Letter Sequence Meeting |
---|
|
Results
Other: ML18193A697, ML18232A438, ML18232A439, ML18289A379, ML18299A124, ML18304A200, ML18346A675, ML18354B066, ML19010A383, ML19023A227, ML19308A006, ML20054A175
|
MONTHYEARRS-17-149, Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from The.2017-12-15015 December 2017 Spent Fuel Pool Evaluation Supplemental Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from The. Project stage: Supplement RS-18-033, Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal2018-03-15015 March 2018 Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal Project stage: Request RS-18-043, Supplement to Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal2018-03-28028 March 2018 Supplement to Request for Extension of Due Date for Seismic Probabilistic Risk Assessment Submittal Project stage: Request ML18116A3242018-04-26026 April 2018 Annual Radioactive Effluent Release Report 60: January 1, 2017 Through December 31, 2017 Project stage: Request ML18193A6972018-07-10010 July 2018 Cover Letter Submitting Subsequent License Renewal Application Project stage: Other RS-18-098, Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from ...2018-08-28028 August 2018 Seismic Probabilistic Risk Assessment Report, Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from ... Project stage: Response to RAI ML18232A4392018-09-0404 September 2018 Federal Register Notice - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Other ML18232A4372018-09-0404 September 2018, 10 September 2018 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process Project stage: Request ML18232A4382018-09-10010 September 2018 Letter - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process for Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Other ML18288A4382018-09-25025 September 2018 Transcript from Peach Bottom SLR Envr Scoping Meeting 2018-09-25 Project stage: Request ML18275A3712018-09-25025 September 2018 Subsequent License Renewal Environmental Scoping Meeting 9-25-18 Project stage: Meeting ML18299A1242018-10-0101 October 2018 Pennsylvania State Historic Preservation Office Scoping Comments Concerning Peach Bottom Atomic Power Station, Units 2 & 3 Subsequent License Renewal Application Project stage: Other ML18282A1692018-10-0909 October 2018 Comment (3) of Richard Mccorkle on Exelon Generation Company, LLC; Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Request ML18289A5092018-10-18018 October 2018 09/25/2018 Summary of Meeting for Environmental Review of Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Meeting ML18289A3792018-10-25025 October 2018 License Renewal Environmental Site Audit Plan Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Other ML18288A1942018-10-25025 October 2018 Summary of the Site Visit Related to the Review of the Subsequent License Renewal Application for the Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Approval ML18304A2002018-11-0606 November 2018 License Renewal Severe Accident Mitigation Alternatives Audit Plan Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application Project stage: Other ML18323A7492018-11-19019 November 2018 Beyond Nuclear Hearing Request and Petition to Intervene Project stage: Request ML18330A1572018-11-23023 November 2018 Subsequent License Renewal Environmental Requests for Additional Information Project stage: RAI ML19010A3832018-12-0707 December 2018 Additional Documents Needed for Peach Bottom SLR Environmental Review Project stage: Other ML18348B0292018-12-13013 December 2018 Subsequent License Renewal Severe Accident Mitigation Alternatives Requests for Additional Information Project stage: RAI ML18354B0612018-12-20020 December 2018 Response to NRC Request for Additional Information, Dated November 23, 2018, Regarding the Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Application, Environmental Requests for Additional Information Project stage: Response to RAI ML18354B0662018-12-20020 December 2018 Summary of Monitoring Well Installation Details Project stage: Other ML19028A2802019-01-28028 January 2019 Response to NRC Request for Additional Information, Dated December 13, 2018, Regarding Peach Bottom Atomic Power Station, Units 2 and 3, Subsequent License Renewal Severe Accident Mitigation Alternatives Requests for Additional Information Project stage: Response to RAI ML18346A6752019-01-31031 January 2019 Summary of the Subsequent License Renewal Environmental Audit Project stage: Other ML19023A2272019-02-0505 February 2019 Summary of the Subsequent License Renewal Severe Accident Mitigation Alternatives Audit Project stage: Other ML19037A3482019-07-25025 July 2019 Issuance of Environmental Scoping Summary Report Associated with the Staff'S Review of the Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Application Project stage: Approval ML19210C5712019-07-31031 July 2019 Schedule Revision for the Review of the Peach Bottom Atomic Power Station Units 2 & 3 Subsequent License Renewal Application (EPID Nos. L-2018-RNW-0012/L-2018-RNW-0013) Project stage: Approval ML19199A1152019-08-0101 August 2019 Federal Register Notice - Peach Bottom Atomic Power Station Notice of Availability of the Draft Plant-Specific Draft Supplement 10 Second Renewal to the Generic Environmental Impact Statement for SLR Project stage: Draft Other ML19199A1142019-08-0101 August 2019 Notice of Availability of Draft Supplement 10, Second Renewal to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Subsequent License Renewal for Peach Bottom Atomic Power Station Units 2 and 3 Project stage: Draft Other ML19260F9652019-08-0101 August 2019, 12 September 2019, 23 September 2019, 2 October 2019 Nuclear Regulatory Commission'S Public Meeting on the Draft Supplemental Environmental Impact Statment for Subsequent License Renewal of Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Request ML19256E3522019-09-12012 September 2019 Slides - Peach Bottom SLRA Dseis Public Meeting - Sep 12 2019 Project stage: Request ML19308A0062019-09-16016 September 2019 Jennifer Shang Comments on Pb Dseis Project stage: Other ML19273B9692019-10-0202 October 2019 September 12, 2019 - Public Meeting to Discuss Draft Supplement 10, Second Renewal, to the Generic EIS for License Renewal of Nuclear Plants Regarding Peach Bottom Atomic Power Station Units 2 and 3 SLRA (EPID: L-201-RNW-0013) ML19303D1662019-10-31031 October 2019 Requests for Additional Information for the Environmental Review of the Peach Bottom Subsequent License Renewal Application - Set 2 (EPID No. L-2018-RNW-0013)- RAIs Project stage: RAI ML20054A1752020-01-28028 January 2020 Notification of the Availability of the Final Supplement 10, Second Renewal to the GEIS for Peach Bottom Atomic Power Station, Units 2 and 3 Project stage: Other 2018-07-10
[Table View] |
|
---|
Category:Slides and Viewgraphs
MONTHYEARML24029A1742024-01-30030 January 2024 Constellation Pre-Application January 30, 2024, Meeting Slides - Proposed Alternative to Utilize Code Case N-932, Alternative Requirements for Acceptance of Containment Base Metal Corrosion or Erosion ML23317A0712023-11-14014 November 2023 NRC Pre-Submittal Meeting on November 14th, 2023 - TSTF-591 and Selected 50.69 License Condition Updates (EPID L-2023-LLM-0098) (Slides) ML23251A0782023-09-0606 September 2023 DRE1 Decom Pre-Submittal Slides ML23255A1042023-08-11011 August 2023 Slides - Constellation - Pre-Application EP 9/18/2023 Draft CEG Presubmittal SG Performance Monitoring Plan Meeting Handout ML23170A0082023-06-29029 June 2023 Decommissioning Presentation for NRC Pre-submittal Meeting, June 29, 2023 ML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML23094A1492023-04-11011 April 2023 Licensee Presentation on Whr Exemption Request for Public Meeting on April 11, 2023 ML23076A0442023-03-16016 March 2023 Pb U2 Scram Barrier Presentation KT Session NEI 99-01, Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides2023-02-21021 February 2023 Slides - Constellation - Pre-Application EP 2/23/2023 Meeting Slides ML21314A4472021-11-10010 November 2021 Slides for Presubmittial Meeting for Proposed Alternative to Adopt ASME Code Case N-921 to Extend the Inservice Inspection Interval ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21162A3322021-06-11011 June 2021 BWR Fleet Relief Request Associated with RPV Instrument Nozzle Repairs ML20261G7322020-09-16016 September 2020 Pre-Submittal Slides Extend 120-month Isi/Ist Interval Under 50.55a ML20178A4202020-06-30030 June 2020 NEI Slides for June 30, 2020, Public Meeting on COVID-19 Response ML20175A8722020-06-23023 June 2020 Risk-Informed Inservice Inspection - U.S Nuclear Regulatory Commission (NRC) - Four Element Risk-Informed Approach ML20170B0212020-06-23023 June 2020 NRC Pre-Submittal Meeting Byron Unit 2 One-Time Deferral of Reactor Pressure Vessel Head Penetration Nozzle (Rpvhpn) Inspections ML20163A6542020-06-18018 June 2020 2020 NRC Annual Assessment Webinar Presentation - Pennsylvania and Maryland Facilities (Beaver Valley, Calvert Cliffs, Limerick, Peach Bottom, Susquehanna) ML20163A6552020-06-16016 June 2020 6-16-20 Byron Unit 2 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections ML20169A5592020-06-16016 June 2020 Steam Generator License Amendment Request Pre-Submittal Meeting (NRC) - Byron Unit 2 LAR for One-Time Deferral of Steam Generator Inspections (Rev 1) ML20168A3192020-06-15015 June 2020 Joint Annual Assessment Meeting for Pa/Md Power Plants - Webinar Presentation ML19308B9262019-11-0505 November 2019 ACRS Plant License Renewal Subcommittee - Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Safety Evaluation Report (SER) with Confirmatory Item ML19256E3852019-09-12012 September 2019 SLR Dseis Public Meeting Sept 12 2019 - Scott Portzline - Former Three Mile Island Alert Presentation ML19256E3522019-09-12012 September 2019 Slides - Peach Bottom SLRA Dseis Public Meeting - Sep 12 2019 ML19157A0542019-06-0606 June 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - NRC Presentation Slides ML18347B3142018-12-19019 December 2018 Bwrvip/Asme Relief Request Discussion December 19, 2018 ML18334A2162018-11-30030 November 2018 Presentation Slides: Exelon BWR MSIV (Boiling-Water Reactor - Main Steam Isolation Valve) Leakage Optimization for NRC Pre-Submittal Meeting of December 6, 2018 ML18319A1272018-11-19019 November 2018 Slides for 11/19/18 Public Meeting - Exelon Fleet LAR for Common Language for TS 5.7 High Radiation Areas ML18275A3712018-09-25025 September 2018 Subsequent License Renewal Environmental Scoping Meeting 9-25-18 ML18141A3072018-05-21021 May 2018 18 - SLR Status ML18054B3592018-02-27027 February 2018 Slide: NRC Pre-Submittal Meeting for Exelon Fleet LAR to Relocate TS Unit Staff Qualification ANSI Requirements to the QATR, February 27, 2018, Profile Info: Submitted by Frank Mascitelli ML18017A1172018-01-18018 January 2018 NRC PBAPS SLRA Pre-Submittal Meeting Jan 2018 PM Copy ML17320A2002017-11-15015 November 2017 Insights from Implementing FLEX in the Peach Bottom Seismic PRA Model ML17257A1612017-09-19019 September 2017 September 19, 2017 Pre-application Public Meeting Presentation on Peach Bottom Subsequent License Renewal Application ML16106A2792016-04-15015 April 2016 Meeting Slides for License Amendment Request for Measurement Uncertainty Recapture Uprate NRC Pre-Submittal Meeting April 26, 2016 ML16077A1562016-03-22022 March 2016 Fleet: Pre-application Teleconference with Exelon to Discuss a Potential License Amendment Request Regarding Operating Training Standards ML13255A3762013-09-16016 September 2013 Soarca Peach Bottom Uncertainty Analysis (UA) Acrc Briefing - Sept 2013 ML12159A2662012-06-11011 June 2012 County Generating Station Pre-Application Meeting Extended Power Uprate: Replacement Steam Dryers. June 11, 2012 ML12130A0992012-05-0909 May 2012 Annual Assessment Meeting Slides Presentation Rev. 0, 2012 ML12124A0782012-04-26026 April 2012 Power Point Presentation: Peach Bottom - Timing and Criteria for RCS Failure ML1208701402012-03-27027 March 2012 Licensee Slides for Exelon Fleet Pre-Submittal Public Meeting 4-10-12 Licensed Operator Eligibility Requirements LAR NRC-2012-0022, Comment (18) of Scott D. Portzline on Behalf of Three Mile Island Alert, on State of the Art Reactor Consequence Analyses (Soarca) Reports2012-02-28028 February 2012 Comment (18) of Scott D. Portzline on Behalf of Three Mile Island Alert, on State of the Art Reactor Consequence Analyses (Soarca) Reports ML12262A4762012-02-22022 February 2012 TMI Alert Portzline Presentation NUREG-0654 Public Mtg ML1110800952011-04-14014 April 2011 NRC Slides for Peach Bottom Public Meeting on April 13, 2011 ML1011100672010-04-20020 April 2010 NRC Slides for Peach Bottom Atomic Power Station Annual Assessment Meeting April 19, 2010 ML1011100652010-04-20020 April 2010 Slides for PBAPS Aam, April 19, 2010 ML0929400522009-10-22022 October 2009 Meeting Power Uprate Meeting Slides ML11228A2312009-08-13013 August 2009 State-of-the-Art Reactor Consequence Analyses (Soarca); Semi-Annual Briefing for Commission Tas ML0918109342009-06-16016 June 2009 Hand-outs for June 16, 2009 Public Meeting with Exelon ML11228A2302009-04-14014 April 2009 State-of-the-Art Reactor Consequence Analyses; Semi-Annual Briefing for Commission Technical Assistants 2024-01-30
[Table view] |
Text
Subsequent License Renewal Scoping Meeting Peach Bottom Units 2 and 3 September 25, 2018 Bennett Brady, Safety Project Manager Lauren Gibson, Environmental Project Manager
Agenda
- Overview
- Safety Review
- Environmental Review
- Public Comments regarding scoping of the Peach Bottom Environmental Review 2
Subsequent License Renewal Review Process and Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)
Subsequent License NRC Renewal Renewal Application Hearings* Decision (SLRA) Accepted 10 CFR 2 (10 CFR 54.29)
Safety ACRS Review Recommendation (10 CFR 54) (10 CFR54.25)
- If a Request for Hearing is Granted 3
Safety Review Acceptance Review Operating In-Office Review Experience On-Site Audit In-Office Audit Audit Issue Safety Evaluation Report (SER) 4
Safety Review Regulations Existing Regulatory Process Additional and Guidance Aging Management Operating Support for Licensing Experience Decisions Oversight 5
Environmental Review Issue Environmental Draft Issue Site Audit Supplemental Consider Final Environmental Public Supplemental Public Scoping Impact Comments Environmental Meeting Statement Impact for Public Statement Comment 6
Scoping Process
- Process to determine the scope of issues and alternatives to be considered in the Supplemental Environmental Impact Statement
- Scoping is intended to ensure that problems are identified early and properly studied 7
Scoping Documentation
- Press Release and newspaper ads
Environmental Resources 9
Interagency Coordination 10
Agency Decision
- Safety Evaluation Report (SER)
- Supplemental Environmental Impact Statement (EIS)
- Advisory Committee for Reactor Safeguards
- Hearings (if applicable) 11
Review Milestones Application Received July 10, 2018 Application Accepted August 27, 2018 Notice of Opportunity for Hearing September 10, 2018 Environmental Scoping Meeting September 25, 2018 Scoping Comments Due October 10, 2018 Hearing Opportunity Closes November 5, 2018 Issue Draft Supplemental EIS July 2019 Issue Final Safety Evaluation Report September 2019 ACRS Subcommittee Meeting October 2019 ACRS Full Committee Meeting December 2019 Issue Final Supplemental EIS January 2020 Agency Decision (w/o hearing) March 2020 12
How to Submit Comments After the Meeting
- By mail: May Ma, Director, Program Management, Announcements and Editing Branch Office of Administration Mailstop: TWFN-7A6OM, U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
- Comments due by October 10, 2018 13
Further Information
https://www.nrc.gov/reactors/operating/licensing/renewal.html
https://www.nrc.gov/reactors/operating/licensing/renewal/applications/peach-bottom-subsequent.html
- Application available at: Harford County Public Library: Whiteford Branch, 2407 Whiteford Rd, Whiteford, MD 21160
- David Drucker, Environmental Project Manager Phone: 1-301-415-6223 Email: david.drucker@nrc.gov
- Bennett Brady, Safety Project Manager Phone: 1-301-415-2981 Email: bennett.brady@nrc.gov 14
Questions and Answers
- Questions on preceding NRC presentation
- State your name and affiliation
- Spell your name if difficult 15
Comments
- State your name and affiliation
- Spell your name if difficult 16