Subsequent License Renewal Scoping Meeting Peach Bottom Units 2 and 3 September 25, 2018 Bennett Brady, Safety Project Manager Lauren Gibson, Environmental Project Manager

Agenda

- Overview

- Safety Review

- Environmental Review

  • Public Comments regarding scoping of the Peach Bottom Environmental Review 2

Subsequent License Renewal Review Process and Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)

Subsequent License NRC Renewal Renewal Application Hearings* Decision (SLRA) Accepted 10 CFR 2 (10 CFR 54.29)

Safety ACRS Review Recommendation (10 CFR 54) (10 CFR54.25)

  • If a Request for Hearing is Granted 3

Safety Review Acceptance Review Operating In-Office Review Experience On-Site Audit In-Office Audit Audit Issue Safety Evaluation Report (SER) 4

Safety Review Regulations Existing Regulatory Process Additional and Guidance Aging Management Operating Support for Licensing Experience Decisions Oversight 5

Environmental Review Issue Environmental Draft Issue Site Audit Supplemental Consider Final Environmental Public Supplemental Public Scoping Impact Comments Environmental Meeting Statement Impact for Public Statement Comment 6

Scoping Process

  • Process to determine the scope of issues and alternatives to be considered in the Supplemental Environmental Impact Statement
  • Scoping is intended to ensure that problems are identified early and properly studied 7

Scoping Documentation

  • Notice of Intent
  • Scoping Letters
  • Press Release and newspaper ads
  • Scoping Summary Report 8

Environmental Resources 9

Interagency Coordination 10

Agency Decision

  • Safety Evaluation Report (SER)
  • Supplemental Environmental Impact Statement (EIS)
  • Advisory Committee for Reactor Safeguards
  • Hearings (if applicable) 11

Review Milestones Application Received July 10, 2018 Application Accepted August 27, 2018 Notice of Opportunity for Hearing September 10, 2018 Environmental Scoping Meeting September 25, 2018 Scoping Comments Due October 10, 2018 Hearing Opportunity Closes November 5, 2018 Issue Draft Supplemental EIS July 2019 Issue Final Safety Evaluation Report September 2019 ACRS Subcommittee Meeting October 2019 ACRS Full Committee Meeting December 2019 Issue Final Supplemental EIS January 2020 Agency Decision (w/o hearing) March 2020 12

How to Submit Comments After the Meeting

  • By mail: May Ma, Director, Program Management, Announcements and Editing Branch Office of Administration Mailstop: TWFN-7A6OM, U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001
  • Comments due by October 10, 2018 13

Further Information

https://www.nrc.gov/reactors/operating/licensing/renewal.html

https://www.nrc.gov/reactors/operating/licensing/renewal/applications/peach-bottom-subsequent.html

  • Application available at: Harford County Public Library: Whiteford Branch, 2407 Whiteford Rd, Whiteford, MD 21160
  • David Drucker, Environmental Project Manager Phone: 1-301-415-6223 Email: david.drucker@nrc.gov
  • Bennett Brady, Safety Project Manager Phone: 1-301-415-2981 Email: bennett.brady@nrc.gov 14

Questions and Answers

  • Questions on preceding NRC presentation
  • Speak into a microphone
  • State your name and affiliation
  • Spell your name if difficult 15

Comments

  • Fill out a yellow card
  • Speak at the podium
  • State your name and affiliation
  • Spell your name if difficult 16