. T. Gucwa WE:eb Enclosure xc:
J. T. Beckham, Jr.
H. C. Nix, Jr.
J. P. O'Reilly (NRC-Region II)