ML18044A539

From kanterella
Jump to navigation Jump to search
Results of Insp & Testing Program in Response to IE Bulletin 79-02 & Revisions (for Interim Plant Operations) for CPC Facility in South Haven,Mi, Revision 0
ML18044A539
Person / Time
Site: Palisades Entergy icon.png
Issue date: 02/11/1980
From:
BECHTEL GROUP, INC.
To:
Shared Package
ML18044A534 List:
References
IEB-79-02, IEB-79-2, NUDOCS 8002200400
Download: ML18044A539 (8)


Text

Attachment 1, Inspection ana Testing Program, Rev 0 RESULTS OF INSPECTION AND TESTING PROGRAM IN RESPONSE TO NRC IE BULLETIN 79-02 AND ITS REVISIONS (FOR INTERIM PLANT OPERATION)

FOR CONSUMERS POWER COMPANY PALISADES NUCLEAR PLANT SOUTH HAVEN, MICHIGAN

  • 8 o 02 2 oo 'fO{Jr:,,: ...

INSPECTION AND TESTING PROGRAM

              • NRC IE BULLETIN 79-02 AND ITS REVISIONS

.CONSUMERS POWER COMPANY PALISADES NUCLEAR PLANT

1. GENERAL An inspection and testing program is currently being performed at the Palisades nuclear plant to fulfill the requirements of NRC IE Bulletin 79-02 and its revisions for safety seismic pipe supports using concrete expansion anchor bolts.

The program consists of pull-testing the concrete expansion anchor bolts at 200% of their design allowables and verifi-cation of installation parameters such as shoulder-.to-cone dimensions, protrusions, thread engagements, base plate hole sizes, and edge distances. This inspection and testing program was also discussed and agreed upon in meetings between the NRC, CPCo, and Bechtel in Chicago and Washingt6n D.C., on October 26 and Nove~ber 21, 1979, respectively.

2. INSPECTION AND TESTING STATUS The following is a summary of inspection and testing completed for safety seismic piping supports for piping 2-1/2 inches and larger as of January 29, 1980.

Auxiliary Building Containment and Other A. Expansion Anchor Bolts

1) Inspected and tested 634 (348)* 903 (290)*
2) Inaccessible 98 (69)* . 69 (26)*
3) Failures a) She11*type (pull test) 2 14 b) Wedge type (pull test) 1 c) Inspection (2)* (3)*
  • As of January 9, 1980
        • 1

Inspection and Testing Program Auxiliary Building Containment and Other B. Base Plates

1) Total number of base 246 691 plates involved
2) Number of base plates 186 (178)* 184 (144)*

inspected

3.

SUMMARY

OF INSPECTION AND TESTING RESULTS A total failure of 17 out of 1,537 available anchors tested indicates an acceptable rate of failure to ensure a required 95% confidence level. Therefore, further pull testing of concrete expansion anchors has been terminated.

  • Approximately 72% of all shell anchors inspected meets the shoulder-to-cone and protrusion acceptance criteria. An adequate thread engagement existed in 88% of the bolts.

Fourteen percent of the base plates inspected had oversized holes (greater than one bolt head). However, all such anchors or base plates which did not meet the engineering acceptance criteria were reset or repaired during the inspection and

        • testing program as specified. Approximately 11% of supports were found to be inaccessible because of high radiation areas or physical congestion. The above percentage information is based on the data available as of January 9, 1980.
4.

SUMMARY

OF SITE-SPECIFIC TESTING RESULTS Site-specific tests were conducted on shell and wedge type .

anchors to establish the following:

A. TORQUE-TENSION RELATIONSHIPS Torque-tension results indicate a confirmation of.

reinstallation torque values as specified and provide an average tension values in excess of two times the allowable design load for all anchors.

B. RELAXATION TESTS Relaxation losses were found to vary from 12 to 50%

with an average of 26% over a 2-week period. Further relaxation is not expected because other tests (on wedge anchors) indicate that nearly all relaxation losses occur within the first 7 days after torquing *

  • *As of January 9, 1980 2

Inspection and Testing Program C. ULTIMATE CAPACITIES

  • 5.

The data from the ultimate strength tests on partially expanded anchors produced definitions of acceptance criteria for shoulder-to-cone dimensions.

INSPECTION AND TESTING PROGRAM FOR PLANT OPERATION The following program is currently being performed to complete inspection and testing inside the containment and inaccessible areas outside the containment for pipe sizes 2-1/2 inches and larger under normal plant operating conditions.

A. Further pull testing is being discontinued.

However, each anchor will be tested because there will be a reinstallation .torque.

B. All base plates, bolts, and expansion anchors will be inspected. to conform with engineering acceptance criteria. These include shoulder-to-cone measurements and resetting, if required.

C. If inspection (with appropriate analysis) shows that installation does not meet acceptance criteria, modifications will be made.

    • 6. BASIS FOR INTERIM PLANT OPERATION To provide a basis for interim operations, the data from the completed testing and inspection program for large and small piping supports are used to assess the condition of the remaining population of anchors installed at the Palisades plant as described below in Sections 7 and 8.
7. LARGE PIPING SUPPORTS (2-1/2 INCHES AND LARGER)

A. TESTING As indicated in Section 3, a total failure of 17 out of 1,537 available anchors pull tested provides an accept-able rate of failure to ensure a required 95% confidence

  • lev~l for the remainder of the anchor population installed at the Palisades plant.

B. INSPECTION PARAMETERS

1) Shoulder-to-Cone Dimensions and Protrusions Twenty-eight percent of the total number of shell anchors inspected did not meet tpe shoulder-to-cone and protrusion acceptance criteria. The ultimate strength tests conducted at the Palisades plarit on partially exp~nded shell anchors indicate 3_

Inspection and Testing Program that these anchors retain a significant portion of their average ultimate strengths for varying degrees of expansion even outside of the acceptance criteria limits. This indication was also con-firmed by the fact that these same anchors that did not meet the shoulder-to-cone acceptance criteria did withstand a pull test load equal to a

~inimum of 200% of the anchors' allowable design loads.

Based on the above trend, 72% of the remaining shell type anchors installed at the Palisades plant should meet the shoulder-to-cone acceptance criteria. The shoulder-to-cone acceptance criteria ensure that an anchor is capable of withstanding an average ultimate load of at least five times the allowable design load based on the ultimate strength tests conducted at the Palisades plant.

The remaining 28% of the anchor population would

  • have a minimum strength exceeding 200% of the allowable design loads based on the proof load .

tests (200% pull tests). Thus, shell type anchors installed at the Palisades plant have a minimum safety factor of two or more with at least a 95%

confidence level.

  • 2) oversized Holes Results of inspection showed that only 14% of the base plates were .. found to have holes larger than a bolt head. These oversized holes apparently were made to perrnit'fit-up for support base plate installation. According to known facts, plate washers were installed over these holes which would ensure transfer of load between the bolt and the plate. In 93.5% of the cases (of the 14%

indicated above), these anchor bolts had calculated safety factors of much in excess of two. Nevertheless, all of the base plates inspected having oversized holes have been repaired, and* repairs will be made for the remaining population of similar base plates as a part of the inspection and testing program during the plant operation.

3) Thread Engagement Twelve percent of the bolts did not meet the thread engagement acceptance criteria. However, all of these bolts had an excess of three threads which will provide a safety factor of at least five, based on ultimate strength. As a part of inspection and testing during a plant operation, all such bolts not meeting the thread engagement acceptance criteria will be replaced or reinstalled.

4

Inspection and Testing Program

4) Miscellaneous Anchor Bolt Removal Approximately 47 (7.4%) of a total of 638 anchors (as of January 9, 1980) were replaced without pull testing because of various reasons *. A detailed review of completed data sheets was made to deter-mine if some of these anchor bolts would have failed if they had been subjected to a pull test.

It is conservatively estimated that five of them probably would have failed based on examination of various inspection parameters.

c. FACTORS OF SAFETY l) Calculated Support Loads The ultimate capacity of existing pipe support anchor bolt sizes was compared with the calculated support loads. In 91.5% of the cases (a total of 514 anchors analyzed), the factors of safety were found to be equal to two or more *. Further detailed anaylses on those supports having safety factors of less than two are in progress. The results to date indicate that the calculated safety factors will be in excess of two. Based on this, it is expected that the remaining population of anchor.
  • bolts will have a safety factor of two or more *
2) Calculated Support Loads Versus Test Load In those cases where the anchors were tested successfully to 200% of their allowable design loads irrespective of their shoulder-to-cone dimensions, the factors of safety will be calculated using the 200% test load as the ultimate capacity.
3) Inaccessible Supports A total of 11% (167) of the supports were reported to be inaccessible for testing because of high
  • radiation areas or physical congestion. In all evaluated cases for which the design loads and as-buil t information were available to date .(15% of 11%), the safety factors were well over five *
  • 5

D.

SUMMARY

A comprehensive review of testing and inspection parameters as described above indicates that a minimum safety factor of two will be met for the remaining population of anchor bolts installed at the Palisades plant.

Out of a total of 638 anchors, 17 anchor bolts failed the pull test equivalent of 200% of the allowable design criteria. An additional five anchors are con-servatively included as failures as mentioned in Subparagraph 7.B.4. A total failure of 22 provides a required confidence level of 95%1 that is, no more than 5% of the anchors installed at the Palisades plant are defective for the remaining population of anchors.

8. SMALL PIPING (2 INCHES AND SMALLER)

A. TESTING A total of 33 available ~mall pipe supports have been inspected and tested as of January 29, 1980. Out of a total of 58 shell anchors, none failed the pull test, equivalent to 200% of their allowable design loads.

This provides an acceptable 95% confidence level that no more than 5% of the bolts are defective in the remaining population of anchor bolts.

B. INSPECTION PARAMETERS Inspection of base plates and anchor bolts indicates generally a similar trend of installation parameters (such as oversized holes, shoulder-to-cone dimensions, and thread engagements as that described above for large piping).

C. FACTORS OF SAFETY The ultimate capacity of existing pipe. support anchor bolt sizes was compared with support loads. The support loads were derived using simplified techniques and standard support components and were based upon as-buil t conditions of typical small diameter piping systems. In all such cases, the calculated safety factors were well in excess of two with the exception of one support. However, there were a large number of supports having safety factors as high as 10 or greater.

Additionally, the support loads obtained are conser-vative as compared to computer-analyzed piping support

  • 6

Inspectio~ and T~sting Program

  • loads. Previous comparisons between computer-analyzed piping and the simplified techniques indicate.the re-sults to be conservative by a factor of two or greater.

D. BASIS FOR PLANT OPERATION The basis for plant operation for large piping as outlined above is also applicable to small piping. The data from the completed testing and inspection program are used to project trends for the remaining population of small pipe anchor bolts and base plates.

9* BLOCK WALLS As indicated in CPCO's December 11, 1979, response to NRC IE Bulletin 79-02, Rev 2, the block wall separating the diesel

.generators was identified as not meeting the acceptance criteria for Seismic Category I loading conditions. This wall will be reinforced, and Category I piping supports attached to it will be relocated as appropriate prior to plant startup.

10. CONCLUSION Based on considerations as outlined above, the intent of NRC IE Bulletin 79-02, Revisions 1 (Supplement 1) and 2 would be met for interim operation of the plant~ i.e., a minimum safety factor of two will be maintained for all pipe support anchor bolts.

7