ML16127A155

From kanterella
Jump to navigation Jump to search
Inspection Report 05000443-2016008 Related to Alkali-Silica Reaction Affects on Safety Related Concrete Structures and Notice of Violation, February 1�5, 2016 and March 21�24, 2016
ML16127A155
Person / Time
Site: Seabrook NextEra Energy icon.png
Issue date: 05/06/2016
From: Mel Gray
Engineering Region 1 Branch 1
To: Dean Curtland
NextEra Energy Seabrook
Gray M
References
EA-16-101 IR 2016008
Download: ML16127A155 (24)


See also: IR 05000443/2016008

Text

[Type here]

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BLVD.

KING OF PRUSSIA, PA 19406-2713

May 6, 2016

EA-16-101

Mr. Dean Curtland

Vice President, Seabrook Station

c/o Mr. Michael Ossing

NextEra Energy Seabrook, LLC

626 Lafayette Rd.

Seabrook, NH 03874

SUBJECT:

SEABROOK STATION - INSPECTION REPORT 05000443/2016008

RELATED TO ALKALI-SILICA REACTION AFFECTS ON SAFETY-RELATED

CONCRETE STRUCTURES AND NOTICE OF VIOLATION

Dear Mr. Curtland:

On March 24, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at Seabrook Station. The enclosed inspection report documents the inspection results, which

were discussed at the exit meeting, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, examined structures in the field, and

interviewed personnel related to your actions to address the effects of Alkali-Silica Reaction

(ASR) on safety-related concrete structures at the Seabrook Station. Specifically, a team of

inspectors assessed NextEras performance to identify, evaluate and resolve ASR effects

involving discrete wide cracking and deformation (which is different than the micro-cracking

typically associated with ASR). These conditions were previously described in NRC findings

over the past two years involving the Containment Enclosure Building, Residual Heat Removal

Equipment Vault and Fuel Storage Building. The inspection focused on the adequacy of

NextEras reviews and evaluations to ensure ASR-affected structures remain capable of

performing their intended safety functions.

During the exit meeting, the inspection team conclusions and observations were summarized

regarding NextEras corrective actions to resolve the ASR non-conforming condition. The team

concluded, based on review of NextEra recently completed operability determination

documents, that ASR-affected structures are capable of performing their safety-related functions

considering the observed cracking and deformation. The team further indicated that additional

attention by NextEra staff is warranted to implement Seabrooks structures monitoring and

operability screening processes to ensure conclusions regarding structural capability are

updated and technically supported.

D. Curtland

- 2 -

One violation of very low safety significance (Green) is cited in a Notice of Violation (Notice) and

the circumstances surrounding it are described in the enclosed inspection report. The violation

describes two examples where initial and prompt operability determinations were not completed

by NextEra staff when additional information regarding the effects of ASR on safety-related

concrete structures was identified. Prompt operability determinations have since been

developed and were reviewed during this inspection. The violation is similar to several non-

cited violations (NCVs) of very low safety significance identified by the NRC within the past two

years for which corrective actions have not been fully effective. The violation was evaluated in

accordance with the NRCs Enforcement Policy. The current Enforcement Policy is available for

review on the NRCs Website http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-

pol.html. This violation meets the criteria in Section 2.3.2a of the Enforcement Policy to

disposition it as an NCV. However the NRC is issuing a Notice of Violation because corrective

actions have not been effective in addressing ASR-related structural issues. Specifically,

corrective actions to address NRC findings involving identification and evaluation of ASR effects

on structures over the past two years were not effective to ensure prompt operability

determinations were maintained with the latest information. Accordingly, the NRC is issuing the

Notice of Violation and requiring a response regarding your plans to address this concern.

You are required to respond to this letter and follow the instructions specified in the enclosed

Notice when preparing your response. Your response in accordance with the instructions

should describe your actions to address the violation and your plans and milestones to resolve

the non-conforming condition involving ASR-affected Seabrook structures. If you have

additional information that you believe the NRC should consider, you may provide it in your

response to the Notice. The NRCs review of your response to the Notice will determine

whether additional enforcement action is necessary to ensure compliance with regulatory

requirements.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's

"Rules of Practice," a copy of this letter, its enclosure, and your response, will be available

electronically, for public inspection, in the NRCs Public Document Room or from the Publicly

Available Records component of the NRCs document system, Agencywide Documents Access

and Management System (ADAMS). ADAMS is accessible from the NRCs Website at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Mel Gray, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No. 50-443

License No. NPF-86

Enclosure:

1. Inspection Report No. 05000443/20160008

w/Attachment: Supplemental Information

2. Notice of Violation

cc w/encl: Distribution via ListServ

D. Curtland

- 2 -

One violation of very low safety significance (Green) is cited in a Notice of Violation (Notice) and

the circumstances surrounding it are described in the enclosed inspection report. The violation

describes two examples where initial and prompt operability determinations were not completed

by NextEra staff when additional information regarding the effects of ASR on safety-related

concrete structures was identified. Prompt operability determinations have since been

developed and were reviewed during this inspection. The violation is similar to several non-

cited violations (NCVs) of very low safety significance identified by the NRC within the past two

years for which corrective actions have not been fully effective. The violation was evaluated in

accordance with the NRCs Enforcement Policy. The current Enforcement Policy is available for

review on the NRCs Website http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-

pol.html. This violation meets the criteria in Section 2.3.2.a of the Enforcement Policy to

disposition it as an NCV. However the NRC is issuing a Notice of Violation because corrective

actions have not been effective in addressing ASR-related structural issues. Specifically,

corrective actions to address NRC findings involving identification and evaluation of ASR effects

on structures over the past two years were not effective to ensure prompt operability

determinations were maintained with the latest information. Accordingly, the NRC is issuing the

Notice of Violation and requiring a response regarding your plans to address this concern.

Accordingly, the NRC is issuing the Notice of Violation and requiring a response regarding your

plans to address this concern.

You are required to respond to this letter and follow the instructions specified in the enclosed

Notice when preparing your response. Your response in accordance with the instructions

should describe your actions to address the violation and your plans and milestones to resolve

the non-conforming condition involving ASR-affected Seabrook structures. If you have

additional information that you believe the NRC should consider, you may provide it in your

response to the Notice. The NRCs review of your response to the Notice will determine

whether additional enforcement action is necessary to ensure compliance with regulatory

requirements.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's

"Rules of Practice," a copy of this letter, its enclosure, and your response, will be available

electronically, for public inspection, in the NRCs Public Document Room or from the Publicly

Available Records component of the NRCs document system, Agencywide Documents Access

and Management System (ADAMS). ADAMS is accessible from the NRCs Website at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Mel Gray, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No. 50-443

License No. NPF-86

Enclosure:

1. Inspection Report No. 05000443/20160008

w/Attachment: Supplemental Information

2. Notice of Violation

cc w/encl: Distribution via ListServ

D. Curtland

- 3 -

Letter to Mr. Dean Curtland from Mr. Mel Gray dated May 6, 2016

SUBJECT:

SEABROOK STATION - INSPECTION REPORT 05000443/2016008

RELATED TO ALKALI-SILICA REACTION (ASR) AFFECTS ON

SAFETY-RELATED CONCRETE STRUCTURES

DISTIRBUTION w/encl: (via e-mail)

DLew, actg RA

SFlanders, actg DRA

MScott, DRP

DPelton, DRP

RLorson, DRS

BSmith, DRS

FBower, DRP

RBarkley, DRP

MDraxton, DRP

RVadella, DRP

PCataldo, DRP, SRI

JVazquez, DRP, Actg RI

ACass, DRP, Resident AA

MGray, DRS

NFloyd, DRS

ABuford, NRR

BLehman, NRR

JBowen, RI, OEDO

BBickett, RI, ORA

WCook, RI, DRS

RidsNrrPMSeabrook Resource

RidsNrrDorlLpl1-2 Resource

RidsNrrDLR Resource

ROPreports Resource

DOCUMENT NAME: G:\\DRS\\Engineering Branch 1\\ -- Gray M\\Seabrook Standalone Report 2016-008.docx

ADAMS Accession Number: ML16127A155

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available

OFFICE

RI/DRS

NRR/DLR

RI/DRP

RI/DRS

RI/ORA

NAME

WCook/ WC

ABuford / concurred by

e-mail

FBower/ FLB

MGray/ MG

BBickett/ BB

DATE

05/03/2016

05/05/2016

05/05/2016

05/06/2016

05/05/2016

OFFICIAL RECORD COPY

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Docket No.

50-443

License No.

NPF-86

Report No.

05000443/2016008

Licensee:

NextEra Energy Seabrook, LLC

Facility:

Seabrook Station

Location:

Seabrook, NH 03874

On-Site Dates:

February 1 - 5 and March 21 - 24, 2016

Inspector:

William A. Cook, Senior Reactor Analyst

Region I

Accompanied by:

Angela Buford, Structural Engineer

Office of Nuclear Reactor Regulation (NRR)

Bryce Lehman, Structural Engineer, NRR

Approved by:

Mel Gray, Chief

Engineering Branch 1

Division of Reactor Safety

Enclosure 1

NOTICE OF VIOLATION

NextEra Energy Seabrook, LLC

Docket No. 50-443

Seabrook Station

License No. NPF-86

EA-16-101

During an NRC inspection conducted between February 1 and March 24, 2016, a violation of

NRCs requirements was identified. In accordance with the NRC Enforcement Policy, the

violation is listed below:

10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, states, in part,

that activities affecting quality shall be prescribed by documented instructions, procedures or

drawings, of a type appropriate to the circumstances, and shall be accomplished in accordance

with these instructions, procedures or drawings.

NextEra Nuclear Fleet Administrative Procedure, EN-AA-203-1001, Operability

Determinations/Functionality Assessments, identifies the responsibilities and requirements for

preparation and approval of Immediate Operability Determinations (IOD) and Prompt Operability

Determinations (POD) for establishing the acceptability of continued operation of a plant

structure, system, or component that is suspected to be degraded or nonconforming. Per

Section 2.0, Terms and Definitions, IODs are performed by the Shift Manager without delay

(within 8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> of discovery), using best available information to make an operability declaration.

Upon request of the Shift Manager, a POD is performed as a follow-up to an IOD when

additional information is needed to confirm the declaration of operability.

Contrary to the above, on two occasions between March 17, 2015, and January 22, 2016,

Energy Seabrook, LLC (NextEra) did not accomplish an activity affecting quality in accordance

with its procedure. Specifically, NextEra received information from vendors identifying non-

conforming conditions adversely impacting two reinforced concrete structures at Seabrook

Station, and did not complete an appropriate IOD or initiate a follow-up POD to evaluate the

impact of that non-conforming condition on structural performance. In particular,

1) On March 17, 2015, NextEra entered a WJE report, entitled Condition Assessment

of the Cracking in the RHR and CS Equipment Vault, into the station document

tracking system and added the reports recommendations into the Corrective Action

Program under Action Report (AR) 01977456, without completing an appropriate IOD

or initiating a POD. The report identified structural loading (a load not considered by

ACI 318-71, the design and construction code of record) due to ASR as the cause for

the excessive bulk expansion and cracking of the RHR/CS Vault interior and exterior

support walls; and

2) On December 2, 2015, NextEra initiated AR 02094762 to track recommendations

from SG&H report entitled Evaluation and Design Confirmation of As-Deformed

CEB, without completing an appropriate IOD or initiating a POD. The report also

identified structural loading due to ASR as the cause for deformation of the

Containment Enclosure Building (CEB), a condition not conforming with ACI 318-71.

2

This violation is associated with a Green Significance Determination Process finding.

Pursuant to the provisions of 10 CFR 2.201, NextEra is hereby required to submit a written

statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN: Document Control

Desk, Washington, DC 20555-0001 with a copy to the Regional Administrator, Region I, and a

copy to the NRC Resident Inspector at Seabrook Station, within 30 days of the date of the letter

transmitting this Notice of Violation (Notice). This reply should be clearly marked as a Reply to

a Notice of Violation EA-16-101 and should include: (1) the reason for the violation, or, if

contested, the basis for disputing the violation or severity level; (2) the corrective steps that

have been taken and the results achieved; (3) the corrective steps that will be taken including a

comprehensive and integrated ASR corrective action plan (ACAP) for resolving ASR-induced

non-conformances with the current licensing basis (CLB) and the date when your structures

monitoring program will be revised to monitor the progression of ASR degradation related to

bulk expansion and deformation; and (4) the date when full compliance will be achieved. Your

response may reference or include previous docketed correspondence, if the correspondence

adequately addresses the required response. If an adequate reply is not received within the

time specified in this Notice, an Order or a Demand for Information may be issued as to why the

license should not be modified, suspended, or revoked, or why such other action as may be

proper should not be taken. Where good cause is shown, consideration will be given to

extending the response time.

If you contest this enforcement action, you should provide a copy of your response, with the

basis for your denial, to the Director, Office of Enforcement, United States Nuclear Regulatory

Commission, Washington, DC 20555-0001. Because your response will be made available

electronically for public inspection in the NRC Public Document Room or from the NRCs

document system (ADAMS), accessible from the NRCs Website at http://www.nrc.gov/reading-

rm/adams.html, to the extent possible, it should not include any personal privacy, proprietary, or

safeguards information so that it can be made available to the public without redaction. If

personal privacy or proprietary information is necessary to provide an acceptable response,

then please provide a bracketed copy of your response that identifies the information that

should be protected and a redacted copy of your response that deletes such information.

If you request withholding of such material, you must specifically identify the portions of your

response that you seek to have withheld and provide in detail the bases of your claim of

withholding (e.g., explain why the disclosure of information required by 10 CFR 2.390(b) to

support a request for withholding confidential commercial or financial information).

If Safeguards information is necessary to provide an acceptable response, please provide the

level of protection described in 10 CFR 73.21.

In accordance with 10 CFR 19.11, you may be required to post this Notice within two working

days of receipt.

Dated this 6th day of May 2016

Enclosure 2

SUMMARY

IR 05000443/2016008; 2/01/2016 - 3/24/2016; Seabrook Station (Problem Identification and

Resolution; Follow-up on Operability Determinations).

This report covers an inspection by a regional Senior Reactor Analyst, with assistance from

Office of Nuclear Reactor Regulation (NRR) structural specialists. One Green finding was

identified. The significance of most findings is indicated by their color (Green, White, Yellow,

Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination Process

(SDP). The cross-cutting aspects for the findings were determined using IMC 0310,

Components Within Cross-Cutting Areas. The NRCs program for overseeing the safe

operation of commercial nuclear power reactors is described in NUREG-1649, Reactor

Oversight Process, Revision 4, dated December 2006.

Cornerstone: Mitigating Systems

Green. The team identified a violation of Appendix B, Criterion V, Instructions, Procedures, and

Drawings, and NextEra Nuclear Fleet Administrative Procedure, EN-AA-203-1001, Operability

Determinations/Functionality Assessments, involving Seabrook Station staff failing to perform

operability evaluations for identified non-conforming conditions. Specifically, the team identified

that following receipt of a vendors structural assessment of the RHR/CS Vault on March 17,

2015, the Seabrook staff failed to complete an appropriate immediate operability evaluation or

initiate a Prompt Operability Determination (POD) for an identified structural load (ASR induced)

not considered by ACI 318-1971, the design and construction code of record. The team also

identified that following receipt of another vendors report, Structural Evaluation and Design

Confirmation of the CEB, on December 2, 2015, that the Seabrook staff failed to complete an

immediate and follow-on POD to address ASR induced loads (due to internal expansion and

externally applied by ASR-affected concrete backfill) that are causing CEB structural

deformation.

The team determined that the two examples of failure to identify structural loading due to ASR

expansion as a non-conforming condition and to then promptly evaluate the impact of this

condition on the operability of the affected structures is a performance deficiency. This

performance deficiency is considered to be more than minor because the non-conforming

condition adversely impacts the structural integrity design attribute of the reactor safety barrier

integrity and mitigating systems objectives. In addition, the finding is similar to more than minor

Example 3.i of Appendix E of IMC 0612. The finding was evaluated in accordance with IMC 0609, Appendix A, The Significance Determination Process for Findings At-Power, Exhibit 3,

Barrier integrity Screening Questions, and screened as very low safety significance (Green)

because the finding only represents a degradation in design margin and did not impact the

radiological barrier function of the affected structures. The finding had a cross cutting aspect in

the area of problem identification and resolution, P3, timely resolution of issues. Specifically,

NextEra did not fully evaluate conditions adverse to quality, including evaluating the effects of

the ASR expansion-induced loads on operability of certain structures, in a timely manner

following identification by an engineering analysis. (Section 4OA5)

REPORT DETAILS

Background

The alkali-silica reaction (ASR) is a chemical reaction in concrete, which occurs over time in the

presence of water, between the alkaline cement paste and reactive non-crystalline silica that is

found in some common coarse aggregates. In the presence of water, the ASR forms a gel that

expands, causing micro-cracks that change the physical structural properties of the concrete,

including compressive and tensile strength, modulus of elasticity, and Poisson Ratio. At

Seabrook Station, reinforced concrete structures have shown evidence of ASR degradation.

In the summer 2010, NextEra performed an Immediate and Prompt Operability Determination

(POD) for the control building B electrical tunnel structure based on core samples taken from

the building. NRC inspection Report 05000443/2010004, issued November 1, 2010, ADAMS

Accession No. (ML103050447) documented the NRC review of the POD with no findings. From

2010-2012, the NRC completed further inspections (ML111330689; ML112241543;

ML120480066) of NextEras activities to investigate, evaluate and monitor Seabrook structures

affected by ASR. These inspections resulted in the NRC issuing Confirmatory Action Letter

No. 1-2012-002 dated May 16, 2012, to document NextEras commitments to address ASR-

affected Seabrook structures (ML12125A172). The commitments involved NextEra establishing

a bounding prompt operability determination for all ASR-affected buildings as well as interim

monitoring actions to ensure ASR related degradation is effectively managed. Additional

commitments included the commencement of test programs at the Ferguson Structural

Engineering Laboratory (FSEL), University of Texas at Austin to validate monitoring methods, to

assess structural performance, and to enhance the Seabrook Structures Monitoring Program

(SMP) to manage ASR.

NextEra concluded that ASR-affected structures remained operable, but were non-conforming

with the site design and licensing basis. The NRC completed team inspections to verify

NextEra staff completed their commitments and documented the results in inspection reports

dated December 3, 2012, and August 9, 2013 (M112338A283 and ML13221A172). The NRC

documented how each commitment was determined to be met and closed the CAL via NRC

letter dated October 9, 2013 (ML13274A670).

The NRC continued to conduct inspections approximately every six months to evaluate

NextEras activities to investigate, monitor and affirm the structural capability of Seabrook

structures affected by ASR.

NextEras testing of large scale ASR-affected test specimens at FSEL commenced in late 2013

and was planned to be completed under NextEras direction by February 2016. In 2014-2015,

the inspectors documented findings of very low safety significance associated with discrete,

large horizontal cracks in an internal wall of the residual heat removal and containment spray

(RHR/CS) Vault (ML14212A458); cracks associated with the fuel storage building

(ML15037A172); and global relative deformation of the containment enclosure building (CEB)

(ML15217A256). The staff concluded these findings were of very low safety significance

because the safety function of these structures was not affected.

Based on FSELs large scale testing program developments in 2015, NextEra revised their

structures monitoring/ASR monitoring aging management program to include through-wall

expansion monitoring. This expansion will be monitored by devices installed in 2016 in several

dozen representative locations.

2

In the fall 2015, the inspectors completed an inspection to follow-up on the results of NextEras

evaluations and monitoring of the CEB and RHR/CS Vault. In an NRC inspection report dated

February 12, 2016, (ML16043A391) the inspectors documented unresolved item (URI)

05000443/2015-01, regarding NextEras implementation of the Seabrook SMP. The inspectors

determined that structural evaluations, performed by contractors and accepted by NextEra staff

via their foreign print document control process, included discussions that identified the

potential to exceed limits in the applicable design and construction code (ACI 318-71) for

specific locations in the CEB and RHR/CS Vault walls. The evaluations further recommended

actions to determine whether this was the case. The inspectors noted that the Seabrook staff

screened or reviewed these evaluations without documenting a justification in a revision or

update to the open prompt operability determination (PODs) for these structures. The

inspectors requested additional information (ML15357A326) and identified that follow-up

inspection was necessary to determine whether there was a performance deficiency. This

report documents a follow-up inspection conducted to close this unresolved item 05000443/2015004-01 utilizing NRC Inspection Procedure 71152, Problem Identification and

Resolution.

4.

OTHER ACTIVITIES

4OA2

Problem Identification and Resolution (71152)

.1

Annual Sample: Review of Corrective Actions for Alkali-Silica Reaction Affected Structures

a. Inspection Scope

A Senior Risk Analyst from the NRC Region I Office and two structural engineers from

the NRC Office of Nuclear Reactor Regulation (NRR) conducted in-office reviews and

two onsite inspections (weeks of February 1 - 5, 2016 and March 21 - 24, 2016) at the

Seabrook Station to review NextEras root cause evaluation and corrective actions

related to the identification of differential movement, or deformation, of the containment

enclosure building (CEB). This condition was previously described in an NRC inspection

report dated August 25, 2015 (ML15217A256). NRC inspectors also reviewed

evaluations related to discrete cracks identified in below grade, internal walls in the

residual heat removal and containment spray (RHR/CS) equipment vault. This condition

was previously described in an NRC inspection report dated August 5, 2014,

(ML14212A458).

The inspectors performed an in-depth review of NextEras Prompt Operability

Determinations (PODs) and associated evaluations and corrective actions to these non-

conforming conditions and NextEras response (ML16117A312) dated April 14, 2016, to

related questions communicated by the NRC staff on December 23, 2015

(ML15357A326).

The inspectors also assessed the problem identification threshold, extent of condition

reviews, and the prioritization and timeliness of corrective actions to determine whether

NextEra personnel were appropriately identifying, evaluating ASR-related problems

associated with the CEB, RHR/CS Vault and other ASR-affected structures at Seabrook

Station. The inspectors compared actions taken by the Seabrook staff to NextEras

Corrective Action Program (CAP) implementing procedures and 10 CFR 50, Appendix B.

3

b. Findings

Residual Heat Removal and Containment Spray (RHR/CS) Vault

Introduction. The team identified a violation of Appendix B, Criterion V, Instructions,

Procedures, and Drawings involving Seabrook Station staff failing to perform an

operability evaluation for an identified non-conforming condition. Specifically, the team

identified that NextEra staff accepted their vendors structural assessment report of the

RHR/CS Vault on March 17, 2015, which identified an ASR induced structural load not

considered in the design code of record. However, Seabrook staff did not complete an

appropriate immediate operability evaluation, initiate a new Prompt Operability

Determination or revise their POD for the RHR/CS Vault to evaluate this information.

Description. The team reviewed the following Action Reports (ARs) and corrective

action program documents to assess NextEras response to observed ASR-related

structural deformation and bulk expansion and cracking of the RHR/CS Vault:

ARs 01664399 and 01757861 - These two ARs address a Prompt Operability

Determination, dated June 25, 2012, that concluded the RHR/CS Vault, along

with a number of other ASR-affected structures at Seabrook Station, were

operable but degraded. NextEra staff identified that the presence of ASR

adversely affected the mechanical properties of concrete. The basis for

concluding that the ASR-affected structures remained operable was the result

of re-evaluating design basis calculations for these structures assuming a

bounding value for critical limit state degradation and confirming sufficient

margin remained between design capacity and design demand/loads to

account for the assumed worst-case ASR degradation. The inspectors

determined that Revision 2 to this POD has remained in effect and valid since

mid-2012, but did not address the bulk expansion associated with ASR and

the consequential impact of structural cracking and deformation.

AR 01929460 - Initiated on December 23, 2013, to address concerns

expressed by the NRC resident inspectors that the observed macro-crack at

the minus 26-foot elevation of the RHR/CS Vault may have adverse structural

implications and may degrade the fire barrier rating of the wall separating the

RHR and CS equipment trains. The Operability Notes stated that NextEra

engineering staffs review concluded the cracks do not cause an

unacceptable condition for either a fire barrier or structural consideration.

This immediate operability evaluation was later supplemented by a Condition

Evaluation, dated December 23, 2013, and then revised on January 13,

2014.

Assignment 03 was initiated to have a vendor complete a condition

assessment of the RHR/CS Vault using ACI 349.3R guidelines. The

Completion Notes for Assignment 03 stated that the follow-up actions

(recommendations) from the Wiss, Janney, Elstner Associates (WJE)

Condition Assessment (FP100903) have been added to AR 01977456.

AR 01977456 - Initiated on July 10, 2014, to address the NRC resident

inspectors having identified a Green finding involving the failure to have

appropriately addressed the RHR/CS Vault macro crack in accordance with

Seabrook Station Structures Monitoring Program (SMP).

4

Specifically, the observed macro crack exceeded the SMP Tier 2 criteria

(reference ACI 349.3R) and warranted a structural evaluation, but NextEra

staff had failed to complete the structural evaluation. The inspectors

determined the Operability Notes used a template operability assessment

statement that identified that the issue (failure to adhere to the SMP) did not

directly relate to the functionality of system, structure or component.

The inspectors determined NextEra staff processed and accepted the WJE Condition

Assessment of the Cracking in RHR and CS Equipment Vault, dated March 5, 2015,

into the Seabrook documentation tracking system under Foreign Print (FP) 100903 on

March 17, 2015. Included in this document was a limited structural analysis

(Section 5.2) which described the cracks as likely resulting from an ASR-related load not

previously accounted for in the design basis structural calculation. The inspectors

determined that this statement represented a non-conforming structural loading

condition and was not identified by NextEra staff as new information which impacted

their RHR/CS Vault prompt operability determination (POD). The inspectors observed

the FP100903 recommendations (Section 7) were added to this AR (01977456) under

Assignments 13, 17 and 18, for tracking purposes.

In response to NRC inspectors questions, NextEra staff issued a POD (Action 20) under

AR01977456 on February 12, 2016, for the RHR/CS Vault to address the non-

conforming condition identified in FP100903. The POD concluded the RHR/CS Vault

was operable, but nonconforming. Based upon NRC inspector review, the more

correct characterization, per EN-AA-203-1001, should be operable, but degraded. This

non-compliance with EN-AA-203-1001 is considered a minor issue, but is documented

for assessment purposes (reference AR 02120109, Assignment 04). The teams

technical review of the RHR/CS Vault POD is documented in Section 4OA2.2 of this

report.

AR 02085029 - Initiated on October 23, 2015, following an NRC resident

inspector briefing of plant management. The inspectors questioned the

timeliness of implementation of recommendations NextEra staff accepted as

outlined in the WJE Condition Assessment. The inspectors identified that

implementation dates of June 2015 were revised to December 2015, without

NextEra staff receiving approval from their internal management review

committee (MRC). The Operability Notes for this AR was a template

operability statement (same as used for AR01929460 above). See Section

4OA2.3 below for disposition of this observation.

Containment Enclosure Building (CEB)

Introduction. The team identified a violation of Appendix B, Criterion V, Instructions,

Procedures, and Drawings involving NextEra staff at the Seabrook Station failing to

perform an operability evaluation for an identified non-conforming condition. Specifically,

the team identified that NextEras staff accepted their vendors report related to the CEB

which described ASR induced loads from internal expansion not considered in the

design code of record (ACI 318-71). Further, Seabrook staff did not complete an

appropriate immediate operability evaluation, initiate a new POD or revise their current

POD for the CEB to evaluate this information.

5

Description. The team reviewed the following ARs and corrective action program

documents to assess NextEras response to observed ASR-related structural

deformation of the CEB:

ARs 01664399 and 01757861 - These two ARs address a Prompt Operability

Determination, dated June 25, 2012, that concluded the CEB, along with a

number of other ASR-affected structures at Seabrook Station, were operable,

but degraded. The inspectors observed Revision 2 to this POD remained in

effect and valid since mid-2012, but does not address the bulk expansion

associated with ASR or the consequential CEB deformation.

AR 02004748 - Initiated on November 4, 2014, as a result of the NRC

resident inspectors identifying a degraded mechanical seal in the mechanical

penetration area of the Containment Enclosure Ventilation Area (CEVA)

building. Follow-up examination by NextEra staff identified that the fire seal

and associated seismic gap was degraded due to differential movement or

deformation of the CEB wall relative to the CEVA building walls. This AR

resulted in the Seabrook staff initiating a POD (AR 02044627) to ensure the

CEB seismic gaps were being maintained. In addition, NextEra staff initiated

an Apparent Cause Evaluation (ACE) to evaluate the causes and effect of the

CEB deformation.

AR 02014325 - Initiated on December 19, 2014, as a result of the findings

from the engineering staffs preliminary CEB walkdowns (required or initiated

per AR 02004748). The title of AR 02014325 is Assess potential aggregate

impact of CEB movement, and listed seven separate ARs identifying

impacted systems or components. The Operability Notes for this AR stated

that This AR is written to evaluate the overall impact of an observed plant

condition. The results will need to be evaluated for operability as they come

up. This AR by itself has no impact on operability of TS or SSCs. Per

Assignment 02 of this AR, the Seabrook Management Review Committee

(MRC) approved a charter to complete a root cause evaluation (RCE) of the

observed CEB deformation and canceled the ACE assigned via AR

02004748. The inspectors noted that a CEB structural evaluation was

integral to the RCE efforts.

AR 02044627 - Initiated on April 30, 2015, following the completion of 93

measurements completed by NextEras contractor Simpson,

Gumpertz & Heger Associates (SG&H) of the CEB seismic gaps. During

MRC review of this AR on May 5, 2015, a POD was assigned (02) due by

May 7, 2015, and completed on June 11, 2015. In addition, assignments

were initiated to revise the SMP (04), perform periodic (six month frequency)

seismic gap measurements (07), and complete a revision to the Updated

Final Safety Report (UFSAR) (08).

CEB RCE Report entitled Containment Enclosure Building Local

Deformation, was issued August 5, 2015, and approved August 31, 2015.

The RCE used the following Problem Statement: Structural movement of

the seismic Category 1 CEB structure, which has resulted in damage to fire

seals and movement in flexible conduit connections, could result in future

adverse impact to the CEB ventilation function and adjacent structures and

components.

6

NextEra identified two major causal factors, as follows:

RC1 - Internal expansion (strain) in the CEB concrete produced by ASR in the in-

plane direction of the CEB shell and ASR expansion in the backfill concrete,

coincident with a unique building configuration.

RC2 - Due to an organizational mindset that conditions such as concrete cracks,

water infiltration and misalignment issues were acceptable and inconsequential, the

Organization failed to formally perform and document comprehensive evaluations of

building conditions. These building conditions could have potentially revealed more

significant underlying conditions affecting other structures, such as localized

deformation of the CEB.

Multiple corrective actions were initiated by NextEra staff, including several PODs for

systems impacted by the CEB deformation. However, NextEra staff did not initiate a

POD or re-evaluate the current open PODs (AR 01664399/AR 1757861) to assess CEB

structural performance with the newly identified ASR deformation mechanism. Further,

the assignment to complete a structural evaluation per AR 02014325 was not

implemented. The team viewed this as a missed opportunity by the NextEra staff to

have assessed CEB structural performance, following the identification of a new and

different ASR impact (load) on affected structures.

AR 02094762 - Initiated on December 2, 2015, as a result of NextEra receipt

of SG&H report (FP100985) titled Evaluation and Design Confirmation of As-

Deformed CEB. This evaluation was completed coincident with the CEB

RCE. The AR was initiated to track the implementation of recommendations

from the SG&H structural evaluation involving the performance of additional

engineering reviews and monitoring. The team identified that the Operability

Notes documented a template operability paragraph, stating that an

operability determination was not required. The teams review of FP100985

identified that the vendor had concluded that the CEB deformation was a

result of structural response to both internal loading due to ASR expansion

and external loading due to expansion of ASR-affected concrete backfill.

Review of CAP records by the team identified that the MRC reviewed this AR

on December 8, 2015, and assigned an action to complete a Condition

Evaluation by December 30, 2015. The Condition Evaluation was entered

into the CAP on December 30, 2015, and provided a qualitative basis for the

continued operability of the CEB. Per the December 30, 2015, Condition

Evaluation, AR 02094762 Assignment 02 was initiated to update the current

CEB POD (AR 01664399) by February 29, 2016. These assignments were

made in the timeframe when NRC inspectors were questioning NextEra staff

regarding the POD process and the information in FP100985.

On February 19, 2016, NextEra approved a POD (under AR 02094762) that addressed

the CEB nonconforming conditions identified in FP100985 involving ASR bulk expansion

loading of the structure resulting in building deformation. The POD concluded the CEB

was operable, but degraded. The teams detailed technical review of the CEB POD is

documented in Section 4OA2.2 of this report.

7

AR 02109229 - Initiated on February 10, 2016, as a result of an onsite NRC

PI&R inspection debrief with station management. The inspectors

questioned whether NextEra staff had defined ASR induced deformation in

the context of the current licensing basis and ACI 318-71. The teams review

concluded that the results of the SG&H structural evaluation of the CEB and

WJE condition assessment of the RHR/CS Vault independently identified that

the deformation (and macro-cracking) caused by ASR expansion represented

a structural load not considered by ACI 318-71. Accordingly, this ASR-

induced structural loading is a non-conforming condition.

Summary - NRC Team Reviews of the RHR/CS Vault and CEB

The team determined that NextEra staff did not complete an appropriate review of the

WJE report (FP100903) for the purpose of assessing the implications of the report

conclusions on current RHR/CS Vault structural performance and operability. The

teams review of the WJE Condition Assessment identified that the report contained

sufficient information to conclude that ASR generated loads (internally generated by the

structure) were causing the RHR/CS Vault wall displacement and cracking, and that no

design basis loads could have conceivably caused the observed condition.

Consequently, it was reasonable to conclude that the ASR imparted structural loading

constitutes a non-conformance with ACI 318-71, the building and construction code of

record, which does not consider ASR-induced loads.

The team also concluded, based upon their review of the SG&H structural evaluation

(FP100985), that sufficient information was documented in the evaluation for NextEra to

have concluded that a new or updated operability determination for the CEB was

warranted. Specifically, the ASR-induced loads resulting in the deformation of the CEB

were not considered in the original design loading calculations (non-conforming

condition), and based upon the preliminary finite element analysis (FEA) results, design

margins were potentially impacted due to ASR expansion induced loading.

From review of the above ARs and follow-up interviews with Seabrook staff, the team

determined that NextEra did not consider the results of either the WJE condition

assessment (FP100903) or SG&H structural evaluation (FP100985) as representing

significantly new or different information that would change their engineering judgment

(albeit undocumented) regarding the continued operability of either the RHR/CS Vault or

CEB. However, the inspectors concluded NextEra staff did not adhere to their Fleet

Procedure EN-AA-203-1001 in documenting this operability determination until identified

by the NRC.

Analysis. The team determined that the two examples of failure to identify structural

loading due to ASR expansion as a non-conforming condition and to promptly evaluate

the impact of this condition on the operability of the affected structures is a performance

deficiency. This performance deficiency is considered to be more than minor because

the non-conforming condition adversely impacts the structural integrity design attribute of

the reactor safety barrier integrity and mitigating systems objectives. In addition the

finding is similar to more than minor Example 3.i of Appendix E of IMC 0612. The finding

was evaluated in accordance with IMC 0609, Appendix A, The Significance

Determination Process for Findings At-Power, Exhibit 3, Barrier Integrity Screening

Questions, and screened as very low safety significance (Green) because the finding

only represents a degradation in design margin and did not impact the radiological

barrier function of the affected structures. The finding had a cross cutting aspect in the

area of problem identification and resolution, P3, timely resolution of issues.

8

Specifically, NextEra did not fully evaluate conditions adverse to quality, including

evaluating the effects of the ASR expansion-induced loads on operability of certain

structures, in a timely manner following identification by a vendor provided engineering

analysis.

Enforcement. 10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, and

Drawings, states that activities affecting quality shall be prescribed by documented

instructions, procedures and drawings, and shall be accomplished in accordance with

these instructions, procedures or drawings. NextEra Nuclear Fleet Administrative

Procedure, EN-AA-203-1001, Operability Determinations/Functionality Assessments,

Sections 4.2 thru 4.4 identify the responsibilities and requirements for preparation and

approval of Immediate Operability Determinations (IOD) and Prompt Operability

Determinations (POD) for establishing the acceptability of continued operation of a plant

structure, system, or component that is suspected to be degraded or nonconforming.

Contrary to the above: (1) no immediate operability determination (IOD) was performed

on March 17, 2015, (or Prompt Operability assigned) when NextEra entered the WJE

condition assessment recommendations into Assignment 03 of AR 01977456; and (2) no

IOD was performed on December 2, 2016, (or Prompt Operability assigned) when the

NextEra staff entered the SG&H structural evaluation recommendations in to the CAP

per Assignment 01 of AR 02094762. Operability determinations were not initiated for the

RHR/CS Vault or CEB until prompted by the NRC staff (on or about December 23, 2015)

following a conference call between the NRC and NextEra staffs to convey questions

regarding the NRCs review of the CEB RCE and FPs 100895 and 100903.

Because this performance deficiency is a repeat problem and representative of an

organizational insensitivity to the need for prompt identification and evaluation of an

ongoing ASR degradation mechanism (a unique structural performance challenge), this

violation is being cited and warrants a docketed response to address the corrective

actions taken or planned to prevent recurrence. (NOV 5000443/2016008-01 Failure to

Complete Operability Determinations for ASR-Affected Structures)

c. Observations

The team conducted in-office reviews and follow-up discussions with the Seabrook staff

and contractors regarding NextEras response to the questions posed during a

December 23, 2015 conference call (ML14014A378). The team considered the

responses to better understand the technical bases for NextEras engineering

evaluations and operability assessments of the CEB and RHR/CS Vault. NextEras

revised response was provided to the NRC on April 14, 2016 and is publicly available in

(ML16117A312).

1) The team re-examined the Containment POD (AR 1804477), Revision 00, dated

November 1, 2012, to re-assess the validity of the operability evaluation based upon the

recent identification of ASR induced bulk expansion and deformation of other safety

related ASR-affected structures. Based upon NRC staff and licensee walkdowns, no

evidence of ASR-related bulk expansion has been identified on the containment

structure. As documented in the POD, the accessible outer surface of containment

(the inner surface is inaccessible due to the stainless steel liner/fission product barrier)

exhibits evidence of localized ASR micro-cracking in three areas in the annulus region

and one location in the mechanical penetration area. The micro-cracking in the

mechanical penetration area exceeded the ACI 349.3R Tier 2 criteria and prompted the

structural evaluation accompanying the POD. Team review of the containment POD

concluded that the operability evaluation remains valid and that the ASR-affected

9

concrete remains non-conforming with ASME Section III, Division 2, (the design and

construction code of record for the containment). The team noted that the five-year

ASME Section XI, IWL-2410 in-service inspection of the entire outer containment

surface is scheduled by NextEra to be completed later in 2016.

Based upon the teams review of the POD, Revision 00, it was unclear how NextEras

staff classified the ASR-affected concrete of containment. Specifically, the POD used

Revision 1 of Form EN-AA-203-1001-F01 of the NextEra Fleet Procedure EN-AA-203-

1001, and classified the ASR impact on containment as Operable and above Full

Qualification. This classification also considered that the degraded SSC meets Full

Qualification as described in the Current Licensing Basis. The inspectors review of the

current revision to EN-AA-203-1001-F01, Revision 09, identified that the comparable

POD classification would be Operable and Fully Qualified with Reduced Margin. The

Revision 09 classification implied that the subject SSC meets all CLB and qualification

requirements. However, the teams review of the Seabrook Updated Final Safety

Analysis Report (UFSAR), Sections 3.8.1.6.a (page 45) and 3.8.4.6 (page 146) identified

that ASR is considered to be a degraded nonconforming condition pursuant to

Regulatory Issue Summary (RIS) 2005-20.

UFSAR Revision 13-011, dated March 4, 2013, updated the description of the

containment structure and all other Category 1 structures. NextEra acknowledged this

observation and took action to revise their containment POD to ensure that the non-

conforming condition is addressed in their planned license amendment request submittal

(Reference AR 02120109, Assignment 10).

2) The team reviewed the results of a December 18, 2015, concrete core removed from the

Spent Fuel Pool telltale drain sump. This core was removed in accordance with a

license renewal commitment (No. 67) and was tracked via AR 00392697. Petrographic

examination of the core specimen (designated FSB-1) identified no evidence of boric

acid degradation, but did reveal minor ASR features. The examination was

documented in Laboratory Report 151303-LR-1, Revision 0, Microscopic Examination

of a Concrete Core Removed from Seabrook Station for Deterioration Mechanisms,

(Foreign Print 101052).

In conjunction with the review of the SFP sump core results, the team reviewed a series

of ARs and associated evaluations completed to assess structural movement

(deformation) of the reinforced concrete in the Fuel Storage Building (FSB). Dating back

to 2009 (reference AR 00196973) movement of FSB structural elements around the

spent fuel pool caused deformation of deck plates above the fuel transfer canal and

around the new fuel vault. Since 2010, NextEra, utilizing a contractor, has performed

periodic laser measurements of the FSB to monitor the deformation. Team review of the

measurement data taken between December 2010 and February 24, 2016, concluded

that the measurement trends are not attributable to building settlement or thermal

expansion and contraction. Instead, the trends indicate a bulk expansion affect,

attributable to ASR, in spite of the absence of the more typical signs of ASR, such as

patterned cracking and associated ASR gel surface extrusions. NextEra staff

acknowledged this observation and indicated that the FSB would be one of a number of

additional structures to receive a comprehensive Finite Element Analysis (FEA) to

evaluate the impact of ASR on structural performance and possible POD (Reference AR

02120109, Assignment 09).

10

3) The team confirmed through their detailed review of the associated ARs involving

structural deformation, that assignments were initiated to revise the UFSAR to reflect

this newly identified ASR attribute.

4) New PODs were documented for the structural deformation impacting the RHR/CS Vault

and the CEB. The team observed that for both of these reinforced concrete structures, a

second POD (ARs 01664399 and 01757861) was in effect addressing the material

property degradation associated with ASR. Although the respective PODs addressed

different attributes of an ASR-affected structure (one material property and the other

deformation caused by bulk ASR expansion), in the case of the CEB structural

evaluation and the supporting FEA, the material property degradation is concluded to not

have a detrimental impact on structural performance based on tests completed at FSEL.

Consequently, the team concluded the CEB deformation POD was inconsistent with the

original material properties POD. NextEra acknowledged this observation and planned

to conduct a collective review of the open PODs to determine how best to address the

non-conforming ASR-related attributes (Reference AR 02120109, Assignment 11).

5) For both the RHR/CS Vault and CEB PODs, the team identified that neither POD

identified a monitoring method to periodically affirm the validity of the operability

evaluations. The inspectors determined monitoring (either time or measurement based)

is warranted because ASR appears to be slowly progressing in reinforced concrete

structures at Seabrook Station. The team noted that an important assumption used in

the CEB FEA is that the modeling depicted a limited strain value of 0.03% (comparable

to the most advanced ASR aged large specimens in the FSEL testing program).

NextEra staff acknowledged this observation and planned to develop appropriate

monitoring methods and associated evaluation thresholds to ensure operability

evaluations remain valid and that remediation actions, if necessary, are implemented

prior to ASR-affected structures becoming compromised (Reference AR 02120109,

Assignments 03 and 05).

.2

Review of Prompt Operability Determinations

CEB POD Review

The POD for the CEB concluded that deformation in the structure was attributed

primarily to ASR expansion in CEB concrete and concrete backfill surrounding the CEB.

The POD concluded that the structure is operable but degraded. This conclusion was

based on the results of an FEA of a model of the CEB that accounted for the deformed

shape and effects of ASR expansion. The team reviewed the POD and the associated

FEA, and found the assumptions and conclusions reasonable. The team observed that

the POD followed NextEras criteria for operable but degraded in that the CEB does not

meet all CLB requirements, but is capable of performing specified functions. The team

also affirmed NextEras determination that compensatory measures are required.

NextEra staff indicated that they are in the process of collecting additional information,

and will update their POD, as necessary, based on additional information. During its

review, the team noted that NextEra staff made an assumption regarding the yield

strength of the concrete reinforcing steel that was not fully supported by the available

construction test results. NextEra staff acknowledged this issue and tracked actions to

revise their POD to include an appropriate steel yield strength value, for operability,

based on Certified Material Test Results (Reference AR 02120109, Assignment 06).

This issue was considered minor as it did not impact POD conclusions. The team also

questioned the limits as to which the POD would continue to be applicable and valid

11

considering ASR is an ongoing degradation mechanism. NextEra staff stated they plan

to revise their POD to include a threshold value (either time based or measurement

based) that will determine the applicability of the POD and will require the POD and

conclusions to be re-evaluated if the threshold is reached (AR 02120109, Assignment

05). The team observed that NextEra staff continued to refine their FEA to more

accurately represent the in-situ conditions in the model: (1) taking more measurements

of the structure to better represent the actual shape within the model; (2) refining the

application of the ASR degradation to the model to more accurately represent the ASR

identified on the actual structure; and (3) developing load factors to use when assessing

the internal ASR expansion loading in the structure.

NextEra staff stated that developing these load factors would allow them to apply the

ASR effects to the model in a fashion that is similar to that used in the design code of

record. NextEra staff further indicated that these updates will be applied to the model

and the structure will be reanalyzed, and any necessary updates will be made to the

operability determination.

RHR/CS POD Review

The POD for the RHR/CS Vault concluded that the observed horizontal macro cracking

is likely due to internal strain from ASR expansion in the vertical direction and that the

structure is operable but nonconforming. The team reviewed the POD and found the

assumptions reasonable based on NextEras current understanding of the cracking

mechanism. However, the team questioned NextEras conclusion that the structure is

operable but nonconforming. NextEras guidance states that an operable but

nonconforming SSC meets CLB functional requirements, but is nonconforming due to

inadequate design, testing, construction, modification, or documentation. The team

determined that NextEra staff has not shown that the concrete components affected by

the horizontal cracking meets all CLB functional requirements, and therefore the

classification level should be operable but degraded. NextEra staff acknowledged this

observation and planned to revise their POD (Reference AR 02120109, Assignment 04).

The team concluded this issue was minor because, notwithstanding their original

conclusion, NextEra staff were developing monitoring plans appropriate for a structural

designation of operable but degraded.

NextEra staff indicated that they may revise their POD based on the results of ongoing

investigations being conducted by their contractor (WJE). These investigations are

expected to be completed by May 2016. NextEra staff also plan to revise their POD to

include a threshold value (either time based or measurement based) that will limit the

applicability of the POD and will require the POD to be updated if the threshold is

reached (Reference AR 02120109, Assignment 03). NextEra staff further indicated that

they intend to include the RHR/CS Vault in a susceptibility analysis to determine how

likely it is that the vault may undergo additional cracking due to ASR. Depending on the

results of the analysis, NextEra staff stated that they may develop a finite element model

to address RHR/CS Vault operability. The team concluded these planned actions were

appropriate to continue to verify the RHR/CS Vault capability to perform its intended

safety related functions.

12

.3

RHR Vault Corrective Action Timeliness Observation

The inspectors determined that NextEras implementation of corrective actions

associated with the NRC identified degradation of the RHR vault concrete structure

(AR 01977456) was not completed in a timely manner and contrary to NextEra

Procedure PI-AA-104-1000, Corrective Action, Revision 6. Specifically,

PI-AA-104-1000 provides guidelines to consider when establishing due dates for low risk

corrective actions and states that routine corrective actions to prevent recurrence should

be completed within 120 days. In addition, PI-AA-104-1000 states that the Management

Review Committee (MRC) is responsible for reviewing justifications and approving due

date extensions for significance level (SL) 1, 2 or 3 AR assignments.

Contrary to this procedural guidance, SL 2 AR 01977456, Assignment 17, Develop

design change to implement (FP100903) recommendations, was initially assigned a

due date of April 30, 2015, extended to June 30, 2015, and then extended again to

December 1, 2015, without appropriate justification or MRC approval. Assignment 17

was extended to January 8, 2016 with MRC approval and closed-out on January 7, 2016

with the issuance of an Engineering Design Change. The elapsed time from corrective

action assignment to completion was 245 days, well in excess of the 120 day guidance

without MRC justification and approval.

The specific corrective actions associated with this SL 2 AR and incorporated into a

design change package involve:

Install crack gauges at 25 locations to monitor progression of RHR vault

cracking

Extract 20 concrete cores from the RHR vaults for material testing to identify

expansion mechanism

Install large-scale measurement devices to monitor vertical expansion of the

RHR vault walls

Install relative humidity and temperature probes at three locations in each

train of the RHR vaults to measure moisture gradient in the wall to better

understand ongoing behavior of ASR and/or drying shrinkage mechanisms

The inspectors evaluated this performance deficiency in accordance with the guidance in

IMC 0612, Appendix B, Issue Screening, and Appendix E, Examples of Minor Issues,

and concluded this performance deficiency was minor in safety significance.

Additionally, this issue is closely related to NextEras inadequate performance in not

initiating appropriate immediate and prompt operability determinations (PODs) when

new information was received in FP100903. An appropriate POD would have better

informed the timing of planned corrective actions. This issue is addressed in the Notice

of Violation included in this report. Accordingly, this performance deficiency is not

subject to further enforcement action, but is addressed in the Seabrook CAP (reference

AR 02085029) and documented for performance assessment purposes.

13

4OA5 Other Activities

.1

(Closed) Unresolved Item 05000443/2015004-01, Issue of Concern Regarding

Implementation of the Seabrook Structures Monitoring Program and Structural

Evaluations of the CEB and RHR/CS Vault.

The inspectors had identified potential shortcomings in NextEras implementation of the

Seabrook Structures Monitoring Program, acceptance of evaluations via the document

control (Foreign Print) process, and implementation of the Corrective Action Program as it

relates to Foreign Print 100895 for the CEB and Foreign Print 100903 for the RHR/CS

Vault walls. Additional inspection identified a performance deficiency and associated

violation (cited in this report) with two examples, involving NextEras failure to

appropriately evaluate non-conforming conditions identified in Foreign Print 100895 for the

CEB and Foreign Print 100903 for the RHR/CS Vault (See Section 4OA2.1.b).

This unresolved item is closed.

4OA6 Meetings, Including Exit

On March 24, the inspectors presented the results of this inspection to

Mr. Dean Curtland, Site Vice President, and other members of Seabrook Station and

NextEra Corporate staffs. The inspectors also confirmed with NextEra that no

proprietary information was retained by inspectors during the course of the inspection.

A-1

Attachment

SUPPLEMENTARY INFORMATION

KEY POINTS OF CONTACT

NextEra Personnel

B. Brown, Design Engineer

V. Brown, Senior Licensing Analyst

K. Browne, Special Projects Director

E. Carley, Engineering Supervisor

S. Chesno, Performance Improvement Manager

M. Collins, Engineering Director

D. Curtland, Site Vice President

A. Dodds, Plant General Manager

K. Douglas, Maintenance Director

M. Guth, Licensing Manager, Turkey Point

M. Hanson, Assistant Operations Manager

L. Nicholson, Regulatory Affairs Director

M. Ossing, Licensing Manager

V. Pascucci, Manager, Nuclear Oversight

S. Ramdeen, Civil Engineering Chief

D. Ritter, Operations Director

J. Simons, MPR Associates

C. Thomas, Senior Licensing Engineer

LIST OF ITEMS OPENED, CLOSED, DISCUSSED, AND UPDATED

Opened

05000443/2016-008-01

NOV

Failure to Complete Operability Determinations for

ASR-affected Structures (4OA2.1)

Closed:

05000443/2015-004-01 URI

Issue of Concern Regarding Implementation of the

Seabrook Structures Monitoring Program and

Structural Evaluations of the CEB and RHR/CS

Vault (4OA5)

A-2

LIST OF DOCUMENTS REVIEWED

Procedures

EN-AA-203-1001, Operability Determinations/Functionality Assessments, Revision 21

PI-AA-104-1000, Corrective Action, Revision 6

Engineering Department Standard 36180, Structural Monitoring Program, Revision 06

NexEra Nuclear Policy PI-AA-01, Corrective Action Program and Condition Reporting,

Revision 03

Plant Engineering Guidelines, PEG-98, CEB Extent of Condition Equipment Walkdown,

Revision 00

Reports

Seabrook Station Updated Final Safety Analysis Report, Revision 16 Foreign Print (FP100903),

Wiss, Janney, Elstner (WJE) Associates Condition Assessment of the Cracking in RHR and

CS Equipment Vault, dated March 5, 2015, Revision 0

FP101055, Condition Assessment of Cracking in the RHR and CS Equipment Vault -

Second Visit, dated 2/6/16

Containment Enclosure Building Local Deformation, Event Date December 19, 2014, issued

August 5, 2015 (reference CR 2014325)

FP100985, Evaluation and Design Confirmation of As-Deformed CEB, dated November 2015

FP100915, CEB Site Visit Report, dated July 14, 2015

Evaluation of OASIS Inspection Data, dated January 2015

OASIS Report, NextEra Energy Services Seabrook, NH, Fuel Storage Building Inspection,

dated February 23-24, 2016

FP100903, Condition Assessment of Cracking in RHR and CS Equipment Vault, dated

3/17/2015

Action Request

02016863

00196973

02094762

01804477

02094762

02014325

02044627

02004748

02108728

02085029

02056483

01977456

01929460

02109229

A-3

LIST OF ACRONYMS

AR

Action Request

ACE

Apparent Cause Evaluation

ACI

American Concrete Institute

ASR

Alkali-Silica Reaction

ASME

American Society of Mechanical Engineers

CB

Control Building

CEB

Containment Enclosure Building

CEVA

Containment Enclosure Ventilation Area

CFR

Code of Federal Regulations

CLB

Current Licensing Basis

CR

Condition Report

CS

Containment Spray System

DRS

Division of Reactor Safety

EC

Engineering Change

EN

Procedural Notice for Engineering Department

FEA

Finite Element Analysis

FIN

Finding

FP

Foreign Print

FSB

Fuel Storage Building

FSEL

Ferguson Structural Engineering Laboratory (At UT-Austin)

IMC

Inspection Manual Chapter

IOD

Immediate Operability Determination

IP

Inspection Procedure

KSI

Kilo-pounds per square inch

LAR

License Amendment Request

LRA

License Renewal Application

MRC

Management Review Committee

NCV

Non-Cited Violation

NOV

Notice of Violation

NRC

U.S. Nuclear Regulatory Commission

NRR

Office of Nuclear Reactor Regulation

OD

Operability Determination

PD

Performance Deficiency

POD

Prompt Operability Determination

PSIG

Pounds per square inch (gage)

RCA

Radiological Controlled Area

RCE

Root Cause Evaluation

RHR

Residual Heat Removal System

SDP

Significance Determination Process

SG&H

Simpson, Gumpertz & Heger Associates

SL

Severity Level

SR

Safety-related

SSC

Structure, System, or Component

TIA

Task Interface Agreement

TS

Technical Specification

UFSAR

Updated Final Safety Analysis Report

URI

Unresolved Item

WJE

Wiss, Janney, Elstner Associates