Meeting Slides for License Amendment Request for Measurement Uncertainty Recapture Uprate NRC Pre-Submittal Meeting April 26, 2016
ML16106A279
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 04/15/2016
From:
Exelon Generation Co
To: Richard Ennis
Plant Licensing Branch 1
Ennis R, NRR/DORL/LPLI-2
References
CAC MF7532, CAC MF7533
Download: ML16106A279 (23)


Text

Peach Bottom Atomic Power Station Units 2 and 3 License Amendment Request for Measurement Uncertainty Recapture Uprate NRC Pre-Submittal Meeting April 26, 2016

Introductions

Attendance

  • Dave Henry - Station Engineering Director Exelon
  • John Rommel - Director Engineering Exelon
  • Steve Minnick - MUR Sr Project Manager Exelon
  • Jim Armstrong - Station Regulatory Assurance Mgr. Exelon
  • Kevin Borton - Sr Manager Exelon
  • Andy Olson - Sr Staff Engineer, Fuels Exelon
  • Bill McDonald - Manager Engineering Exelon
  • David Neff - Principal Regulatory Engr. Exelon
  • George Paptzun - Manager Projects GEH
  • Larry King - Project Director GEH
  • Jim Harrison - Project Manager, Licensing GEH
  • John Hannah - Technical Leader, Methods GEH 3

Agenda

- Power History Overview

- Equipment Upgrades and Performance

  • License Amendment Request Quality
  • Technical Evaluations
  • GEH TSAR Examples
  • MUR Project Schedule 4

PBAPS Station Power History / Upgrades and Performance Dave Henry

Station Overview

  • Containment design pressure 56 psig
  • Began commercial operation in 1974, OLTP 3293 MWt
  • Current Power Level 3951 MWt, EPU U2 and U3 2015
  • 24 month operating cycle
  • GNF2 full core
  • Licensed for Increased Core Flow (ICF) (110%)
  • Caldon CheckPlus Leading Edge Flow Meter (LEFM) currently installed on Units 2 and 3 6

PBAPS Power History Key Milestones Year MWth Full Power Operating License 1973 (U2) 3293 (Original Licensed Thermal Power - OLTP) 1974 (U3) 3293 1994 (U2) 3458 Stretch Power Uprate (105% OLTP) 1995 (U3) 3458 MELLLA Operating Domain 1995 N/A 2002 (U2) 3514 MUR Uprate (1.62% increase) 2002 (U3) 3514 Renewed Operating License 2003 N/A Option III Stability Solution 2005 N/A GNF2 Fuel Introduction 2010 N/A 2015 (U2) 3951 Extended Power Uprate (120% OLTP) 2015 (U3) 3951 MELLLA+ Using DSS-CD 2016 N/A 2018 (U2) 4016 Proposed MUR 2018 (U3) 4016 7

PBAPS Upgrades and Performance Replaced Steam Dryers Upgraded Reactor Feedpump Added Main Steam Safety Turbines Valves Replaced Feedwater Heaters Eliminated Containment Reactor Water Clean Up Accident Pressure Credit System Improvements Increased Standby Liquid Generator and Turbine Retrofit Control B-10 Enrichment Auto Voltage Regulator Condensate Storage Tank Improvements Modifications MPT Upgrades Added Condensate Filter MELLLA+ Provides Greater Demineralizers Operations Flexibility and Replaced Condensate Control Pumps and Motors Plant upgrades provide margin to operate at TPO power levels 8

License Amendment Request Kevin Borton

License Amendment Request (LAR) Quality

  • NRC SE for Thermal Power Optimization (TPO) Licensing Topical Report NEDC-32938P-A SE Section 3.0 - Licensing Approach:

....In section 4.2.1 and Appendix B to the TPO LTR, GENE proposes categorizing the evaluations supporting a TPO as follows:

1. Bounded by the CLTP Analysis and Evaluations
2. Generically Dispositioned
3. Plant-specific Evaluation SE Section 4.2 - Applicability of the TPO LTR to Extended Power Uprate:

.plants seeking to apply a TPO uprate to a previous uprate that would result in licensed thermal power (LTP) in excess of 120 percent of the original licensed thermal power (OLTP) must provide plant-specific evaluation for those evaluations not performed at 102 percent current licensed thermal power.

The staff finds the approach acceptable since for EPU plants the TSAR will either confirm that the analyses and evaluations performed at the CLTP bound the TPO operating condition, or provide plant-specific justification and evaluation or analysis.

10

LAR Continued..

  • Therefore, the methods used for evaluating the PBAPS MUR are:

- Existing PBAPS evaluations that are bounded by the current CLTP evaluations (performed at > 102% CLTP)

- Plant -specific evaluations

  • Generically dispositioned evaluations will not apply
  • PBAPS plant-specific evaluations will include the GEH TPO LTR evaluation methods (TSAR examples)
  • EPU and MELLLA+ will be included in the existing and plant-specific licensing bases evaluations 11

LAR Continued..

  • License Application Request

- Cross-reference to guidance in RIS 2002-03, Guidance on the Content of MUR Power Uprate Applications

- GEH Safety Evaluation (TSAR) incorporates previous Industry responses to applicable RAIs for MURs

- Use of approved guidance where applicable

  • GEH licensing topical report TPO LTR
  • Caldon LEFM topical reports and NRC safety evaluation criteria

Technical Evaluations John Rommel

Technical Evaluations

  • Using existing EPU and MELLLA+ methods
  • Existing Caldon CheckPlus LEFM equipment
  • Technical Evaluations

- ECCS NPSH for Appendix R

- ATWS and ATWSI (MELLLA+)

- Replacement Steam Dryer

- Turbine Control Valve Position

  • Do not Anticipate Plant Equipment Modifications

GEH TSAR Examples TSAR Examples

  • Although same approach and methods, the TSAR sections will include additional content changes that will support the NRC Review

- EPU licensing basis

- MELLLA+ licensing basis

- No generic dispositions 16

Example of TSAR Existing Evaluation 4.1 CONTAINMENT SYSTEM PERFORMANCE TLTR Appendix G presents the methods, approach, and scope for the TPO uprate containment evaluation for LOCA. The current existing plant-specific containment evaluations were performed at 102% of CLTP. Although the nominal operating conditions change slightly because of the TPO uprate, the required initial conditions for containment analysis inputs remain the same as previously documented in the current licensing basis which includes EPU and MELLLA+.

The following table summarizes the effect of the TPO uprate on the various aspects of the containment system performance, and was verified against the current evaluation performed at 102% CLTP.

Topic Key Parameters TPO Effect Short term Pressure and Temperature Response Gas Temperature Break Flow and Energy Pressure Break Flow and Energy Long-Term Suppression Pool Temperature response Current Analysis Bulk Pool Decay Heat Based on 102% of CLTP Local Temperature with Decay Heat SRV Discharge Containment Dynamic Loads Loss-of-Coolant Break Flow and Energy Accidents Loads Safety-Relief-Valve Decay Heat Loads Sub compartment Break Flow and Energy Pressurization Containment Isolation Ability of containment isolation valves Section 4.1.1 provides confirmation that MOVs are And operators to perform their required capable of performing Design Basis functions at Functions is not affected because the evaluations have been TPO Conditions. performed at 102% of CLTP 17

Example of TSAR Plant-Specific Evaluation 3.9 REACTOR CORE ISOLATION COOLING The reactor core isolation cooling (RCIC) system provides inventory makeup to the reactor vessel when the vessel is isolated from the normal high pressure makeup systems. A plant-specific evaluation was performed for PBAPS using the evaluation approach The generic evaluations presented in the TLTR Section 5.6.7. are consistent for application to the PBAPS TPO uprate considering The plant-specific evaluation was performed using the current licensing basis which includes EPU and MELLLA+, and specifically verified that there is no change in the following: operating pressure or the pressure set-points of the SRVs, the capability of the turbine-driven system to successfully develop the horsepower and speed required by the pumps is unchanged. The plant-specific evaluation also concludes that the LOFW analysis-of-record for the plant-specific applications bounds the TPO uprate operating condition, the RCIC capacity and the decay heat calculations are unchanged (based on 102 percent CLTP), and the capability to maintain the water level above the TAF will remain unchanged. the current licensing basis. The TPO uprate does not affect the RCIC system operation, initiation, or capability requirements.

18

Example of TSAR Additional Basis Evaluation 9.3.1 Anticipated Transient Without Scram A plant-specific evaluation was performed using the approach in the current licensing basis. ,

present a generic evaluation of the sensitivity of an ATWS to a change in power typical of the TPO uprate. The evaluation is based on previous analyses for power uprate projects. For a TPO uprate, if a plant has sufficient margin for the projected changes in peak parameters given in TLTR Section L.3.5, Accordingly, a plant-specific analysis of the limiting ATWS events, consistent with the MELLLA+

Safety Analysis Report (Reference YY), was performed at the TPO power level. The assumptions and approaches in this analysis are consistent with those stated in Reference YY.

Additional details as applicable from the TSAR ATWS text..

The ATWS results at the TPO power level, including the MELLLA+ results in Table 9-X , show that all criteria are met.

Similarly, an analysis was performed for the limiting ATWS with Instability (ATWSI) event, from the TPO power level on the MELLLA+ licensed upper boundary (rod line). Because the ATWSI response is largely based on the rod line, there is very little impact to the slight increase in the initial power level. The key ATWSI results shown in Table 9-Z show essentially the same results and confirm an acceptable clad temperature response.

19

Example of TSAR Plant-specific Evaluation 6.5 STANDBY LIQUID CONTROL SYSTEM The SLCS is designed to shut down the reactor from rated power conditions to cold shutdown in the postulated situation that all or some of the control rods cannot be inserted. This manually operated system pumps a highly enriched sodium pentaborate solution into the vessel to achieve a sub critical condition. A plant-specific evaluation was performed for PBAPS using the evaluation approach presented in the TLTR Section 5.6.5. The generic evaluation presented in TLTR Section 5.6.5 (SLCS) and Appendix L.3 (ATWS Evaluation) is applicable to the PBAPS TPO uprate.

The maximum reactor lower plenum pressure following the limiting ATWS event reaches X,XXX psig during the time the SLCS is analyzed to be in operation. The TPO evaluation shows the pressure margin for the SLCS pump discharge relief valves is XXX psig , which is above the minimum value needed to ensure that the SLCS relief valves remain closed during system injection. The minimum reactor pressure, just prior to the time when SLCS initiates, remains low enough to ensure SLCS relief valve closure prior to the analyzed SLCS initiation time in the event of an early initiation of the SLCS during the initial ATWS transient pressure response.

Therefore, SLCS operation during an ATWS at the TPO power level is acceptable considering the MELLLA+ operating domain expansion.

The PBAPS TPO ATWS analysis is presented in Section 9.3.1. The ATWS evaluation shows that the TPO has no adverse effect on the ability of the SLCS to mitigate an ATWS. The TPO uprate does not affect shutdown or injection capability of the SLCS. Because the shutdown margin is reload dependent, the shutdown margin and the required reactor boron concentration are confirmed for each reload core.

20

Example of TSAR Section 3.6 3.6 REACTOR RECIRCULATION SYSTEM A plant-specific evaluation was performed for the PBAPS The reactor recirculation system (RRS), evaluation process is described using the evaluation approach presented in TLTR Section 5.6.2. considering the current licensing basis, which includes EPU/MELLLA+. The TPO uprate has a minor effect on the RRS and its components. Operation at the TPO uprated power is accomplished along an extension of the current MELLLA+ rod line with no increase in the maximum core flow. The TPO uprate does not require an increase in the maximum core flow. No significant reduction of the maximum flow capability occurs due to the TPO uprate because of the small increase in core pressure drop (< 1 psi). The effect on pump net positive suction head (NPSH) at TPO conditions is negligible. An evaluation has confirmed that no significant increase in RRS vibration occurs due to TPO operating conditions.

The cavitation protection interlock for the recirculation pumps and jet pumps is expressed in terms of FW flow. This interlock is based on sub-cooling and thus is a function of absolute FW flow rate and FW temperature at less than full thermal power operating conditions. Therefore, the interlock is not changed by TPO.

21

PBAPS MUR Project Schedule Steve Minnick

Schedule

  • Analysis / LAR development - June 2016 thru Aug 2017
  • Submit License Application - Sept 2017
  • Post Submittal meeting w/Key NRC reviewers - Oct 2017
  • Request NRC approval - Sept 2018
  • Unit 2 and Unit 3 Implementation - Sept thru Nov 2018 Both Units will be Ready for Power Ascension Upon LAR approval 23