|
---|
Category:Letter type:SBK
MONTHYEARSBK-L-24030, 2023 Annual Environmental Operating Report2024-04-12012 April 2024 2023 Annual Environmental Operating Report SBK-L-23053, Radiological Emergency Plan (Ssrep), Revision 802023-06-22022 June 2023 Radiological Emergency Plan (Ssrep), Revision 80 SBK-L-23031, 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 2022 Annual Radioactive Effluent Release Report SBK-L-23044, 2022 Annual Radiological Environmental Operating Report2023-04-28028 April 2023 2022 Annual Radiological Environmental Operating Report SBK-L-23033, 2022 Annual Environmental Operating Report2023-04-11011 April 2023 2022 Annual Environmental Operating Report SBK-L-22093, 75 Day and 150 Day Submittal Letters2022-12-0101 December 2022 75 Day and 150 Day Submittal Letters SBK-L-22113, Radiological Emergency Plan (Ssrep), Revision 792022-11-16016 November 2022 Radiological Emergency Plan (Ssrep), Revision 79 SBK-L-22114, Independent Spent Fuel Storage Installation (Isfsi), Cask Registration2022-11-0909 November 2022 Independent Spent Fuel Storage Installation (Isfsi), Cask Registration SBK-L-22112, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2022-11-0303 November 2022 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration SBK-L-22094, Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2)2022-10-26026 October 2022 Relief Request 4RA-22-001, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) SBK-L-22105, Supplement to 2021 Annual Radioactive Effluent Release Report2022-10-24024 October 2022 Supplement to 2021 Annual Radioactive Effluent Release Report SBK-L-22103, 5 to the Physical Security Plan, Training and Qualification Plan and Safeguards Contingency Plan2022-10-12012 October 2022 5 to the Physical Security Plan, Training and Qualification Plan and Safeguards Contingency Plan SBK-L-22102, Independent Spent Fuel Storage Installation (ISFSI) Cask Registration2022-10-0606 October 2022 Independent Spent Fuel Storage Installation (ISFSI) Cask Registration SBK-L-22080, Submittal of 10 CFR 72.48 Report of Changes, Tests and Experiments for August 2020 to July 20222022-08-12012 August 2022 Submittal of 10 CFR 72.48 Report of Changes, Tests and Experiments for August 2020 to July 2022 SBK-L-22054, SBK-L-22054 - License Amendment Request 22-01, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2022-06-0909 June 2022 SBK-L-22054 - License Amendment Request 22-01, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections SBK-L-22044, 2021 Annual Radioactive Effluent Release Report2022-04-29029 April 2022 2021 Annual Radioactive Effluent Release Report SBK-L-22036, Steam Generator Tube Inspection Report2022-04-25025 April 2022 Steam Generator Tube Inspection Report SBK-L-22040, Radiological Emergency Plan (Ssrep), Revision 7822022-04-20020 April 2022 Radiological Emergency Plan (Ssrep), Revision 782 SBK-L-22024, Response to Request for Additional Information (Raj) Regarding License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2022-03-0707 March 2022 Response to Request for Additional Information (Raj) Regarding License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-22003, Inservice Inspection Examination Report2022-01-24024 January 2022 Inservice Inspection Examination Report SBK-L-21126, Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan2022-01-0404 January 2022 Fourth 10 Year Interval - Inservice Inspection (ISI) Program Plan SBK-L-21135, Submittal of Changes to the Seabrook Station Technical Specification Bases2021-12-29029 December 2021 Submittal of Changes to the Seabrook Station Technical Specification Bases SBK-L-21108, Core Operating Limits Report for Cycle 222021-11-0404 November 2021 Core Operating Limits Report for Cycle 22 SBK-L-21106, Transmittal of WCAP-18607-NP, Analysis of Capsule X from the NextEra Energy Seabrook Unit 1 Reactor Vessel Radiation Surveillance Program2021-09-30030 September 2021 Transmittal of WCAP-18607-NP, Analysis of Capsule X from the NextEra Energy Seabrook Unit 1 Reactor Vessel Radiation Surveillance Program SBK-L-21105, Withdrawal of Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink One-Time Allowed Outage Time (AOT) Extension2021-09-27027 September 2021 Withdrawal of Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink One-Time Allowed Outage Time (AOT) Extension SBK-L-21104, Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink Onetime Allowed Outage Time (AOT) Extension2021-09-25025 September 2021 Emergency License Amendment Request 21-02, Service Water System I Ultimate Heat Sink Onetime Allowed Outage Time (AOT) Extension SBK-L-21103, Request for Exercise of Enforcement Discretion2021-09-25025 September 2021 Request for Exercise of Enforcement Discretion SBK-L-21098, Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2021-09-22022 September 2021 Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-21083, NextEra Energy Seabrook, LLC - Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage2021-08-18018 August 2021 NextEra Energy Seabrook, LLC - Relief Request 3IR-18 and 3IR-19 for End of Third 10-Year ISI Interval for Examinations with Limited Coverage SBK-L-21067, License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements2021-07-21021 July 2021 License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements SBK-L-21049, Revision to Updated Final Response to NRC Generic Letter 2004-022021-06-24024 June 2021 Revision to Updated Final Response to NRC Generic Letter 2004-02 SBK-L-21056, Response to Request for Additional Information Regarding Seabrook Steam Generator Tube Inspection Report Review References:2021-05-20020 May 2021 Response to Request for Additional Information Regarding Seabrook Steam Generator Tube Inspection Report Review References: SBK-L-21044, 2020 Annual Radiological Environmental Operating Report2021-04-30030 April 2021 2020 Annual Radiological Environmental Operating Report SBK-L-21045, Submittal of 2020 Annual Radioactive Effluent Release Report2021-04-30030 April 2021 Submittal of 2020 Annual Radioactive Effluent Release Report SBK-L-21042, Response to RIS 2021-01 Preparation and Scheduling of Operator Licensing Examinations2021-04-22022 April 2021 Response to RIS 2021-01 Preparation and Scheduling of Operator Licensing Examinations SBK-L-21033, Response to Request for Additional Information (RAI) Regarding License Amendment Request (LAR) 20-02, Resolve Non-Conservative Heat Flux Hot Channel Factor (Fo(Z)) Requirements2021-03-24024 March 2021 Response to Request for Additional Information (RAI) Regarding License Amendment Request (LAR) 20-02, Resolve Non-Conservative Heat Flux Hot Channel Factor (Fo(Z)) Requirements SBK-L-21023, Radiological Emergency Plan (Ssrep), Revision 772021-03-0404 March 2021 Radiological Emergency Plan (Ssrep), Revision 77 SBK-L-20154, Submittal of Changes to the Seabrook Station Technical Specification Bases2020-12-22022 December 2020 Submittal of Changes to the Seabrook Station Technical Specification Bases SBK-L-20149, Response to Request for Additional Information in Respect to One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-12-0808 December 2020 Response to Request for Additional Information in Respect to One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic SBK-L-20146, One-Time Exemption Request for the Biennial Emergency Preparedness Exercise Requirements of 10 CFR 50, Appendix E. IV.F.2.b and IV.F.2.c2020-12-0303 December 2020 One-Time Exemption Request for the Biennial Emergency Preparedness Exercise Requirements of 10 CFR 50, Appendix E. IV.F.2.b and IV.F.2.c SBK-L-20144, Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-23023 November 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic SBK-L-20143, Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-022020-11-19019 November 2020 Withdrawal of Exemption Request Supporting Updated Final Response to NRC Generic Letter 004-02 SBK-L-20132, Fourth Interval Inservice Testing (IST) Program2020-10-21021 October 2020 Fourth Interval Inservice Testing (IST) Program SBK-L-20127, Generator Tube Inspection Report2020-10-20020 October 2020 Generator Tube Inspection Report SBK-L-20117, Response to Request for Additional Information Regarding Technical Specification 3/4.8.1 for a One-Time Extension of Allowed Outage Time License Amendment Request2020-09-23023 September 2020 Response to Request for Additional Information Regarding Technical Specification 3/4.8.1 for a One-Time Extension of Allowed Outage Time License Amendment Request SBK-L-20103, Inservice Inspection Examination Report2020-07-27027 July 2020 Inservice Inspection Examination Report SBK-L-20068, License Amendment Request 20-01, One-Time Change to the Seabrook Technical Specifications A.C. Sources - Operating2020-07-13013 July 2020 License Amendment Request 20-01, One-Time Change to the Seabrook Technical Specifications A.C. Sources - Operating SBK-L-20092, Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-411 and TSTF-4182020-07-13013 July 2020 Response to Request for Additional Information Regarding License Amendment Requests to Adopt TSTF-411 and TSTF-418 SBK-L-20085, Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic2020-06-16016 June 2020 Supplement to Exemption Request for Access Authorization and Fitness for Duty Requirements Due to COVID-19 Pandemic SBK-L-20077, Core Operating Limits Report for Cycle 212020-06-0101 June 2020 Core Operating Limits Report for Cycle 21 2024-04-12
[Table view] |
Text
May 10,2012 SBK-L-12104 DocketNo.50443 U.S. Nuclear Regulatory Commission Attention: Document Conftol Desk One White FlintNorth 11555 Rockville Pike Rockville, MD 20852 Seabrook Station
$upplenneJt.Le Actionsifor Rgsqlu!!-qts.f Alkali Sjlisa-Reacli-on-(ASR) Issues
Reference:
- 1. Public Meeting between NextEra Energy Seabrook" LLC (NextEra Energy Seabrook) and the u.s. Nuclear Regulatory commission, April 23,2012 (MI-121070659),
- 2. NextEra Energy Seabrook letter SBK-L-12098, "Actions for Resolution of Alkali Silica Reaction (ASR) Issues," to NRC, dated May 3,20L2.
During the above referenced meeting, NextEra Energy Seabrook committed to the U.S. Nuelear Regulatory Commission (NRC) to provide a list of aotions it is taking to resolve ASR issues at Seabrook Station. NextEra Energy Seabrook provided the list of actions in Reference 2.ln a subsequent conference call with the NRC on May 7,2012, NextEra Energy Seabrook committed to providing supplementary information regarding the list of actions.
NextEra Energy Seabrook will take the following actions to resolve ASR at Seabrook Station:
- 1. Revise the prompt operability determination (POD) associated with AR581434581434 'Reduced Concrete Properties Below Grade in "Bo'Electrical Tunnel Exterior Wall,' by May 25, 2012. NextEra Energy Seabrook will notifr the site NRC Resident Inspector upon completion of this action.
) Revise the POD associated with AR16 64399, 'Reduced Concrete Modulus of Elastioity Below Grade in Containment Enclosure Building, RHR Equipment Vaults, EFW Pump House, and Diesel Generator Fuel Oil Storage Rooms,' by June 30,2012. The expanded scope buildings will be included in this POD. NextEra Energy Seabrook will notiff the site NRC Resident lnspector upon completion of this action.
NextEra Energy Seabrook, LLC, P,O. Box 300, Lafayette Road, Seabrook, NH 03874
United States Nuclear Regulatory Commission SBK-L-I2104/ Page 2
- 3. Complete short term aggregate expansion testing (ASTM C 1260 Mortar Bar Expansion Test) by June 30, 2012. Results will be available for NRC review approximately 30 days after testing is complete.
- 4. Complete long term aggregate expansion testing (ASTM C 1293 Concrete Prism Test) by June 30,2013. Results will be available forNRC review approximately 30 days after testing is complete.
- 5. Submit the root cause for the organizational causes associated with the occunence of ASR at Seabrook Station and related corrective actions by May 25,2012.
- 6. Submit the License Renewal Aging Management Program for ASR-affected structures by May 25,2012.
- 7. Submit the evaluation, "Impact of ASR on Concrete Structures and Attachments,"
(Foreign Print 100716) by May 25,2012.
- 8. Submit the corrective action plan for the continued assessment of ASR in concrete structures at Seabrook Station including development of remedial actions to rnitigate the affects of ASR, where waranted, by June 8,2012.
- 9. Submit the technical details of the testing planned at the contracted research and development facility by June 34,2012,
- 10. Update the Maintenance Rule Structures Monitoring Program to include monitoring requirements for selected locations in areas that exhibit ASR by July 15, 2012. NextEra Energy Seabrook will notiff the site NRC Resident Inspector upon completion of this action.
- 11. Perform six-month interval crack measurements and crack indexing at 20 locations in areas that exhibit the highest crack indices by July 15,2012. NextEra Energy Seabrook will notifu the site NRC Resident Inspector upon completion of this action, Crack measurement will be performed at six-month intervals until a reliable trend of ASR progression is established.
- 12. Complete anchor test program by December 31, 2012. Results will be available for NRC review approximately 30 days aftertesting is complete' The dates identified above reflect NextEra's current plans and are subject to change based upon testing conditions and other considerations. In the event that a date changes, NextEra will notiff the NRC in writing.
Regulatory commitnents are listed in the attachrnent to this letter.
United States Nuclear Regulatory Commission SBK-L-I2104/ Page 3 If you have any questions regarding this correspondence, please contact Mr. Michael O'Keefe, Licensing Manager, at (603) 773-7745.
Sincerely, NextEra Energy Seabrook, LLC Paul O. Freeman Site Vice President cc:
W.M. Dean, NRC Region I Administrator J. G. Lamb, NRC Project Manager, Project Direstorate I-2 W. J. Raymond, NRC Resident lnspector A.D. Cunanan, NRC Project Manager, License Renewal M. Wentzel, NRC Project Manager, License Renewal Mr. Christopher M. Pope Director Homeland Security and Emergency Management New Hampshire Department of Safety Division of Homeland Security and Emergency Management Bureau of Emergency Management 33 Hazen Drive Concord, NH 03305 John Giamrsso, Jr., Nuclear Preparedness Manager The Commonwealth of Massachusetts Emergency Management Agency 400 Worcester Road Framingham, MA 01702 -5399
Attachment to SBK-L-12104 List of Regulatory Commitments
Commitment Commitmeut Completion Number Date SBK-L-12098-01 Revise the prompt operability determination (POD) May 25,2412.
associated with AR581434581434 'Reduced Concrete Properties Below Grade in "B" Electrical Tunnel Exterior Wall.' NextEra Energy Seabrook will notifu the site NRC Resident Inspector upon completion of this action.
SBK-L-I2098-02 Revise the POD associated with AR1664399, June 30,2012.
'Reduced Concrete Modulus of Elasticity Below Grade in Containment Fnclosure Building RHR Equipment Vaults, EFW Pump House, and Diesel Generator Fuel Oil Storage Rooms.' The expanded scope buildings will be included in this POD.
NextEra Energy Seabrook will notiff the site NRC Resident Inspector upon completion of this action.
SBK-L-12098-03 Complete short term aggregate expansion testing Iune30,2012.
(ASTM C 1260 Mortar Bar Expansion Test).
Results will be available forNRC review approximately 30 days after testing is complete.
SBK-L-12098-04 Complete long term aggregate expansion testing June 30,2012.
(ASTM C 1293 Concrete Prism Test).
Results will be available forNRC review approximately 30 days after testing is complete.
SBK-L-12098-05 Submit the root cause for the orgarizational causes May 25,2012.
associated with the occurtence of ASR at Seabrook Station and related corrective actions.
SBK-L-12098-06 Submit the License Renewal Aging Management May 25,2Q12.
Program for ASR-affected structures.
Commitment Commitment Completion Number Date SBK-L-I2098-07 Submit the evaluatiory "Impact of ASR on Concrete May25,2012.
Structures and Attachments," (Foreign Print l0o7r6).
SBK-L-12098-08 Submit the conective action plan for the continued June 8, 2012.
assessment of ASR in concrete structures at Seabrook Station including development of remedial actions to mitigate the affects of AS& where warranted.
SBK-L-12098-09 Submit the technical details of the testing planned at June 30,2012.
the corrtracted research and development facility.
SBK-L-12098-10 Update the Maintenance Rule Structures Monitoring July 15,2012, Program to include monitoring requirements for selected locations in areas that exhibit ASR.
NextEra Energy Seabrook will notify the site NRC Resident Inspector upon completion of this action.
SBK-L-12098-11 Perform six-month interval crack measurements and July 75,2012.
crack indexing at 20locations in areas that exhibit the highest crack indices. NextEra Energy Seabrook will notiff the site NRC Resident Inspector upon completion of this action. Crack measurement will be performed at six-month intervals until a reliable trend of ASR progression is established.
SBK-L-12098-12 Complete anchor test program. December 31,2012.
Results will be available forNRC review approximately 30 days after testing is cornplete.