o NSF N O ft T H E R N 5TATES POWER COMPANY M I N N E A PO L.l S. M I N N E SCTA 584Q1 August 8, 1980 o

Director of Nuclear Reactor Regulation U S Nuclear Regulatory Co= mission Washington, DC 20555 PRAIRIE ISI.AND NUCI. EAR GENERATING PLC.T Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 Revised Schedule for Fire Protection Modifications The following information related to revised i=plementation dates for fire protection =edifications is provided in accordance with paragraph 2.C.4 of the operating licenses for the Prairie Island Nuclear Generating Plant.

Paragraph 2.C.4 requires the ec=pletion of sodifications identified in section 3.1 of the NRC's Fire Protection Safety Evaluation, dated September 6, 1979.

If any modification cannot be completed on schedule, a report explaining the circumstances and proposing a revised schedule must be submitted for NRC Staff approval.

The following =cdifications cannot be co pleted as scheduled:

Item Modification Reason for Delay 3.1.2(4) 3 coster hoses with variable Six reels, each with 100 nozzles feet of 1-inch hose, have been in-stalled. We have experienced difficulty in obtaining variable gallonage nozzles, however.

Vendors cannot provide the variable gallonage feature and at the same time certify that l

the fog density required for l

electrical safety is =aintained.

l As an alternative, we will install l

23 gpm industrial electrical fog nozzles for use with the one-inch home reels.

In additica, a 60 gpm icw capacity 1-h inch fog nozzle will be available in the brigade locker for use with standard fire hoses. The nozzles should be I

received and installed by October 31, 1980.

, c)C)f l

5 8 00801s,o gq g

)/

NCRTHERN STATES POWER COMPANY Office of Nuclear Reactor Regulation August 8, 1980 Page 2 Ite Modification Reason for Delav 3.1.4(1) through Various trenches, ramps, Detailed design was delayed by work 3.1.4(4) and curbs having a higher priority. The design 3.1.4(11) change package has been prepared and work will ce==ence soon. The presently scheduled completion date of August 31, 1980 =ay not be met.

All work should be complaced by October 31, 1980.

3.1.5(1)

Strue: ural steel coating The scope of this project is larger than originally thought. Our engineer-ing consultant has prepared specifica-tions following a detailed review of the alternatives available. '4crk is n:w scheduled for completion by October 31, 1980.

3.1.6(1)

Propane cylinder relocation one of the :wo lab propane cylinders has been reloca:ed. The other cylinder, which is not in a safety related area, will be relocated prior to October 31, 1980. Approx-i=ately 250 feet of new piping are required for relocating the remaining cylinder =aking the task more difficul: than originally thought.

Please contact us if you require idditional information related to our revised schedule for completing these fire protection modifications.

. l9. Sby L 0 Mayer, PE Manager of Nuclear Suppor: Services LCM /DMM/jh cc J G Keppler G Charnoff I

NSP

' NORTHERN 5TATES POWER COMPANY M I N N E A PO b8 8. MI N N E SCTA 5 5 4Q1 August 8, 1980 Director of Nuclear Reactor Regulation U S Nuclear Regulatory Co= mission Washington, DC 20555 PRAIRIE ISLAND Ni! CLEAR GENERATING PLANT Decket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 Revised Schedule for Fire Protection Modifications The following infor ation related to revised i=ple=entation dates for fire protection :odifications is provided in accordance with paragraph 2.C.4 of the opera:ing licenses for the Prairie Island Nuclear Generating Plant.

Paragraph 2.C.4 requires the co=pletion of modifications identified in section 3.1 of the NRC's Fire Protection Safety Evaluation, dated September 6, 1979.

If any modification cannot be co=pleted on schedule, a report explaining :he circu= stances and p,roposing a revised schedule must be submit:ed for NRC Staff approval.

The following modifications cannot be completed as scheduled:

Item Modification Reason for Delav 3.1.2(4) 3ooster hoses w1:h variable Six reels, each with 100 no::les feet of 1-inch hose, have been in-stalled. We have experienced difficulty in obtaining variable gallonage no::ler, however.

Vendors cannot provide the variable gallonage feature and at the same ti=e certify tha:

the fog density required for electrical safety is maintained.

As an alternative, we will install i

1 23 gpm industrial electrical fog no::les for use w1:h the one-inch hose reels. In addition, a 60 gpm low capacity 1-b inch fog no::le l

will be available in the brigade l

locker for use with standard fire hoses. The no::les should be received and installed by October 31, 1980.

f\\oO 5

l l

NORTHEMN STATES PCWEK COMPANY Office of Nuclear Reac:cr Regulation August 3, 1980 Page 2 Item Modifica:ica Ressun for Delav 3.1.4(1) through varicus trenches, ra=ps, Detailed design was delayed by verk 3.1.4(4) and curbs having a higher priori:7 The design 3.1.4(11) change package has been prepared and verk ill ec==ence soon. The prasently scheduled ccepletion da:e of August 31, 1980 nay not be =et.

All verk shculd be cc=pleted by October 31, 1980.

3.1.5(1)

Strue: ural steel coating The secpe of :his projec: is larger than criginally thought. Our engineer-ing consul: ant has prepared specifica-tiens following a detailed review of the al:erna:1ves available.

  • 'o rk a

is acv scheduled for ec=pletion by October 31, 1980.

3.1.6(1)

Propane cylinder relocatica One of :he :vo lab prepane cylinders has been reloca:ed. The Other cylinder, which is net in a safety related area, vill be relocated prior :o Oc: ber 31, 1950. Appr:x-i=ately 250 feet,f new piping are required f:r relocating :he re=aining cylinder zaking the task =cre difficul: than originally though:.

Please contac: us if you require additional informatica related to our revised schedule for cc=pleting these fire protection 20difica:icns.

/fM L 0 Mayer. PE Manager of Nuclear Suppor: Services LCM /DMM/jh cc J G Keppler G Charnoff

1 1

NSP NORTHERN 5TATES POWER COMPANY wo un canou s wiu ~ c SCTA 5540%

August 8, 1980 Director of Nuclear Reactor Regulation U S Nuclear Regulatory Co==ission Washington, DC 20555

?RAIRIE ISLAND NUCLEAR GENERATING PLANT Docket Nos. 50-282 License Nos. DPR-42 50-306 DPR-60 Revised Schedule for Fire Protection Modifications The folicwing infor:ation related to revised i=ple=entation dates for fire protection :odifications is provided in accordance with paragraph 2.C.4 of the operating licenses for the Prairie Island Nuclear Genera:ing Plant.

Paragraph 2.C.4 requires the co=pletion of modifications identified in see:1on 3.1 of :he NRC's fire Protec:1on Safety Evaluation, dated September 6,

1979.

If any modification cannot be completed on schedule, a report explaining the circu= stance.s and proposing a revised schedule =ust be sub=itted for NRC Staff approval.

The folleving =edifications cannot be completed as scheduled:

Item Modification Reason for Delav 3.1.2(4) 3 coster hoses with variable Six reels, each with 100 nc::les feet of 1-inch hose, have been in-stalled. We have experienced difficulty in obtaining variable gallocage no::les, however.

Vendors cannot provide the variable gallonage feature and at the same ti=e certify that the fog density required for electrical safety is =aintained.

As an alternative, we will install 23 gps industrial elec:rical fog no: les for use with :he one-inch hose reels. In addi: ion, a 60 gp=

low capacity 1-b inch fog no::le will be available in the brigade locker for use with standard fire hoses. The no::les should ba received and installed by Cetober 31, 1980.

b f\\t>D$

i i

NCRTHERN STATES PCWER COMPANY Office of Nuclear Reactor Regulation August 8, 1980 Page 2 Ite=

Modification Reason for Delav 3.1.4(1) through Various trenches, ra=ps, Detailed design was delayed by work 3.1.4(4) and curbs having a higher priority. The design 3.1.4(11) change package has been prepared and work vill co==ence soon. The presently scheduled co=pletion date of August 31, 1980 =ay not be met.

All work should be co=pleted by October 31, 1980.

3.1.5(1)

Structural steel coating The scope of this project is larger than originally thought. Our engineer-ing consultant has prepared specifica-tions following a detailed review of the alternatives available. 'Jork is now scheduled for co=pletion by October 31, 1980.

3.1.6(1)

Propane cylinder relocation One of the two lab propane cylinders has been relocated. The other cylinder, which is not in a safety related area, will be relocated prior to October 31, 1980. Approx-i=ately 250 feet of sev piping are required for telocating the re=aining cylinder =aking the task : ore difficult than originally thought.

Please contact us if you require additional infor=ation related to our revised schedule for co=pleting these fire protection =odifications.

.o. %