Letter Sequence Request |
|---|
|
Results
Other: ML20079P712, ML20082J783, ML20091B733, ML20093E411, ML20096F812, ML20096F838, ML20106D353, ML20114B418, ML20262H555, ML20262H558, ML20262H561, ML20262H563, ML20262H567, ML20262H569, ML20262H571, ML20263B925, ML20263B927, ML20263B930, ML20263B932
|
MONTHYEARML20262H5611973-12-14014 December 1973 Details:3,13,19,24,28,35 & 36. Sheet 3 of 3 Project stage: Other ML20262H5551973-12-14014 December 1973 Watertight Door Assy. Sheet 1 of 3 Project stage: Other ML20262H5581973-12-14014 December 1973 Details:1,2,17 & 21 Thru 27,32,33 & 34. Sheet 2 of 3 Project stage: Other ML20262H5671975-06-18018 June 1975 4 Ft X 8 Ft Opening Lhrb Door & Frame Assembly. Sheet 1 of 3 Project stage: Other ML20262H5711975-06-18018 June 1975 Details 2,3,4 & 5. Sheet 3 of 3 Project stage: Other ML20262H5691975-06-18018 June 1975 Details 1 & 6. Sheet 2 of 3 Project stage: Other ML20262H5631982-08-20020 August 1982 Installation of PR2905-4 3 Ft 9 & 1/2 Inches X 7 Ft 1/2 Inch Door & Frame Assy. Sheet 1 of 1.No Revision Date Project stage: Other ML20070V7991983-02-14014 February 1983 Requests Meeting on or After 830329 W/Nrr to Appeal for Reconsideration of NRC Proposed Denial of App R Exemption Request.Addl Info Forthcoming to Clarify 820701 Submittal Project stage: Meeting ML20073S1721983-04-28028 April 1983 Clarifies Requests for Exemptions from 10CFR50.48 & App R Requirements in Response to NRC Request at 830330 Meeting. Rev to 820701 Response to Be Submitted by 830530 Project stage: Meeting ML20023D7611983-05-27027 May 1983 Forwards Revised Response to 820701 Requests for Exemption from 10CFR50.48 & App R Requirements,Per 830330 Request.Rev Reflects Compliance w/10CFR50.48 & App R Requirements & Responds to 830120 Draft SER Concerns Project stage: Draft Other ML20024A3861983-06-14014 June 1983 Forwards Addl Info to Justify 820701 10CFR50.48 & App R Schedule Exemption Requests Discussed at 830330 Meeting. Plan Being Developed to Complete Maint & Design Changes. W/Two Oversize Drawings.Aperture Cards Available in PDR Project stage: Meeting ML20263B9301983-08-18018 August 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 2 of 5 Project stage: Other ML20263B9251983-11-0707 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 4 of 5 Project stage: Other ML20263B9271983-11-0707 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 3 of 5 Project stage: Other ML20263B9321983-11-14014 November 1983 Appendix R Fire Protection Modifications - CPM Schedule. Sheet 1 of 5 Project stage: Other ML20082D3421983-11-16016 November 1983 Forwards Addl Info Justifying Three Requests for Exemption from 10CFR50.48 & App R as Discussed in 830330 Meeting.Rev to 820701 Response Will Be Submitted by 831130 Project stage: Meeting ML20082J7831983-11-30030 November 1983 Forwards Replacement Pages to Re Clarification of App R Exemption Requests,Reflecting Revised Sections of 820701 Response to 10CFR50.48 Project stage: Other ML20083D7541983-12-20020 December 1983 Forwards Revised Pages for Insertion Into 830701 Request for Exemption from 10CFR50.48 & 10CFR50,App R Requirements Re Sprinkler Head/Nozzle & Detector Placement Project stage: Request ML20083D7721983-12-21021 December 1983 Forwards Payment of Fee Required for Review of 810319 Submittal on Safe Alternate Shutdown & Request for Schedular Exemption from Installation of Emergency Lighting Project stage: Request ML17255A6241984-01-16016 January 1984 Forwards App R Alternative Shutdown Sys. New Shutdown Approach Provides Fewer Mods & Allows Phased Implementation as Opposed to Installation of Required Dedicated Shutdown Sys Project stage: Request ML20079P7121984-01-24024 January 1984 Submits Info Documenting Addl Considerations of Projected Phased Improvement in Fire Protection & Mitigating Factors for Areas Unmodified During Extended Implementation Period. Tentative Completion Dates for App R Mods Encl Project stage: Other ML17255A6941984-02-29029 February 1984 Summary of 840222 Meeting W/Util & Bechtel Re Proposed App R Exemption Requests & Alternative Shutdown Sys.Meeting Agenda & List of Attendees Encl Project stage: Meeting ML20084L4301984-04-18018 April 1984 Exemption from Requirements of App R to 10CFR50 Re Licensee Alternate Fire Protection Configuration for East Corridor, Control & Turbine Bldgs & Condensate Pump Area Project stage: Approval ML20084L4461984-04-18018 April 1984 Safety Evaluation Supporting Util 820701 Requests for Exemption from Requirements of App R to 10CFR50 & Approval of Deviations from Several NFPA Codes Per Installation & Maint of Fire Protection Sys Project stage: Approval ML17254A7601984-05-10010 May 1984 Exemption from Schedular Requirements of 10CFR50.48(c)(4) to Extend Implementation of Alternative Shutdown Sys Until Startup from 1986 Refueling Outage Project stage: Approval ML20091B7331984-05-25025 May 1984 Notifies of Commitment to Meet on fire-area-by-fire-area Basis,Either Item 1 or 2 & 3 for Period of Time from Expiration of 10CFR50.48 Schedule Allowance Until Area Complies W/Paragraphs III.G.2 & III.G.3 of 10CFR50,App R Project stage: Other ML20197G5581984-06-0808 June 1984 Requests Addl Info on App R Implementation,Needed to Respond to 840525 Request for Schedular Exemption.Proposed Schedules Appear Acceptable Project stage: Approval ML20096F8121984-09-0404 September 1984 Requests Notification of Determination Re Acceptability of Kaowool as Fire Barrier Project stage: Other ML20096F8381984-09-0404 September 1984 Forwards Proposed Specific Compensatory Measures to Support 840525 Requested 10CFR50.48 Schedular Exemptions for nonoutage-related App R Mods,Per 840608 Request Project stage: Other ML20093E4111984-10-0202 October 1984 Proposes Establishment of Roving Fire Watch to Pass Through Listed Sections of Control & Reactor Bldgs as Compensatory Measures to Support Schedular Extension of App R Mods Project stage: Other ML20106D3531984-10-19019 October 1984 Requests Exemption from 10CFR50.48(c) to Allow Extension Until 861130 of Implementation Schedule for Listed App R Related Mods Which Can Be Implemented During Nonoutage Period Project stage: Other ML20107F1811984-10-26026 October 1984 Provides Basis for Request for Exemption from 10CFR50.48 Requirements Re Implementation of non-outage Related 10CFR50,App R Mods.Fire Protection Enhancement Program Cannot Be Implemented within Expected Time Frame Project stage: Request ML20101E3731984-12-20020 December 1984 Submits Specific Info Re Compensatory Measures for nonoutage-related App R Mods Not Completed within 10CFR50.48 Time Frame,In Support of 841002 Request for Extension of Schedule to Complete Listed Mods Project stage: Request ML20114C0021985-01-10010 January 1985 Environ Assessment & Finding of No Significant Impact Re Util 840904 Request for Schedular Deferment from 10CFR50, App R,Section Iii.G for Fire Protection Equipment Used for Safe Shutdown to 861130.EIS Unwarranted Project stage: Approval ML20114B8481985-01-16016 January 1985 Exemption from Requirements of 10CFR50.48(c) to Extend Deadline for Completion of Fire Protection Mods Not Requiring Plant Shutdown Until 861130 Project stage: Approval ML20114B4181985-01-17017 January 1985 Responds to 850116 Order & Provides Rev to Interim Mitigation Factors for Nonoutage Related App R Mods,Per 850117 Telcon Project stage: Other ML20116E8261985-04-16016 April 1985 Requests Extension Until 861130 to Implementation Schedule for outage-related Fire Protection Mods,Per 10CFR50,App R Requirements.List of outage-related Items to Annunciator Room & Reactor & Control Bldg Encl Project stage: Other ML20117L4581985-05-0707 May 1985 Notice of Issuance of Environ Assessment & Finding of No Significant Impact Re 850416 Request for Schedular Exemption from 10CFR50.48 Requirements Project stage: Approval ML20128B9011985-05-10010 May 1985 Informs of Completion of Review of 850404 Request for Relief from ASME Section XI Code for Leak Testing Msivs.Request Acceptable.Safety Evaluation Encl Project stage: Approval ML20128B9601985-05-10010 May 1985 Safety Evaluation Supporting Relief for 16 MSIVs from 1980 Edition of ASME Section XI Code Requiring Increased Frequency of Leak Rate Testing Based on Leak Rate Trending of 6-inch & Larger Valves Project stage: Approval ML20128H9751985-05-14014 May 1985 Exemption to Schedular Requirements of 10CFR50.48,extending Deadline Until 861130 for Installation of Mods to Fire Protection Sys Project stage: Approval 1984-10-19
[Table View] |
Similar Documents at Hatch |
|---|
|
Text
.
Gec gia Power Ccmpany 333 Padmcat Avenue.
Attanta, Georgia 30308 Telephcne 404 5266526 Maing Address:
Post 0;.lce Box 4545 Atlanta, Georgia 30302 Georgia Power L T. Gucwe the southern eiectu:c system j
Manager Nuclear Engineering
' and Chief Nuclear Engineer NED-84-558
' October 26, 1984 Director of Nuclear Reactor Regulation Attention: Mr. John F. Stolz, Chief Operating Reactors Branch No. 4 Division of Licensing U. S. Nuclear Regulatory Ccmnission Washington, D. C.
20555 NRC DOCKETS 50-321, 50-366 OPERATING LICENSIE DPR-57, hPF-5 ENIN I. HA'IG NUCLEAR PIANT UNITS 1, 2 BASIS FOR RECUEST FOR EXEMPTIN 'IO 10 CFR 50.48 Gentlenen:
In discussions between the NRC staff and representatives of Georgia Pow & Cmpany (GIC) the need to splify upon the necessity for schedular exenption to the provisions of 10 CFR 50.48 was disclosed.
GPC sutmits the following discussion pursuant to that need.
10 CFR 50.48 provides a schedular requirenent which, in part, allows nine months after termination of the tolling provision of Section C [6] for implenentation of non-outage related 10 CFR 50 Appendix R modifications.
Similarly, an allowance to the end of a specific outage (as defined in Section C [3])
is provided for outage related modifications.
These schedular allowances for design, procurenent, and installation of Appendix R modifications were established through conventional rulemaking to address a typical progra for meeting what were then perceived to be the rquirenents of Amendix R.
It was noted by public ccmnents submitted in response to the proposed 10 CER 50.48, published in the May 29, 1980 Federal Register, that insufficient time was provided for cm.pliance.
In - recognition of these connents, and the fact that the effective date of the rule was beyond the stated schedule for empliance, 10 CFR 50.48's implenentation requirenents were revised to the schedular allowances noted above.
However, these allowances are still inadquate for implanentation of a project of the magnitude of the fire protection enhancement progrm at Plant Hatch.
In order to gauge the scope and extent of the progre being undertaken, one 8411050321 841026 0ph PDR ADOCK 05000321 F
PDR v
\\
g, e.
]
p 4
^ '
+
COrgia P0%ki
= Director of Nuclear Reactor Ragulation
~
Attention: Mr. John F. Stolz, Chief-M^
. Operating Reactors-Branch No. 4-
. October 26, 1984--
~
Page h o should note;the projected cost of approximStely twenty-five~ million dollars a
(excluding the alternate. shutdown l system for. the control room / cable.
i spreading ; rom - fire). = Such a progra cannot-be practically -or : effectively
-impleented within the time free estimated in the developent of a the Appendix 1R. regulation.. %is insufficient schedular allowance in the regulation is ' the fundmental cause. of our requested exemption to the provisions of 10 C m 50.48.
In the specific case. of Plant Hatch, see additional' considerations are -
Appendix R' is being worthy of review.
Plant design is not static impleented on a plant. undergoing change.
Consequently, design is predicated on a predicted-plant configuration.'
One of the, fund mental 4
concepts employed in our defense-in-depth - fire protection design.is the~
establishment of fire barriers about safe shutdown related equipent. and -
~
4 l
cables.
Currently, extensive redesign - and modification _ of such sluipent.
I and. cables is underway in response to progres such as equipent l
qualification, operational safety enhance ents, and plant _ reliability -
improvments.
%ese projects are inherently interdependent and, in fact, j
the design for Appendix R cableway barriers must in many cases follow the i_
final - design of the equipent. qualification project..
Indeed, the two designs empliment.one another wherever possible such that installation of l
the new equipent and its related cabling meet the separation requirements
~
of Appendix R and preclude the need of barriers installation. W e scope and implementation delays of the equipent qualification-progre have been the l
subject of separate correspondence.
%e intergration of these efforts is
~
1 necessary for effective safe modification of the plant to. meet ' current i
regulation and hence implementation of Appendix R is _directly impacted by delays in these other progras. Sis special relationship was cited in our letter NED-84-035 dated January 25, 1984.
i
%e design sequences of the Appendix R modifications themselves are more l
emplex than is imediately obvious. After the extensive analysis raguired l
to establish what plant equipent and circuits require protection, design must sequentially address several factors.
In the case of wrapping a cable tray for exmple, the designer must:
- 1) perform a design walkdown to confirm design assmptions; 2) perform a seimic reanalysis of the cable tray; 3) redesign the cable tray supports to account for the increased mass of the barrier material; and - 4) design the barrier wrap.
Neither the final bill-of-saterials with its potential ' associated delivery problems, nor the specifications - for. the bidding of installation contracts can proceed until l[ -. -.,.
-. - _,, ~. -. _ _. -.. -. -.. - -, _,.. -. - _ _. -. - - - -
\\
' cU
- a-
-~.
GeorgiaPbwerI i-Director of Nuclear: Reactor Regulation Attention: Mr. John F. Stolzi Chief Operating Reactors Branch No.-4 October 26, 1984 Page hree L
i
' the design is s near -its final stages.. Following design,. implenentation must-
-logically wait for any rerouting-of cables fra Appendix R or equipnent qualification modifications.
Further, any extensive. fire detection 1 or suppression. modifications in the inmediate vicinity' which might 11ead to d a age.of the wrap 'must be. factored 'into the implementation process.
. Finally, upgrading of the tray supports, as necaaamry, and tray wrapping may
-be acceplished.
This exmple points out see of the difficulty in-implenentation which leads to schedules which are longer.than were anticipated during the development of the regulation.'
I The final. design must follow. acceptance.by the NRC of.the conceptual approach to compliance with Appendix R.
This is provided for by 10 CFR j.
50.48.C [6]. However, in order to meet a schedule such as was last proposed in our letter NED-84-523, dated October 19,'1984, analysis and design has in-fact proceeded at.our risk since the issuance of Appendix R.
A' significant dedication of - the design resources available to GPC from its architect engineers and consultants has been made to achieve the projected cepliance 4
with Appendix R.
Such resources are concurrently _ being soployed to reet other regulatory and safety-related issues at Plant Hatch.
No one requirement or safety enhancenent can-be considered -exclusive of the total demands on available resources.
In this light, GPC has assigned a high i
priority to compliance with Appendix R and = the proposed implenentation schedule has been the result.
GPC requests a timely response to our_ requested extension so that we may -
proceed on our best reasonable effort to meet the requirenents of Appendix R.
If further information is required, please contact this office.
Very truly yours,
/f f - e L. T. Gucwa i
WEB /inb xc:
J. T. Beckhm, Jr.
H. C. Nix, Jr.
J. P. O'Reilly (NRC-Region II) i Senior Resident Inspector' I
i 2 ""4
...