ML17257A161

From kanterella
Jump to navigation Jump to search
September 19, 2017 Pre-application Public Meeting Presentation on Peach Bottom Subsequent License Renewal Application
ML17257A161
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 09/19/2017
From: Ranek N
Exelon Generation Co
To:
Office of Nuclear Reactor Regulation
Nancy Martinez
References
Download: ML17257A161 (7)


Text

Peach Bottom Atomic Power Station Second License Renewal Pre-Application Meeting - Environmental September 19, 2017

AGENDA Opening Remarks

  • Exelon Generation
  • NRC Staff

Background

Discussion of Topics Wrap-up

  • Summary of Action Items
  • Closing Remarks

- Exelon Generation

- NRC Staff Exelon Attendees:

Michael P. Gallagher - Exelon - VP License Renewal & Decommissioning Nancy L. Ranek - Exelon - License Renewal Senior Environmental Lead John G. Hufnagel, Jr. - Exelon - License Renewal Senior Licensing Lead Roberta (Bobbie) Hurley - AECOM - PBAPS SLR ER Project Director David R. Lewis - Pillsbury Winthrop Shaw Pittman LLC - Legal Counsel 1 PBAPS Second License Renewal Pre-Application Meeting - Environmental

Muddy Run Pumped Storage Hydro Facility Background -

Six-mile Radius Holtwood Dam Peach Bottom Atomic Power Station Conowingo Dam 2 PBAPS Second License Renewal Pre-Application Meeting - Environmental

Background - Plant Setting

[COPYRIGHTED AERIAL IMAGE OF PBAPS SITE WILL APPEAR HERE]

N S

3 PBAPS Second License Renewal Pre-Application Meeting - Environmental

Background - Site Layout N

S 4 PBAPS Second License Renewal Pre-Application Meeting - Environmental

Discussion Topics

  • Environmental Report Title
  • No Refurbishment
  • No Incorporation by Reference
  • Groundwater Monitoring Program
  • Transmission Lines
  • Protected Species
  • Clean Water Act Section 401 Certification
  • Coastal Zone Management Act Consistency Determination Not Required
  • No Adverse Effect on Cultural Resources
  • Status of NPDES Permit Renewal (Clean Water Act Sections 316a & 316b)
  • SAMA Analysis Not Required
  • Miscellaneous Other Topics (e.g., No High Burnup Fuel; Reasonable Alternatives) 5 PBAPS Second License Renewal Pre-Application Meeting - Environmental

Wrap Up

  • Summary of Action Items
  • Closing Remarks
  • Exelon Generation