Letter Sequence Other |
|---|
|
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval
Other: ML20038A958, ML20039B843, ML20049J329, ML20054E507, ML20079P712, ML20082J783, ML20091B733, ML20093E411, ML20096F812, ML20096F838, ML20106D353, ML20114B418, ML20203J883, ML20203L369, ML20205Q246, ML20206S023, ML20213G680, ML20213G684, ML20214D723, ML20214K479, ML20215F737, ML20262H555, ML20262H558, ML20262H561, ML20262H563, ML20262H567, ML20262H569, ML20262H571, ML20263B925, ML20263B927, ML20263B930, ML20263B932, ML20265A774, ML20265A780, ML20265A791, ML20265A796, ML20265A801, ML20265A806, ML20265A810, ML20265A816, ML20265A821, ML20265A826, ML20265A832, ML20265A837
|
MONTHYEARML20262H5551973-12-14014 December 1973 Watertight Door Assy. Sheet 1 of 3 Project stage: Other ML20262H5611973-12-14014 December 1973 Details:3,13,19,24,28,35 & 36. Sheet 3 of 3 Project stage: Other ML20262H5581973-12-14014 December 1973 Details:1,2,17 & 21 Thru 27,32,33 & 34. Sheet 2 of 3 Project stage: Other ML20262H5671975-06-18018 June 1975 4 Ft X 8 Ft Opening Lhrb Door & Frame Assembly. Sheet 1 of 3 Project stage: Other ML20262H5711975-06-18018 June 1975 Details 2,3,4 & 5. Sheet 3 of 3 Project stage: Other ML20262H5691975-06-18018 June 1975 Details 1 & 6. Sheet 2 of 3 Project stage: Other ML20038A9581981-11-12012 November 1981 Requests Extension of Schedule for Emergency Lighting Installation Until 811204.Class II Fee Encl Project stage: Other ML20039B8431981-12-0707 December 1981 Exemption Granting Extension of Completion Date of Emergency Lighting Installation from 811117 to 1204 Project stage: Other ML20049J3291982-03-0303 March 1982 Requests Extension to 820701 for Submitting Design Info Re Implementation Schedule of 10CFR50.48 & Encl 2 of NRC Project stage: Other ML20052F4801982-05-0303 May 1982 Exemption from Fire Protection Rule Schedular Requirements of 10CFR50.48(c).Exemption Subj to Listed Conditions. Clarification of Generic Ltr 81-12 & Criteria for Evaluating Exemption Requests Encl Project stage: Approval ML20054E5071982-06-0202 June 1982 Requests Verification of Exemption of Station Battery Room water-tight Doors from Having 3-h Fire Rating Project stage: Other ML20054L8131982-07-0101 July 1982 Forwards Supplemental Responses to 10CFR50.48 & App R to 10CFR50 & Engineering Planning & Mgt,Inc Rept, DC Essential Cabinet Analysis, Per NRC 810220 Request (Generic Ltr 81-12) Project stage: Supplement ML20262H5631982-08-20020 August 1982 Installation of PR2905-4 3 Ft 9 & 1/2 Inches X 7 Ft 1/2 Inch Door & Frame Assy. Sheet 1 of 1.No Revision Date Project stage: Other ML20265A8161982-09-22022 September 1982 Edwin I Hatch Nuclear Plant - 1 & 2 Fire Protection Piping River Intake Structure Project stage: Other ML20070V7991983-02-14014 February 1983 Requests Meeting on or After 830329 W/Nrr to Appeal for Reconsideration of NRC Proposed Denial of App R Exemption Request.Addl Info Forthcoming to Clarify 820701 Submittal Project stage: Meeting ML20073S1721983-04-28028 April 1983 Clarifies Requests for Exemptions from 10CFR50.48 & App R Requirements in Response to NRC Request at 830330 Meeting. Rev to 820701 Response to Be Submitted by 830530 Project stage: Meeting ML20023D7611983-05-27027 May 1983 Forwards Revised Response to 820701 Requests for Exemption from 10CFR50.48 & App R Requirements,Per 830330 Request.Rev Reflects Compliance w/10CFR50.48 & App R Requirements & Responds to 830120 Draft SER Concerns Project stage: Draft Other ML20024A3861983-06-14014 June 1983 Forwards Addl Info to Justify 820701 10CFR50.48 & App R Schedule Exemption Requests Discussed at 830330 Meeting. Plan Being Developed to Complete Maint & Design Changes. W/Two Oversize Drawings.Aperture Cards Available in PDR Project stage: Meeting ML20263B9301983-08-18018 August 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 2 of 5 Project stage: Other ML20263B9251983-11-0707 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 4 of 5 Project stage: Other ML20263B9271983-11-0707 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 3 of 5 Project stage: Other ML20263B9321983-11-14014 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 1 of 5 Project stage: Other ML20082D3421983-11-16016 November 1983 Forwards Addl Info Justifying Three Requests for Exemption from 10CFR50.48 & App R as Discussed in 830330 Meeting.Rev to 820701 Response Will Be Submitted by 831130 Project stage: Meeting ML20082J7831983-11-30030 November 1983 Forwards Replacement Pages to Re Clarification of App R Exemption Requests,Reflecting Revised Sections of 820701 Response to 10CFR50.48 Project stage: Other ML20083D7541983-12-20020 December 1983 Forwards Revised Pages for Insertion Into 830701 Request for Exemption from 10CFR50.48 & 10CFR50,App R Requirements Re Sprinkler Head/Nozzle & Detector Placement Project stage: Request ML20083D7721983-12-21021 December 1983 Forwards Payment of Fee Required for Review of 810319 Submittal on Safe Alternate Shutdown & Request for Schedular Exemption from Installation of Emergency Lighting Project stage: Request ML17255A6241984-01-16016 January 1984 Forwards App R Alternative Shutdown Sys. New Shutdown Approach Provides Fewer Mods & Allows Phased Implementation as Opposed to Installation of Required Dedicated Shutdown Sys Project stage: Request ML20079P7121984-01-24024 January 1984 Submits Info Documenting Addl Considerations of Projected Phased Improvement in Fire Protection & Mitigating Factors for Areas Unmodified During Extended Implementation Period. Tentative Completion Dates for App R Mods Encl Project stage: Other ML17255A6941984-02-29029 February 1984 Summary of 840222 Meeting W/Util & Bechtel Re Proposed App R Exemption Requests & Alternative Shutdown Sys.Meeting Agenda & List of Attendees Encl Project stage: Meeting ML20084L4301984-04-18018 April 1984 Exemption from Requirements of App R to 10CFR50 Re Licensee Alternate Fire Protection Configuration for East Corridor, Control & Turbine Bldgs & Condensate Pump Area Project stage: Approval ML20084L4461984-04-18018 April 1984 Safety Evaluation Supporting Util 820701 Requests for Exemption from Requirements of App R to 10CFR50 & Approval of Deviations from Several NFPA Codes Per Installation & Maint of Fire Protection Sys Project stage: Approval ML17254A7601984-05-10010 May 1984 Exemption from Schedular Requirements of 10CFR50.48(c)(4) to Extend Implementation of Alternative Shutdown Sys Until Startup from 1986 Refueling Outage Project stage: Approval ML20091B7331984-05-25025 May 1984 Notifies of Commitment to Meet on fire-area-by-fire-area Basis,Either Item 1 or 2 & 3 for Period of Time from Expiration of 10CFR50.48 Schedule Allowance Until Area Complies W/Paragraphs III.G.2 & III.G.3 of 10CFR50,App R Project stage: Other ML20197G5581984-06-0808 June 1984 Requests Addl Info on App R Implementation,Needed to Respond to 840525 Request for Schedular Exemption.Proposed Schedules Appear Acceptable Project stage: Approval ML20096F8381984-09-0404 September 1984 Forwards Proposed Specific Compensatory Measures to Support 840525 Requested 10CFR50.48 Schedular Exemptions for nonoutage-related App R Mods,Per 840608 Request Project stage: Other ML20096F8121984-09-0404 September 1984 Requests Notification of Determination Re Acceptability of Kaowool as Fire Barrier Project stage: Other ML20093E4111984-10-0202 October 1984 Proposes Establishment of Roving Fire Watch to Pass Through Listed Sections of Control & Reactor Bldgs as Compensatory Measures to Support Schedular Extension of App R Mods Project stage: Other ML20265A8211984-10-0404 October 1984 Intake Structure Pumps Project stage: Other ML20265A8261984-10-0404 October 1984 As Built Isometrics for Intake Structure Pumps Project stage: Other ML20106D3531984-10-19019 October 1984 Requests Exemption from 10CFR50.48(c) to Allow Extension Until 861130 of Implementation Schedule for Listed App R Related Mods Which Can Be Implemented During Nonoutage Period Project stage: Other ML20101E3731984-12-20020 December 1984 Submits Specific Info Re Compensatory Measures for nonoutage-related App R Mods Not Completed within 10CFR50.48 Time Frame,In Support of 841002 Request for Extension of Schedule to Complete Listed Mods Project stage: Request ML20215F7371984-12-26026 December 1984 Rev 1 to Administrative Control Procedure 40AC-FPX01-0, Fire Protection Program. Portions of Procedures 34AB-OPS-056-1S & 34AB-OPS-056-2S Encl Project stage: Other ML20114C0021985-01-10010 January 1985 Environ Assessment & Finding of No Significant Impact Re Util 840904 Request for Schedular Deferment from 10CFR50, App R,Section Iii.G for Fire Protection Equipment Used for Safe Shutdown to 861130.EIS Unwarranted Project stage: Approval ML20114B8481985-01-16016 January 1985 Exemption from Requirements of 10CFR50.48(c) to Extend Deadline for Completion of Fire Protection Mods Not Requiring Plant Shutdown Until 861130 Project stage: Approval ML20114B4181985-01-17017 January 1985 Responds to 850116 Order & Provides Rev to Interim Mitigation Factors for Nonoutage Related App R Mods,Per 850117 Telcon Project stage: Other ML20117L4581985-05-0707 May 1985 Notice of Issuance of Environ Assessment & Finding of No Significant Impact Re 850416 Request for Schedular Exemption from 10CFR50.48 Requirements Project stage: Approval ML20128B9601985-05-10010 May 1985 Safety Evaluation Supporting Relief for 16 MSIVs from 1980 Edition of ASME Section XI Code Requiring Increased Frequency of Leak Rate Testing Based on Leak Rate Trending of 6-inch & Larger Valves Project stage: Approval ML20128H9751985-05-14014 May 1985 Exemption to Schedular Requirements of 10CFR50.48,extending Deadline Until 861130 for Installation of Mods to Fire Protection Sys Project stage: Approval ML20265A7741985-09-30030 September 1985 Edwin I Hatch Nuclear Plant - Unit 1 Appendix R Path 1 & Path 2 Raceways Diesel Generator Building (Dsl 1A), as-built Project stage: Other ML20265A7801985-09-30030 September 1985 Edwin I Hatch Nuclear Plant - Unit 1 Appendix R Path 1 & Path 2 Raceways Diesel Generator Building (Dsl 1B), as-built Project stage: Other 1983-08-18
[Table View] |
Similar Documents at Hatch |
|---|
|
Text
.
,~ 590.01 UNITED STATES NUCLEAR REGULATORY C0f1 MISSION In the Matter of
)
)
GEORGIA POWER COMPANY, ET AL
)
Docket No. 50-321
)
(Edwin I. Hatch Nuclear Plant,
)
Unit No. 1)
)
EXEMPTION I.
The Georgia Power Company (the licensee) and three other co-owners are the holders of Facility Operating License No. DPR-57 which authorizes operation of the Edwin I. Hatch Nuclear Plant, Unit 1 (Hatch 1 or the facility). The license provides, among other things, that Hatch 1 is subject to all rules, regulations and Orders of the Nuclear Regulatory Comission (the Commission) now or hereafter in effect.
The facility is a boiling water reactor located at the licensee's site in Appling County, Georgia.
II.
Section 50.48(c)(2) of 10 CFR Part 50 requires that certain features of the Hatch 1 fire protection program, specifically, those that involve installa-tion of modifications, shall be implemented b9 Nov6inber 17,1981. One sucn
~
feature is the installation of emergency lighting units in all areas needed
~~
for operation of safe shutdown equipment.
By letter dated November 12, 1981, the licensee requested an exemption from the 50.48 schedular requirement, delaying the installation of these lighting units from November 17, 1981, to December 4,1981. The delay is necessitated by a redesign to ensure seismic integrity of the mounting brackets and subsequent material procurement problems. The licensee stated that a 9112240004 811207 PDR ADOCK 05000321 F
PDR
' i
,- )
. 7590-01 significant amount of emergency lighting is currently installed in Hatch 1, providing adequate illumination for operation of safe shut-down equipment, albeit not yet in compliance with seismic, design criteria for the mounting brackets. Additionally, hand-held emergency lighting is available to plant personnel.
As the licensee will have the system operational in a relatively short period of time, has a "non-seismic" system currently operable, and has backap hand-held emergency lighting available, we conclude that the licensee's request for an extension of the complation date required by 10 CFR 50.48(c)(2) should be granted.
III.
Accordingly, the Commission h:s determined that, pursuant to 10 CFR 50.12, an exemption is authorized by law and will not endanger life or l
property or the common defense and security, is otherwise in the public interest, and is hereby granted.
i l
l The Commission has determined that the grantino of this exemption will not result in any significant environmental impact and that pursuant to 10 l
CFR 51.5(d)(4) an environmental impact statenent or negative declaration and l
environmental impact appraisal need not be prepared in connection with this action.
This exemption is effective upon issuance.
FOR THE NUCLEAR REGULATORY COMt11SSION k4rr2dV/A f.~-
Harold R. Denton, Director Office of Nuclear Reactor Regulation Dated at Bethesda, Maryland, this 7th day of December 1981.
L