April 6, 2021
SUBJECT:
SEABROOK STATION - SECURITY BASELINE INSPECTION REPORT 05000443/2021401
Dear Mr. Moul:
On March 29, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Seabrook Station and discussed the results of this inspection with Mr. Brian Booth, Site Vice President and other members of your staff. The results of this inspection are documented in the enclosed report. Remote inspections were completed on February 15-19 and March 1-29, 2021. On-site inspections were completed on February 22-26, 2021.
One finding of very low security significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Enforcement; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Seabrook Station.
The following cross cutting aspect was assigned to a finding using Inspection Manual Chapter 0310 Aspects Within Cross Cutting Areas: [H.2] - Field Presence.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region I; the Director, Office of Nuclear Security and Incident Response; and the NRC Resident Inspector at Seabrook Station. The enclosed report contains Security-Related Information, so the enclosed report will not be made publicly available in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390(d)(1). If you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information-Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1)
and follow the instructions for withholding in 10 CFR 2.390(b)(1). The NRC is waiving the affidavit requirements for your response in accordance with 10 CFR 2.390(b)(1)(ii).
Sincerely, X /RA/
Signed by: Fred L. Bower
Fred L. Bower, III, Chief Plant Support Branch
Division of Reactor Safety
Docket No. 05000443 License No. NPF-86
Enclosure:
As stated
cc w/o encl: Distribution via LISTSERV
cc w/encl; w/OUO-SRI via BOX Jennifer L. Harper, Director, Division of Homeland Security and Emergency Management Samantha Phillips, Director, MA Emergency Management Agency Bruce Fielding, Manager Site Security John Griffin, Security Operations Supervisor
ML21096A075 (Cover letter w/ enclosure ADAMS ACCESSION NUMBER: ML21096A070 (Cover letter)
Entire Report:
X SUNSI Review Non-Sensitive X Sensitive Publicly Available X Non-Publicly Available Cover Letter Only:
X SUNSI Review X Non-Sensitive Sensitive X Publicly Available Non-Publicly Available OFFICE RI/DRS RI/DRS RI/DRS RI/DRP RI/DRS
NAME KHussar DCaron per email JRey/KH BBickett per email FBower
DATE 4/1/21 4/1/21 4/1/21 4/1/21 4/6/21