ML16225A577

From kanterella
Jump to navigation Jump to search
NRC Integrated Inspection Report 05000483/2016002 and Notice of Violation
ML16225A577
Person / Time
Site: Callaway Ameren icon.png
Issue date: 08/12/2016
From: Nick Taylor
NRC/RGN-IV/DRP/RPB-B
To: Diya F
Union Electric Co
Taylor N
References
IR 2016002
Download: ML16225A577 (81)


See also: IR 05000483/2016002

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION IV

1600 E. LAMAR BLVD.

ARLINGTON, TX 76011-4511

August 12, 2016

Mr. Fadi Diya, Senior Vice President

and Chief Nuclear Officer

Union Electric Company

P.O. Box 620

Fulton, MO 65251

SUBJECT:

CALLAWAY PLANT - NRC INTEGRATED INSPECTION

REPORT 05000483/2016002 AND NOTICE OF VIOLATION

Dear Mr. Diya,

On June 30, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at

your Callaway Plant. On July 19, 2016, the NRC inspectors discussed the results of this

inspection with you and other members of your staff. Inspectors documented the results of this

inspection in the enclosed inspection report.

NRC inspectors documented five findings of very low safety significance (Green) in this report.

Four of these findings involved violations of NRC requirements. The NRC evaluated these

violations in accordance Section 2.3.2.a of the NRC Enforcement Policy, which appears on the

NRCs Web site at http://www.nrc.gov/about-nrc/regulatory/enforcement/enforce-pol.html. The

NRC is treating three violations as non-cited violations (NCVs) consistent with Section 2.3.2.a of

the NRC Enforcement Policy. We determined that one violation did not meet the criteria to be

treated as an NCV because compliance has not been restored within a reasonable period after

the violation was originally identified. Specifically, NRC inspectors identified and documented a

noncompliance in NRC Integrated Inspection Report 05000483/2010006 dated December 17,

2010. This finding was a violation of Title 10 of the Code of Federal Regulations (10 CFR)

Part 50, Appendix B, Criterion XVI, for the failure to take timely corrective actions for water

hammer transients and corrosion on essential service water system components. As of the end

of this inspection (more than 65 months later), compliance had still not been restored. The

inspectors determined that the licensee did not provide an adequate justification for the delay.

You are required to respond to this letter and should follow the instructions specified in the

enclosed Notice of Violation (Notice) when preparing your response. If you have additional

information that you believe the NRC should consider, you may provide it in your response to

the Notice. The NRCs review of your response to the Notice will also determine whether further

enforcement action is necessary to ensure your compliance with regulatory requirements.

If you contest the NCVs or their significance you should provide a response within 30 days of

the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the

Regional Administrator, Region IV, 1600 East Lamar Blvd., Arlington, Texas 76011-4511; the

Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington,

DC 20555-0001; and the NRC resident inspector at the Callaway Plant.

F. Diya

- 2 -

If you disagree with a cross-cutting aspect assignment or a finding not associated with a

regulatory requirement in this report, you should provide a response within 30 days of the date

of this inspection report, with the basis for your disagreement, to the Regional Administrator,

Region IV; and the NRC resident inspector at the Callaway Plant.

In accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding,

a copy of this letter, its enclosure, and your response will be available electronically for public

inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS)

component of the NRC's Agencywide Documents Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the

Public Electronic Reading Room).

Sincerely,

/RA David Proulx Acting for/

Nicholas H. Taylor, Branch Chief

Project Branch B

Division of Reactor Projects

Docket No. 50-483

License No. NPF-30

Enclosures:

1. Notice of Violation

2. Inspection Report 05000483/2016002

w/ Attachment 1: Supplemental Information

Attachment 2: Request for Information

cc w/ encl: Electronic Distribution

ML16225A577

SUNSI Review

By: DLP

ADAMS

Yes No

Non-

Sensitive

Sensitive

Publicly Available

Non-Publicly Available

Keyword:

NRC-002

OFFICE

SRI/DRP/B

RI/DRP/B

C:DRS/OB

C:DRS/PSB2

C:DRS/EB1

C:DRS/EB2

NAME

THartman

MLangelier

VGaddy

RDeese

TFarnholtz

SGraves

SIGNATURE

/RA/

/RA/

/RA/

/RA/

/RA/

/RA/

DATE

8/8/16

8/8/16

8/1/2016

8/1/2016

8/1/2016

8/1/2016

OFFICE

C:DRS/IPAT

SRI:DRS/EB2

SRI:DRP/D

TL:ACES

D:DRP

C:DRP/B

NAME

THipschman

JDrake

JJosey

JKramer

TWPruett

NTaylor

SIGNATURE

/RA/

/RA/

/RA/

/RA/

/RA/

/RA DProulx

Acting, for/

DATE

8/1/2016

8/5/16

8/9/16

8/3/2016

8/12/16

8/12/16

Letter to Fadi Diya from Nicholas H. Taylor August 12, 2016

SUBJECT: CALLAWAY PLANT - NRC INTEGRATED INSPECTION

REPORT 05000483/2016002 AND NOTICE OF VIOLATION

DISTRIBUTION:

Regional Administrator (Kriss.Kennedy@nrc.gov)

Deputy Regional Administrator (Scott.Morris@nrc.gov)

DRP Director (Troy.Pruett@nrc.gov)

DRP Deputy Director (Ryan.Lantz@nrc.gov)

DRS Director (Anton.Vegel@nrc.gov)

DRS Deputy Director (Jeff.Clark@nrc.gov)

Senior Resident Inspector (Thomas.Hartman@nrc.gov)

Resident Inspector (Michael.Langelier@nrc.gov)

Branch Chief, DRP/B (Nick.Taylor@nrc.gov)

Senior Project Engineer, DRP/B (David.Proulx@nrc.gov)

Project Engineer, DRP/B (Steven.Janicki@nrc.gov)

Administrative Assistant (Dawn.Yancey@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Project Manager (John.Klos@nrc.gov)

Team Leader, DRS/TSS (Thomas.Hipschman@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

RIV Congressional Affairs Officer (Angel.Moreno@nrc.gov)

RIV/ETA: OEDO (Jeremy.Bowen@nrc.gov)

RIV RSLO (Bill.Maier@nrc.gov)

ACES (R4Enforcement.Resource@nrc.gov)

ROPreports.Resource@nrc.gov

ROPassessment.Resource@nrc.gov

- 1 -

Enclosure 1

NOTICE OF VIOLATION

Union Electric Company

Docket No. 50-483

Callaway Plant

License No. NPF-30

During an NRC inspection conducted June 6-30, 2016, a violation of NRC requirements was

identified. In accordance with the NRC Enforcement Policy, the violation is listed below:

10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, requires, in part, that

conditions adverse to quality are promptly identified and corrected.

Contrary to the above, from November 2010 through June 2016, the licensee failed to

promptly correct a condition adverse to quality. Specifically, the licensee failed to

adequately resolve water hammer and corrosion issues which were previously identified

by the NRC as non-cited violation 05000483/2010006-01. The failure to resolve these

issues resulted in subsequent safety-related equipment failures.

This violation is associated with a Green Significance Determination Process finding.

Pursuant to the provisions of 10 CFR 2.201, Union Electric Company is hereby required to

submit a written statement or explanation to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001 with a copy to the Regional

Administrator, Region IV, 1600 East Lamar Blvd., Arlington, Texas 76011-4511 and a copy to

the NRC Senior Resident Inspector at the facility that is the subject of this Notice, within 30 days

of the date of the letter transmitting this Notice of Violation (Notice). This reply should be clearly

marked as a Reply to a Notice of Violation, and should include: (1) the reason for the

violation, or, if contested, the basis for disputing the violation or severity level, (2) the corrective

steps that have been taken and the results achieved, (3) the corrective steps that will be taken,

and (4) the date when full compliance will be achieved. Your response may reference or

include previous docketed correspondence if the correspondence adequately addresses the

required response. If an adequate reply is not received within the time specified in this Notice,

an order or a Demand for Information may be issued as to why the license should not be

modified, suspended, or revoked, or why such other action as may be proper should not be

taken. Where good cause is shown, consideration will be given to extending the response time.

If you contest this enforcement action, you should also provide a copy of your response, with

the basis for your denial, to the Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC 20555-0001.

Because your response will be made available electronically for public inspection in the NRC

Public Document Room or from the NRCs Agencywide Documents Access and Management

System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-

rm/adams.html, to the extent possible, it should not include any personal privacy, proprietary, or

safeguards information so that it can be made available to the public without redaction. If

personal privacy or proprietary information is necessary to provide an acceptable response,

then please provide a bracketed copy of your response that identifies the information that

should be protected and a redacted copy of your response that deletes such information. If you

request withholding of such material, you must specifically identify the portions of your response

that you seek to have withheld and provide in detail the bases for your claim of withholding

(e.g., explain why the disclosure of information will create an unwarranted invasion of personal

privacy or provide the information required by 10 CFR 2.390(b) to support a request for

- 2 -

withholding confidential commercial or financial information). If safeguards information is

necessary to provide an acceptable response, please provide the level of protection described

in 10 CFR 73.21.

In accordance with 10 CFR 19.11, you may be required to post this Notice within two working

days of receipt.

Dated this 12th day of August 2016

- 1 -

Enclosure 2

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket:

05000483

License:

NPF-30

Report:

05000483/2016002

Licensee:

Union Electric Company

Facility:

Callaway Plant

Location:

Junction Highway CC and Highway O

Steedman, MO

Dates:

April1 through June 30, 2016

Inspectors:

T. Hartman, Senior Resident Inspector

M. Langelier, P.E., Resident Inspector

J. Drake, Senior Reactor Inspector

P. Hernandez, Health Physicist

J. Josey, Senior Resident Inspector, Comanche Peak

R. Kopriva, Senior Reactor Inspector

J. ODonnell, Health Physicist

Approved By: Nicholas H. Taylor

Chief, Project Branch B

Division of Reactor Projects

- 2 -

SUMMARY

IR 05000483/2016002; 04/01/2016 - 06/30/2016; Callaway Plant, Equipment Alignment, Heat

Sink Performance, Operability Determinations and Functionality Assessments, Problem

Identification and Resolution, Follow-up of Events and Notices of Enforcement Discretion.

The inspection activities described in this report were performed between April 1 and June 30,

2016, by the resident inspectors at the Callaway Plant and inspectors from the NRCs Region IV

office. Five findings of very low safety significance (Green) are documented in this report. Four

of these findings involved violations of NRC requirements. The significance of inspection

findings is indicated by their color (Green, White, Yellow, or Red), which is determined using

Inspection Manual Chapter 0609, Significance Determination Process. Their cross-cutting

aspects are determined using Inspection Manual Chapter 0310, Aspects within the

Cross-Cutting Areas. Violations of NRC requirements are dispositioned in accordance with the

NRC Enforcement Policy. The NRCs program for overseeing the safe operation of commercial

nuclear power reactors is described in NUREG-1649, Reactor Oversight Process.

Cornerstone: Initiating Events

Green. The inspectors reviewed a self-revealed finding for the licensees failure to follow

the plant procedure for foreign material exclusion. Specifically, after finding foreign material

(broken cable ties) within the main generator excitation transformer, established as a foreign

material exclusion Level 2 area, the licensee failed to determine the reason for the foreign

material and enter the issue into the corrective action program for resolution as required by

Procedure APA-ZZ-00801, Foreign Material Exclusion, Revision 32.

The licensees failure to follow the plant procedure for foreign material exclusion was a

performance deficiency. The performance deficiency is more than minor, and therefore a

finding, because it is associated with the equipment performance attribute of the Initiating

Events Cornerstone and adversely affected the cornerstone objective to limit the likelihood

of events that upset plant stability and challenge critical safety functions during shutdown as

well as power operations. Specifically, after identifying several broken cable ties on the floor

inside a foreign material exclusion Level 2 area the licensee did not determine the reason

for the foreign material nor enter the condition into the corrective action program as required

by Procedure APA-ZZ-00801. Because the licensee failed to understand what caused the

cable tie degradation, a subsequent cable tie failure resulted in a plant trip. Using

Inspection Manual Chapter 0609, Appendix A, The Significance Determination

Process (SDP) for Findings At-Power, dated June 19, 2012, the finding was determined to

be of very low safety significance because it did not cause a reactor trip and the loss of

mitigation equipment relied upon to transition the plant from the onset of the trip to a stable

shutdown condition. This finding has a cross-cutting aspect of training in the human

performance area because the organization did not provide training and ensure knowledge

transfer to maintain a knowledgeable, technically competent workforce and instill nuclear

safety values. Specifically, several groups within the licensees organization were unaware

the excitation transformer cabinet was classified as a foreign material exclusion Level 2 area

nor the requirements if foreign material is found within the foreign material exclusion area

[H.9]. (Section 4OA3)

- 3 -

Cornerstone: Mitigating Systems

Criterion III, Design Control, for the licensees failure to account for the essential service

water pipe stresses caused by pressure fluctuations of the known column closure water

hammer phenomenon. The licensee failed to properly account for essential service water

piping membrane stress and impact loads as required by the 1974 ASME Code,Section III,

paragraphs ND-3112.4 and ND-3111. Specifically, the licensees design calculations for the

essential service water system did not account for the pressure fluctuations caused by a

known column closure water hammer phenomenon that occurs during a loss of off-site

power or load sequencer testing. The licensee completed a prompt operability

determination assuring the system was operable under the current conditions and was

completing engineering evaluations of the data collected to demonstrate the operability of

the system under design conditions. The licensee entered this issued into the corrective

action program as Callaway Action Requests 201603472 and 201603819.

The inspectors determined that the licensees failure to account for the pressure fluctuations

caused by a known column closure water hammer phenomenon in the design calculations

for the essential service water system was a performance deficiency. The performance

deficiency is more than minor, and therefore a finding, because it is associated with the

design control attribute of the Mitigating Systems Cornerstone and adversely affected the

associated objective to ensure availability, reliability, and capability of systems that respond

to initiating events to prevent undesirable consequences. Using Inspection Manual

Chapter 0609, Appendix A, The Significance Determination Process (SDP) for Findings

At-Power, dated June 19, 2012, inspectors determined that this finding was of very low

safety significance (Green) because the finding: (1) was not a deficiency affecting the

design and qualification of a mitigating structure, system, or component, and did not result in

a loss of operability or functionality, (2) did not represent a loss of system and/or function,

(3) did not represent an actual loss of function of at least a single train for longer than its

allowed outage time, or two separate safety systems out-of-service for longer than their

technical specification allowed outage time, and (4) does not represent an actual loss of

function of one or more non-technical specification trains of equipment designated as high

safety significant for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in accordance with the licensees maintenance

rule program. This finding has a cross-cutting aspect of conservative bias in the human

performance area because the licensee failed to demonstrate that a proposed action was

safe in order to proceed, rather than unsafe in order to stop. Specifically, when the licensee

recognized that the column separation water hammer phenomenon was occurring in the

essential service water system, they only applied the forces to the containment coolers, not

the entire system [H.14]. (Section 1R04)

Green. The inspectors identified a non-cited violation of 10 CFR 50.55a, Codes and

Standards, for the licensees failure to repair various ASME Code Class 3 components in

accordance with ASME Code,Section XI requirements. Specifically, the licensee did not

follow the applicable ASME Code requirements when making repairs to various components

in the ASME Code Class 3 essential service water system. The licensee reasonably

determined the essential service water system remained operable, and completed the

necessary repairs and testing to restore compliance with ASME Code. The licensee

entered this issue into their corrective action program as Callaway Action

Requests 201603640 and 201604282.

- 4 -

The inspectors determined that the programmatic failure to repair various ASME Code

Class 3 components in the essential service water system in accordance with ASME Code

was a performance deficiency. The performance deficiency is more than minor, and

therefore a finding, because it is associated with the design control attribute of the Mitigating

Systems cornerstone and adversely affected the associated objective to ensure availability,

reliability, and capability of systems that respond to initiating events to prevent undesirable

consequences. Using Inspection Manual Chapter 0609, Appendix A, The Significance

Determination Process (SDP) for Findings At-Power, dated June 19, 2012, inspectors

determined that this finding was of very low safety significance (Green) because the finding:

(1) was not a deficiency affecting the design and qualification of a mitigating structure,

system, or component, and did not result in a loss of operability or functionality, (2) did not

represent a loss of system and/or function, (3) did not represent an actual loss of function of

at least a single train for longer than its allowed outage time, or two separate safety systems

out-of-service for longer than their technical specification allowed outage time, and (4) does

not represent an actual loss of function of one or more non-technical specification trains of

equipment designated as high safety significant for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in accordance with

the licensees maintenance rule program. Specifically, the licensee performed a historical

system health review and reasonably determined the essential service water system

remained operable because periodic system walkdowns by the system owner and shiftly

rounds by operations had not identified significant system leaks, and the appropriate repairs

and testing were completed on the affected components. This finding has a cross-cutting

aspect of training in the human performance area because the organization did not provide

training and ensure knowledge transfer to maintain a knowledgeable, technically competent

workforce and instill nuclear safety values. Specifically, the licensee failed to ensure training

of the personnel was adequate to recognize that the repair of the leaks constituted repairs in

accordance with ASME Code,Section XI and thus failed to include the necessary ASME

testing requirements in the work performance packages to ensure adequate performance of

an activity which affected testing of a safety-related modification/repair to risk-significant

systems, and thereby ensure nuclear safety [H.9]. (Section 1R07)

Green. The inspectors identified a non-cited violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, for the licensees failure to perform an

adequate operability assessment when a degraded or nonconforming condition was

identified. Specifically, after the licensee identified that a severe water hammer transient

would occur following a loss of off-site power, the licensee generated an operability

evaluation that relied on judgement and inaccurate information which failed to establish a

reasonable expectation of operability. Following questions from inspectors the licensee

determined that this judgement was not correct and performed a new evaluation to ensure

operability of the essential service water system. The licensee entered this issue into their

corrective action program as Callaway Action Request 201605488.

The licensees failure to properly assess and document the basis for operability when a

severe water hammer occurred in the essential service water system was a performance

deficiency. The performance deficiency is more than minor, and therefore a finding,

because it is associated with the equipment performance attribute of the Mitigating Systems

Cornerstone and adversely affected the cornerstone objective to ensure availability,

reliability, and capability of systems that respond to initiating events to prevent undesirable

consequences. Specifically, severe water hammer transients in the essential service water

system due to a loss of off-site power, result in a condition where structures, systems, and

components necessary to mitigate the effects of accidents may not have functioned as

required. Using Inspection Manual Chapter 0609, Appendix A, The Significance

- 5 -

Determination Process (SDP) for Findings At-Power, dated June 19, 2012, inspectors

determined that this finding was of very low safety significance (Green) because the finding:

did not involve the loss or degradation of equipment or function specifically designed to

mitigate a seismic event, and (1) was not a deficiency affecting the design and qualification

of a mitigating structure, system, or component, and did not result in a loss of operability or

functionality, (2) did not represent a loss of system and/or function, (3) did not represent an

actual loss of function of at least a single train for longer than its allowed outage time, or two

separate safety systems out-of-service for longer than their technical specification allowed

outage time, and (4) does not represent an actual loss of function of one or more

non-technical specification trains of equipment designated as high safety-significant for

greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in accordance with the licensees maintenance rule program. This

finding has a cross-cutting aspect of conservative bias in the human performance area

because the licensee failed to demonstrate that a proposed action was safe in order to

proceed, rather than unsafe in order to stop. Specifically, the licensees use of unsupported

judgement and incorrect data resulted in an evaluation that failed to demonstrate a

reasonable expectation of operability [H.14]. (Section 1R15)

Green. The inspectors identified a cited violation of 10 CFR Part 50, Appendix B,

Criterion XVI, Corrective Action, associated with the licensees failure to take timely

corrective action for a previously identified condition adverse to quality. Specifically, the

licensee failed to adequately resolve water hammer and corrosion issues that were

previously identified by the NRC as non-cited violation 05000483/2010006-01 and the failure

to resolve these issues resulted in subsequent safety-related equipment failures. The

licensee performed an operability determination that established a reasonable expectation

of operability pending implementation of corrective actions. The licensee entered this issue

into their corrective action program as Callaway Action Request 201604440.

The licensees failure to take timely and adequate corrective actions to correct a condition

adverse to quality was a performance deficiency. The performance deficiency is more than

minor, and therefore a finding, because it is associated with the equipment performance

attribute of the Mitigating Systems Cornerstone and adversely affected the cornerstone

objective to ensure availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. Specifically, the failure to correct water

hammer and corrosion issue resulted in the licensee declaring safety-related room coolers

and chillers inoperable until an analysis of system operability was completed. This affected

their capability to respond to initiating events to prevent undesirable consequences Using

Inspection Manual Chapter 0609, Appendix A, The Significance Determination

Process (SDP) for Findings At-Power, dated June 19, 2012, inspectors determined that this

finding was of very low safety significance (Green) because the finding: (1) was not a

deficiency affecting the design and qualification of a mitigating structure, system, or

component, and did not result in a loss of operability or functionality, (2) did not represent a

loss of system and/or function, (3) did not represent an actual loss of function of at least a

single train for longer than its allowed outage time, or two separate safety systems out-of-

service for longer than their technical specification allowed outage time, and (4) does not

represent an actual loss of function of one or more non-technical specification trains of

equipment designated as high safety-significant for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in accordance

with the licensees maintenance rule program. This finding has a cross-cutting aspect of

resources in the human performance area because the licensee did not ensure that

personnel, equipment, procedures, and other resources were available and adequate to

support nuclear safety. Specifically, by failing to address water hammer and corrosion

issues, station management failed to ensure that the essential service water system was

- 6 -

available and adequately maintained to respond during a loss of off-site power event [H.1].

(Section 4OA2.3)

- 7 -

PLANT STATUS

Callaway began the inspection period at 86 percent power while coasting down at the end of the

operating cycle and on April 2, 2016, the licensee shut the plant down to start Refueling

Outage 21. The reactor was restarted on May 9. On May 14, at approximately 90 percent

power (during power ascension), the plant reduced power to approximately 65 percent to

address a main feedwater pump issue. The licensee repaired the feedwater pump on May 15

and recommenced power ascension. The plant returned to 100 percent power on May 16. The

plant remained at full power for the remainder of the inspection period.

REPORT DETAILS

1.

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R01 Adverse Weather Protection (71111.01)

.1

Summer Readiness for Off-site and Alternate AC Power Systems

a.

Inspection Scope

On June 7, 2016, the inspectors completed an inspection of the stations off-site and

alternate-ac power systems. The inspectors inspected the material condition of these

systems, including transformers and other switchyard equipment to verify that plant

features and procedures were appropriate for operation and continued availability of

off-site and alternate-ac power systems. The inspectors reviewed outstanding work

orders and open Callaway action requests for these systems. The inspectors walked

down the switchyard to observe the material condition of equipment providing off-site

power sources.

The inspectors verified that the licensees procedures included appropriate measures to

monitor and maintain availability and reliability of the off-site and alternate-ac power

systems.

These activities constituted one sample of summer readiness of off-site and alternate-ac

power systems, as defined in Inspection Procedure 71111.01.

b.

Findings

No findings were identified.

.2

Readiness for Impending Adverse Weather Conditions

a.

Inspection Scope

On April 26, 2016, the inspectors completed an inspection of the stations readiness for

impending adverse weather conditions. The inspectors reviewed plant design features,

the licensees procedures to respond to severe weather including thunderstorms,

tornadoes and high winds, and the licensees implementation of these procedures. The

inspectors evaluated operator staffing and accessibility of controls and indications for

those systems required to control the plant.

- 8 -

These activities constituted one sample of readiness for impending adverse weather

conditions, as defined in Inspection Procedure 71111.01

b.

Findings

No findings were identified.

1R04 Equipment Alignment (71111.04)

Partial Walk-Down

a.

Inspection Scope

The inspectors performed partial system walk-downs of the following risk-significant

systems:

May 24, 2016, train A motor-driven auxiliary feedwater system

June 2, 2016, train B class 1E switchgear

June 8, 2016, train A essential service water

June 9, 2016, train B essential service water

The inspectors reviewed the licensees procedures and system design information to

determine the correct lineup for the systems. They visually verified that critical portions

of the trains were correctly aligned for the existing plant configuration.

These activities constituted four partial system walk-down samples as defined in

Inspection Procedure 71111.04.

b.

Findings

Introduction. The inspectors identified a Green non-cited violation of 10 CFR Part 50,

Appendix B, Criterion III, Design Control, for the licensees failure to account for the

essential service water pipe stresses caused by pressure fluctuations of the known

column closure water hammer phenomenon.

Description. With the current essential service water system design, every loss of

off-site power at Callaway would result in a water column separation and subsequent

re-pressurization by the loss of normal service water pumps and the sequencing start of

the essential service water pumps. This phenomenon was not specifically described in

the licensees Updated Final Safety Analysis Report, however, it had been clearly

identified in previous Callaway Action Requests 199800739, 199800740, 199800741,

200207750, 200404532, 200703197, 200703247, 200703257, 200703491, 200810348,

200810384, 200811050, 201003386, 201109846, 201303346, 201303370, 201303451,

201303502, 201303702, 201303736, 201407222, 201407245, 201407246, 201407248,

201602824, 201603472, 201603484, 201604058, and 201604063. This system

characteristic was also described in Callaways response to NRC Generic Letter 96-06,

Assurance of Equipment Operability and Containment Integrity during Design-Basis

Accident Conditions, January 28, 1997. Additionally, there was external operating

experience concerning water hammer phenomena and the impact on system piping.

- 9 -

Callaway is designed to ASME Code,Section III Nuclear Power Components, 1974

and 1974 winter addenda and ANSI B31.1 1973 piping code including the 1973 summer

addendum. Piping analyses are performed to ensure that design Class II and III piping

systems perform their safety-related functions during plant normal, upset, and faulted

conditions. Pipes are subject to various loading conditions like pressures, dead load,

thermal, earthquake, and seismic/thermal anchor motions. The 1974 ASME Code,

Section III, paragraph ND-3112.4, Design Allowable Stress Values, part c states, in

part,

The wall thickness of a component computed by these rules shall be

determined so that the maximum direct membrane stress due to any

combination of loadings that are expected to occur simultaneously does

not exceed the maximum allowable stress permitted at the temperature

that is expected to be maintained in the metal under the condition of

loading being considered.

Section III, paragraph ND-3111, Loading Criteria, of the ASME Code, states in part,

The loading that shall be taken into account in designing a component shall include, but

are not limited to, the following: (b) Impact loads, including rapidly fluctuating

pressures.

Calculation 0096-020-CALC-01, Revision 0, Callaway Water Hammer Load

Calculation, Section 2.0 states in part,

... both Wolf Creek and Callaway are SNUPPS plants, many similarities

exist. This calculation compares the conditions which can affect the

impact velocity and the amount of air in the system, and adjusts the

results from the Wolf Creek pressure vs. time data to account for those

differences.

Even though Callaway recognized the similarities between Wolf Creek and their unit,

they failed to reevaluate their essential service water when Wolf Creek recognized that

their initial assumptions regarding water hammer phenomena were incorrect.

WCN005-PR-0, a report from ENERCON, which addressed water hammer phenomena

in the essential service water system, stated on page 6,

The results shown in the Table in Section 5.1 of the ALTRAN

Report 96225-TR02 were evaluated by an ENERCON structural expert.

His opinion was that the loads shown were significant enough in every

case to warrant further detailed analysis. This analysis requires the

generation of a detailed FTH (Force Time History) that would result from

the CCWH (column closure water hammer) generated in the ESW

(essential service water) for a LOOP (loss of off-site power) event. The

report recommended that these FTHs would then be evaluated using a

structural piping program and the results added to the existing stresses.

Ultimately a new stress analysis of record would be generated. This

would be a revision of the existing one. Modifications to supports may be

required to qualify the system.

- 10 -

The analysis later stated, To perform the reanalysis for the startup of the ESW pumps

following a LOOP requires that Force Time Histories (FTH) be generated. These are

required for the structural analysis.

The ALTRAN report referenced by ENERCON was report number 09-0223-TR-001,

Revision 0. This report, on page 6 of 14, stated in part, The water hammer pressures

calculated are to be used for preliminary structural assessment of the piping systems

ability to withstand this loading and to determine if a more detailed force time history

needs to be generated. On page 7 the report continued, Experience has shown that

the concerns resulting from water hammer events are: (1) Over-pressure of pipes and

components, e.g., ruptured tubes in heat exchangers, and (2) Pipe and component

nozzle stress due to bending moments created by the CCWH force time history (FTH).

Despite the internal and external operating experience, the licensee only updated the

design calculation for the containment coolers to include the pressures associated with

the water hammer phenomena, but did not included these stresses in the design

calculations for the remainder of the essential service water system. The basic

engineering disposition written to address the potential effects of water hammer impact

loads on the structural integrity of the pressure boundary did not include the pressure

stresses induced in the pipe due to the water hammer phenomenon. It stated, in part,

This Basic Engineering Disposition is to document that the potential

effects of water hammer impact loads on the structural integrity of the

pressure boundary have been evaluated for piping affected by pitting

corrosion. Because water hammer pressure waves are of short duration

and are self-limiting (secondary) loads, assuring that the pitted pipe

meets ASME Boiler and Pressure Vessel Code (Code) requirements for

design loads is sufficient to conclude that the pressure boundary has

sufficient margin to withstand impact from water hammer.

This engineering evaluation failed to meet the requirements of ASME Code Section III,

paragraph ND-3111, Loading Criteria,, which states in part, The loading that shall be

taken into account in designing a component shall include, but are not limited to, the

following: ... (b) Impact loads, including rapidly fluctuating pressures. In addition,

operating experience at Callaway has consistently demonstrated that the pressure

boundary lacks sufficient margin to withstand the impact from the water hammer as

documented in the multiple Callaway action requests concerning system leaks after a

water hammer event has occurred.

Although this was a deficiency affecting the design and qualification of the essential

service water system, the licensee was able to demonstrate that the operability and

function of the essential service water system had not been lost because the leaks that

occurred were less than the allowable losses from the ultimate heat sink. The spray

from the leaks did not adversely impact any other equipment, and the components

affected maintained structural integrity.

Analysis. The inspectors determined that the licensees failure to account for the

pressure fluctuations caused by a known column closure water hammer phenomenon in

the design calculations for the essential service water system was a performance

deficiency. The performance deficiency is more than minor, and therefore a finding,

because it is associated with the design control attribute of the Mitigating Systems

- 11 -

Cornerstone and adversely affected the associated objective to ensure availability,

reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences.

Using Inspection Manual Chapter 0609, Appendix A, The Significance Determination

Process (SDP) for Findings At-Power, dated June 19, 2012, inspectors determined that

this finding was of very low safety significance (Green) because the finding: (1) was not

a deficiency affecting the design and qualification of a mitigating structure, system, or

component, and did not result in a loss of operability or functionality, (2) did not

represent a loss of system and/or function, (3) did not represent an actual loss of

function of at least a single train for longer than its allowed outage time, or two separate

safety systems out-of-service for longer than their technical specification allowed outage

time, and (4) does not represent an actual loss of function of one or more non-technical

specification trains of equipment designated as high safety significant for greater

than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in accordance with the licensees maintenance rule program. This finding

has a cross-cutting aspect of conservative bias in the human performance area because

the licensee failed to demonstrate that a proposed action was safe in order to proceed,

rather than unsafe in order to stop. Specifically, when the licensee recognized that the

column separation water hammer phenomenon was occurring in the essential service

water system, they only applied the forces to the containment coolers, not the entire

system [H.14].

Enforcement. Title 10 CFR Part 50 Appendix B, Criterion III, Design Control, states, in

part, that for those structures, systems and components to which this appendix applies,

design control measures shall provide for verifying or checking the adequacy of designs.

Contrary to the above, from June 4, 1985, to the present, for the safety-related essential

service water system, to which 10 CFR Part 50 applies, the licensee failed to provide for

verifying or checking the adequacy of designs. Specifically, the licensee did not include

the pressures induced by the water hammer phenomenon in the design calculation for

the essential service water system as required by the 1974 ASME Code, which the

licensee is committed to follow. The licensee performed a historical system health

review and reasonably determined the essential service water system remained

operable because periodic system walkdowns by the system owner and shiftly rounds by

operations had not identified significant system leaks, and the appropriate repairs and

testing were completed on the affected components. In addition, the licensee conducted

an instrumented run of the system simulating a loss of off-site power and collected data

on the pressure spikes experienced by the system. Following the completion of the test

the licensee conducted a system walkdown to inspection for indications of damage to

the system. Based on the results of this evolution, the licensee completed a prompt

operability determination assuring the system was operable under the current conditions,

and was completing engineering evaluations of the data collected to demonstrate the

operability of the system under design conditions. This violation is being treated as a

non-cited violation, consistent with Section 2.3.2.a of the Enforcement Policy because it

was of very low safety significance, and was entered into the licensees corrective action

program as Callaway Action Requests 201603472 and 201603819:

NCV 05000483/2016002-01, Failure to Account for Water Hammer Stresses in

Essential Service Water System Calculations.

- 12 -

1R05 Fire Protection (71111.05)

Quarterly Inspection

a.

Inspection Scope

The inspectors evaluated the licensees fire protection program for operational status

and material condition. The inspectors focused their inspection on five plant areas

important to safety:

May 12, 2016, train B battery and switchboard rooms (C-15)

June 2, 2016, train A electrical penetration room (A-18)

June 3, 2016, boric acid tank rooms (A-3)

June 9, 2016, train A control room air conditioning room (A-22)

June 9, 2016, train A battery and switchboard rooms (C-16)

For each area, the inspectors evaluated the fire plan against defined hazards and

defense-in-depth features in the licensees fire protection program. The inspectors

evaluated control of transient combustibles and ignition sources, fire detection and

suppression systems, manual firefighting equipment and capability, passive fire

protection features, and compensatory measures for degraded conditions.

These activities constituted five quarterly inspection samples, as defined in Inspection

Procedure 71111.05.

b.

Findings

No findings were identified.

1R07 Heat Sink Performance (71111.07)

a.

Inspection Scope

The inspectors completed an inspection of the readiness and availability of

risk-significant heat exchangers. The inspectors verified the licensee used the industry

standard periodic maintenance method outlined in EPRI NP-7552 for the heat

exchangers. Additionally, the inspectors walked down the heat exchangers to observe

the performance and material condition and/or verified that the heat exchangers were

correctly categorized under the Maintenance Rule and were receiving the required

maintenance.

April 3, 2016, emergency core cooling system room coolers

June 9, 2016, control room chillers

These activities constituted completion of two heat sink performance annual review

samples, as defined in Inspection Procedure 71111.07.

b.

Findings

Introduction. The inspectors identified a Green non-cited violation of 10 CFR 50.55a,

Codes and Standards, for the licensees failure to repair various ASME Code Class 3

- 13 -

components in accordance with ASME Code,Section XI requirements. Specifically, the

licensee did not follow the applicable ASME Code requirements when making repairs to

various components in the ASME Code Class 3 essential service water system.

Description. The inspectors identified a programmatic issue with the licensees inservice

inspection and repair program because the engineering department personnel lacked

adequate training and knowledge of the ASME Code to recognize activities that

constituted repair activities per ASME Section XI. Specifically, the licensee had been

repairing leaking tubes on various ASME Code Class 3 room coolers (SGL09B - B

Safety Injection Pump Room Cooler, SGL10A - A Residual Heat Removal Pump Room

Cooler, SGL10B - B Residual Heat Removal Pump Room Cooler, and SGL13B - B

Containment Spray Pump Room Cooler) as a simple maintenance evolution, and failed

to recognized that this constituted a repair activity per ASME Code,Section XI. The

maintenance activities of concern were repairs to plug tube leaks which consisted of

cutting a tube in order to remove a defect (pinhole), then mechanically installing (no

brazing or welding) a Swagelok cap to plug the tube. Use of Swagelok caps to repair

heat exchanger tube leaks is allowed by ASME Code and licensee procedures. These

jobs were planned and performed as a maintenance activity in accordance with

applicable licensee procedures.

Callaway is currently committed to the 2007 Edition/2008 Addenda of ASME Code,

Section XI. ASME Code,Section XI, IWA-4120(b)(7) exempts ASME Class 2 and 3

mechanical tube plugging; however, the repairs to these components are considered an

ASME Code,Section XI Repair/Replacement Activity. Per footnote 1 in IWA-4110

alterations are considered a repair/replacement activity per Section XI of ASME Code.

This is because the tubes that had the Swagelok fittings installed still see system

pressure: flow through the tube was not isolated. Therefore, the pressure boundary

was altered and the licensee is required to ensure it meets the requirements for ASME

Code Class 3 pressure boundaries.

The physical work that was performed met the requirements of Section XI.

Safety-related Swagelok caps were installed and ASME Code,Section III (the

construction code) sections ND-3646 and ND-3674.1(e) allow the use of caps, so the

repairs met the applicable construction code requirements.

The licensee did not consider the work as a repair activity per ASME Code,Section XI,

therefore, requirements were not documented in the work packages and were not

completed. These requirements were:

ANII notification

Traceability of code pressure retaining parts

Performance of required pressure test - VT-2

The licensee documented these deficiencies under Callaway Action

Request 201603640, verified and documented the use of code pressure retaining parts,

and completed the required VT-2 pressure tests to correct these issues.

The repair performed on SGL13A (Containment Spray Pump A Room Cooler) utilized

brazing to build up base metal of a pinhole leak. This resulted in a repair that was not an

approved method by the ASME Code,Section XI. To correct this condition, the licensee

- 14 -

generated Job 16002356-500, "Repair Tubing that was Improperly Repaired under

Job 10506915."

This job was completed in accordance with ASME Code requirements and a successful

VT-2 was performed. In addition, the engineering department received training on

ASME Code repair recognition and requirements.

Analysis. The inspectors determined that the programmatic failure to repair various

ASME Code Class 3 components in the essential service water system in accordance

with ASME Code was a performance deficiency. The performance deficiency is more

than minor, and therefore a finding, because it is associated with the design control

attribute of the Mitigating Systems cornerstone and adversely affected the associated

objective to ensure availability, reliability, and capability of systems that respond to

initiating events to prevent undesirable consequences.

Using Inspection Manual Chapter 0609, Appendix A, The Significance Determination

Process (SDP) for Findings At-Power, dated June 19, 2012, inspectors determined that

this finding was of very low safety significance (Green) because the finding: (1) was not

a deficiency affecting the design and qualification of a mitigating structure, system, or

component, and did not result in a loss of operability or functionality, (2) did not

represent a loss of system and/or function, (3) did not represent an actual loss of

function of at least a single train for longer than its allowed outage time, or two separate

safety systems out-of-service for longer than their technical specification allowed outage

time, and (4) does not represent an actual loss of function of one or more non-technical

specification trains of equipment designated as high safety significant for greater than

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in accordance with the licensees maintenance rule program. Specifically, the

licensee performed a historical system health review and reasonably determined the

essential service water system remained operable because periodic system walkdowns

by the system owner and shiftly rounds by operations had not identified significant

system leaks, and the appropriate repairs and testing were completed on the affected

components. This finding has a cross-cutting aspect of training in the human

performance area because the organization did not provide training and ensure

knowledge transfer to maintain a knowledgeable, technically competent workforce and

instill nuclear safety values. Specifically, the licensee failed to ensure training of the

personnel was adequate to recognize that the repair of the leaks constituted repairs in

accordance with ASME Code,Section XI and thus failed to include the necessary ASME

testing requirements in the work performance packages to ensure adequate

performance of an activity which affected testing of a safety-related modification/repair to

risk-significant systems, and thereby ensure nuclear safety [H.9].

Enforcement. Title 10 CFR 50.55a, Codes and Standards, requires, in part, that

safety-related pressure vessels, piping, pumps and valves, and their supports must meet

the requirements applicable to components that are classified as ASME Code Class 3.

Contrary to the above, as of April 18, 2016, the licensee failed to ensure that

safety-related pressure vessels, piping, pumps and valves, and their supports must meet

the requirements applicable to components that are classified as ASME Code Class 3.

Specifically, the licensee failed to complete repairs to various ASME Code Class 3

components in the essential service water system because the engineering department

did not recognize that correcting tube leakage constituted a repair activity per ASME

Code,Section XI. The licensee has completed the applicable testing requirements for

the repairs as part of the planned corrective actions. The licensee implemented

- 15 -

immediate correction actions to enter this issue into the corrective action program for

resolution. The licensee also completed the necessary repairs and testing to restore

compliance with ASME Code. This violation is being treated as a non-cited violation,

consistent with Section 2.3.2.a of the Enforcement Policy because it was of very low

safety significance, and was entered into the licensees corrective action program as

Callaway Action Requests 201603640 and 201604282: NCV 05000483/2016002-02,

Failure to Meet Applicable ASME Code Requirements for Repairs to Components in the

Essential Service Water System.

1R08 Inservice Inspection Activities (71111.08)

The activities described below constitute completion of two inservice inspection samples,

as defined in Inspection Procedure 71111.08.

.1

Non-destructive Examination Activities and Welding Activities

a.

Inspection Scope

The inspectors directly observed the following nondestructive examinations:

SYSTEM

WELD IDENTIFICATION

EXAMINATION TYPE

Auxiliary

Feedwater

System

Report Number 5010-16-0057

Condensate Storage Tank to Auxiliary

Feedwater Header Isolation Valve,

Field Weld-25 (Component ALV0202)

Magnetic Particle

Auxiliary

Feedwater

System

Report Number 5010-16-0058

Condensate Storage Tank to Auxiliary

Feedwater Header Isolation Valve,

Field Weld-26 (Component ALV0202)

Magnetic Particle

Auxiliary

Feedwater

System

Report Number 5010-16-0059

Condensate Storage Tank to Auxiliary

Feedwater Header Isolation Valve,

Field Weld-27 (Component ALV0202)

Magnetic Particle

Auxiliary

Feedwater

System

Report Number 5010-16-0060

Condensate Storage Tank to Auxiliary

Feedwater Header Isolation Valve,

Field Weld-28 (Component ALV0202)

Magnetic Particle

Auxiliary

Feedwater

System

Report Number 5010-16-0061

Condensate Storage Tank to Auxiliary

Feedwater Header Isolation Valve,

Field Weld-29 (Component ALV0202)

Magnetic Particle

- 16 -

SYSTEM

WELD IDENTIFICATION

EXAMINATION TYPE

Safety Injection

System

Report Number 5000-16-0010

Safety Injection Accumulator D Outlet,

Upstream Check Valve Test Line

Isolation Valve, Field Weld-01

(Component EPHV8877D)

Penetrant

Safety Injection

System

Report Number 5000-16-0011

Safety Injection Accumulator D Outlet,

Upstream Check Valve Test Line

Isolation Valve, Field Weld-02

(Component EPHV8877D)

Penetrant

Safety Injection

System

Report Number 5000-16-0012

Safety Injection Accumulator D Outlet,

Upstream Check Valve Test Line

Isolation Valve, Field Weld-03

(Component EPHV8877D)

Penetrant

Reactor Coolant

System

Record Number 5030-16-012

Fabricated Pipe Spool Piece Including Valve

BBV0007 Reactor Coolant System Loop 1

Hot Leg to Nuclear Sample System Isolation

Valve, Job Number 16001742-405 (Weld

Joints 16001742-405-FW-05 and 06)

Radiograph

Reactor Coolant

System

Record Number 5030-16-014

Reactor Coolant System Pressurizer

Chemical and Volume Control System

Auxiliary Spray Supply Drain

(Component BBV0400)

Radiograph

Reactor Coolant

System

Record Number UT-16-024

Reactor Pressure Vessel Stud Number 1

(Component 2-CH-STUD-01)

Ultrasonic

Reactor Coolant

System

Record Number UT-16-025

Reactor Pressure Vessel Stud Number 2

(Component 2-CH-STUD-02-R1)

Ultrasonic

Reactor Coolant

System

Record Number UT-16-026

Reactor Pressure Vessel Stud Number 3

(Component 2-CH-STUD-03)

Ultrasonic

- 17 -

SYSTEM

WELD IDENTIFICATION

EXAMINATION TYPE

Reactor Coolant

System

Record Number UT-16-050

Reactor Pressurizer Safety Nozzle A

Inner Radius Area Examination

(Component 2-BB03-10A-A-IR,

Exam Angle 55° + 38°)

Ultrasonic

Reactor Coolant

System

Record Number UT-16-050

Reactor Pressurizer Safety Nozzle A

Inner Radius Area Examination

(Component 2-BB03-10A-A-IR,

Exam Angle 55° - 38°)

Ultrasonic

Reactor Coolant

System

Record Number UT-16-052

Reactor Pressurizer Safety Nozzle B

Inner Radius Area Examination

(Component 2-BB03-10B-B-IR,

Exam Angle 55° + 38°)

Ultrasonic

Reactor Coolant

System

Record Number UT-16-052

Reactor Pressurizer Safety Nozzle B

Inner Radius Area Examination

(Component 2-BB03-10B-B-IR,

Exam Angle 55° - 38°)

Ultrasonic

Reactor Coolant

System

Record Number UT-16-053

Reactor Pressurizer Safety Nozzle B

to Top Head Weld

(Component 2-TBB03-10B-B-W,

Exam Angle 55° - 38°)

Ultrasonic

Reactor Coolant

System

Acquisition Log No. DM/Pipe 22-1

Reactor Outlet Nozzle (Hot Leg) 22°

(Nozzle to Safe-End Dissimilar Metal

Weld 2-RV-301-121-A and Safe-End to Pipe

Weld 2-BB-01-F103)

Ultrasonic

Reactor Coolant

System

Acquisition Log No. DM/Pipe 158-1

Reactor Outlet Nozzle (Hot Leg) 158°

(Nozzle to Safe-End Dissimilar Metal

Weld 2-RV-301-121-B and Safe-End to Pipe

Weld 2-BB-01-F203)

Ultrasonic

- 18 -

SYSTEM

WELD IDENTIFICATION

EXAMINATION TYPE

Reactor Coolant

System

Acquisition Log No. DM/Pipe 202-1

Reactor Outlet Nozzle (Hot Leg) 202°

(Nozzle to Safe-End Dissimilar Metal

Weld 2-RV-301-121-C and Safe-End to Pipe

Weld 2-BB-01-F303)

Ultrasonic

Reactor Coolant

System

Acquisition Log No. DM/Pipe 338-1

Reactor Outlet Nozzle (Hot Leg) 338°

(Nozzle to Safe-End Dissimilar Metal

Weld 2-RV-301-121-D and Safe-End to Pipe

Weld 2-BB-01-F403)

Ultrasonic

Safety Injection

System

Report Number 5041-16-0020

Safety Injection Pumps - Crosstie to Cold

Leg Loops Numbers 1, 2, 3, and 4

(Component Location P049)

Visual

Reactor Coolant

System

Report Number 5041-16-0021

Reactor Pressure Vessel Head

(Component RBB01)

Visual

Essential

Service Water

System

Record Number 5042-16-0035

Essential Service Water System Support

(Component EF02C003142)

Visual

Essential

Service Water

System

Record Number 5042-16-0036

Essential Service Water System Support

Hanger (Component EF03C034134)

Visual

Essential

Service Water

System

Record Number 5042-16-0037

Essential Service Water System Support

(Component EF01C012311)

Visual

Emergency

Diesel

Generator

Record Number 5042-16-0038

Diesel Generator A Jacket Water Heat

Exchanger Supports (Component EKJ06A)

Visual

Emergency

Diesel

Generator

Record Number 5042-16-0039

Diesel Generator A Jacket Water Heat

Exchanger Supports (Component EJH06A)

Visual

- 19 -

SYSTEM

WELD IDENTIFICATION

EXAMINATION TYPE

Chemical and

Volume Control

System

Report Number 5042-16-0056

Chemical and Volume Control System

Pipe Support (Component BG23H004231)

Visual

The inspectors reviewed records for the following nondestructive examinations:

SYSTEM

IDENTIFICATION

EXAMINATION TYPE

Condensate

System

Report Number 5010-16-0040

High Pressure Condensate Main Steam

Dump Valve Low Point Drain Steam Trap

Bypass Valve (Component ABV0184)

Magnetic Particle

Auxiliary

Feedwater

System

Report Number 5010-16-0042

Condensate Storage Tank to Auxiliary

Feedwater Pump Suction Check Valve

(Component ALV0217)

Magnetic Particle

Auxiliary

Feedwater

System

Report Number 5010-16-0048

Auxiliary Feedwater System 3-inch

Tee to 3-inch Spool Piece

(Job Number 15001243, Field

Weld FW-16)

Magnetic Particle

Auxiliary

Feedwater

System

Report Number 5010-1-0049

Hardened Condensate Storage Tank

to Auxiliary Feedwater Pump Header

Isolation Valve (Component ALV0202,

Job Number 15000069, Field

Weld FW-30)

Magnetic Particle

Safety Injection

System

Report Number 5000-16-0008

Safety Injection Pump B Loop 4 Hot Leg

Test Line Isolation HV

(Component EMHV8889D)

Penetrant

Safety Injection

System

Report Number 5000-16-0010

Safety Injection Accumulator D Outlet

Upstream Check Valve Test Line Isolation

(Component EPHV8877D, Downstream

Side of Valve)

Penetrant

- 20 -

SYSTEM

IDENTIFICATION

EXAMINATION TYPE

Safety Injection

System

Report Number 5000-16-0011

Safety Injection Accumulator Outlet

Upstream Check Valve Test Line Isolation

(Component EPHV8877D, Upstream

Side of Valve)

Penetrant

Chemical and

Volume Control

System

Report Number 5000-16-0018 Chemical

and Volume Control System Letdown

Throttle Valve B (Component BGV0002)

Penetrant

Reactor Coolant

System

Record Number 5030-16-010

Fabricated Pipe Spool Piece Including

Valve BBV0007-Reactor Coolant System

Loop 1 Hot Leg to Nuclear Sample

System Isolation Valve

(Job Number 16001742-400, Field Weld

Joint 16001742-400-FW-01)

Radiograph

Reactor Coolant

System

Record Number 5030-16-011

Fabricated Pipe Spool Piece Including

Valve BBV0007-Reactor Coolant System

Loop 1 Hot Leg to Nuclear Sample

System Isolation Valve

(Job Number 16001742-400, Field Weld

Joint 16001742-400-FW-02)

Radiograph

Reactor Coolant

System

Report Number 5042-16-028

Reactor Pressure Vessel Head

(Component RBB01, Second Inspection)

Visual

During the review and observation of each examination, the inspectors observed

whether activities were performed in accordance with the ASME Code requirements and

applicable procedures. The inspectors also reviewed the qualifications of all

nondestructive examination technicians performing the inspections to determine whether

they were current.

- 21 -

The inspectors directly observed a portion of the following welding activities:

SYSTEM

WELD IDENTIFICATION

WELD TYPE

Reactor Coolant

System

Valve BBV-0400, Reactor Coolant

System Pressurizer Chemical and

Volume Control System Auxiliary

Spray Supply Drain

(Job 15001126-500, ASME Code

Class 2, Field Weld FW-03)

Manual Gas Tungsten Arc

Welding

Chemical and

Volume Control

System

Valve BGV-0003, CVCS Letdown

Orifice A Outlet Throttle Valve Piping

(Job 13005673-510, ASME Code

Class 2, Field Weld FW-03, -04

and -05)

Manual Gas Tungsten Arc

Welding

Chemical and

Volume Control

System

Valve BGV-0002, CVCS Letdown

Orifice A Outlet Throttle Valve Piping

(Job 13005672-510, ASME Code

Class 2, Field Weld FW-01, -02,

and -03)

Manual Gas Tungsten Arc

Welding

Auxiliary

Feedwater

System

Hardened Condensate Storage

Tank Re-Circulation Line And

Tie-In to Existing Auxiliary

Feedwater System Piping

(Job 15001243-500, Field Welds

FW-11, -12, -13, -14, -15, and -16)

Manual Gas Tungsten Arc

Welding

The inspectors reviewed records of the following welding activities:

SYSTEM

WELD IDENTIFICATION

WELD TYPE

Chemical and

Volume Control

System

Valve BGV-0001, CVCS Letdown

Orifice A Outlet Throttle Valve Piping

(Job 13005670-510, ASME Code

Class 2, Field Weld FW-03, -04,

and -05)

Manual Gas Tungsten Arc

Welding

Chemical and

Volume Control

System

Valve BGV-0001, CVCS Letdown

Orifice A Outlet Throttle Valve Piping

(Job 13005670-010, ASME Code

Class 2, Field Weld FW-01, and -02)

Manual Gas Tungsten Arc

Welding

- 22 -

Chemical and

Volume Control

System

Valve BGV-0002, CVCS Letdown

Orifice A Outlet Throttle Valve Piping

(Job 13005672-010, ASME Code

Class 2, Field Weld FW-04, and -05)

Manual Gas Tungsten Arc

Welding

The inspectors reviewed whether the welding procedure specifications and the welders

had been properly qualified in accordance with ASME Code,Section IX requirements.

The inspectors also determined whether essential variables were identified, recorded in

the procedure qualification record, and formed the bases for qualification of the welding

procedure specifications.

b.

Findings

No findings were identified.

.2

Vessel Upper Head Penetration Inspection Activities

a.

Inspection Scope

The inspectors reviewed the results of the licensees bare metal visual inspection of the

reactor vessel upper head penetrations to determine whether the licensee identified any

evidence of boric acid challenging the structural integrity of the reactor head components

and attachments. The inspectors also verified that the required inspection coverage was

achieved and limitations were properly recorded. The inspectors reviewed whether the

personnel performing the inspection were certified examiners to their respective

nondestructive examination method.

b.

Findings

The licensee replaced the reactor head during the last refueling outage, RF-20, during

the fall 2014, and elected to do a visual inspection of the reactor head at the completion

of the first inservice cycle. Some items of interest were identified requiring further

inspection. The licensee concluded that there was no leakage associated with any of

the reactor vessel closure head penetrations which was documented in Callaway Action

Request 201603166. The inspectors witnessed the inspection, discussed the concern

with the individuals that had performed the inspection, reviewed the photographs of the

areas of concern, and agreed with the licensees conclusion.

No findings were identified.

.3

Boric Acid Corrosion Control Inspection Activities

a.

Inspection Scope

The inspectors reviewed the licensees implementation of its boric acid corrosion

control program for monitoring degradation of those systems that could be adversely

affected by boric acid corrosion. The inspectors reviewed the documentation

associated with the licensees boric acid corrosion control walkdown as specified in

Procedure EDP-ZZ-01004, Boric Acid Corrosion Control Program, Revision 18. The

inspectors reviewed whether the visual inspections emphasized locations where boric

acid leaks could cause degradation of safety significant components and whether

- 23 -

engineering evaluation used corrosion rates applicable to the affected components and

properly assessed the effects of corrosion induced wastage on structural or pressure

boundary integrity. The inspectors observed whether corrective actions taken were

consistent with the ASME Code and 10 CFR Part 50, Appendix B requirements.

The inspectors reviewed licensee boric acid evaluations where boric acid deposits were

found on reactor coolant system piping components and other components:

COMPONENT

NUMBER

DESCRIPTION

CALLAWAY ACTION

REQUEST

BBHV8002A and

BHV8002B

Reactor Head Vent Valve Tailpieces on Top

of the Reactor Head

201406993

EEJ01A

Residual Heat Removal (RHR) System

Heat Exchanger A - Flange

201406827

EEJ01B

Residual Heat Removal (RHR) System

Heat Exchanger B - Flange

201406528

BB10-C503

Hangar BB10-C503 (Adjacent Valve

BBHV8141C, RCP C SEAL # 1 SEAL WTR

OUT ISO HV Experienced Packing

Leakage)

201407170

EMHV8923A

Refueling Water Storage Tank to Safety

Injection Pump A Suction Isolation Valve

201407454

EPV0124

Downstream Isolation Valve for Test Header

Valve EPHV8879D

201407589

EMV0179

ENV0123

Safety Injection Pump A from Residual Heat

Removal Heat Exchanger A Suction Vent

Valve

B Containment Spray Pump Casing and

Seal Housing Vent Valve

201408130

EJ8842

Residual Heat Removal Trains A&B Safety

Injection System Hot Leg Recirculation

Supply Header Pressure Relief Valve

201409218

BBHV8351A

Reactor Coolant Pump A Seal Water Supply

Isolation Valve

201500874

BGFCV0110A

BGPIS0141

Blending Tee Flow Control Valve and

Seal Water Injection Filter B

201503867

- 24 -

BGV0551

Chemical and Volume Control System Seal

Water Injection Filter B Outlet Drain Valve

(Bolted Blind Flange Assembly Downstream

of Valve)

201504450

EPHV8877B

Safety Injection System Upstream Check

Test Line Isolation Valve

201505362

EMHV8923A

Refueling Water Storage Tank to Safety

Injection Pump A Suction Isolation Valve

201600224

b.

Findings

No findings were identified.

.4

Steam Generator Tube Inspection Activities

a.

Inspection Scope

The inspectors reviewed the steam generator tube eddy current examination scope and

expansion criteria to determine whether these criteria met technical specification

requirements, EPRI guidelines, and commitments made to the NRC. The inspectors

also reviewed whether the eddy current examination inspection scope included areas of

degradations that were known to represent potential eddy current test challenges such

as the top of tubesheet, tube support plates, and U-bends. The inspectors confirmed

that repairs were required at the time of the inspection.

Steam Generator Inspection

The inspectors verified that the number and sizes of steam generator tube

flaws/degradation identified were consistent with the licensees previous outage

operational assessment predictions.

The inspectors verified that steam generator eddy current examination scope

and expansion criteria met technical specification requirements.

The inspectors verified that eddy current probes and equipment configurations

used to acquire data from the steam generator tubes were qualified to detect the

known/expected types of steam generator tube degradation in accordance with

Appendix H, Performance Demonstration for Eddy Current Examination of EPRI

Document 1013706.

Eddy current bobbin probe examinations all four steam generators (100 percent

of all inservice tubes, full length tube-end to tube-end) was performed.

Eddy current array probe examinations (all four steam generators) was

performed.

- 25 -

The inspectors reviewed the licensees identification of the following tube degradation

mechanisms:

All inservice 1R18 tube support plate multi-land wear indications, including the

following:

o Steam Generator C (8 lands)

o Steam Generator D (4 lands)

Anti-vibration bar (AVB) wear

All cold leg tubes having non-nominal tubesheet drill hole diameters

20 percent of hot leg tubes with sludge from the 1R18 sludge analysis

Tube Repair

The inspectors verified that the licensee implemented repair methods which were

consistent with the repair processes allowed in the plant technical specification

requirements and to determine if qualified depth sizing methods were applied to

degraded tubes accepted for continued service. The licensee repaired a total of

25 tubes. The following repairs were made.

Steam Generator A - 9 tubes plugged

Steam Generator C - 14 tubes plugged

Steam Generator D - 2 tubes plugged

Secondary Side Inspections

The inspectors observed and reviewed secondary side inspection results and verified

the licensee took corrective actions in response to the observed degradation.

Inspections performed were:

Top of tubesheet water lancing on all four steam generators:

o Prior to water lancing, a pre-look visual inspection was performed to

examine the sludge piles in two steam generators.

Foreign object search and retrieval (FOSAR)

Visual inspections of steam drums in steam generator A and steam generator D

Visual Examinations

The inspectors observed and reviewed the visual examination inspection results.

Inspections performed were:

As-found and as-left visual examination of primary channel heads (both hot leg

and cold leg)

- 26 -

Nuclear Safety Advisory Letter 12-1 (and Information Notice 2013-20) primary

bowl inspections

b.

Findings

No findings were identified.

.5

Identification and Resolution of Problems

a.

Inspection scope

The inspectors reviewed 22 Callaway action request reports which dealt with inservice

inspection activities and found the corrective actions for inservice inspection issues were

appropriate. From this review the inspectors concluded that the licensee has an

appropriate threshold for entering inservice inspection issues into the corrective action

program and has procedures that direct a root cause evaluation when necessary. The

licensee also has an effective program for applying industry inservice inspection

operating experience.

b.

Findings

No findings were identified.

.6

Essential Service Water System Inspection

a.

Inspection Scope

Inspectors performed a focused baseline inspection of the essential service water

system due to concerns with system reliability as a result of ongoing corrosion and water

hammer issues. The scope of the inspection included system walkdowns as well as

review of design calculations, Callaway action requests, operability determinations, and

testing and surveillances associated with the essential service water system.

b.

Findings

A finding of very low safety significance was identified and is discussed in Section 1R07,

Heat Sink Performance.

1R11 Licensed Operator Requalification Program and Licensed Operator

Performance (71111.11)

.1

Review of Licensed Operator Requalification

a.

Inspection Scope

On May 31, 2016, the inspectors observed an evaluated simulator scenario performed

by an operating crew. The inspectors assessed the performance of the operators and

the evaluators critique of their performance. The inspectors also assessed the modeling

and performance of the simulator during the activities.

These activities constituted completion of one quarterly licensed operator requalification

program sample, as defined in Inspection Procedure 71111.11.

- 27 -

b.

Findings

No findings were identified.

.2

Review of Licensed Operator Performance

a.

Inspection Scope

On April 2, 2016, the inspectors observed the performance of on-shift licensed operators

in the plants main control room. At the time of the observations, the plant was in a

period of heightened activity due to shutdown activities for Refueling Outage 21,

including the main turbine overspeed trip testing.

In addition, the inspectors assessed the operators adherence to plant procedures,

including Procedure ODP-ZZ-00001, Operations Department - Code of Conduct,

Revision 97, and other operations department policies.

These activities constituted completion of one quarterly licensed operator performance

sample, as defined in Inspection Procedure 71111.11.

b.

Findings

No findings were identified.

1R12 Maintenance Effectiveness (71111.12)

a.

Inspection Scope

On March 24, 2016, the inspectors reviewed the emergency core cooling system room

coolers for instances of degraded performance or condition of safety-related structures,

systems, and components.

The inspectors reviewed the extent of condition of possible common cause structure,

system, and component failures and evaluated the adequacy of the licensees corrective

actions. The inspectors reviewed the licensees work practices to evaluate whether

these may have played a role in the degradation of the structures, systems, and

components. The inspectors assessed the licensees characterization of the

degradation in accordance with 10 CFR 50.65 (the Maintenance Rule), and verified that

the licensee was appropriately tracking degraded performance and conditions in

accordance with the Maintenance Rule.

These activities constituted completion of one maintenance effectiveness sample, as

defined in Inspection Procedure 71111.12.

b.

Findings

A finding of very low safety significance was identified and is discussed in Section 1R07,

Heat Sink Performance.

- 28 -

1R13 Maintenance Risk Assessments and Emergent Work Control (71111.13)

a.

Inspection Scope

The inspectors reviewed three risk assessments performed by the licensee prior to

changes in plant configuration and the risk management actions taken by the licensee in

response to elevated risk:

April 4, 2016, yellow risk for reduced reactor coolant system inventory to support

reactor vessel head assembly removal for refuel

April 19, 2016, yellow risk for train B spent fuel cooling system out-of-service and

train B electrical switchgear work in progress

May 6, 2016, risk evaluation in accordance with Technical Specification 3.0.4.b

for the atmospheric steam dumps, feedwater regulating valves, and

turbine-driven auxiliary feedwater pump inoperable for moving from Mode 4 to

Mode 3

The inspectors verified that these risk assessment were performed timely and in

accordance with the requirements of 10 CFR 50.65 (the Maintenance Rule) and plant

procedures. The inspectors reviewed the accuracy and completeness of the licensees

risk assessments and verified that the licensee implemented appropriate risk

management actions based on the result of the assessments.

The inspectors also observed portions of two emergent work activities that had the

potential to affect the functional capability of mitigating systems:

April 12, 2016, train A emergency diesel generator pump seals installed

backwards

June 21, 2016, loose bolts on train B control room air conditioning system

The inspectors verified that the licensee appropriately developed and followed a work

plan for these activities. The inspectors verified that the licensee took precautions to

minimize the impact of the work activities on unaffected structures, systems, and

components.

These activities constituted completion of five maintenance risk assessments and

emergent work control inspection samples, as defined in Inspection Procedure 71111.13.

b.

Findings

No findings were identified.

1R15 Operability Determinations and Functionality Assessments (71111.15)

a.

Inspection Scope

The inspectors reviewed six operability determinations and functionality assessments

that the licensee performed for degraded or nonconforming structures, systems, or

components:

- 29 -

April 11, 2016, operability determination of safety related instrument bus inverters

April 14, 2016, operability determination of leaks identified during train B

engineering safety feature actuation system testing

April 17, 2016, operability determination of containment electrical penetrations

May 24, 2016, functionality assessment of the emergency off-site facility with no

air conditioning and no off-site power

May 31, 2016, power-operated relief valve block valve closed

June 28, 2016, operability determination for train A emergency diesel generator

due to jacket water heater not cycling off

The inspectors reviewed the timeliness and technical adequacy of the licensees

evaluations. Where the licensee determined the degraded structures, systems, or

components to be operable or functional, the inspectors verified that the licensees

compensatory measures were appropriate to provide reasonable assurance of

operability or functionality. The inspectors verified that the licensee had considered the

effect of other degraded conditions on the operability or functionality of the degraded

structure, system, or component.

These activities constituted completion of six operability and functionality review

samples, as defined in Inspection Procedure 71111.15.

b.

Findings

Introduction. The inspectors identified a Green non-cited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, associated with the

licensees failure to perform adequate operability assessments when a degraded or

nonconforming condition was identified. Specifically, after the licensee identified that a

severe water hammer transient would occur following a loss of off-site power, the

licensee generated an operability evaluation that relied on judgement and inaccurate

information which failed to establish a reasonable expectation of operability.

Description. On April 4, 2016, the licensee identified that during a loss of off-site power

event the essential service water system will experience a column separation that results

in a severe water hammer transient that could subject portions of the system to transient

pressures and dynamic forces in excess of current station analyses. In response to this,

the licensee initiated Callaway Action Request 201603472 to capture the issue in the

stations corrective action program. The licensee subsequently documented a prompt

operability determination for the essential service water system.

Inspectors subsequently reviewed the licensees prompt operability determination.

During their review, the inspectors noted that the licensee had based their operability

determination on the results of a special test conducted on April 27, 2016, to simulate

system response to a loss of off-site power event. Specifically, the licensee had

collected data during the test associated with the strength of the system pressure wave,

- 30 -

which was used to estimate pipe and support loads, and performed system walkdowns

following the test and did not note any system damage.

Inspectors noted the following concerns with the licensees determination:

The special test was run with the essential service water system at 68 degrees -

the temperature had not been corrected to 95 degrees (design basis temperature

of the ultimate heat sink). This resulted in a non-conservative result since water

hammer transients are more severe at elevated temperatures.

Due to the location of monitoring equipment, the measured strength of the

system pressure wave was not representative of the peak pressure seen in the

system. Therefore, the use of the measured peak pressure was

non-conservative.

The testing lineup did not have all system components in their accident lineup

which resulted in a non-conservative damping of the severity of the water

hammer transient.

Based on this, the inspectors determined that although the licensees evaluation

provided a reasonable expectation of operability under the current plant conditions, it

failed to establish a reasonable expectation of operability for the identified condition at

worst case design conditions for the system. Inspectors informed the licensee of their

concerns and the licensee initiated Callaway Action Request 201605488. The licensee

performed a new operability evaluation, and based on engineering judgement,

determined that the leaks that had previously been identified would not prevent the

system from providing sufficient cooling to safety-related components or challenge the

required essential service water system inventory.

Analysis. The licensees failure to properly assess and document the basis for

operability when a severe water hammer occurred in the essential service water system

was a performance deficiency. The performance deficiency is more than minor, and

therefore a finding, because it is associated with the equipment performance attribute of

the Mitigating Systems Cornerstone and adversely affected the cornerstone objective to

ensure availability, reliability, and capability of systems that respond to initiating events

to prevent undesirable consequences. Specifically, severe water hammer transients in

the essential service water system due to a loss of off-site power result in a condition

where structures, systems, and components necessary to mitigate the effects of

accidents may not have functioned as required.

Using Inspection Manual Chapter 0609, Appendix A, The Significance Determination

Process (SDP) for Findings At-Power, dated June 19, 2012, inspectors determined that

this finding was of very low safety significance (Green) because the finding: did not

involve the loss or degradation of equipment or function specifically designed to mitigate

a seismic event, and (1) was not a deficiency affecting the design and qualification of a

mitigating structure, system, or component, and did not result in a loss of operability or

functionality, (2) did not represent a loss of system and/or function, (3) did not represent

an actual loss of function of at least a single train for longer than its allowed outage time,

or two separate safety systems out-of-service for longer than their technical specification

allowed outage time, and (4) does not represent an actual loss of function of one or

more non-technical specification trains of equipment designated as high

- 31 -

safety-significant for greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in accordance with the licensees

maintenance rule program. This finding has a cross-cutting aspect of conservative bias

in the human performance area because the licensee failed to demonstrate that a

proposed action was safe in order to proceed, rather than unsafe in order to stop.

Specifically, the licensees use of unsupported judgement and incorrect data resulted in

an evaluation that failed to demonstrate a reasonable expectation of operability [H.14].

Enforcement. Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures,

and Drawings, requires, in part, that activities affecting quality shall be accomplished in

accordance with instructions, procedures, or drawings of a type appropriate to the

circumstances. Callaway Procedure ODP-ZZ-00001, Addendum 15, Operability and

Functionality Determinations, an Appendix B quality related procedure, provides

instructions for performing operability determinations. Procedure ODP-ZZ-00001,

Addendum 15, step 3.2.2 states, in part, The SM should ENSURE an appropriate level

of questioning and challenging of assumptions occurs to ensure that a sound basis for

operability exists throughout the OD process. Contrary to the above, on April 14, 2016,

the licensee failed to ensure an appropriate level of questioning and challenging of

assumptions occurred to ensure that a sound basis for operability existed throughout the

operability determination process. Specifically, after the licensee identified that a severe

water hammer transient would occur following a loss of off-site power, the licensee

generated an operability evaluation that relied on judgement and inaccurate information

which failed to establish a reasonable expectation of operability. The licensee

implemented immediate correction actions to enter this issue into the corrective action

program for resolution. The licensee also performed an operability determination which

established a reasonable expectation of operability pending implementation of corrective

actions. This violation is being treated as a non-cited violation, consistent with

Section 2.3.2.a of the Enforcement Policy because it was of very low safety significance,

and was entered into the licensees corrective action program as Callaway Action

Requests 201605488: NCV 05000483/2016002-03, Failure to Adequately Evaluate

Operability for a Degraded Condition.

1R18 Plant Modifications (71111.18)

Permanent Modifications

a.

Inspection Scope

The inspectors reviewed three permanent plant modifications that affected risk

significant structures, systems, and components:

May 19, 2016, modification that tied in the newly built hardened condensate

storage tank to the auxiliary feedwater system (Modification Package 13-0033)

June 10, 2016, modification that installed new check valves in the service water

supply lines to the essential service water system (Modification

Package 10-0003)

June 10, 2016, modification that revised sequencer operation of EFHV0037

and EFHV0038 (Modification Package 10-0004)

- 32 -

The inspectors reviewed the design and implementation of the modifications. The

inspectors verified that work activities involved in implementing the modifications did not

adversely impact operator actions that may be required in response to an emergency or

other unplanned event. The inspectors verified that post-modification testing was

adequate to establish the operability and functionality of the structures, systems, or

components as modified.

These activities constituted completion of three samples of permanent modifications, as

defined in Inspection Procedure 71111.18.

b.

Findings

No findings were identified.

1R19 Post-Maintenance Testing (71111.19)

a.

Inspection Scope

The inspectors reviewed five post-maintenance testing activities that affected

risk-significant structures, systems, or components:

March 24, 2016, train A residual heat removal room cooler leak

April 13, 2016, train A emergency diesel generator maintenance window

April 14, 2016, containment recirculation sump to train A residual heat removal

pump suction isolation valve

June 8, 2016, spring cans supporting the essential service water piping to the

component cooling water heat exchanger

June 20, 2016, letdown heat exchanger outlet pressure control valve repairs

The inspectors reviewed licensing- and design-basis documents for the structures,

systems, and components and the maintenance and post-maintenance test procedures.

The inspectors observed the performance of the post-maintenance tests to verify that

the licensee performed the tests in accordance with approved procedures, satisfied the

established acceptance criteria, and restored the operability of the affected structures,

systems, and components.

These activities constituted completion of five post-maintenance testing inspection

samples, as defined in Inspection Procedure 71111.19.

b.

Findings

No findings were identified.

- 33 -

1R20 Refueling and Other Outage Activities (71111.20)

a.

Inspection Scope

During the stations refueling outage that concluded on May 10, 2016, the inspectors

evaluated the licensees outage activities. The inspectors verified that the licensee

considered risk in developing and implementing the outage plan, appropriately managed

personnel fatigue, and developed mitigation strategies for losses of key safety functions.

This verification included the following:

Review of the licensees outage plan prior to the outage

Review and verification of the licensees fatigue management activities

Monitoring of shut-down and cool-down activities

Verification that the licensee maintained defense-in-depth during outage activities

Observation and review of reduced-inventory activities

Observation and review of fuel handling activities

Monitoring of heat-up and startup activities

These activities constituted completion of one refueling outage sample, as defined in

Inspection Procedure 71111.20.

b.

Findings

No findings were identified.

1R22 Surveillance Testing (71111.22)

a.

Inspection Scope

The inspectors observed three risk-significant surveillance tests and reviewed test

results to verify that these tests adequately demonstrated that the structures, systems,

and components were capable of performing their safety functions:

Inservice tests:

April 6, 2016, emergency core cooling system full flow test

Other surveillance tests:

April 14, 2016, train B engineering safety feature actuation system testing

June 29, 2016, train B emergency diesel generator slow start and 1-hour run

The inspectors verified that these tests met technical specification requirements, that the

licensee performed the tests in accordance with their procedures, and that the results of

the test satisfied appropriate acceptance criteria. The inspectors verified that the

licensee restored the operability of the affected structures, systems, and components

following testing.

These activities constituted completion of three surveillance testing inspection samples,

as defined in Inspection Procedure 71111.22.

- 34 -

b.

Findings

No findings were identified.

2.

RADIATION SAFETY

Cornerstones: Public Radiation Safety and Occupational Radiation Safety

2RS1 Radiological Hazard Assessment and Exposure Controls (71124.01)

a.

Inspection Scope

The inspectors evaluated the licensees performance in assessing the radiological

hazards in the workplace associated with licensed activities. The inspectors assessed

the licensees implementation of appropriate radiation monitoring and exposure control

measures for both individual and collective exposures. The inspectors walked down

various portions of the plant and performed independent radiation dose rate

measurements. The inspectors interviewed the radiation protection manager, radiation

protection supervisors, and radiation workers. The inspectors reviewed licensee

performance in the following areas:

Radiological hazard assessment, including a review of the plants isotopic mix

and isotopic percent abundance, hard-to-detect radionuclides and potential alpha

hazards. The inspectors also reviewed the licensees evaluations of changes in

plant operations and radiological surveys to identify and detect dose rates,

neutron hazards, hot particle exposures, severe dose gradients, airborne

radioactivity monitoring, and surface contamination levels.

Instructions to workers, including labeling or marking containers of radioactive

material, radiation work permits, actions for electronic dosimeter alarms, and

changes to radiological conditions.

Contamination and radioactive material control including release of potentially

contaminated material from the radiologically controlled area, radiological survey

performance, radiation instrument sensitivities, material control and release

criteria, procedural guidance, and control and accountability of sealed radioactive

sources.

Radiological hazards control and work coverage including field observations of

job performance and adequacy of radiological controls. During walk downs of

the facility and job performance observations, the inspectors evaluated ambient

radiological conditions, radiological postings, adequacy of radiological controls,

radiation protection job coverage, and contamination controls. The inspectors

also evaluated the use of electronic dosimeters in high noise areas, dosimetry

selection and placement, implementation of effective dose equivalent for external

exposures (EDEX), and the application of dosimetry to effectively monitor

exposure for work in areas with significant dose rate gradients. The inspectors

examined the licensees controls for highly activated or contaminated materials

(non-fuel) stored within spent fuel and other storage pools and evaluated

airborne radioactive controls and monitoring.

- 35 -

High radiation area and very high radiation area controls including posting and

physical controls for high radiation areas and very high radiation areas. During

plant walk downs, the inspectors verified the adequacy of posting and physical

controls, including for areas of the plan with the potential to become

risk-significant high radiation areas.

Radiation worker performance and radiation protection technician proficiency

with respect to radiation protection work requirements. The inspectors

determined if workers were aware of the significant radiological conditions in their

workplace, radiation work permit controls/limits in place, and were aware of their

electronic alarming dosimeter dose and dose rate set points. The inspectors

observed radiation protection technician job performance, including the

performance of radiation surveys.

Problem identification and resolution for radiological hazard assessment and

exposure controls. The inspectors reviewed audits, self-assessments, and

corrective action program documents to verify problems were being identified

and properly addressed for resolution.

These activities constituted completion of the seven required samples of radiological

hazard assessment and exposure control program, as defined in Inspection

Procedure 71124.01.

b.

Findings

No findings were identified.

2RS3 In-plant Airborne Radioactivity Control and Mitigation (71124.03)

a.

Inspection Scope

The inspectors evaluated whether the licensee controlled in-plant airborne radioactivity

concentrations consistent with as low as reasonably achievable (ALARA) principles and

that the use of respiratory protection devices did not pose an undue risk to the wearer.

During the inspection, the inspectors interviewed licensee personnel, walked down

various areas in the plant, and reviewed licensee performance in the following areas:

Engineering controls, including the use of permanent and temporary ventilation

systems to control airborne radioactivity. The inspectors evaluated installed

ventilation systems, including review of procedural guidance, verification the

systems were used during high-risk activities, and verification of airflow capacity,

flow path, and filter/charcoal unit efficiencies. The inspectors also reviewed the

use of temporary ventilation systems used to support work in contaminated areas

such as high-efficiency particulate air/charcoal negative pressure units.

Additionally, the inspectors evaluated the licensees airborne monitoring

protocols, including verification that alarms and set points were appropriate.

Use of respiratory protection devices and evaluation of the licensees respiratory

protection program including use, storage, maintenance, and quality assurance

of National Institute for Occupational Safety and Health-certified equipment,

air quality and quantity for supplied-air devices and self-contained breathing

- 36 -

apparatus (SCBA) bottles, qualification and training of personnel, and user

performance.

Self-contained breathing apparatus for emergency use including the licensees

capability for refilling and transporting SCBA air bottles to and from the control

room and operations support center during emergency conditions, hydrostatic

testing of SCBA bottles, status of SCBA staged and ready for use in the plant

including vision correction, mask sizes, etc., SCBA surveillance and maintenance

records, and personnel qualification, training, and readiness.

Problem identification and resolution for airborne radioactivity control and

mitigation. The inspectors reviewed audits, self-assessments, and corrective

action documents to verify problems were being identified and properly

addressed for resolution.

These activities constituted completion of the four required samples of in-plant

airborne radioactivity control and mitigation program, as defined in Inspection

Procedure 71124.03.

b.

Findings

No findings were identified

4.

OTHER ACTIVITIES

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency

Preparedness, Public Radiation Safety, Occupational Radiation Safety, and

Security

4OA1 Performance Indicator Verification (71151)

.1

Safety System Functional Failures (MS05) and Mitigating Systems Performance Index:

Heat Removal Systems (MS08)

a.

Inspection Scope

For the period of second quarter 2015 through first quarter 2016, the inspectors

reviewed licensee event reports, maintenance rule evaluations, and other records that

could indicate whether safety system functional failures had occurred. The inspectors

used definitions and guidance contained in Nuclear Energy Institute Document 99-02,

Regulatory Assessment Performance Indicator Guideline, Revision 7, and

NUREG-1022, Event Reporting Guidelines: 10 CFR 50.72 and 50.73, Revision 3, to

determine the accuracy of the data reported.

These activities constituted verification of the safety system functional failures

performance indicator and the mitigating system performance index performance

indicator, as defined in Inspection Procedure 71151.

b.

Findings

No findings were identified.

- 37 -

.2

Reactor Coolant System Identified Leakage (BI02)

a.

Inspection Scope

The inspectors reviewed the licensees records of reactor coolant system identified

leakage for the period of second quarter 2015 through first quarter 2016 to verify the

accuracy and completeness of the reported data. The inspectors reviewed the

performance of Procedure OSP-BB-00009, RCS Inventory Balance, Revision 37,

conducted on May 12, 2016. The inspectors used definitions and guidance contained in

Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance

Indicator Guideline, Revision 7, to determine the accuracy of the reported data.

These activities constituted verification of the reactor coolant system leakage

performance indicator, as defined in Inspection Procedure 71151.

b.

Findings

No findings were identified.

.3

Occupational Exposure Control Effectiveness (OR01)

a.

Inspection Scope

The inspectors verified that there were no unplanned exposures or losses of radiological

control over locked high radiation areas and very high radiation areas during the period

of October 1, 2015, through March 31, 2016. The inspectors reviewed a sample of

radiologically controlled area exit transactions showing exposures greater than

100 mrem. The inspectors used definitions and guidance contained in Nuclear Energy

Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline,

Revision 7, to determine the accuracy of the reported data.

These activities constituted verification of the occupational exposure control

effectiveness performance indicator as defined in Inspection Procedure 71151.

b.

Findings

No findings were identified.

.3

Radiological Effluent Technical Specifications/Off-site Dose Calculation Manual

Radiological Effluent Occurrences (PR01)

a.

Inspection Scope

The inspectors reviewed corrective action program records for liquid or gaseous effluent

releases that occurred between October 1, 2015, and March 31, 2016, and were

reported to the NRC to verify the performance indicator data. The inspectors used

definitions and guidance contained in Nuclear Energy Institute Document 99-02,

Regulatory Assessment Performance Indicator Guideline, Revision 7, to determine the

accuracy of the reported data.

- 38 -

These activities constituted verification of the radiological effluent technical

specifications/off-site dose calculation manual radiological effluent occurrences

performance indicator as defined in Inspection Procedure 71151.

b.

Findings

No findings were identified.

4OA2 Problem Identification and Resolution (71152)

.1

Routine Review

a.

Inspection Scope

Throughout the inspection period, the inspectors performed daily reviews of items

entered into the licensees corrective action program and periodically attended the

licensees condition report screening meetings. The inspectors verified that licensee

personnel were identifying problems at an appropriate threshold and entering these

problems into the corrective action program for resolution. The inspectors verified that

the licensee developed and implemented corrective actions commensurate with the

significance of the problems identified. The inspectors also reviewed the licensees

problem identification and resolution activities during the performance of the other

inspection activities documented in this report.

b.

Findings

No findings were identified.

.2

Semiannual Trend Review

a.

Inspection Scope

To verify that the licensee was taking corrective actions to address identified adverse

trends that might indicate the existence of a more significant safety issue, the inspectors

reviewed corrective action program documentation associated with the following

licensee-identified trends:

Negative trend on essential service water leaks from safety related room coolers

(Callaway Action Request 201602658)

Negative trend involving leaks on plant equipment as a result of train B

engineering safety feature actuation system testing (Callaway Action

Request 201603472)

These activities constitute completion of one semiannual trend review sample, as

defined in Inspection Procedure 71152.

b.

Observations and Assessments

The inspectors review of the possible trends noted above produced the following

observations and assessments:

- 39 -

During the period of March 23 to May 3, 2016, the licensee had twelve leaks

across eight safety-related room coolers serviced by essential service water. The

licensee considered this a negative trend and performed a root cause evaluation

in Callaway Action Request 201602658 to determine the causes for the negative

trend. The licensee determined the equipment reliability process did not

adequately address the long-standing equipment issues associated with safety

related copper-nickel heat exchangers.

To address the issue, the licensee replaced several room coolers during the

recent refueling outage and has a plan to replace all but the containment coolers

during the current online cycle. The containment coolers are planned for

replacement during the next refueling outage. The inspectors evaluated the

licensees response to the negative trend and determined the actions were

appropriate.

Since April 2007, the Callaway plant has experienced leaks on plant equipment

as a result of engineering safety feature actuation system testing. These leaks

did not occur during every test, but several components have had repetitive

failures and a leak had occurred on a component every refueling outage since

2013. The licensee considered this a negative trend and performed a root cause

evaluation in Callaway Action Request 201603472 to determine the causes for

the negative trend. The licensee determined the original design of the system

did not appropriately account for water column separation and collapse during

functional operation and the corrective action process did not adequately drive

the organization to correct the condition.

To address the issue, the licensee hardened several components during the

recent refueling outage and has hired an external company to evaluate the

pressures expected during a design-based accident. The licensee will address

the results of the analysis when it becomes available. The inspectors evaluated

the licensees response to the negative trend and determined the actions were

appropriate.

c.

Findings

A finding associated with these trends is documented in Section 4OA2.3.

.3

Annual Follow-up of Selected Issues

a.

Inspection Scope

The inspectors selected one issue for an in-depth follow-up:

On June 10, 2016, the inspectors reviewed Callaway Action Request 201010634

associated with Callaways response to a non-cited violation that was issued in

Inspection Report 05000483/2010006 (ML103540576).

The inspectors assessed the licensees problem identification threshold, cause

analyses, extent of condition reviews and compensatory actions. The inspectors

identified that the licensee failed to appropriately prioritize the corrective actions

and that these actions were not adequate to correct the condition.

- 40 -

These activities constituted completion of one annual follow-up sample as defined in

Inspection Procedure 71152.

b.

Findings

Introduction. Inspectors identified a Green cited violation of 10 CFR Part 50,

Appendix B, Criterion XVI, Corrective Action, associated with the licensees failure to

take timely corrective action for a previously identified condition adverse to quality.

Specifically, the licensee failed to adequately resolve water hammer and corrosion

issues that were previously identified by the NRC as non-cited

violation 05000483/2010006-01 and the failure to resolve these issues resulted in

subsequent safety-related equipment failures.

Description. Inspectors reviewed licensees actions taken to address Non-cited

Violation 05000483/2010006-01, Failure to Correct Degraded Condition in Essential

Service Water System in a Timely Manner, which was documented in Callaway Action

Request 201010634. This non-cited violation was issued because the licensee had

been experiencing water hammer events which had caused leaks in safety-related joints

and when coupled with system corrosion issues had resulted in leaks in heat exchanger

tubes, fittings, and other components.

Inspectors reviewed the licensees corrective actions taken in response to Non-cited

Violation 05000483/2010006-01. Inspectors noted that the licensee had implemented

modifications to the station, Modification Packages 10-0003 and 10-0004, which

installed check valves in the service water supply lines to the essential service water

system and changed the timing sequence for valve operation in the essential service

water system. The purpose of these modifications was to reduce the pressure transient

imposed on the essential service water system from water hammer events caused by

column separation. Inspectors determined that the licensee had not implemented

corrective actions to address the corrosion issues that were also identified in the non-

cited violation and Callaway Action Request 201010634 was closed.

Inspectors performed a subsequent review of the licensees corrective action program

documents and noted that water hammer events continued to occur when the essential

service water system was operated during simulated accident conditions (engineering

safety feature actuation system testing). Inspectors identified 28 instances where water

hammer events and corrosion issues had damaged safety-related components since

Non-cited Violation 05000483/2010006-01 had been issued. Examples include:

November 17, 2011, train B component cooling water heat exchanger tube side

relief valve and the inlet tube side drain valve were found the be leaking by

following engineering safety feature actuation system testing

December 6, 2011, train A motor driven auxiliary feedwater pump room cooler

tube leak

April 12, 2012, train A centrifugal charging pump room cooler tube leak

April 29, 2012, train B component cooling water room cooler gasket leak

following engineering safety feature actuation system testing

- 41 -

May 1, 2013, train B motor driven auxiliary feedwater pump room cooler tube

leak following engineering safety feature actuation system testing

October 17, 2014, train A centrifugal charging pump room cooler tube leak, B

motor driven auxiliary feedwater pump room cooler tube leak, B control room air

conditioning condenser endbell gasket leak, and B emergency diesel generator

intercooler expansion joint leak following engineering safety feature actuation

system testing

Additionally, from March 23 to May 3, 2016, the licensee had identified twelve leaks

across eight safety-related room coolers serviced by essential service water and

damaged gaskets on the safety-related control room chiller (Licensee Event Report

2016-001-00).

Based on this, inspectors determined that the modifications, Modifications Packages

10-0003 and 10-0004 that were implemented by the licensee were not adequate to

mitigate the effects of a water hammer transient. Specifically, system corrosion issues

and column separation/water hammer events continued to occur, and these events

continued to cause damage to safety related components.

Based on this, inspectors determined that the licensee had failed to take timely and

adequate corrective actions to correct the water hammer and corrosion issues in the

essential service water system.

Inspectors informed the licensee of their observations and the licensee initiated

Callaway Action Request 201604440 to capture this issue in the stations corrective

action program. The licensee also generated an operability determination, and based on

engineering judgement, determined that though water hammer transients had caused

leaks in the system, the leaks that had previously been identified would not prevent the

system from providing sufficient cooling to safety-related components or challenge the

required essential service water system inventory.

Analysis. The licensees failure to take timely and adequate corrective actions to correct

a condition adverse to quality was a performance deficiency. The performance

deficiency is more than minor, and therefore a finding, because it is associated with the

equipment performance attribute of the Mitigating Systems Cornerstone and adversely

affected the cornerstone objective to ensure availability, reliability, and capability of

systems that respond to initiating events to prevent undesirable consequences.

Specifically, the failure to correct water hammer and corrosion issue resulted in the

licensee declaring safety-related room coolers and chillers inoperable until an analysis of

system operability was completed. This affected their capability to respond to initiating

events to prevent undesirable consequences.

Using Inspection Manual Chapter 0609, Appendix A, The Significance Determination

Process (SDP) for Findings At-Power, dated June 19, 2012, inspectors determined that

this finding was of very low safety significance (Green) because the finding: (1) was not

a deficiency affecting the design and qualification of a mitigating structure, system, or

component, and did not result in a loss of operability or functionality, (2) did not

represent a loss of system and/or function, (3) did not represent an actual loss of

function of at least a single train for longer than its allowed outage time, or two separate

- 42 -

safety systems out-of-service for longer than their technical specification allowed outage

time, and (4) does not represent an actual loss of function of one or more non-technical

specification trains of equipment designated as high safety-significant for greater than

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in accordance with the licensees maintenance rule program. This finding has

a cross-cutting aspect of resources in the human performance area because the

licensee did not ensure that personnel, equipment, procedures, and other resources

were available and adequate to support nuclear safety. Specifically, by failing to

address water hammer and corrosion issues, station management failed to ensure that

the essential service water system was available and adequately maintained to respond

during a loss of off-site power event [H.1].

Enforcement. Title 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action,

requires, in part, that measures shall be established to assure that conditions adverse to

quality are promptly identified and corrected. Contrary to the above, from

November 2010 through June 2016, for quality related components associated with the

essential service water system, to which 10 CFR Part 50, Appendix B applies, the

licensee failed to assure that conditions adverse to quality were promptly identified and

corrected. Specifically, the licensee failed to adequately resolve water hammer and

corrosion issues which were previously identified by the NRC as Non-cited

Violation 05000483/2010006-01 and the failure to resolve these issues resulted in

subsequent safety-related equipment failures. The licensee implemented immediate

correction actions to enter this issue into the corrective action program for resolution.

The licensee also performed an operability determination that established a reasonable

expectation of operability pending implementation of corrective actions. The violation

was entered into the licensees corrective action program as Callaway Action

Request 201604440. This violation is being treated as a cited violation, consistent with

Section 2.3.2.a of the NRC Enforcement Policy, because the licensee did not restore

compliance (or demonstrate objective evidence of plans to restore compliance) within a

reasonable period of time (i.e., in a time frame commensurate with the significance of

the violation) after the violation was identified. A Notice of Violation is documented in

Enclosure 1: VIO 05000483/2016002-04, Failure to Promptly Correct Conditions

Adverse to Quality.

4OA3 Follow-up of Events and Notices of Enforcement Discretion (71153)

(Closed) Licensee Event Report 2014-006-00, Main Generator Excitation Transformer

Faulted to Ground, Causing Reactor Trip

a. Inspection Scope

On December 3, 2014, a turbine and reactor trip occurred, when the main generator

excitation transformer faulted to ground. The reactor trip was classified as

uncomplicated and all safety systems performed as designed at the onset of the plant

trip. However, during recovery the valve providing flow from the motor-driven auxiliary

feedwater pump B to steam generator D (ALHV0005) failed to throttle closed. The

problems with ALHV0005 were the subject of a special inspection and were

dispositioned in NRC Inspection Report 05000483/2015009 (ADAMS Accession

Number ML16013A021). Repair of the excitation transformer was completed and the

plant returned to power operations on December 6, 2014.

- 43 -

The construction of the excitation transformer includes high voltage jumper cables

between termination points inside its protective enclosure and the winding taps of the

transformer coils. The jumper cables are routed above the iron core of the transformer

and are supported by insulating boards and restrained by nylon cable ties. The fault to

ground was caused when a jumper cable dropped onto the iron transformer core after

failure of the nylon cable ties. The cable ties were an original part of the transformer

installed in 2007.

The licensee determined the root cause of the transformer failure was inadequate design

(routing cables above the transformer core) and material selection (use of nylon cable

ties) during the manufacture of the transformer.

Corrective actions included replacing the nylon cable ties with Tefzel cable ties, which

are designed for higher temperatures and longer life expectancy, as well as adding

lacing to supplement the Tefzel cable ties. The inspectors reviewed the licensees

submittal along with corrective action documents and determined that the licensee

adequately documented the event, including the potential safety consequences and

necessary corrective actions. A finding related to a failure to follow the licensees foreign

material exclusion procedure is documented in this section. This licensee event report is

closed.

b. Findings

Introduction. Inspectors reviewed a Green, self-revealed finding for the licensees failure

to follow the plant procedure for foreign material exclusion. Specifically, after finding

foreign material (broken cable ties) within the main generator excitation transformer,

established as a foreign material exclusion Level 2 area, the licensee failed to determine

the reason for the foreign material and enter the issue into the corrective action program

for resolution as required by Procedure APA-ZZ-00801, Foreign Material Exclusion,

Revision 32.

Description. On December 3, 2014, an unexpected turbine and reactor trip occurred.

The licensees investigation determined the direct cause of the event was nylon cable tie

wraps used to restrain a critical vendor cable failed allowing the cable to fall onto the hot

transformer core, where the cable insulation degraded quickly resulting in a

phase-to-ground short. The nylon cable ties became brittle from the environmental

conditions inside the cabinet.

The licensees root cause of the event was inadequate design and material selection

during the manufacture of the transformer. This transformer was installed in April 2007

to update old and obsolete main generator exciters. The transformer was manufactured

and installed by the vendor as a single component. The design used low-grade nylon

cable ties to restrain high voltage jumper cables on insulating boards located above the

transformer core. No preventive maintenance strategy was provided by the transformer

manufacturer nor identified by the licensees engineering personnel.

In July 2013, while the plant was off-line, the licensee performed an inspection inside the

excitation cabinet. The cabinet was identified as a foreign material exclusion

Level 2 (FME-2) area and was considered a standard risk area. These areas require

boundaries and cleanliness controls. While inside the cabinet, an engineer identified

several cable ties on the floor of the transformer. The cable ties were very brittle and

- 44 -

disintegrated in his hand when he picked them up off of the floor. The engineer was

unaware the transformer cabinet was being controlled as a FME-2 area and did not

consider the broken cable ties as foreign material. The engineer notified the engineering

war room of the issue. The licensee took no further action.

Licensee Procedure APA-ZZ-00801, defines foreign material as Any material that is

NOT part of a system or component as designed. Section 4.8 of the procedure also

directs individuals that enter an FME-2 area to

Inspect for the presence of any As-Found foreign material WHEN the

system or component is initially breached. IF present, retrieve the foreign

material in accordance with an approved recovery plan or document the

review and approval of system operation with the foreign material in the

system. Try to determine the source of, and the reason for, the foreign

material. Report the loss of FME integrity in the corrective action request

system.

The licensee determined the source of the foreign material, but did not determine the

reason for the foreign material nor enter the loss of foreign material exclusion integrity

into their corrective action program. As a result, the licensee did not evaluate the

condition related to the degradation of nylon cable ties inside the cabinet.

The licensee addressed the issue in Callaway Action Request 201606129. Corrective

actions included reminding employees about the importance of foreign material and

adherence to the foreign material exclusion procedure.

Analysis. The licensees failure to follow the plant procedure for foreign material

exclusion was a performance deficiency. The performance deficiency is more than

minor, and therefore a finding, because it is associated with the equipment performance

attribute of the Initiating Events Cornerstone and adversely affected the cornerstone

objective to limit the likelihood of events that upset plant stability and challenge critical

safety functions during shutdown as well as power operations. Specifically, after

identifying several broken cable ties on the floor inside a FME-2 area the licensee did

not determine the reason for the foreign material nor enter the condition into the

corrective action program as required by Procedure APA-ZZ-00801. Because the

licensee failed to understand what caused the cable tie degradation, a subsequent cable

tie failure resulted in a plant trip.

Using Inspection Manual Chapter 0609, Appendix A, The Significance Determination

Process (SDP) for Findings At Power, dated June 19, 2012, the finding was determined

to be of very low safety significance because it did not cause a reactor trip and the loss

of mitigation equipment relied upon to transition the plant from the onset of the trip to a

stable shutdown condition. This finding has a cross-cutting aspect of training in the

human performance area because the organization did not provide training and ensure

knowledge transfer to maintain a knowledgeable, technically competent workforce and

instill nuclear safety values. Specifically, several groups within the licensees

organization was unaware the excitation transformer cabinet was classified as an FME-2

area nor the requirements if foreign material is found within the foreign material

exclusion area [H.9].

- 45 -

Enforcement. Inspectors did not identify a violation of regulatory requirements

associated with this finding. Because this finding does not involve a violation and is of

very low safety significance, it is identified as: FIN 05000483/2016002-05, Failure to

Follow Plant Foreign Material Exclusion Procedure.

These activities constituted completion of one event follow-up sample, as defined in Inspection

Procedure 71153.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On April 15, 2016, regional inspectors presented the radiation safety inspection results to

Mr. T. Hermann, Site Vice President, and Mr. B. Cox, Senior Director, Nuclear Operations,

and other members of the licensee staff. The licensee acknowledged the issues presented.

The licensee confirmed that any proprietary information reviewed by the inspectors had been

returned or destroyed.

On April 22, 2016, regional inspectors presented the inservice inspection results to Mr. F. Diya,

Senior Vice President and Chief Nuclear Officer, and other members of the licensee staff. The

licensee acknowledged the issues presented. The inspectors acknowledged review of

proprietary material during the inspection which had been or will be returned to the licensee.

On July 19, 2016, the resident inspectors presented the inspection results to Mr. F. Diya, Senior

Vice President and Chief Nuclear Officer, and other members of the licensee staff. The licensee

acknowledged the issues presented. The licensee confirmed that any proprietary information

reviewed by the inspectors had been returned or destroyed.

A1-1

Attachment 1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

K. Blair, Engineer, Steam Generators

B. Cox, Senior Director, Nuclear Operations

D. Davis, Non-Destructive Testing, Level III

F. Diya, Senior Vice President and Chief Nuclear Officer

T. Elwood, Supervising Engineer, Regulatory Affairs/Licensing

G. Forster, Non-Destructive Testing Supervisor, Level III

J. Geyer, Manager, Radiation Protection

M. Hoehn II, Engineering Supervisor, Engineering Programs

C. Hendricks, Coordinator, Quality Control

T. Herrmann, Site Vice President

R. Hughey, Manager, Shift Operations

L. Kanuckel, Director, Nuclear Oversight

S. Kovaleski, Director, Engineering Design

S. McLaughlin, Manager, Performance Improvement

J. Nurrenbern, Program Owner, Boric Acid

S. Petzel, Engineer, Regulatory Affairs

D. Purvis, Supervisor, Quality Control

F. Stuckey, Senior Health Physicist

S. Thomure, Training Supervisor, Welding Engineering

T. Trent, Senior Health Physicist, Radiation Protection

M. Vonderhaar, Supervisor, Radiation Protection

R. Wink, Manager, Regulatory Affairs

T. Witt, Engineer, Regulatory Affairs

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed 05000483/2016002-01 NCV

Failure to Account for Water Hammer Stresses in Essential

Service Water System Calculations (Section 1R04)05000483/2016002-02 NCV

Failure to Meet Applicable ASME Code Requirements for

Repairs to Components in the Essential Service Water System

(Section 1R07)05000483/2016002-03 NCV

Failure to Adequately Evaluate Operability for a Degraded

Condition (Section 1R15)05000483/2016002-05 FIN

Failure to Follow Plant Foreign Material Exclusion Procedure

(Section 4OA3)

Open 05000483/2016002-04

VIO

Failure to Promptly Correct Conditions Adverse to Quality

(Section 4OA2.3)

A1-2

Closed

05000483/2014-006-00 LER

Main Generator Excitation Transformer Faulted to Ground,

Causing Reactor Trip (Section 4OA3)

LIST OF DOCUMENTS REVIEWED

Section 1R01: Adverse Weather Protection

Procedures

Number

Title

Revision

AUE-ADM-2222

Communication and Coordination

0

AUE-ADM-2223

Disturbance Reporting

0

AUE-ADM-2227

Reliability Coordination - Responsibility and Authorities

0

OSP-NE-00001

Class 1E Electrical Source Verification

39

OSP-NE-00003

Technical Specification Actions - A.C. Sources

30

OTO-MA-00008

Rapid Load Reduction

34

OTO-ZZ-00012

Severe Weather

33

PDP-ZZ-00027

Seasonal Readiness Program

6

Callaway Action Requests

201508013

201604020

Jobs

13000681

Miscellaneous

Number

Title

Revision

2016 Summer Reliability Plan

3

2010009

Health Issue: Given an EDG HVAC equipment failure,

operability cannot be restored within the 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> allowed

outage time

2015005

Health Issue: Degradation of ESW Piping in Containment

A1-3

Section 1R04: Equipment Alignment

Procedures

Number

Title

Revision

OTN-AL-00001

Auxiliary Feedwater System

34

OTN-AL-00001,

Checklist 1

Auxiliary Feedwater Valve Alignment

22

OTN-AL-00001

Checklist 2

MD-AFP A and B Switch Alignment

18

Drawings

Number

Title

Revision

E-012.2-00002

Large Induction Motors Outline

4

E-21010(Q)

DC Main Single Line Diagram

14

LP-06

NB/NG/NK/NN-1, Safeguards Power Training Diagram

1

M-22AL01(Q)

Auxiliary Feedwater System Piping and Instrumentation

Diagram

46

M-143A-00003

Concentric Restricting Orifice Plates Outline Drawing

19

Miscellaneous

Number

Title

Revision

GEK-72150

General Electric Instructions for Class 1E Auxiliary

Feedwater Pump Motors

0

Section 1R05: Fire Protection

Procedures

Number

Title

Revision

APA-ZZ-00703

Fire Protection Operability Criteria and Surveillance

Requirements

26

APA-ZZ-00750

Hazard Barrier Program

37

EDP-ZZ-04107

HVAC Pressure Boundary Control

29

OTO-KC-00001

Add A-03

Auxiliary Building 1974 - Boric Acid Tank Rooms

0

OTO-KC-00001

Add A-18

Auxiliary Building 2026 - North Electrical Pen Room

0

OTO-KC-00001

Add C-15

Control Building 2016 Switchboard and Battery Rooms 2

and 4

0

A1-4

Procedures

Number

Title

Revision

OTO-KC-00001

Add C-16

Control Building 2016 Switchboard and Battery Rooms 1

and 3

0

OSP-KC-00015

Fire Door Inspections

17

Drawings

Number

Title

Revision

A-2804

Architectural Fire Delineation Floor Plan, El 2047-6

27

Callaway Action Requests

201605406

Jobs

16003139

Miscellaneous

Number

Title

Revision

Fire Preplan Manual

38

KC-64

C-15 Detailed Fire Modeling Report

1

KC-65

C-16 Detailed Fire Modeling Report

1

KC-83

Fire Safety Analysis Calculation for Fire Area A-3

1

KC-98

Fire Safety Analysis Calculation for Fire Area A-18

1

KC-126

Fire Safety Analysis for Fire Area C-15

1

KC-102

Fire Safety Analysis Calculation for Fire Area A-22

1

KC-127

Fire Safety Analysis Calculation for Fire Area C-16

1

ME-014

Detailed Fire Modeling

0

Section 1R08: Inservice Inspection Activities

Callaway Action Requests

199800739

199800740

199800741

200207750

200404532

200703197

200703247

200703257

200703491

200810348

200810384

200811050

201003386

201109846

201303346

201303370

201303451

201303502

201303702

201303736

A1-5

Callaway Action Requests

201406864

201407222

201407245

201407246

201407248

201408130

201500430

201501125

201502944

201503385

201504450

201504861

201504926

201505694

201505757

201506100

201506290

201506544

201507559

201508349

201508887

201600224

201600727

201601320

201601742

201602378

201602824

201603031

201603166

201603256

201603472

201603484

201604058

201604063

201603640

201603661

Drawings

Number

Title

Revision

BG23-H004/231 (Q)

Pip Supports - CVCS Charging and Excess Letdown

Sys. Reactor Building

7

EF01-C012/311 (Q)

Pipe Supports - Essential Service Water Sys. Control

Bldg. - Trains A & B

4

EF02-C003/142 (Q)

Pipe Supports - Essential Service Water Sys. Aux.

Bldg. A Train Supply

6

EF03-C034/134 (Q)

Pipe Supports - Essential Service Water Sys. Aux.

Bldg. A Train Return

6

M-22EM01 (Q)

Piping and Instrumentation Diagram High Pressure

Coolant Injection System

36

M-23EF01

Piping Isometric Essential Service Water System

Control Building

25

M-23EF02

Piping Isometric Essential Service Water System

Auxiliary Building A Train Supply

33

M-23EF03

Piping Isometric Essential Service Water System

Auxiliary Building A Train Return

33

M-23EF04

Piping Isometric Essential Service Water System

Auxiliary Building B Train Supply

22

M-23EF05

Piping Isometric Essential Service Water System

Auxiliary Building B Train Return

22

M-23EF06

Piping Isometric Essential Service Water System

Auxiliary Building A and Train Supply and Return

26

M-25BG23 (Q)

Hanger Location Drawing - CVCS Charging & Excess

Letdown Reactor Building

16

A1-6

Drawings

Number

Title

Revision

M-25EF01 (Q)

Hanger Location Drawing - Essential Service Water

Control Bldg. (A &B Train)

14

M-25EF02 (Q)

Hanger Location Drawing - Essential Service Water

Sys. Aux. Bldg. A Train Supply

44

M-25EF03 (Q)

Hanger Location Drawing - Essential Service Water

Sys. Aux. Bldg. A Train Return

31

Procedures

Number

Title

Revision

APA-ZZ-00350

Measuring and Test Equipment Program

29

APA-ZZ-00500

Corrective Action Program

63

APA-ZZ-00500,

Appendix 1

Operability and Functionality Determinations

25

APA-ZZ-00500,

Appendix 2

Non-Conforming Materials Report

17

APA-ZZ-00500,

Appendix 3

Past Operability and Reportability Evaluations

18

APA-ZZ-00500,

Appendix 4

Transient Evaluation

2

APA-ZZ-00500,

Appendix 5

Maintenance Rule

19

APA-ZZ-00500,

Appendix 6

Collection and Preservation of Evidence

2

APA-ZZ-00500,

Appendix 7

Effectiveness Reviews

10

APA-ZZ-00500,

Appendix 8

Corrective Action Program Training Requirements

13

APA-ZZ-00500,

Appendix 9

Mitigating Systems Performance Index (MSPI)

7

APA-ZZ-00500,

Appendix 10

Trending Program

11

APA-ZZ-00500,

Appendix 11

Degraded And Nonconforming Condition Resolution 8

APA-ZZ-00500,

Appendix 12

Significant Adverse Condition - Significance Level 1

24

A1-7

Procedures

Number

Title

Revision

APA-ZZ-00500,

Appendix 13

Adverse Condition - Significance Level 2

25

APA-ZZ-00500,

Appendix 14

Adverse Condition - Significance Level 3

23

APA-ZZ-00500,

Appendix 15

Adverse Condition - Significance Level 4

20

APA-ZZ-00500,

Appendix 16

Adverse Condition - Significance Level 5

13

APA-ZZ-00500,

Appendix 17

Screening Process Guidelines

27

APA-ZZ-00500,

Appendix 18

Equipment Performance Evaluation

8

APA-ZZ-00500,

Appendix 19

Common Cause Evaluation (CCE)

5

APA-ZZ-00500,

Appendix 20

Prompt Human Performance Evaluation (PHPE)

3

APA-ZZ-00500,

Appendix 21

Other Issues

18

APA-ZZ-00500,

Appendix 22

Corrective Action Program Definitions

13

APA-ZZ-00661

Administration of Welding

16

APA-ZZ-00661,

Appendix 3

Personnel Approved to Perform Weld

Inspections/Examinations

3

APA-ZZ-00662

ASME Section XI Repair/Replacement Program

22

APA-ZZ-00662,

Appendix A

ASME Section XI Repair/Replacement Program

Mandatory Requirements Class 1, 2 And 3 Items and

Their NF Supports (Fourth Inspection Interval)

5

APA-ZZ-00662

Appendix B

ASME Section XI Code Cases Applied to the Fourth

Inspection Interval

6

APA-ZZ-00662

Appendix E

ASME Section XI Repair/Replacement Matrix Minor

4

APA-ZZ-00662

Appendix G

ASME Section XI Repair/Replacement Program

Mandatory Requirements Class MC and CC Items

and their NF Supports (Second Inspection Interval)

0

APA-ZZ-00750

Hazard Barrier Program

37

EDP-ZZ-00018

Heat Exchanger Eddy Current Testing Methodology

3

A1-8

Procedures

Number

Title

Revision

EDP-ZZ-01004

Boric Acid Corrosion Control Program

17

EDP-ZZ-01121

Raw Water Systems Predictive Performance

Program

21

ESP-ZZ-01016

ASME Section XI IWE Containment Pressure

Boundary Inspection

6

MDP-ZZ-LM001

Fluid Leak Management Program

15

MSM-ZZ-QW005

Mechanical Snubber Functional Test

17

MTW-ZZ-WP001

ASME/ANSI General Welding Requirements

26

MTW-ZZ-WP002

Welder Performance Qualification

27

MTW-ZZ-WP003

Control Of Welding Filler Materials

24

MTW-ZZ-WP004

Post Weld Heat Treatment

11

MTW-ZZ-WP006

Qualification of Welding Procedures

9

MTW-ZZ-WP007

Callaway Plant Maintenance Welding Procedure

AWS D1.1 General Welding Requirements

4

MTW-ZZ-WP501

Callaway Plant Maintenance Welding Procedure

Welding of P-1 Materials

14

MTW-ZZ-WP502

Callaway Plan Maintenance Welding Procedure

Welding of P-1 to P-3 Materials

10

MTW-ZZ-WP503

Callaway Plan Maintenance Welding Procedure

Welding of P-1 to P-4 Materials

8

MTW-ZZ-WP504

Callaway Plan Maintenance Welding Procedure

Welding of P-1 to P-5 Materials

10

MTW-ZZ-WP505

Callaway Plan Maintenance Welding Procedure

Welding of P-1 to P-8 Materials

10

MTW-ZZ-WP506

Callaway Plan Maintenance Welding Procedure

Welding of P-4X (Including Welding of P-1 and P-8 to

P-4X) Materials

8

MTW-ZZ-WP509

Callaway Plan Maintenance Welding Procedure

Welding of P-3 Materials

8

MTW-ZZ-WP510

Callaway Plan Maintenance Welding Procedure

Welding of P-4 Materials

9

MTW-ZZ-WP511

Callaway Plan Maintenance Welding Procedure

Welding of P-5 Materials

10

MTW-ZZ-WP512

Callaway Plan Maintenance Welding Procedure

Welding of P-5 to P-8 Materials

5

A1-9

Procedures

Number

Title

Revision

MTW-ZZ-WP513

Callaway Plan Maintenance Welding Procedure

Welding of P-6 to P-8 Materials

4

MTW-ZZ-WP514

Callaway Plan Maintenance Welding Procedure

Welding of P-8 Materials

16

MTW-ZZ-WP524

Callaway Plan Mechanical Technical Procedure

Torch Brazing of Copper Alloys

8

MTW-ZZ-WP525

Callaway Plan Maintenance Welding Procedure

Welding of P-4 to P-8 Materials

4

MTW-ZZ-WP526

Callaway Plan Maintenance Welding Procedure

Welding of P-8 to P-34 Materials

3

MTW-ZZ-WP527

Callaway Plan Maintenance Welding Procedure

Welding of P-34 Materials

3

MTW-ZZ-WP560

Callaway Plan Maintenance Welding Procedure

Fusing of High Density Polyethylene (HDPE)

Materials for Nuclear Service

9

MTW-ZZ-WP561

Callaway Plan Maintenance Welding Procedure

Fusing of High Density Polyethylene (HDPE)

Materials for Non-Nuclear Service

5

MTW-ZZ-WP701

AWS Welding of P-1 Materials

3

MTW-ZZ-WP702

Callaway Plant Maintenance Technical Procedure

AWS Welding of Studs

2

PDI-ISI-254-SE

Remote Inservice Examination of Reactor Vessel

Nozzle to Safe End, Nozzle to Pipe and Safe End to

Pipe Welds

2

PDI-ISI-254-SE-NB

Remote Inservice Examination of Reactor Vessel

Nozzle to Safe End, Nozzle to Pipe and Safe End to

Pipe Welds Using the Nozzle Scanner

0

QCP-ZZ-05000

Liquid Penetrant Examination

25

QCP-ZZ-05010

Magnetic Particle Examination

19

QCP-ZZ-05019

Ultrasonic Thickness Measurement

14

QCP-ZZ-05030

Radiographic Procedure for Examination of

Weldments and Castings

17

QCP-ZZ-05041

Visual Examination to ASME VT-2

26

QCP-ZZ-05048

Boric Acid Walkdown for Reactor Coolant System

Pressure Boundary

8

QCP-ZZ-05049

Reactor Pressure Vessel Head Bare Metal

Examination

3

A1-10

Procedures

Number

Title

Revision

UT-2

Ultrasonic Examination of Vessel Welds and

Adjacent Base Metal

30

UT-94

Ultrasonic Examination of Ferritic Piping Welds

9

UT-95

Ultrasonic Examination of Austenitic Piping Welds

8

UT-96

Ultrasonic Through Wall Sizing in Piping Welds

7

UT-103

Ultrasonic Examination of Dissimilar Metal Piping

Welds

5

WDI-SSP-1101

Manual Ultrasonic Examination of Reactor Vessel

Threads in Flange for Callaway Unit 1

1

WDI-STD-088

Underwater Remote Visual Examination of Reactor

Vessel Internals

9

WDI-STD-146

ET Examination of Reactor Vessel Pipe Welds Inside

Surface

11

Relief Requests

Number

Title

Date

Letter: Michael T.

Markley to Fadi

Diya

Callaway Plant, Unit 1 - Request for Relief 14R-01,

Alternative to ASME Code Inservice Inspection

Requirements for Class 3 Buried Piping

(TAC NO. MF4271)

May 12, 2015

ULNRC-06115

NRC Letter, "Relief Request 13R-10 for Third 10-Year

Inservice Inspection Interval - Use of Polyethylene Pipe

in Lieu of Carbon Steel Pipe in Buried Essential Service

Water Piping System (TAC No. MD6792)," dated

November 7, 2008 (Accession No. ML083100288)

June 10, 2014

ULNRC-06146

Ameren Missouri Letter ULNRC-06115, "10 CFR 50.55a

Request: Proposed Alternative to ASME Section XI

Requirements for Class 3 Buried Piping," dated

June 10, 2014 (ADAMS Accession No. ML14161A399)

September 30,

2014

UNNRC-06214

Docket Number 50-483 Callaway Plant Unit 1 Union

Electric Co. Facility Operating License NPF-30 Revision

of 10 CFR 50.55a Request: Proposed Alternative to

ASME Section XI Requirements for Class 3 Buried

Piping (TAC NO. MF4271)

April 24, 2015

Work Packages

15000069-520

15507345

16001742-405

16503498

15000069-505

15507967

16001742-405

16503745

A1-11

Work Packages

15001243-500

16001742-550

16001743-400

Jobs

10002667

16001870

Miscellaneous

Number

Title

Revision/Date

Various Non Destructive Examination Reports for

ESW components

206EZ-FLO

Garlock Sealing Technologies Expansion Joint

Test

November 15, 2006

0516-19-F01

Secondary Side Visual Inspection Plan for

Ameren UE, Callaway RF 21

February 10, 2016

51-9252420-000

AREVA Engineering Information Record:

Callaway 1RF021 SG ECT Inspection Plan

March 21, 2016

51-9253319-000

AREVA Engineering Information Record:

Callaway 1R21 Degradation Assessment

April 2016

96225-TR-002

Containment F Cooler Response to a

Simultaneous LOCA & LOOP Event

1

0096-020-CALC-01

Callaway Water Hammer Load Calculation

0

A190.0002

Procedure Review Form UT-2 Ultrasonic

Examination of Vessel Welds and Adjacent Base

Metal, Revision 30

October 8, 2014

A190.0002

Procedure Review Form UT-94 Ultrasonic

Examination of Ferritic Piping Welds, Revision 9

October 8, 2014

A190.0002

Procedure Review Form UT-95 Ultrasonic

Examination of Austenitic Piping Welds,

Revision 8

October 8, 2014

A190.0002

Procedure Review Form UT-96 Ultrasonic

Through Wall Sizing in Piping Welds, Revision 7

October 8, 2014

A190.0002

Procedure Review Form UT-103 Ultrasonic

Examination of Dissimilar Metal Piping Welds,

Revision 5

October 8, 2014

AP14-008

Self-Assessment: Nuclear Oversight ISI - IST

Audit

October 8, 2014

EDP-ZZ-00016

Self-Assessment: Checklist for Program Review

of Alloy 600 Program

October 8, 2014

EDP-ZZ-00016

Self-Assessment: ISI Program

June 20, 2014

A1-12

Miscellaneous

Number

Title

Revision/Date

RIS 2016-02

OMB Control

No. 3150-0011

NRC Regulatory Issue Summary 2016-02,

Design Basis Issues Related to Tube-To-

Tubesheet Joints in Pressurized-Water Reactor

Steam Generators. (ML15169A543)

March 23, 2016

T65.0212 6

Callaway Fall Protection

February 14, 2014

Section 1R11: Licensed Operator Requalification Program

Procedures

Number

Title

Revision

ODP-ZZ-00001

Operations Department - Code of Conduct

97

OSP-AC-00005

Turbine Actual Overspeed Trip

11

OTG-ZZ-00005

Plant Shutdown 20% Power to Hot Standby

47

Callaway Action Requests

200601332

201600670

Miscellaneous

Title

Date

Dynamic Simulator Exam Scenario, Cycle 16-2 As Found

February 1, 2016

Section 1R12: Maintenance Effectiveness

Procedures

Number

Title

Revision

EDP-ZZ-01128

Maintenance Rule Program

24

EDP-ZZ-01128,

Appendix 1

SSCs in Scope of the Maintenance Rule at Callaway

10

EDP-ZZ-01128,

Appendix 4

Maintenance Rule System Functions

16

A1-13

Callaway Action Requests

201602435

201602658

201602738

201602824

201603229

201603471

201603472

201603473

201603484

Jobs

11504345

16001349

Miscellaneous

Number

Title

Revision/Date

Procon1, LLC Evaluation of Room Cooler SGL-10A

Tube Leak Repair

April 13, 2016

1784

Union Electric Company Laboratory Services -

Metallurgical Report - Examination of Failed Room

Cooler Tubing

September 22, 1994

04060221

AmerenUE Technical Support Services - Metallurgical

Report - Examination of Callaway Room Cooler Tubes

September 30, 2004

13050249

Ameren Missouri Technical Support - Metallurgical

Report - Examination of Callaway Room Cooler Tubing

May 23, 2013

GL-137

SGL10A/B Room Cooler Heat Removal Capabilities

0

Section 1R13: Maintenance Risk Assessment and Emergent Work Controls

Procedures

Number

Title

Revision

APA-ZZ-00315

Configuration Risk Management Program

14

ODP-ZZ-00002,

Appendix 1

Protected Equipment Program

23

ODP-ZZ-00002,

Appendix 1,

Checklist 5

Placing Train A Protected Equipment Barriers, Mode 5 & 6

2

ODP-ZZ-00002,

Appendix 1,

Checklist 7

Placing Train B Protected Equipment Barriers, Mode 5 & 6

2

A1-14

Procedures

Number

Title

Revision

ODP-ZZ-00002,

Appendix 1,

Checklist 9

Placing Train A Protected Equipment Barriers, Defueled

2

ODP-ZZ-00002,

Appendix 1,

Checklist 17

Placing Protected Equipment Barriers for SFP Cooling

Outage

1

ODP-ZZ-00002,

Appendix 2

Risk Management Actions for Planned Risk Significant

Activities

11

ODP-ZZ-00002,

Appendix 2,

Checklist 9

Postings for Lowered Inventory Operations

2

Callaway Action Requests

201601830

201602875

201603382

201605725

201605766

Jobs

06112970

06116947

10505244

13507816

13507818

14512791

14512792

14512793

14512629

14512630

14512631

14512632

14512774

14512780

14512784

14512873

14513123

14513124

14513125

14512846

14512893

14512923

14513455

14514354

15506373

16003488

16003529

16003530

16003531

Miscellaneous

Number

Title

Revision

Shutdown Safety Management Plan

3

PRAER 16-405

PRA Evaluation Request - Mode Change from Mode 4 to

Mode 3 with Equipment OOS

0

Section 1R15: Operability Evaluations

Procedures

Number

Title

Revision

KDP-ZZ-00013

Emergency Response Facility and Equipment Evaluation

13

MTE-ZZ-QA013

MOVATS UDS Testing of Torque Controlled Limitorque

Motor Operated Rising Stem Valves

19

A1-15

Procedures

Number

Title

Revision

ODP-ZZ-00002

Equipment Status Control

83

OSP-EJ-V002A

RHR Pump Containment Sump Suction and RWST Suction

Inservice Test

31

Drawings

Number

Title

Revision

8600-X-89645

High Pressure & Low Pressure Nitrogen Gas Storage &

Transfer System Site Gas Systems (KH2) Piping and

Instrumentation Diagram

15

E-23BB12A(Q)

RHR Loop 1 Inlet Isolation Valve Schematic Diagram

12

E-1038-00004

Schematic 7.5kVA Inverter 125VDC, 120VAC, 1PH, 60Hz -

Alarms

1

E-1038-00003

Schematic 7.5kVA Inverter 120VAC, 1ø, 60Hz

2

E-1038-00006,

S002

Outline 7.5kVA Inverter Front Panel Identification

2

M-22AB02(Q)

Main Steam System Piping and Instrumentation Diagram

17

M-22FA01

Auxiliary Boiler System Piping and Instrumentation Diagram 18

M-22KH01

Service Gas System Piping and Instrumentation Diagram

29

M-622.1-00023

Condensing Unit

19

E-23KJ08A(Q)

Standby Jacket Coolant Heater EKJ01A Schematic Diagram 2

E-23KJ09B(Q)

Standby Jacket Coolant Circ. Pump PKJ01A Schematic

Diagram

2

M-22KJ01(Q)

Standby Diesel Generator A Cooling Water System Piping

and Instrumentation Diagram

24

Callaway Action Requests

201603312

201603353

201603598

201603711

201603739

201603758

201604998

201605016

201605045

201605324

201605917

201105227

Jobs

10507721

10507762

13505626

14511766

16001888

16002253

16002356

16003607

A1-16

Miscellaneous

Number

Title

Revision

BO-05

Addendum 19

Revised Temperatures for 3601, 3605, and 3609 for Station

Black Out

1

BO-07

Control Room SBO Heat Load Calculation

11

EF-123

UHS Thermal Performance Analysis using GOTHIC 7.2(b)

CAR#201001813

1

RFR 17478

Perform Evaluation for NRC GL96-06 Response

C

RFR 201603756 Request for Resolution: Modify low pressure nitrogen

system piping and penetrations

0

Section 1R18: Plant Modifications

Procedures

Number

Title

Revision

APA-ZZ-00600

Design Change Control

57

EDP-ZZ-04015

Evaluating and Processing Requests for Resolution (RFR)

70

Drawings

Number

Title

Revision

M-22AL01(Q)

Auxiliary Feedwater System Piping and Instrumentation

Diagram

46

M-22AN01

Demineralized Water Storage and Transfer System Piping

and Instrumentation Diagram

42

M-22AP01

Condensate Storage and Transfer System Piping and

Instrumentation Diagram

31

M-22AP02

Hardened Condensate Storage Tank Composite Piping and

Instrumentation Diagram

0

M-22AQ02

Feedwater Chemical Addition System Piping and

Instrumentation Diagram

17

M-22KA09

Instrument Air System Piping and Instrumentation Diagram

25

Miscellaneous

Number

Title

Revision/Date

50.59 Screen for MP 13-0033 Hardened Condensate

Storage Tank Refuel 21 Tie-Ins

4

Applicability Determination for MP 13-0033 Hardened

Condensate Storage Tank Refuel 21 Tie-Ins

4

A1-17

Miscellaneous

Number

Title

Revision/Date

Evaluation of Scissor Lift Impact on HCST

May 6, 2016

16-05

50.59 Evaluation for MP 13-0033 Hardened Condensate

Storage Tank Refuel 21 Tie-Ins

4

MP 13-0033

Hardened Condensate Storage Tank Refuel 21 Tie-Ins

4

Section 1R19: Post-Maintenance Testing

Procedures

Number

Title

Revision

APA-ZZ-00100

Written Instructions Use and Adherence

33

APA-ZZ-00320

Work Execution

56

APA-ZZ-00322

Appendix C

Job Planning

43

MTE-ZZ-QA013

MOVATS UDS Testing of Torque Controlled Limitorque

Motor Operated Rising Stem Valves

19

OSP-JE-00001

Emergency Fuel Oil Transfer Pumps Cross-connection Line

Fill Verification Test

13

OSP-NE-0001A

Standby Diesel Generator A Periodic Tests

62

OTN-NB-0001A

Addendum 3

NB01 transfer to XNB02 Single Offsite Source Operation

and Restoration

8

OTN-NE-0001A

Standby Diesel Generation System -Train A

48

Drawings

Number

Title

Revision

E-23BB12A(Q)

RHR Loop 1 Inlet Isolation Valve Schematic Diagram

12

M22-KH01

Service Gas System Piping and Instrumentation Diagram

29

Callaway Action Requests

201602435

201603496

201603598

201603758

201604092

201605141

201605393

Jobs

10507721

10507762

16001888

16001887

16001349

14005657

15505373

13505566

14511620

16002253

A1-18

Jobs

16003027

Section 1R20: Refueling and Other Outage Activities

Procedures

Number

Title

Revision

APA-ZZ-00908

Fitness for Duty Programs

34

APA-ZZ-00911

Fatigue Management

5

ESP-ZZ-00024

Low Power Physics Testing Data Acquisition

9

OSP-SA-00004

Visual Inspection of Containment for Loose Debris

25

OTG-ZZ-00001

Plant Heatup Cold Shutdown to Hot Standby

85

OTG-ZZ-00002

Reactor Startup - IPTE

57

OTG-ZZ-00003

Plant Startup Hot Zero Power to 30 Percent Power - IPTE

60

OTG-ZZ-00005

Plant Shutdown 20 Percent Power to Hot Standby

47

OTG-ZZ-00006

Plant Cooldown Hot Standby to Cold Shutdown

74

OTG-ZZ-00007

Refueling Preparation, Performance and Recovery

38

Callaway Action Requests

201600506

201603464

201603496

201603498

201603531

201603598

201603725

201603729

201603739

201603799

201603889

201603909

201603917

201603931

Section 1R22: Surveillance Testing

Procedures

Number

Title

Revision

APA-ZZ-00350

Measuring and Test Equipment Program

29

OSP-BN-V0005

BN Suction Header Valves Inservice Test

5

OSP-EJ-0006A

RHR Mini Flow Valve Time Response Test Train A

2

OSP-EJ-0006B

RHR Mini Flow Valve Time Response Test Train B

2

OSP-EJ-PV04A

Train A RHR and RCS Check Valve Inservice Test

10

OSP-EJ-PV04B

Train B RHR and RCS Check Valve Inservice Test

12

OSP-EJ-V002B

RWST to RHR Suction Check Valve Inservice Test

10

A1-19

Procedures

Number

Title

Revision

OSP-EM-P0002

Train A and Train B Safety Injection Comprehensive Pump

Test

9

OSP-EM-V0003

ECCS Check Valve Inservice Test

33

OSP-EM-V003A

CCP A and B Full Flow Test

24

OSP-EM-V0004

RHR Check Valve and SI Pump Recirc Valve Inservice Test

22

OSP-EM-V0005

EM8922A and EM8922B Closure Inservice Test

11

OSP-EP-V0006

SI Accumulator Discharge Check Valve Test

9

OSP-NE-0001B

Standby Diesel Generator B Periodic Tests

64

OSP-SA-2413B

Train B Diesel Generator and Sequencer Testing

26

OTN-NE-0001B

Standby Diesel Generation System - Train B

51

OTS-SB-0002B

SSPS Train B Operation in Modes 5, 6, and No Mode

6

Callaway Action Requests

201604838

201508227

201503020

Jobs

10506673

13504474

13504816

14511319

14511384

14511393

14511394

14511398

14511402

14511437

14511604

14511834

14512880

16507235

15004983

Section 2RS1: Radiological Hazard Assessment and Exposure Controls

Procedures

Number

Title

Revision

APA-ZZ-00014

Conduct of Operations - Radiation Protection

22

APA-ZZ-01000

Callaway Energy Center Radiation Protection Program

41

APA-ZZ-01004

Radiological Work Standards

27

HDP-ZZ-01200

Radiation Work Permits

29

HDP-ZZ-01500

Radiological Postings

44

HDP-ZZ-03000

Radiological Survey Program

43

HDP-ZZ-03000

APPA

Frequency and Location of Routine Radiological Surveys

13

HTP-ZZ-02004

Control of Radioactive Sources

39

A1-20

Procedures

Number

Title

Revision

HTP-ZZ-06001

High Radiation / Locked High Radiation / Very High

Radiation Area Access

50

Callaway Action Requests

201507836

201507921

201508154

201508367

201508546

201508801

201600369

201601938

201602105

201602672

Specific Radiation Work Permits

Number

Title

Revision

13005670

Replace Valves BGV001, BGV002, and BGV003

0

14006281

BB8948D Maintenance, Disassemble, Inspect, Repair

leak-by and Reassemble Check Valve BB8948D

1

14006280

BB8949D Disassembly and Repair, Remove/Reinstall

Insulation, Disassemble, Repair Leak, Clean Studs,

Reassemble, Perform VT-1 and VT-3 Inspection and

Engineering Oversight

1

210803625

Motor Change on B Reactor Coolant Pump and Associated

Tasks

1

15001126500

Replace BBV0400

0

Radiation Survey Records

Survey Number

Title

Date

01181621

Fuel Building 2047

December 27,

2012

CA-M-20140715-4

RW7225 Low Level Drum Storage Area

July 15, 2014

CA-M-20150821-4

1106 Moderating Heat Exchanger Room - Deposit from

HRA

August 21,

2015

CA-M-20151119-11

1124 Valve Area BACC Walkdown, Job 15505065

November 19,

2015

CA-M-20160104-5

1322 South Piping Pen Monthly Routine

January 4,

2016

CA-M-20160203-1

7225 Low Level Drum Storage Area

February 3,

2016

CA-M-20160402-8

RB2000 Initial Entry General Area for RFO21

April 2, 2016

CA-M-20160404-1

1322 South Piping Penetration Rm - Down Posting

April 4, 2016

A1-21

Radiation Survey Records

Survey Number

Title

Date

CA-M-20160404-25 1323 North Piping Penetration Room

April 4, 2016

CA-M-20160408-33 RB2026VC Pre-job BGV-001, 002, 003

April 8, 2016

CA-M-20160409-9

1124 Valve Compartment Hold Off, Job 10505104

April 9, 2016

CA-M-20160410-29 RB2026VC 14512081/500 Pre-shielding survey

April 10, 2016

CA-M-20160411-33

RB2000 Routine Daily

April 11, 2016

CA-M-20160412-5

RB2026VC Letdown Valve Cubicle fit-up and welding of

new BGV-001 valve and piping

April 12, 2016

Air Sampling

Sample Number

Location

Date

1604101612

Cavity

April 10, 2016

1604111442

RB 2026 Letdown Cubicle

April 11, 2016

1604120400

RB 2026

April 12, 2016

1604121345

BB8948D RB 2000

April 12, 2016

1604121800

D SG Manway

April 13, 2016

1604122215

BB8949D

April 13, 2016

Miscellaneous

Number

Title

Date

Accountable Source Inventory List

Custodial Source Inventory List

15507830

HSP-ZZ-00001: Sealed Beta-Gamma Source Leak Test

January 19,

2016

Section 2RS3: In-plant Airborne Radioactivity Control and Mitigation

Procedures

Number

Title

Revision

HDP-ZZ-08000

Respiratory Protection Program

23

HDP-ZZ-08002

Respiratory Protection Issue and Use

42

HTP-ZZ-08203-DTI-

REGULATORS

Testing Scott Regulators And Respirators Using The

Biosystems Posichek3 Tester

8

A1-22

Procedures

Number

Title

Revision

HTP-ZZ-08208-DTI-

FITPRO-TESTING

Quantitative Respirator Fit Testing Using The Tsi

Portacount Pro System

2

HTP-ZZ-08208-DTI-

FIT-TESTING

Quantitative Respirator Fit Testing Using The Tsi

Portacount Plus System

6

HTP-ZZ-08300-DTI-

AIRPAK75

Scott Air-Pak 75 SCBA Respirator Inspection and

Storage

9

HTP-ZZ-08300-DTI-

POST HYDRO

Post Hydrostatic Testing of Breathing Air Cylinders

4

HTP-ZZ-08300-DTI-

SKAPAK

SKA-PAK at SCBA Respirator Storage and Inspection

8

HTP-ZZ-08301-DTI-

RESPRO CLEAN

Manual Cleaning of Respiratory Protection Equipment

1

HTP-ZZ-08301-DTI-

SCOTT-RES-CLEAN

Manual Cleaning of Scott Mask Mounted Regulator

4

HTP-ZZ-08501-DTI-

AIR TEST

Testing of Breathing Air

5

HTP-ZZ-08502-DTI-

MAC-CAL

Scott Mobile Air Cart Calibration

3

HTP-ZZ-08503-DTI-

UNIIICOMPRESSOR

Operation of Bauer UNICUS III, 25 CFM Breathing Air

Compressor and Breathing Air Cascade System

4

RP-DTI-RESPRO-

STORAGE

Storage of Respirators

3

Callaway Action Requests

201407682

201407882

201408905

201500688

201501023

201502128

201502189

201502356

201503288

201503299

201503490

201600547

201600548

Title

Date

SCBA and Ska-Pak CBT Records

March 9, 2016

Ska-Pak Proficiency Certification Record

March 9, 2016

Breathing Air Sample Data Sheet

March 26, 2014

Breathing Air Sample Data Sheet

June 26, 2014

Breathing Air Sample Data Sheet

September 12, 2014

Breathing Air Sample Data Sheet

December 29, 2014

A1-23

Title

Date

Breathing Air Sample Data Sheet

March 17, 2015

Breathing Air Sample Data Sheet

June 19, 2015

Breathing Air Sample Data Sheet

September 22, 2015

Breathing Air Sample Data Sheet

December 15, 2015

Breathing Air Sample Data Sheet

March 7, 2016

Training Certificates

Number

Title

Date

Technician A

Air-Pak 2.2/3.0/4.5/Fifty/75 SCBA Maintenance and

Overhaul

September 20, 2016

Technician B

Air-Pak 2.2/3.0/4.5/Fifty/75 SCBA Maintenance and

Overhaul

July 13, 2017

Miscellaneous

Title

Date

Respiratory Protection Maintenance Records

2014-2015

Respiratory Protection Equipment Inspection Record

April 2015 - March 2016

Section 4OA1: Performance Indicator Verification

Procedures

Number

Title

Revision

RRA-ZZ-00001

NRC Performance Indicator Program

9

OSP-BB-00009

RCS Inventory Balance

37

Callaway Action Requests

201502229

201505332

201505796

Jobs

16503927

Miscellaneous

Number

Title

Revision Date

Mitigating Systems Performance Index (MSPI) Basis

Document

16

A1-24

Miscellaneous

Number

Title

Revision Date

NRC Performance Indicator Transmittal Report, Second

Quarter 2015, Mitigating Systems Cornerstone

July 9, 2015

NRC Performance Indicator Transmittal Report, Third

Quarter 2015, Mitigating Systems Cornerstone

October 12,

2015

NRC Performance Indicator Transmittal Report, Fourth

Quarter 2015, Mitigating Systems Cornerstone

January 11,

2016

NRC Performance Indicator Transmittal Report, First

Quarter 2016, Mitigating Systems Cornerstone

April 13, 2016

MSPI Derivation Report, MSPI Heat Removal System,

Unavailability Index (UAI)

June 2015

MSPI Derivation Report, MSPI Heat Removal System,

Unreliability Index (URI)

June 2015

MSPI Derivation Report, MSPI Heat Removal System,

Unavailability Index (UAI)

September

2015

MSPI Derivation Report, MSPI Heat Removal System,

Unreliability Index (URI)

September

2015

MSPI Derivation Report, MSPI Heat Removal System,

Unavailability Index (UAI)

December 2015

MSPI Derivation Report, MSPI Heat Removal System,

Unreliability Index (URI)

December 2015

MSPI Derivation Report, MSPI Heat Removal System,

Unavailability Index (UAI)

March 2015

MSPI Derivation Report, MSPI Heat Removal System,

Unreliability Index (URI)

March 2015

Reactor Coolant System Identified Leakage Data

April 1, 2015

through

March 30, 2016

NRC Performance Indicator Transmittal Report, Second

Quarter 2015, Barrier Integrity Cornerstone

July 6, 2015

NRC Performance Indicator Transmittal Report, Third

Quarter 2015, Barrier Integrity Cornerstone

October 12,

2015

NRC Performance Indicator Transmittal Report, Fourth

Quarter 2015, Barrier Integrity Cornerstone

January 11,

2016

NRC Performance Indicator Transmittal Report, First

Quarter 2016, Barrier Integrity Cornerstone

April 8, 2016

LER 2015-001-00

Licensee Event Report - Completion of a Shutdown

Required by the Technical Specifications

0

A1-25

Miscellaneous

Number

Title

Revision Date

LER 2015-002-00

Licensee Event Report - Manual Auxiliary Feedwater

Actuation

0

LER 2015-003-00

Licensee Event Report - Reactor Trip Caused by

Transmission Line Fault

0

LER 2015-003-01

Licensee Event Report - Reactor Trip Caused by

Transmission Line Fault

1

LER 2015-004-00

Licensee Event Report - Auxiliary Feedwater Flow

Control Valve Inoperable due to Faulty Electronic

Positioner Card

0

Section 4OA2: Identification and Resolution of Problems

Procedures

Number

Title

Revision

APA-ZZ-00500,

Appendix 8

Corrective Action Program Training Requirements

13

APA-ZZ-00500,

Appendix 9

Mitigating Systems Performance Index (MSPI)

7

APA-ZZ-00500,

Appendix 10

Trending Program

11

APA-ZZ-00500,

Appendix 11

Degraded And Nonconforming Condition Resolution

8

APA-ZZ-00500,

Appendix 12

Significant Adverse Condition - Significance Level 1

24

APA-ZZ-00500,

Appendix 13

Adverse Condition - Significance Level 2

25

APA-ZZ-00500,

Appendix 14

Adverse Condition - Significance Level 3

23

APA-ZZ-00500,

Appendix 15

Adverse Condition - Significance Level 4

20

APA-ZZ-00500,

Appendix 16

Adverse Condition - Significance Level 5

13

APA-ZZ-00500,

Appendix 17

Screening Process Guidelines

27

APA-ZZ-00500,

Appendix 18

Equipment Performance Evaluation

8

A1-26

Procedures

Number

Title

Revision

APA-ZZ-00500,

Appendix 19

Common Cause Evaluation (CCE)

5

APA-ZZ-00500,

Appendix 22

Corrective Action Program Definitions

13

APA-ZZ-00600

Design Change Control

57

Drawings

Number

Title

Revision

M-22AE01

Piping and Instrumentation Diagram Service Water System

22

Callaway Action Requests

201010634

20160440

201602658

201603472

201605488

201109846

201110442

201202852

201303346

201303370

201303451

201303502

201303608

201303702

201303736

201307879

201309041

201309046

201400458

201402778

201406213

2014072222

201407248

201407246

201407245

201503637

201602824

201603119

201603346

201603472

201603471

201603472

201603484

201603526

201604063

201604058

201604092

201604297

201604235

201604378

Jobs

16002133

16002339

Miscellaneous

Number

Title

Revision

MP 10-0003

Install Service Water Check Valves to Minimize ESW Water

Hammer During LOOP and ESFAS Testing

1

MP 10-0004

Revise Sequencer Operation of EFHV0037 and EFHV0038

2

Section 4OA3: Event Follow-Up

Procedures

Number

Title

Revision

APA-ZZ-00500

Corrective Action Program

57

A1-27

Procedures

Number

Title

Revision

APA-ZZ-00801

Foreign Material Exclusion

32

Callaway Action Requests

200603505

201408897

201606129

Jobs

11509869

13004764

Miscellaneous

Number

Title

Revision

E-1051-00104

IM for Dry Type Transformer Installation

0

A2-1

Attachment 2

The following items are requested for the

Occupational Radiation Safety Inspection

at Callaway Plant

(April 11 - 15, 2016)

Integrated Report 2016002

Inspection areas are listed in the attachments below.

Please provide the requested information on or before March 21, 2016.

Please submit this information using the same lettering system as below. For example, all

contacts and phone numbers for Inspection Procedure 71124.01 should be in a file/folder titled

1- A, applicable organization charts in file/folder 1- B, etc.

If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at

least 30 days later than the onsite inspection dates, so the inspectors will have access to the

information while writing the report.

In addition to the corrective action document lists provided for each inspection procedure listed

below, please provide updated lists of corrective action documents at the entrance meeting.

The dates for these lists should range from the end dates of the original lists to the day of the

entrance meeting.

If more than one inspection procedure is to be conducted and the information requests appear

to be redundant, there is no need to provide duplicate copies. Enter a note explaining in which

file the information can be found.

If you have any questions or comments, please contact the lead inspector, Pete Hernandez at

(817) 200-1168 or Pete.Hernandez@nrc.gov.

PAPERWORK REDUCTION ACT STATEMENT

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget,

control number 3150-0011.

A2-2

1.

Radiological Hazard Assessment and Exposure Controls (71124.01)

Date of Last Inspection:

October 26, 2015

A.

List of contacts (with official title) and telephone numbers for the Radiation Protection

Organization Staff and Technicians

B.

Applicable organization charts

C.

Audits, self-assessments, and LERs written since date of last inspection, related to this

inspection area

D.

Procedure indexes for the radiation protection procedures

E.

Please provide specific procedures related to the following areas noted below.

Additional Specific Procedures may be requested by number after the inspector reviews

the procedure indexes.

1. Radiation Protection Program Description

2. Radiation Protection Conduct of Operations

3. Personnel Dosimetry Program

4. Posting of Radiological Areas

5. High Radiation Area Controls

6. RCA Access Controls and Radworker Instructions

7. Conduct of Radiological Surveys

8. Radioactive Source Inventory and Control

9. Declared Pregnant Worker Program

F.

List of corrective action documents (including corporate and subtiered systems) since

date of last inspection

a. Initiated by the radiation protection organization

b. Assigned to the radiation protection organization

c. Identify any CRs that are potentially related to a performance indicator event

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide documents which are searchable so that the inspector

can perform word searches.

If not covered above, a summary of corrective action documents since date of last

inspection involving unmonitored releases, unplanned releases, or releases in which any

dose limit or administrative dose limit was exceeded (for Public Radiation Safety

Performance Indicator verification in accordance with IP 71151)

G.

List of radiologically significant work activities scheduled to be conducted during the

inspection period (If the inspection is scheduled during an outage, please also include a

list of work activities greater than 1 rem, scheduled during the outage with the dose

estimate for the work activity.)

H.

List of active radiation work permits

I.

Radioactive source inventory list

A2-3

3.

In-Plant Airborne Radioactivity Control and Mitigation (71124.03)

Date of Last Inspection:

October 27, 2014

A.

List of contacts and telephone numbers for the following areas:

1. Respiratory Protection Program

2. Self-contained breathing apparatus

B.

Applicable organization charts

C.

Copies of audits, self-assessments, vendor or NUPIC audits for contractor support

(SCBA), and LERs, written since date of last inspection related to:

1. Installed air filtration systems

2. Self-contained breathing apparatuses

D.

Procedure index for:

1. use and operation of continuous air monitors

2. use and operation of temporary air filtration units

3. Respiratory protection

E.

Please provide specific procedures related to the following areas noted below.

Additional Specific Procedures may be requested by number after the inspector reviews

the procedure indexes.

1. Respiratory protection program

2. Use of self-contained breathing apparatuses

3. Air quality testing for SCBAs

F.

A summary list of corrective action documents (including corporate and subtiered

systems) written since date of last inspection, related to the Airborne Monitoring program

including:

1. continuous air monitors

2. Self-contained breathing apparatuses

3. respiratory protection program

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide documents which are searchable.

G.

List of SCBA qualified personnel - reactor operators and emergency response personnel

H.

Inspection records for SCBAs staged in the plant for use since date of last inspection.

I.

SCBA training and qualification records for control room operators, shift supervisors,

STAs, and OSC personnel for the last year.

A selection of personnel may be asked to demonstrate proficiency in donning, doffing,

and performance of functionality check for respiratory devices.