MONTHYEARML20217J4721999-10-15015 October 1999 Forwards NRC Physical Security Insp Repts 50-315/99-27 & 50-316/99-27 on 990920-24.Two Violations Noted & Being Treated as Ncvs,Consistent with App C of Enforcement Policy. Areas Examined Exempt from Disclosure,Per 10CFR73.21 IA-99-379, First Final Response to FOIA Request for Documents.Documents Listed in App a Being Released in Entirety1999-10-0808 October 1999 First Final Response to FOIA Request for Documents.Documents Listed in App a Being Released in Entirety ML20217D9241999-10-0808 October 1999 First Final Response to FOIA Request for Documents.Documents Listed in App a Being Released in Entirety ML17335A5511999-10-0707 October 1999 Forwards LER 99-023-00, Inadequate TS Surveillance Testing of ESW Pump ESF Response Time. Commitments Identified in LER Listed ML20217D9361999-09-30030 September 1999 FOIA Request for Document Re Section 9.7 of SE by Directorate of Licensing,Us Ae Commission in Matter of Indiana & Michigan Electric Co & Indiana & Michigan Power Co,Dc Cook Nuclear Plan,Units 1 & 2 ML17326A1541999-09-20020 September 1999 Provides Notification of Change in Senior Licensed Operator Status.Operating Licenses for CR Smith,License SOP-30159-4 & Tw Welch,License SOP-30654-2 Are No Longer Required & Should Be Withdrawn ML17326A1441999-09-17017 September 1999 Submits Trace on Second Shipment of Two Plant,Unit 2 Steam Generators.Info Re Shipment Submitted ML17326A1261999-09-17017 September 1999 Forwards LER 99-022-00 Re Electrical Bus Degraded Voltage Setpoints Too Low for Safety Related Loads.Listed Commitment Identified in Submittal ML17326A1531999-09-16016 September 1999 Submits Info Pertaining to Plant Proposed Operator Licensing Exam Requirements Through Yr 2003.NRC Form 536, Operator Licensing Exam Data, Which Provides Required Info Encl ML17326A1101999-08-27027 August 1999 Forwards LER 99-021-00, GL 96-01 Test Requirements Not Met in Surveillance Tests. List of Commitments Identified in LER Provided ML17326A0991999-08-26026 August 1999 Forwards LER 99-020-00,re EDGs Being Declared Inoperable. Commitments Made by Util Are Listed ML17326A1221999-08-23023 August 1999 Forwards Revised Page 2 to 1998 Annual Environ Operating Rept, for DC Cook Nuclear Plant,Correcting Omission to App I ML17326A0981999-08-23023 August 1999 Forwards fitness-for-duty Program Performance Data for Period of 990101-0630 for DC Cook Nuclear Plants,Units 1 & 2,per 10CFR26.71(d) ML17326A0891999-08-16016 August 1999 Forwards LER 99-019-00,re Victoreen Containment High Range Monitors Not Beign Environmentally Qualified to Withstand post-LOCA Conditions.Commitments Made by Util Are Listed ML17326A0811999-08-10010 August 1999 Notifies NRC of Changes in Commitments Made in Response to GL 98-01,supplement 1, Yr 2000 Readiness of Computer Sys Ar Npps, Dtd 990623 ML17326A0821999-08-0606 August 1999 Informs That Util Is Submitting Encl Scope & Objectives for 991026 DC Cook Nuclear Plant Emergency Plan Exercise to G Shear of NRC Plant Support Branch.Exercise Will Include Full State & County Participation ML17326A1451999-08-0404 August 1999 Requests Withholding of WCAP-15246, Control Rod Insertion Following Cold Leg Lbloca. ML17326A0751999-08-0404 August 1999 Forwards LER 98-029-01, Fuel Handling Area Ventilation Sys Inoperable Due to Original Design Deficiency. Supplemental Rept Represents Extensive Rev to Original LER & Replaces Rept in Entirely.Commitment Listed ML17326A0721999-07-29029 July 1999 Forwards LER 99-018-00 Re Refueling Water Storage Tank Suction Motor Operated Valves Inoperable,Due to Inadequate Design.Listed Commitments Were Identified in LER ML17326A0711999-07-27027 July 1999 Responds to 980123 RAI Re NRC GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Unresolved Safety Issue (USI) A-46. ML17326A0601999-07-22022 July 1999 Forwards UFSAR, IAW 10CFR50.71(e) & Rept of Changes,Tests & Experiments as Required by 10CFR50.59(b)(2) for DC Cook Nuclear Plant,Units 1 & 2.Without UFSAR ML17326A0631999-07-22022 July 1999 Forwards LER 98-014-03, Response to High-High Containment Pressure Procedure Not Consistent with Analysis of Record. Revised Info Marked by Sidebars in Right Hand Margin. Commitments Made by Util,Listed ML17326A0311999-07-0101 July 1999 Forwards LER 99-004-01 Re Failure to Perform TS Surveillance Analyses of Reactor Coolant Chemistry with Fuel Removed. Commitments Made by Util Are Listed ML20196K5961999-06-30030 June 1999 Ltr Contract:Task Order 40, DC Cook Extended Sys Regulatory Review Oversight Insp, Under Contract NRC-03-98-021 ML17326A0281999-06-28028 June 1999 Provides Response to 981116 & 960228 RAIs Re GL 92-01. Revised Pressurized Thermal Shock Evaluation Based on New Weld Chemistry Info & Copy of W Rept WCAP-15074, Evaluation of 1P3571 Weld Metal from Surveillance Programs... Encl ML17326A0241999-06-23023 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants. Y2K Readiness Disclosure for Plant & List of Commitments Encl ML17326A0121999-06-18018 June 1999 Forwards LER 99-014-00 Re Requirement of TS 4.0.5 Not Met for Boron Injection Tank Bolting.Commitments Identified in Submittal Listed ML17326A0111999-06-11011 June 1999 Provides Response to NRC RAI Re GL 97-01, Degradation of Crdm/Cedm Nozzle & Other Vessel Closure Head Penetrations. ML17325B6281999-06-0101 June 1999 Forwards LER 99-S03-00,re Nonconforming Vital Area Barriers.Commitments Made by Util Are Listed ML17325B6401999-06-0101 June 1999 Forwards LER 99-013-00 Re Safety Injection & Centrifugal Charging Throttle Valve Cavitation During LOCA Could Lead to ECCS Pump Failure.Listed Commitments Identified in Submittal ML17325B6331999-05-28028 May 1999 Forwards LER 99-S02-00,re Vulnerability in Safeguard Sys That Could Allow Unauthorized or Undetected Access to Protected Area.Commitments Made by Util Are Listed ML17265A8201999-05-24024 May 1999 Forwards LER 98-037-01,representing Extensive Rev to Original LER & Replacing Rept in Entirety.Listed Commitments Identified in Submittal ML17325B6111999-05-21021 May 1999 Forwards Annual Radioactive Effluent Release Rept for 980101-1231 for DC Cook Nuclear Plant,Units 1 & 2. Transmittal of Submittal Was Delayed Due to Administrative Error in Regulatory Affairs Dept ML17325B6031999-05-21021 May 1999 Provides Response to NRC GL 98-04, Potential for Degradation of ECCS & Containment Spray Sys After LOCA Because of Const & Protective Coating Deficiencies & Foreign Matl in Containment. ML20207A9201999-05-21021 May 1999 Ack Receipt of 990319 Response to Notice of Violation & Proposed Imposition of Civil Penalty .On 981124, Licensee Remitted Check for Payment of Civil Penalties. Licensee Requests for Extension for Response,Granted ML17325B5971999-05-20020 May 1999 Forwards LER 99-012-00,re Auxiliary Building ESF Ventilation Sys Not Being Capable of Maintaining ESF Room Temps post-accident.Commitment,listed ML17335A5281999-05-12012 May 1999 Forwards DC Cook Nuclear Plant Fitness for Duty Program Performance Dtd for six-month Period of 980701-1231,IAW 10CFR26.71(d).Info Was Delayed Due to Administrative Error in Regulatory Affairs Dept ML17335A5271999-05-11011 May 1999 Forwards Details Re Sources & Levels of Insurance Maintained for DC Cook,Units 1 & 2,as of 990401,per 10CFR50.54(w)(3). Info Was Delayed Beyond Required Date Due to Internal Oversight ML17325B5841999-05-10010 May 1999 Forwards LER 99-002-00 Re TS 4.0.5 Requirements Not Being Met Due to Improperly Performed Test.Commitments Identified in Ler,Listed ML17325B5871999-05-0707 May 1999 Forwards Current Revs of Expanded Sys Readiness Review (Essr) Implementing Procedures,For Info Purposes to Support Current NRC Insps.Current Esrr Schedule Provided for Info Purposes,Reflecting Revised Target Dates ML17325B5791999-05-0404 May 1999 Forwards LER 99-011-00,concerning Air Sys for EDG Not Supporting Long Term Operability.Commitments Made by Util Listed ML17325B5821999-05-0404 May 1999 Provides Addl Background,Description & Clarification of Previous & Revised Commitments Re UFSAR Revalidation Effort. Commitment Change Involved Alignment of UFSAR Revalidation Program Methodology to Strategy Contained in Current Plan ML17325B5741999-05-0303 May 1999 Forwards LER 99-010-00 Re RCS Leak Detection Sys Sensitivity Not in Accoradnce with Design Requirements.Listed Commitments Identified in Submittal ML17325B5631999-04-22022 April 1999 Forwards Results of Independent Chemical Evaluations Performed from Sept 1997 Through Feb 1999,re Resolution of Issues Related to License Amend 227 ML17325B5561999-04-16016 April 1999 Forwards LER 99-006-00, Fuel Crane Loads Lifted Over SFP Could Impact Energies Greater than TS Limits, IAW 10CFR50.73.Submittal Was Delayed to Allow for Resolution of Questions.Commitment Made by Licensee,Listed ML20205P0591999-04-14014 April 1999 Ninth Partial Response to FOIA Request for Documents.App Records Already Available in Pdr.Records in App T Encl & Being Made Available in Pdr.App U Records Being Released in Part (Ref FOIA Exemption 7).App V Records Withheld Entirely ML17325B5451999-04-12012 April 1999 Forwards LER 99-009-00 Re as-found RHR Safety Relief Valve Lift Setpoint Greater than TS Limit.Commitments Identified in Submittal Listed ML17325B5301999-04-0707 April 1999 Forwards LER 99-S01-01, Vulnerability in Locking Mechanism of Four Vital Area Gates, Per 10CFR50.73.Commitments Made by Util,Listed ML17325B5241999-04-0505 April 1999 Forwards Revs 0 & 1 to Cook Nuclear Plant Restart Plan, Dtd 980307 & 0407.Rev 5 Is Current Cook Nuclear Plant Restart & Supercedes Previous Revs in All Respects ML17325B5121999-04-0101 April 1999 Forwards LER 99-007-00, Calculations Show That Divider Barrier Between Upper & Lower Containment Vols May Be Overstressed. Commitments Made by Util Are Listed 1999-09-30
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML17335A5511999-10-0707 October 1999 Forwards LER 99-023-00, Inadequate TS Surveillance Testing of ESW Pump ESF Response Time. Commitments Identified in LER Listed ML20217D9361999-09-30030 September 1999 FOIA Request for Document Re Section 9.7 of SE by Directorate of Licensing,Us Ae Commission in Matter of Indiana & Michigan Electric Co & Indiana & Michigan Power Co,Dc Cook Nuclear Plan,Units 1 & 2 ML17326A1541999-09-20020 September 1999 Provides Notification of Change in Senior Licensed Operator Status.Operating Licenses for CR Smith,License SOP-30159-4 & Tw Welch,License SOP-30654-2 Are No Longer Required & Should Be Withdrawn ML17326A1261999-09-17017 September 1999 Forwards LER 99-022-00 Re Electrical Bus Degraded Voltage Setpoints Too Low for Safety Related Loads.Listed Commitment Identified in Submittal ML17326A1441999-09-17017 September 1999 Submits Trace on Second Shipment of Two Plant,Unit 2 Steam Generators.Info Re Shipment Submitted ML17326A1531999-09-16016 September 1999 Submits Info Pertaining to Plant Proposed Operator Licensing Exam Requirements Through Yr 2003.NRC Form 536, Operator Licensing Exam Data, Which Provides Required Info Encl ML17326A1101999-08-27027 August 1999 Forwards LER 99-021-00, GL 96-01 Test Requirements Not Met in Surveillance Tests. List of Commitments Identified in LER Provided ML17326A0991999-08-26026 August 1999 Forwards LER 99-020-00,re EDGs Being Declared Inoperable. Commitments Made by Util Are Listed ML17326A1221999-08-23023 August 1999 Forwards Revised Page 2 to 1998 Annual Environ Operating Rept, for DC Cook Nuclear Plant,Correcting Omission to App I ML17326A0981999-08-23023 August 1999 Forwards fitness-for-duty Program Performance Data for Period of 990101-0630 for DC Cook Nuclear Plants,Units 1 & 2,per 10CFR26.71(d) ML17326A0891999-08-16016 August 1999 Forwards LER 99-019-00,re Victoreen Containment High Range Monitors Not Beign Environmentally Qualified to Withstand post-LOCA Conditions.Commitments Made by Util Are Listed ML17326A0811999-08-10010 August 1999 Notifies NRC of Changes in Commitments Made in Response to GL 98-01,supplement 1, Yr 2000 Readiness of Computer Sys Ar Npps, Dtd 990623 ML17326A0821999-08-0606 August 1999 Informs That Util Is Submitting Encl Scope & Objectives for 991026 DC Cook Nuclear Plant Emergency Plan Exercise to G Shear of NRC Plant Support Branch.Exercise Will Include Full State & County Participation ML17326A1451999-08-0404 August 1999 Requests Withholding of WCAP-15246, Control Rod Insertion Following Cold Leg Lbloca. ML17326A0751999-08-0404 August 1999 Forwards LER 98-029-01, Fuel Handling Area Ventilation Sys Inoperable Due to Original Design Deficiency. Supplemental Rept Represents Extensive Rev to Original LER & Replaces Rept in Entirely.Commitment Listed ML17326A0721999-07-29029 July 1999 Forwards LER 99-018-00 Re Refueling Water Storage Tank Suction Motor Operated Valves Inoperable,Due to Inadequate Design.Listed Commitments Were Identified in LER ML17326A0711999-07-27027 July 1999 Responds to 980123 RAI Re NRC GL 87-02, Verification of Seismic Adequacy of Mechanical & Electrical Equipment in Operating Reactors,Unresolved Safety Issue (USI) A-46. ML17326A0601999-07-22022 July 1999 Forwards UFSAR, IAW 10CFR50.71(e) & Rept of Changes,Tests & Experiments as Required by 10CFR50.59(b)(2) for DC Cook Nuclear Plant,Units 1 & 2.Without UFSAR ML17326A0631999-07-22022 July 1999 Forwards LER 98-014-03, Response to High-High Containment Pressure Procedure Not Consistent with Analysis of Record. Revised Info Marked by Sidebars in Right Hand Margin. Commitments Made by Util,Listed ML17326A0311999-07-0101 July 1999 Forwards LER 99-004-01 Re Failure to Perform TS Surveillance Analyses of Reactor Coolant Chemistry with Fuel Removed. Commitments Made by Util Are Listed ML17326A0281999-06-28028 June 1999 Provides Response to 981116 & 960228 RAIs Re GL 92-01. Revised Pressurized Thermal Shock Evaluation Based on New Weld Chemistry Info & Copy of W Rept WCAP-15074, Evaluation of 1P3571 Weld Metal from Surveillance Programs... Encl ML17326A0241999-06-23023 June 1999 Responds to GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants. Y2K Readiness Disclosure for Plant & List of Commitments Encl ML17326A0121999-06-18018 June 1999 Forwards LER 99-014-00 Re Requirement of TS 4.0.5 Not Met for Boron Injection Tank Bolting.Commitments Identified in Submittal Listed ML17326A0111999-06-11011 June 1999 Provides Response to NRC RAI Re GL 97-01, Degradation of Crdm/Cedm Nozzle & Other Vessel Closure Head Penetrations. ML17325B6401999-06-0101 June 1999 Forwards LER 99-013-00 Re Safety Injection & Centrifugal Charging Throttle Valve Cavitation During LOCA Could Lead to ECCS Pump Failure.Listed Commitments Identified in Submittal ML17325B6281999-06-0101 June 1999 Forwards LER 99-S03-00,re Nonconforming Vital Area Barriers.Commitments Made by Util Are Listed ML17325B6331999-05-28028 May 1999 Forwards LER 99-S02-00,re Vulnerability in Safeguard Sys That Could Allow Unauthorized or Undetected Access to Protected Area.Commitments Made by Util Are Listed ML17265A8201999-05-24024 May 1999 Forwards LER 98-037-01,representing Extensive Rev to Original LER & Replacing Rept in Entirety.Listed Commitments Identified in Submittal ML17325B6111999-05-21021 May 1999 Forwards Annual Radioactive Effluent Release Rept for 980101-1231 for DC Cook Nuclear Plant,Units 1 & 2. Transmittal of Submittal Was Delayed Due to Administrative Error in Regulatory Affairs Dept ML17325B6031999-05-21021 May 1999 Provides Response to NRC GL 98-04, Potential for Degradation of ECCS & Containment Spray Sys After LOCA Because of Const & Protective Coating Deficiencies & Foreign Matl in Containment. ML17325B5971999-05-20020 May 1999 Forwards LER 99-012-00,re Auxiliary Building ESF Ventilation Sys Not Being Capable of Maintaining ESF Room Temps post-accident.Commitment,listed ML17335A5281999-05-12012 May 1999 Forwards DC Cook Nuclear Plant Fitness for Duty Program Performance Dtd for six-month Period of 980701-1231,IAW 10CFR26.71(d).Info Was Delayed Due to Administrative Error in Regulatory Affairs Dept ML17335A5271999-05-11011 May 1999 Forwards Details Re Sources & Levels of Insurance Maintained for DC Cook,Units 1 & 2,as of 990401,per 10CFR50.54(w)(3). Info Was Delayed Beyond Required Date Due to Internal Oversight ML17325B5841999-05-10010 May 1999 Forwards LER 99-002-00 Re TS 4.0.5 Requirements Not Being Met Due to Improperly Performed Test.Commitments Identified in Ler,Listed ML17325B5871999-05-0707 May 1999 Forwards Current Revs of Expanded Sys Readiness Review (Essr) Implementing Procedures,For Info Purposes to Support Current NRC Insps.Current Esrr Schedule Provided for Info Purposes,Reflecting Revised Target Dates ML17325B5821999-05-0404 May 1999 Provides Addl Background,Description & Clarification of Previous & Revised Commitments Re UFSAR Revalidation Effort. Commitment Change Involved Alignment of UFSAR Revalidation Program Methodology to Strategy Contained in Current Plan ML17325B5791999-05-0404 May 1999 Forwards LER 99-011-00,concerning Air Sys for EDG Not Supporting Long Term Operability.Commitments Made by Util Listed ML17325B5741999-05-0303 May 1999 Forwards LER 99-010-00 Re RCS Leak Detection Sys Sensitivity Not in Accoradnce with Design Requirements.Listed Commitments Identified in Submittal ML17325B5631999-04-22022 April 1999 Forwards Results of Independent Chemical Evaluations Performed from Sept 1997 Through Feb 1999,re Resolution of Issues Related to License Amend 227 ML17325B5561999-04-16016 April 1999 Forwards LER 99-006-00, Fuel Crane Loads Lifted Over SFP Could Impact Energies Greater than TS Limits, IAW 10CFR50.73.Submittal Was Delayed to Allow for Resolution of Questions.Commitment Made by Licensee,Listed ML17325B5451999-04-12012 April 1999 Forwards LER 99-009-00 Re as-found RHR Safety Relief Valve Lift Setpoint Greater than TS Limit.Commitments Identified in Submittal Listed ML17325B5301999-04-0707 April 1999 Forwards LER 99-S01-01, Vulnerability in Locking Mechanism of Four Vital Area Gates, Per 10CFR50.73.Commitments Made by Util,Listed ML17325B5241999-04-0505 April 1999 Forwards Revs 0 & 1 to Cook Nuclear Plant Restart Plan, Dtd 980307 & 0407.Rev 5 Is Current Cook Nuclear Plant Restart & Supercedes Previous Revs in All Respects ML17325B5121999-04-0101 April 1999 Forwards LER 99-007-00, Calculations Show That Divider Barrier Between Upper & Lower Containment Vols May Be Overstressed. Commitments Made by Util Are Listed ML17325B5141999-03-30030 March 1999 Forwards Rept on Status of Decommissioning Funding.Attached Rept Includes Amount of Decommissioning Funds Estimated to Be Required Pursuant to 10CFR50.75(b) & (C) ML17325B5191999-03-29029 March 1999 Forwards LER 99-001-00,re Degraded Component Cw Flow to Containment Main Steam Line Penetrations.Commitment, Listed ML20204F6401999-03-19019 March 1999 Responds to NRC 981013 NOV & Proposed Imposition of Civil Penalty.Violations Cited in Subject NOV Were Initially Identified in Referenced Five Insp Repts.Corrective Actions: Ice Condensers Have Been Completely Thawed of Any Blockage ML17325B4751999-03-18018 March 1999 Forwards LER 99-004-00,re Failure to Perform TS Surveillance Analyses of Reactor Coolant Chemistry with Fuel Removed. Commitment Made by Util,Listed ML17325B4721999-03-18018 March 1999 Forwards LER 99-005-00,re Reactor Trip Breaker Manual Actuations During Rod Drop Testing Not Previously Reported. Listed Commitments Identified in Submittal ML17325B4641999-03-17017 March 1999 Withdraws Response to Issue 1 of NRC Cal,Dtd 970919. Comprehensive Design Review Effort in Progress to Validate Resolution of Issue for Future Operation 1999-09-30
[Table view] |
Text
WCCECEawrED DOCmmr Y DiS rarsu'r>OX SvSrEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
CCESSION NBR:9309140055 DOC.DATE: 93/09/07 NOTARIZED: YES DOCKET ¹ CIL:50-315 Donald C. Cook Nuclear Power Plant, Unit 1, Indiana M 05000315 50-316 Donald C. Cook Nuclear Power Plant, Unit 2, Indiana M 05000316 AUTH. NAME AUTHOR AFFILIATION FITZPATRICK,E. Indiana Michigan Power Co. (formerly Indiana & Michigan Ele R RECIP.NAME RECIPIENT AFFILIATION MARTINPJ.B. Document Control Branch (Document Control Desk)
SUBJECT:
Responds to NRC 930809 ltr re violations noted in insp repts 50-315/93-15 & 50-316/93-15 on 930607-18.Corrective actions: D changed maint head instruction to allow use of job order completion date for scheduling next PM task.
DISTRIBUTION CODE'EOID COPIES RECEIVED'LTR General (50 Dkt)-Insp Rept/Notice of Vi&o i ENCL ation L
Response
SIZE'ITLE:
NOTES:
RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL D PD3-1 PD 1 . 1 DEANPW 1 1 D
INTERNAL: AEOD/DEIB 1 1 AEOD/DSP/ROAB 1' AEOD/DSP/TPAB 1 1 AEOD/TTC 1 1 DEDRO 1 1 NRR/DORS/OEAB 1 1 NRR/DRCH/HHFB 1 1 NRR/DRIL/RPEB 1 1 NRR/DRSS/PEPB 1 1 NRR/PMAS/ILPBl 1 1 NRR/PMAS/ILPB2 1 1 NUDOCS-ABSTRACT 1 1 1 1 OGC/HDS2 1 1 REG ILE 02 1 1 RES/HFB 1 1 RGN FILE 01 1 1 EXTERNAL EG&G/BRYCEP J H 1 1 NRC PDR 1 1 NSIC 1 1 D
D NOTE TO ALL"RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE! CONTACI'HE DOCUMEN'I'ONTROI. DI:SK.
ROOM Pl-37 (EXT. 504-2065) TO ELIMINATEYOUR NAME Fli.OM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!
TOTAL NUMBER OF COPIES REQUIRED: LTTR 22 ENCL 22
Indiana Michigan Power Company P.O. Box 16631 Cofumbus, OH 43216 INDIANA NICHIGiAN PWER AEP: NRC: 1184E 10 CFR 2.201 Donald C. Cook Nuclear Plant Units 1 and 2 Docket Nos. 50-315 and 50-316 License Nos. DPR-58 and DPR-,74 NRC INSPECTION REPORTS NO. 50-315/93015 (DRS)
AND 50-316/93015 (DRS)
REPLY TO NOTICE OF VIOLATION U. S. Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555 Attn: Mr. J. B. Martin September 7, 1993
Dear Mr. Martin:
This letter is in response to your letter dated August 9, 1993, which forwarded a Notice of Violation. The Notice of Violation resulted from a routine, announced inspection of maintenance activities conducted by H. A. Walker, M. K. Khanna, W. D. Pegg, and D. L. Schrum on June 7 through 18, 1993. The violations are associated with inadequate procedures and procedure compliance, inadequate document control, and failure to adequately maintain safe shutdown lighting.
Our reply to the Notice of Violation is provided in the attachment to this letter.
This letter is submitted pursuant to 10 CFR 50.54(f) and, as such, an oath statement is enclosed.
Sincerely, E. E. Fi patrick Vice President dr Attachment r>~
9309140055 930907 I PDR ADOCK 05000315 PDR
Mr. J. B. Martin AEP:NRC:1184E cc: A. A. Blind Bridgman G. Charnoff T. E. Murley, NRC - Washington, D.C.
NRC Resident Inspector NFEM Section Chief J. R. Padgett
STATE OF OHIO)
COUNTY OF FRANKLIN)
E. E. Fitzpatrick, begin duly sworn, deposes and says that he is the Vice President of licensee Indiana Michigan Power Company, that he has read the forgoing response to NRC INSPECTION REPORTS NO. 50-315/93015 (DRS) AND 50-316/93015 (DRS) and knows the contents thereof; and that said contents are true to the best of his knowledge and belief.
Subscribed and sworn to before me this day of
~ia~ 5 NOTARY PUBLIC Cu~~c~yi ~
ATTACHMENT TO AEP.NRC: 1184E REPLY TO,NOTZCE OP VZOLATZON
Attachment to AEP:NRC:1184E Page 1
Background
A routine, announced inspection of maintenance activities using selected portions of NRC inspection module 62700 to ascertain whether maintenance was effectively accomplished and assessed by the Donald C. Cook Nuclear Plant was conducted by Messrs. H. A.
Walker, M. K. Khanna, W. D. Pegg, and D. L. Schrum from July 7 to 18( 1993 During this inspection, three items were found to be in violation.
The violations were identified with:
(1) inadequate procedures and procedure compliance (a discrepancy was identified between a procedure, MHI-5030, and the method of how the work was actually performed; explicitly, the procedure required that the interval for performing periodic preventive maintenance tasks be based on the date the task was last performed; however, the preventive maintenance task program is configured to set this interval based on the date when the maintenance work package was closed rather than the date the preventive maintenance task was last performed);
(2) inadequate document control (out of date maintenance head instruction procedures and indices were found to be in use in the Safety and Assessment library); and (3) failure to adequately maintain safe shutdown lighting (approximately a dozen emergency battery lights out of 221 were found to be aimed incorrectly or otherwise not functional).
These violations were set forth in a letter containing the notice of violation dated August 9, 1993 from Mr. Geoffrey C. Wright, Chief, Engineering Branch. The letter was received August 11, 1993. Our response to the notice of violation is contained within this document.
/)
gl
~ ~
Attachment to AEP:NRC:1184E Page 2 NRC Violation I "10 CFR 50, Appendix B, Criterion V states that activities affecting quality shall be prescribed by documented instructions or procedures, or a type appropriate to the circumstances and shall be accomplished in accordance with these instructions or procedures.
Procedure MHI-5030, "Preventive Maintenance Program",
Revision 13, with change sheets 1 through 5, paragraphs 4.13 and 6.3.2.A, required that the interval for performing periodic preventive maintenance tasks be based on the date the task was last performed.
Contrary to the above, from January 1993 to June 9, 1993, preventive maintenance task intervals were based on the date when the maintenance work package was closed rather than the date the preventive maintenance task was last performed.
This is a Severity Level IV violation. "
Response to Violation I Admission or Denial of the Alle ed Violation Indiana Michigan Power admits to the violation as cited in the NRC Notice of Violation.
20 Reasons for the Vio ation Starting in Januaryg 1993g preventive maintenance (PM) tasks have been scheduled via use of a computerized work control system. Under this system, PM tasks are automatically rescheduled based on the date the associated job order is administratively closed, not the date the PM activity is completed.
Normally, the job order close-out date is very close to the PM activity completion date. However, jobs requiring significant restoration activities, such as installation of insulation or removal of scaffolding, can delay close-out of the job order, and thus, the rescheduling of the PM tasks. This has the undesired effect of extending the period between consecutive PM tasks beyond the period established by the PM program.
Attachment to AEP:NRC:1184E Page 3 The plant staff was aware of the rescheduling problem, but at the time of the inspection had not yet identified an effective solution. Furthermore, the problem was not recognized as a procedural violation, and, therefore, it had not been reported via the plant's corrective action reporting system.
The PM tasks affected by this rescheduling problem did not involve any Technical Specification surveillance tests, nor were they considered mandatory for the continued operability of safety>>related equipment.
- 3. Corrective Actions Taken and Results Achieved The maintenance head instruction (MHZ-5030) has been changed to allow the use of the job order completion date for scheduling of the next PM task.
The change to MHZ-5030 allows the task interval to be based on the date the work package is closed, and brings the scheduling process in full compliance with the procedure requirements.
4 Corrective Actions Taken to Avoid Further Violations Additional guidance will be provided to plant personnel involved in the scheduling and tracking of PM task job order activities, emphasizing the importance of completing PM task support activities and reporting their status in a timely manner. This guidance will be issued by September 24, 1993.
Software enhancements that will allow rescheduling based on the date that the PM task activity is performed rather than using the job order closeout date will be pursued. Until these enhancements are obtained, a periodic review will be performed of open PM task job orders to identify those PM task activities that have been open for an excessive amount of time.
- 5. Date When Full Com liance will be Achieved Full compliance was achieved with the change to MHZ-5030, Revision 13, Change Sheet 7, on August 30, 1993.
Attachment to AEP:NRC:1184E Page 4 NRC Violation ZZ "10 CFR Part 50, Appendix B, Criterion VI states that measures shall assure that documents, including changes, are reviewed for adequacy and approved for release by authorized personnel and are distributed to and used at the location where the prescribed activity is performed.
Contrary to the above, from 1990 to June 16, 1993, approved changes to maintenance head instructions were not distributed to the safety and assessment satellite library, which was used by licensee personnel to obtain work related instructions.
This is a Severity Level ZV violation."
Response to Violation IZ 1~ Admission or Den a of the Alle ed Violatio Indiana Michigan Power admits to the violation as cited in the NRC Notice of Violation.
2 ~ Reasons or the V olation Zn 1990, the Safety and Assessment (S&A) library was removed from distribution of the MHI series procedures.
The SGA library continued to receive updates to the MHP and ZHP series procedures. At the time that the MHZ series procedures were removed from distribution for the SGA library, Maintenance Department did not verify that the existing MHZ series procedures in the SGA library were returned or destroyed. This accounts for why the MHZ series procedures were out of date in the SN library.
Zn late 1992, the Maintenance Department reissued their department procedure indices for the MHZ@ MHPg and ZHP series procedures to the plant including to the SGA library. This accounts for why the information on the Maintenance Department indices in the SN library does not match the version of the MHZ series procedures contained in the SQA library.
Attachment to AEP:NRCs 1184E Page 5 30 Corrective Actions Taken and Results Achieved On June 24, 1993, the S&A library was placed back on the distribution list for the MHZ series procedures.
The outdated set of MHZ series procedures was removed from the MA library and a current set of the MHZ series procedures and associated index were placed in the SQA library.
- 4. Corrective Actions Taken to Avoid Further Violations A review is being conducted of the SGA library to identify and correct any other procedure errors of this type. This review will be completed by October 29, 1993.
On July 29, 1993 a letter was issued to department heads sensitizing them to this event. The letter also explained the document control requirements that should have prevented 'this event.
On August 31, 1993, PMZ-2030, Plant Manager Instruction on Document Control, was revised to clearly state the document control requirements.
- 5. Date W en Full Com 1 ance will be Ac ieved Full compliance was achieved June 24, 1993 when the SQA library was placed back on the distribution list for the MHZ series procedures, the outdated set of MHZs removed and the updated set added.
Attachment to AEP:NRC:1184E Page 6 NRC Violation IZZ "10 CFR Part 50, Appendix R, Section ZZZ.J states that emergency lighting units with at least an 8<<hour battery power supply shall be provided in all areas needed for operation of safety shutdown equipment and in access and egress routes thereto.
Contrary to the above, from January 1993 to June 15, 1993, emergency lighting was not provided in all areas needed for operation of safe shutdown equipment and in access and egress routes thereto due to conditions that existed on a number of emergency lighting units'that rendered the units inoperable.
This is a Severity Level IV violation."
Response to Violation ZZI
- 1. ,Admission or Denial of the Alle ed Violation Indiana Michigan Power admits to the violation as cited in the NRC Notice of Violation.
2~ Reasons for the Violation The cause of the inoperability of a number of emergency lighting units was the deferral of the Preventive Maintenance (PM) for the emergency battery lights.
- 3. Co ective Actions aken and Results c ieved During the time period of the NRC inspection, a corrective maintenance action request (Action Request No. 46622) was generated to verify that all Appendix R emergency battery lights were properly aimed and functional. This action request was generated on June 10, 1993 and completed on June 14, 1993. All emergency battery lights were properly aimed and corrective maintenance action requests were written for eight emergency battery lights which were found not to be functional. The eight non-functional emergency battery lights were restored to functional status by July 20, 1993.
Attachment to AEP:NRC:1184E Page 7 In June 1993, drawdown testing started and remains in progiess.
- 4. Corrective Actions Taken to Avoid Further Violations In order to ensure that further violations are avoided, two preventive actions have been taken. A comprehensive emergency battery light program has been developed. This program includes:
- 1) The development of, an emergency battery light program manual; 11
- 2) Revision of the preventive maintenance task from a data sheet into a new, stand alone procedure
(+*12 IHP 5030.EMP.010, "Emergency Battery Light Units")g and
- 3) The assignment of a cognizant technical lead to oversee the program.
The program manual delineates the roles and responsibilities of personnel involved in the program, data collection, maintenance of information collected, testing frequency, battery and lamp replacement requirements, definition of failures of units, condition report requirements, procurement of and maintenance of spare batteries, and change process for the program manual.
The new procedure provides the mechanism to perform and properly document emergency battery light maintenance and discrepancies.
The second preventive action has also been established.
MHI-5030, "Preventive Maintenance Program", which is the parent document for the preventive maintenance program, has been revised such that deferral requests must be submitted prior to the due date of the surveillance and it must be reviewed and approved by the Plant Engineering Department Superintendent:. Plant Engineering Department has recently assumed ownership of the program and is now required to review and approve deferrals.
Attachment to AEP:NRC:1184E Page 8
- 5. Date When Full Com liance will be Achieved The corrective action of verifying the correct aiming and functionality of battery lights was completed on July 20, 1993. Drawdown testing is in progress and will be completed by January 30, 1994. Therefore, full compliance will be achieved on January 30, 1994.