NRR E-mail Capture - Fermi 2 - Acceptance of Requested Licensing Action to Revise TS 3.3.5.3, RPV Water Inventory Control Instrumentation
ML19080A216
Person / Time
Site: Fermi DTE Energy icon.png
Issue date: 03/21/2019
From: Sujata Goetz
Plant Licensing Branch III
To: Jonathan Haas
DTE Electric Company
References
L-2019-LLA-0041
Download: ML19080A216 (3)


Text

NRR-DMPSPEm Resource From: Goetz, sue Sent: Thursday, March 21, 2019 9:48 AM To: Jason R Haas

Subject:

Fermi 2 - Acceptance of Requested Licensing Action to Revise TS 3.3.5.3, RPV Water Inventory Control Instrumentation (EPID: L-2019-LLA-0041)

Dear Mr. Haas,

By letter dated February 27, 2019 (Agencywide Document and Access Management System (ADAMS)

Accession No. ML19058A251) DTE Electric Company submitted a license amendment request for Fermi 2.

The proposed amendment would revise technical specification (TS) 3.3.5.3, Reactor Pressure Vessel (RPV)

Water Inventory Control Instrumentation. The proposed amendment would provide a Note prior to the Surveillance Requirements section of TS 3.3.5.3 that would allow delayed entry into the associated conditions and required actions when a channel is placed in an inoperable status solely for testing, provided the associated Function maintains emergency core cooling system initiation capability.

The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 400 hours16.667 days <br />2.381 weeks <br />0.548 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is February 2020. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me.

Sujata Goetz Project Manager, Fermi 2 1

Nuclear Regulatory Commission 11555 Rockville Pike Office of the Nuclear Reactor Regulation NRC/NRR/DORL/LPL3 Office O8F2 Mailroom O8-B1A Rockville, MD 20852-2738 Washington, DC 20555-0001 (o) 301.415.8004 (f) 301.415.3313 2

Hearing Identifier: NRR_DMPS Email Number: 875 Mail Envelope Properties (Sujata.Goetz@nrc.gov20190321094800)

Subject:

Fermi 2 - Acceptance of Requested Licensing Action to Revise TS 3.3.5.3, RPV Water Inventory Control Instrumentation (EPID: L-2019-LLA-0041)

Sent Date: 3/21/2019 9:48:02 AM Received Date: 3/21/2019 9:48:00 AM From: Goetz, sue Created By: Sujata.Goetz@nrc.gov Recipients:

"Jason R Haas" <haasj@dteenergy.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 3396 3/21/2019 9:48:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: