ML15329A157

From kanterella
Jump to navigation Jump to search
IR 05000354/2015007; 9/21/15 to 10/23/15; Hope Creek Generating Station; Component Design Bases Inspection
ML15329A157
Person / Time
Site: Hope Creek 
Issue date: 11/25/2015
From: Paul Krohn
Engineering Region 1 Branch 2
To: Braun R
Public Service Enterprise Group
References
IR 2015007
Download: ML15329A157 (42)


See also: IR 05000354/2015007

Text

R. Braun

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BLVD., SUITE 100

KING OF PRUSSIA, PA 19406-2713

November 25, 2015

Mr. Robert Braun

President and Chief Nuclear Officer

PSEG Nuclear LLC - N09

P. O. Box 236

Hancocks Bridge, NJ 08038

SUBJECT:

HOPE CREEK GENERATING STATION - COMPONENT DESIGN BASES

INSPECTION REPORT 05000354/2015007

Dear Mr. Braun:

On October 23, 2015, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection

at the Hope Creek Generating Station. The enclosed inspection report documents the

inspection results, which were discussed on October 23, 2015, with Mr. Eric Carr, Plant

Manager, and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

In conducting the inspection, the team examined the adequacy of selected components to

mitigate postulated transients, initiating events, and design basis accidents. The inspection

involved field walkdowns, examination of selected procedures, calculations and records, and

interviews with station personnel.

This report documents two NRC-identified findings that were of very low safety significance

(Green). These findings were determined to involve violations of NRC requirements. However,

because of the very low safety significance of the violations and because they were entered into

your corrective action program, the NRC is treating these findings as non-cited violations

(NCVs) consistent with Section 2.3.2.a of the NRC Enforcement Policy. If you contest any NCV

in this report, you should provide a response within 30 days of the date of this inspection report,

with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document

Control Desk, Washington, D.C. 20555-0001, with copies to the Regional Administrator,

Region I; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission,

Washington, D.C. 20555-0001; and the NRC Senior Resident Inspector at Hope Creek. In

addition, if you disagree with the cross-cutting aspect assigned to any finding in this report, you

should provide a response within 30 days of the date of this inspection report, with the basis for

your disagreement, to the Regional Administrator, Region I, and the NRC Senior Resident

Inspector at Hope Creek.

R. Braun

-2-

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 2.390 of the

NRCs Rules of Practice, a copy of this letter, its enclosure, and your response (if any) will be

available electronically for the public inspection in the NRC Public Docket Room or from the

Publicly Available Record System (PARS) component of NRCs document system, Agencywide

Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC

Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Paul G. Krohn, Chief

Engineering Branch 2

Division of Reactor Safety

Docket No.

50-354

License No. NPF-57

Enclosure:

Inspection Report 05000254/2015007

w/Attachment: Supplementary Information

cc w/encl: Distribution via ListServ

ML15329A157

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available

OFFICE

RI/DRS

RI/DRS

RI/DRP

RI/DRS

NAME

JSchoppy

WCook

FBower

PKrohn

DATE

11/8/15

11/9/15

11/12/15

11/25/15

i

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION I

Docket No:

50-354

License No:

NPF-57

Report No:

05000354/2015007

Licensee:

Public Service Enterprise Group (PSEG) Nuclear LLC

Facility:

Hope Creek Generating Station (HCGS)

Location:

P.O. Box 236

Hancocks Bridge, NJ 08038

Inspection Period:

September 21 through October 23, 2015

Inspectors:

J. Schoppy, Senior Reactor Inspector, Team Leader

Division of Reactor Safety (DRS)

J. Brand, Reactor Inspector, DRS

J. Kulp, Senior Reactor Inspector, DRS

S. Makor, Reactor Inspector, RIV/DRS

S. Kobylarz, NRC Electrical Contractor

M. Yeminy, NRC Mechanical Contractor

Approved By:

Paul G. Krohn, Chief

Engineering Branch 2

Division of Reactor Safety

ii

SUMMARY

IR 05000354/2015007; 9/21/15 - 10/23/15; Hope Creek Generating Station; Component Design

Bases Inspection.

The report covers the Component Design Bases Inspection conducted by a team of four NRC

inspectors and two NRC contractors. Two findings of very low safety significance (Green) were

identified, both of which were considered to be non-cited violations (NCVs). The significance of

most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual

Chapter (IMC) 0609, Significance Determination Process. Cross-cutting aspects associated

with findings are determined using IMC 0310, Components Within the Cross-Cutting Areas.

The NRCs program for overseeing the safe operation of commercial nuclear power reactors is

described in NUREG-1649, Reactor Oversight Process, Revision 5.

NRC-Identified Findings

Cornerstone: Mitigating Systems

Green. The team identified a finding of very low safety significance involving a

non-cited violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, because PSEG

did not establish appropriate acceptance criteria for the time allowed for starting the

residual heat removal (RHR) and core spray pumps during simulated loss-of-coolant

accident/loss-of-offsite power (LOCA/LOP) conditions in the 18-month integrated

emergency diesel generator (EDG) surveillance test (ST) for the vital 4KV buses.

Specifically, the ST acceptance criteria failed to confirm that the pumps started in

accordance with the design basis loading sequence described in the design analyses

and Updated Final Safety Analysis Report Table 8.3-1. PSEGs short-term corrective

actions included reviewing LOCA/LOP test results and plant historical data to confirm

current operability of the RHR and core spray pumps, and initiating corrective action

notifications to determine the appropriate ST acceptance criteria and to trend pump

start times.

The team determined that the failure to specify adequate acceptance limits for the design

basis assigned start times for the RHR and core spray pumps during LOCA/LOP conditions

in the 18-month integrated EDG ST procedure was a performance deficiency. The

performance deficiency was more than minor because it was associated with the procedure

quality attribute of the Mitigating Systems Cornerstone and affected the cornerstone

objective of ensuring the availability, reliability, and capability of systems that respond to

initiating events to prevent undesirable consequences. The team evaluated the finding in

accordance with IMC 0609, Appendix A, The Significance Determination Process (SDP) for

Findings at Power, Exhibit 2 - Mitigating Systems Screening Questions, and determined that

the finding was of very low safety significance (Green) because the finding was a design

deficiency that did not result in the loss of operability or functionality. The team determined

that this finding has a cross-cutting aspect in Human Performance, Documentation, in that

PSEG failed to maintain accurate test acceptance documentation to aid plant staff in the

identification of equipment performance that was outside the acceptable limits of design.

(H.7) (Section 1R21.2.1.1)

iii

Green. The team identified a finding of very low safety significance involving a

non-cited violation of Title 10 of the Code of Federal Regulations (10 CFR) Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, because PSEG

did not provide adequate work order instructions for the reinstallation of service water

(SW) pump discharge isolation valve EAHV-2198C following planned valve

maintenance in October 2013. Specifically, the inadequate work order instructions

contributed directly to maintenance technicians installing the valve in the opposite

orientation compared to the intended orientation. PSEG entered this issue into their

corrective action program. In addition, PSEGs corrective actions included

completing several associated technical evaluations, calculations, operability

determinations, and motor-operated valve performance tests.

The team determined that the failure to provide adequate work order instructions for the

installation of safety-related SW valve 2198C was a performance deficiency. The team

determined that this performance deficiency was more than minor in accordance with

IMC 0612, Power Reactor Inspection Report, Appendix B, because it was associated with

the procedure quality attribute of the Mitigating Systems Cornerstone and affected the

cornerstone objective of ensuring the availability, reliability, and capability of systems (SW)

that respond to initiating events to prevent undesirable consequences. Additionally, the

team determined that it was more than minor in accordance with IMC 0612, Appendix E,

Example 3j, because PSEGs associated operability and technical evaluations did not

adequately consider the worst case conditions, resulting in a potential underestimation of

the maximum required opening torque and in a condition where there was a reasonable

doubt on the operability of the C SW train. The team evaluated the finding in accordance

with IMC 0609, Appendix A, The Significance Determination Process (SDP) for Findings at

Power, Exhibit 2 - Mitigating Systems Screening Questions, and determined that the finding

was of very low safety significance (Green) because the finding was a deficiency that

affected the design and qualification of safety-related SW valve 2198C but did not result in

the loss of operability or functionality. The team determined that this finding has a cross-

cutting aspect in Human Performance, Documentation, in that PSEG failed to ensure that

design documentation and work packages were complete, thorough, accurate, and current.

(H.7) (Section 1R21.2.1.2)

Other Findings

None

REPORT DETAILS

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R21 Component Design Bases Inspection (IP 71111.21)

.1

Inspection Sample Selection Process

The team selected risk significant components for review using information contained in

the Hope Creek Probabilistic Risk Assessment (PRA) model and the U. S. Nuclear

Regulatory Commissions (NRC) Standardized Plant Analysis Risk (SPAR) model for the

Hope Creek Generating Station (HCGS). Additionally, the team referenced the Plant

Risk Information e-Book (PRIB) for Hope Creek in the selection of potential components

for review. In general, the selection process focused on components that had a Risk

Achievement Worth (RAW) factor greater than 1.3 or a Risk Reduction Worth (RRW)

factor greater than 1.005. The components selected were associated with both

safety-related and non-safety related systems, and included a variety of components

such as pumps, tanks, diesel engines, batteries, electrical buses, circuit breakers, and

valves.

The team initially compiled a list of components based on the risk factors previously

mentioned. Additionally, the team reviewed the previous component design bases

inspection (CDBI) reports and excluded the majority of those components previously

inspected. The team then performed a margin assessment to narrow the focus of the

inspection to 16 components and 5 operating experience (OE) items. The team selected

the suppression pool and a drywell spray valve to review for large early release

frequency (LERF) implications. The teams evaluation of possible low design margin

included consideration of original design issues, margin reductions due to modifications,

or margin reductions identified as a result of material condition/equipment reliability

issues. The assessment also included items such as failed performance test results,

corrective action history, repeated maintenance, Maintenance Rule (a)(1) status,

operability reviews for degraded conditions, NRC resident inspector insights, system

health reports, and industry OE. Finally, consideration was also given to the uniqueness

and complexity of the design and the available defense-in-depth margins.

The team performed the inspection as outlined in NRC Inspection Procedure (IP)

71111.21. This inspection effort included walkdowns of selected components; interviews

with operators, system engineers, and design engineers; and reviews of associated

design documents and calculations to assess the adequacy of the components to meet

design basis, and licensing basis requirements. Summaries of the reviews performed

for each component and OE sample are discussed in the subsequent sections of this

report. Documents reviewed for this inspection are listed in the Attachment.

2

.2

Results of Detailed Reviews

.2.1

Results of Detailed Component Reviews (16 samples)

.2.1.1 C' Emergency Diesel Generator (Electrical Review) and C 4KV Bus 10A403

a. Inspection Scope

The team inspected the C EDG and its associated 4KV electrical bus (10A403) to verify

that they were capable of performing their design functions in response to transients and

accidents. The team reviewed technical specifications (TSs), operating procedures, and

the Updated Final Safety Analysis Report (UFSAR) to determine the licensing and

operating basis for selected electrical components utilized for starting the C EDG and

for connecting the generator to the safety-related C 4KV bus. The team reviewed the

EDG loading design basis requirements for postulated loss-of-coolant accident (LOCA)

and loss-of-offsite power (LOP) conditions. The team reviewed ST results to verify that

operation of the EDG, and selected emergency core cooling system (ECCS) pumps,

conformed to design basis loading requirements. The team reviewed voltage drop

calculations for the diesel air starting solenoids and the generator field flash circuitry to

assure that adequate voltage was available during limiting design basis conditions. The

team interviewed the system engineer, reviewed the system health report, and

performed a walkdown of the C EDG and the C 4KV bus to assess the observable

material condition. The team also reviewed maintenance records and corrective action

documents to ensure that PSEG properly maintained the components and identified and

corrected deficiencies.

b. Findings

Introduction. The team identified a Green non-cited violation (NCV) Title 10 of the Code

of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, because PSEG did not establish appropriate acceptance

criteria for the time allowed for starting the residual heat removal (RHR) and core spray

pumps during simulated LOCA/LOP conditions in the 18-month integrated EDG ST for

the vital 4KV buses. Specifically, the ST acceptance criteria failed to confirm that the

pumps started in accordance with the design basis loading sequence described in the

design analyses and UFSAR Table 8.3-1.

Description. The team noted that the start time acceptance criteria in the 18-month

integrated C EDG ST for the RHR and core spray pump motors in HC.OP-ST.KJ-0007,

Steps 5.4.8.S and 5.4.8.V, respectively, was 40 seconds and 27 seconds, respectively,

after initiation of a simulated LOCA/LOP condition. Based on a review of the General

Electric (GE) design drawings for the RHR and core spray pump start circuits, the team

noted that the RHR pump was designed to start immediately when 4KV bus power was

available either during a LOCA condition (with offsite power available) or during

LOCA/LOP conditions after the EDG established bus power, and then for the core spray

pump to start six seconds later by a timer circuit which was initiated when the bus power

was available.

3

The team identified that the integrated EDG 18-month ST acceptance criteria did not

correctly incorporate the GE pump start design criteria for the RHR and core spray

pumps. For example, the EDG was designed to establish bus power nominally within

13-seconds after LOCA conditions and the RHR pump should then start immediately, but

the ST acceptance criteria allowed for the pump to start up to 27 seconds later

(40 seconds minus the 13 seconds for power to be established by the EDG after the

LOCA conditions are detected). In addition, although the RHR pump should start

immediately when the EDG breaker closes and 4KV power is available, followed

6 seconds later by the core spray pump in accordance with GE criteria, the acceptance

criteria for the RHR pump was 40 seconds and 27 seconds for the core spray pump.

These acceptance criteria could allow the core spray pump to start before the RHR

pump, resulting in an unanalyzed condition contrary to the design basis loading

sequence described in the design analyses and UFSAR Table 8.3-1. In fact, the team

identified that technicians recorded pump start times in the last integrated B EDG

18-month ST conducted in April 2015 that indicated that the core spray pump had

started before the RHR pump, which would have been contrary to the GE design criteria

for the pump starting sequence. The team also noted that PSEG had failed to identify

this test anomaly during their post-test acceptance review. The team noted that PSEG

had based the ST acceptance criteria on the maximum time for pump flow to be

delivered to the reactor vessel and not the designed pump start time for the RHR and

core spray pumps. Based on this, the team concluded that the ST start time acceptance

criteria for the RHR and core spray pumps was incorrect and non-conservative. During

the inspection, upon further review of the plant historical data and strip chart recordings

from the April 2015 test, PSEG determined that the RHR and core spray pump start

times recorded by the technicians were inadvertently swapped in the ST

documentation as the actual recorded test data confirmed that the RHR pump actually

started before the core spray pump in accordance with the GE design. This

NRC-identified test discrepancy was neither identified nor evaluated by PSEG during

their review of the test results in April 2015.

Notwithstanding, upon further review of the swapped data, the team found that the core

spray pump started approximately 3.8 seconds after the EDG breaker was closed to

establish bus power. However, starting the core spray pump 3.8 seconds after power

was established during a LOCA/LOP was not in accordance with TS acceptance criteria

for the minimum time for the core spray pump to start which was 5 seconds (6 seconds

+/- 1 second) when power was available. For this case, during the inspection, PSEG

engineers reviewed the strip chart recorder record traces for the EDG voltage and

frequency conditions during the core spray pump start and confirmed that the voltage

and frequency recovered within acceptable limits, thereby assuring EDG operability.

Based on a review of the two most recent LOCA/LOP STs for each 4KV vital bus

(completed in the Fall of 2013 and the Spring of 2015), the team also identified several

additional examples of discrepant RHR and core spray pump start time data in the

recorded and accepted test results. These discrepancies included:

1. During the A EDG test in 2013, the core spray pump started only 3 seconds

after bus power was established by the EDG (the TS minimum acceptance

limit was 5 seconds as noted above). During the D EDG test in 2013, the

core spray pump started 4.9 seconds after power was established, which was

4

also not in accordance with the minimum TS acceptance limit. Subsequent

STs performed since 2013 confirmed the proper operation and operability for

the subject core spray pumps.

2. For the A EDG test in 2015, for the corrected data for the B EDG test in

2015, and for the C EDG test in 2013, the recorded test data indicated that

the RHR pump started before the EDG breaker was closed to establish bus

power. The team noted that this condition was not possible based upon a

review of GEs design drawings for the RHR pump start circuit.

Based upon further review and discussions onsite, the team noted that the accuracy of

technicians recorded data was questionable and that some (see item 2 above), but not

all, of the above discrepant conditions could be due to technician response time when

using a stopwatch to record pump start times. Once again, the above NRC-identified

discrepancies were neither identified nor evaluated by PSEG during their review of the

test results at the time of the testing.

The team noted that the non-conservative ST acceptance criteria for the RHR and core

spray pump start times had the potential to mask conditions where equipment performed

outside expected design limits, and these conditions could neither be detected nor

evaluated by PSEG for impact to plant equipment and systems. PSEG initiated

notification (NOTF) 20706543 to evaluate test results for any adverse trend in pump start

times and NOTF 20706542 to evaluate the ST test acceptance criteria for the RHR and

core spray pump start times.

Analysis. The team determined that the failure to specify adequate acceptance limits for

the design basis assigned start times for the RHR and core spray pumps during

LOCA/LOP conditions in the 18-month integrated EDG ST procedure was a performance

deficiency. The team determined that this finding was more than minor because it was

associated with the procedure quality attribute of the Mitigating Systems Cornerstone

and affected the cornerstone objective of ensuring the availability, reliability, and

capability of systems that respond to initiating events to prevent undesirable

consequences. Specifically, PSEG failed to identify appropriate EDG loading

acceptance criteria for the RHR and core spray pump motor start timing that was used in

the ST to confirm that safety-related equipment was operating in accordance with the

limits specified in the design analyses. The team evaluated the finding in accordance

with Inspection Manual Chapter (IMC) 0609, Appendix A, The Significance

Determination Process (SDP) for Findings at Power, Exhibit 2 - Mitigating Systems

Screening Questions, and determined that the finding was of very low safety significance

(Green) because the finding was a design deficiency that did not result in the loss of

operability or functionality. The team determined that this finding had a cross-cutting

aspect in Human Performance, Documentation, in that PSEG failed to maintain accurate

test acceptance documentation to aid plant staff in the identification of equipment

performance that was outside the acceptable limits of design. (H.7)

Enforcement. Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures,

and Drawings, states, in part, that procedures shall include appropriate quantitative or

qualitative acceptance criteria for determining that important activities have been

5

satisfactorily accomplished. Contrary to the above, prior to October 22, 2015, PSEG

had not established appropriate acceptance criteria in HC.OP-ST.KJ-0007, Steps 5.4.8.S

and 5.4.8.V, respectively, for the time allowed for starting the RHR pump and core spray

pumps during simulated LOCA/LOP conditions in the 18-month integrated EDG ST for

the vital 4KV buses.

Specifically, the ST acceptance criteria failed to confirm that the pump(s) starting would

be in accordance with the design basis loading sequence described in design analyses

and UFSAR Table 8.3-1, Emergency Loads Assignment of Class 1E and Selected

Non-Class 1E Loads on Standby Diesel Generator Buses. PSEGs short-term

corrective actions included reviewing LOCA/LOP test results and plant historical data to

confirm current operability of the RHR and core spray pumps and initiating corrective

action NOTFs to determine the appropriate ST acceptance criteria and trend pump start

times. Because this finding was of very low safety significance and because it was

entered into PSEGs corrective action program (NOTFs 20706542 and 20706543), this

violation is being treated as an NCV, consistent with Section 2.3.2 of the NRC

Enforcement Policy. (NCV 05000354/2015007-01, Failure to Establish Appropriate

Acceptance Criteria for RHR and Core Spray Pump Start Times during Simulated

LOCA/LOP Testing)

.2.1.2 Service Water Pump Discharge Valves (EAHV- 2198C and EAHV- 2198D)

a. Inspection Scope

The team reviewed applicable portions of TSs, the UFSAR, and system design basis

documents (DBDs) to identify design basis requirements for service water (SW) pump

discharge valves EAHV-2198 C and D. The team reviewed drawings and vendor

documents to verify that the installed configuration of the valves and their Limitorque

motor operators supported the design basis function under normal and accident

conditions. The team reviewed the valves orientation and their distance from elbows

and from the pumps discharge check valves to assess possible cavitation and flow

disturbances. The team interviewed the system engineer and the motor-operated valve

(MOV) engineer to discuss the valves analyses and operational and maintenance

history, and to verify that PSEG appropriately addressed potentially degraded conditions.

The team reviewed test procedures and recent test results against design bases

documents to verify that acceptance criteria for tested parameters were supported by

calculations or other engineering documents and that individual tests and analyses

served to validate component operation under accident conditions. The team also

reviewed MOV test data and valve operator test traces to validate that the torque

required to open the valves did not exceed the rating of their Limitorque operators. The

team reviewed vendor documentation, system health reports, preventive and corrective

maintenance history, and corrective action system documents to verify that potential

degradation was monitored or prevented, and that scheduled component inspections or

replacements were consistent with trend data and vendor recommendations. The team

conducted several detailed walkdowns to visually inspect the physical/material condition

of the valves, their motor operators and support systems, and to ensure adequate

configuration control.

6

b. Findings

Introduction. The team identified a Green NCV of 10 CFR Part 50, Appendix B, Criterion

V, Instructions, Procedures, and Drawings, because PSEG did not provide adequate

work order instructions for the installation of SW pump discharge isolation valve 2198C

following planned valve maintenance in October 2013. Specifically, the inadequate work

order instructions contributed directly to maintenance technicians installing the valve in

the opposite orientation compared to the intended orientation.

Description. 1EAHV-2198C is the C SW pump discharge isolation valve. The valve is a

28-inch Weir Tricentric butterfly valve with a SMB-1/HBC-4 (60-1) Limitorque motor

operator. The valve has an active safety function in the open position to provide normal

SW flow to the safety-related safety auxiliaries cooling system (SACS) heat exchangers

(HXs) and non-1E reactor auxiliaries cooling system (RACS) HXs, and emergency SW

flow to other systems. PSEG had originally intentionally installed all four 1EAHV-2198

valves in the reverse flow direction to permit the downstream header pressure to seat

the valve tighter to minimize seat leakage during SW pump and strainer on-line

maintenance. During refueling outage 18 (RF18) in October 2013, PSEG performed a

planned refurbishment of the 2198C valve and SMB-1 actuator under work order

60112463-410, Step 1.D. On October 22, 2013, maintenance technicians initiated

NOTF 20626219 to document that while installing the 1EAHV-2198C adapter plate, they

noticed that the valve was installed 180 degrees different from where it was removed

and requested support. The NOTF also documented that the MOV engineer agreed that

reconfiguring the valve operator would be the easiest way to correct the issue. In an

October 23, 2013, update to the NOTF, maintenance stated that they had applied match

marks to ensure that the valve would be installed in the same orientation, but during the

course of the work the match marks were erased. Maintenance also updated the NOTF

to reflect that they had identified that the 2198 valve installation orientation design

specification was not documented in valve drawing M-10-1 or the vendor manual (VTD

323981) as expected. The team also noted that several diagrams within the work order

depicted the wrong valve orientation and may have contributed to the configuration

control error. Finally, the team noted that there was no documented evaluation of the

impact of this misalignment and configuration error prior to operations declaring the C

SW pump operable following the 2198C maintenance on October 23. PSEG initiated

NOTF 20705874 for this operability screening performance gap.

Based on the narrative logs, the team noted that operators started and stopped the

C SW pump several times during the period October 23 - 26, 2013 (with proper

function of the 2198C). At 10:59 p.m. on October 26, 2013, operators started the C SW

pump (in support of the ongoing A LOCA/LOP ST), but the 2198C failed to open.

Operators promptly initiated NOTF 20627235 and entered an unplanned TS limiting

condition for operation (LCO) for the C SW pump. PSEG performed troubleshooting

and identified that a high opening torque (> ~ 9500 ft-lbs) tripped the torque switch

removing power to the valve actuator and resulting in a failure to stroke. PSEG bumped

up the torque switch setting to ~ 13,200 ft-lbs and successfully stroked the valve open.

At 4:44 p.m. on October 27, 2013, while stroking open the valve, engineers recorded a

maximum opening torque of 10,201 ft-lbs via a MOV dynamic trace. At 8:53 p.m. on

October 27, 2013, operators declared the C SW pump operable and exited the TS LCO.

7

The team noted that there was no apparent documented evaluation of the cause of the

unexpected high opening torque or an assessment of the recorded maximum opening

torque (10,201 ft-lbs) relative to the maximum expected opening torque under design

basis conditions compared to the MOVs weak link analysis and Limitorque limits.

On February 7, 2014, Weir Valves & Controls USA filed an Interim 10 CFR Part 21

Report for a potential failure associated with Weir valves installed in the forward flow

orientation (like the 2198C valve). Based on testing (by PSEG and Weir in December

2013), Weir determined that there existed an unseating load which was not accounted

for in Weir's Tricentric triple offset product line operator sizing methodology. A potential

operator sizing issue could exist on Tricentric valves which have an open safety function

during an event. Weir identified that the direction of flow across the non-symmetrical

disc had an impact on the torque required to open/close the valve. PSEG initiated

NOTF 20639544 and order 70163546 to evaluate and resolve the potential issue. For

Hope Creek, PSEG determined that 17 MOVs could be affected by this issue. The

preliminary evaluation under order 70163546-020 only identified one potential

operational issue requiring any further evaluation (the 1EAHV-2198C valve that

maintenance had installed backwards during RF18, prior to the issuance of the Part 21).

For this installation, the maximum differential pressure (DP) only exists on the inlet side

of the disc during disc opening when the C SW pump is the first pump started in the

A SW loop. Engineering determined that the required stem torque to open the 2198C

valve was above the component rating. PSEGs MOV program procedure guidance

allows this condition (up to 113 percent of the rated torque) for a limited number of

strokes (100). PSEG also initiated NOTF 20673076 to reverse the flow direction of the

valve during RF20 in October 2016, so the allowed strokes would not be exceeded. In

addition, PSEG performed a technical evaluation to assess the adequacy of MOV

1EAHV-2198C in its installed orientation and evaluated it for a Use-As-Is interim

disposition as defined by PSEG procedure CC-AA-11 (70163546-070).

While performing the technical evaluation, engineering identified that the 2198C opening

torque would exceed the 113 percent rated torque (14,464 ft-lbs) if they used the SW

pump shutoff head in their calculation of maximum DP. PSEG contracted with MPR

Associates to perform a more detailed evaluation. MPRs associated calculation

reduced the required opening torque from 17,479 ft-lbs to 13,814 ft-lbs (108 percent of

the Limitorque limit). The team observed that PSEGs associated technical evaluation

noted the high opening torque (10,201 ft-lbs) recorded on October 27, 2013; however,

the evaluation only cited it as evidence that the opening torque remained acceptable

when opening the 2198C valve (while starting the C SW pump) with the A SW pump

running under normal operating conditions (less than the maximum DP expected under

design basis conditions). The team noted that there was no apparent documented

evaluation comparing the recorded actual opening torque (10,201 ft-lbs) to the expected

opening torque (calculated based on the DP at the time) to ensure validity and

applicability of the Weir calculation methodology.

During the 2015 CDBI, based on the extremely high opening torque recorded under

normal conditions and the valves lack of margin, the team questioned the operability of

the 2198C valve to function under design basis conditions (starting the C SW pump

without the A SW pump running). Based on the teams concern, engineering initiated

8

NOTF 20704783 to perform a technical evaluation to determine if the 2198C actuator

was capable of opening the valve under all required conditions based on the actual

measured data. Engineering used conservative assumptions and appropriate

engineering rigor to determine the approximate DP that existed when the 2198C valve

opened on October 27, 2013, when the dynamic MOV trace recorded an opening torque

of 10,201 ft-lbs. Engineering estimated the DP at 50.2 pounds square inch differential

(PSID). PSEG entered this DP into the Weir spreadsheet (provided with the associated

Interim Part 21 Report) and noted that it resulted in a much lower required opening

torque (8,375 ft-lbs compared to 10,201 ft-lbs). The apparent disparity between the

measured value (10,201 ft-lbs) and the calculated value (8,375 ft-lbs) affirmed the teams

concern that other factors may be at play affecting the torque required to open this

particular valve and/or called into question the validity of the Weir spreadsheet

calculation for this particular configuration (parallel pump operation, closing the

discharge isolation valve with the parallel pump running). Based on the 21.8 percent

difference between the calculated Weir expected opening torque of 8,375 ft-lbs at 50.2

PSID and the measured torque of 10,201 ft-lbs, PSEGs technical evaluation

(70180794-010) added an additional 3,039 ft-lbs (22 percent) to the Weir expected

maximum opening torque of 13,814 ft-lbs at the MPR calculated maximum DP of 80.7

PSID to bound the potential impact.

This resulted in an expected maximum opening torque of 16,853 ft-lbs utilizing the Weir

Tricentric unseating torque evaluation model. However, PSEG recognized that this final

expected torque would exceed the Limitorque 113 percent rating of 14,464 ft-lbs,

requiring additional analysis. To ensure sufficient torque margins, PSEG contracted with

Kalsi Engineering to perform H4BC gear box torque analyses for the 2198C valve.

Based on the Kalsi analysis, the EAHV-2198C H4BC gear box can continue to operate

safely for at least 9 cycles (open strokes) at an opening torque level up to 20,000 ft-lbs.

In addition, PSEGs technical evaluation noted that the torque switch is bypassed during

C SW pump starts under LOCA/LOP conditions ensuring that the torque switch would

not preclude valve opening if the open torque exceeded 13,200 ft-lbs. Based on the

Kalsi analysis and bypass of the open torque switch under accident conditions, the team

concurred with PSEGs determination that the 2198C valve remained operable (although

non-conforming).

The team noted that PSEGs technical evaluation also credited starting the C SW pump

twice in RF19 in April 2015, with the A SW pump not running, demonstrating that the

EAHV-2198C valve was fully capable of opening under the worst case condition (highest

expected DP) without tripping the torque switch (not needing the additional torque

margin calculated by Kalsi). The team independently reviewed the operator narrative

logs and plant historical SW flow data associated with the two credited C SW pump

starts to verify that the conditions actually represented worst case conditions. The team

confirmed that the A SW pump was indeed out of service when operators started the

C SW pump on both occasions. However, the team identified that the A SW pump was

also not running on both occasions when the operators stopped the C SW pump. More

importantly, the A SW pump discharge pressure was not present on the backside of the

2198C valve while it was closing (prior to the subsequent opening). The team recalled

that the Weir Interim Part 21 Report stated that the DP across the valve while closing the

valve made a noted difference to the subsequent unseating torque when re-opening the

9

valve. The team noted that the A SW pump was running when closing the 2198C on

both occasions in October 2013 prior to the 2198C experiencing a relatively high torque

on the subsequent opening. Thus, based on the facts and actual plant configuration

during the October 2013 and April 2015 C SW pump starts, the team determined that

the C SW pump starts in April 2015 did not adequately demonstrate the capability of the

2198C valve to function under worst case design basis conditions, and could not be

credited solely to confirm continued operability of the 2198C. Also, based on the

information provided during the inspection, the team noted that Weirs testing in support

of their February 2014 Interim Part 21 Report did not include parallel pump combinations

and potential effects of closing the subject valve with the redundant (parallel) pump in

service.

During the inspection, the team also noted that engineering did not completely and

accurately follow PSEG procedure CC-AA-11, Nonconforming Materials, Parts, or

Components, during their technical evaluation in response to the Weir Interim Part 21

Report (70163546-070). In particular, the team identified that engineering did not enter

the operability determination process (OP-AA-108-115) as required by procedure

CC-AA-11 for safety-related components which would likely had resulted in a

determination of operable but non-conforming for the degraded 2198C valve. The team

noted that this represented a minor procedure violation; however, failing to properly

classify the condition as operable non-conforming represented a potential missed

opportunity as PSEG management may have elected to correct the condition in May

2015 (RF19). PSEG initiated NOTF 20707031 for this issue.

The team noted that PSEG identified the underlying performance deficiency (less than

adequate work order instructions and drawings) associated with the issue of concern

discussed above. However, in accordance with NRC IMC 0612, NRC-identified findings

include issues initially identified by the licensee to which the inspector has identified a

previously unknown weakness in the licensees classification, evaluation, or corrective

actions associated with the licensees correction of a finding or violation (i.e., NRC

added value). As noted above, the NRC-identified PSEG shortcomings included:

operability determination screenings and evaluations, procedure use and adherence,

and adequacy of engineering rigor and questioning attitude in technical evaluations.

Analysis. The team determined that the failure to provide adequate work order

instructions for the installation of safety-related SW isolation valve 2198C was a

performance deficiency. Specifically, PSEG did not provide adequate instructions and

drawings for the reinstallation of valve 2198C, which was previously removed for

maintenance, nor did PSEG adequately analyze the resulting condition. The team

determined that this performance deficiency was more than minor because it was

associated with the procedure quality attribute of the Mitigating Systems Cornerstone

and affected the cornerstone objective of ensuring the availability, reliability, and

capability of systems (SW) that respond to initiating events to prevent undesirable

consequences. Additionally, the team determined that it was more than minor in

accordance with IMC 0612, Power Reactor Inspection Reports, Appendix B, and

Appendix E, Example 3j, because PSEGs associated operability and technical

evaluations did not adequately consider the worst case conditions, resulting in a

10

potential underestimation of the maximum required opening torque and in a condition

where there was a reasonable doubt on the operability of the C SW train.

The team evaluated the finding in accordance with IMC 0609, Appendix A, The

Significance Determination Process (SDP) for Findings at Power, Exhibit 2 - Mitigating

Systems Screening Questions, and determined that the finding was of very low safety

significance (Green) because the finding was a deficiency that affected the design and

qualification of safety-related SW valve 2198C but did not result in the loss of operability

or functionality. The team determined that this finding had a cross-cutting aspect in

Human Performance, Documentation, in that PSEG failed to ensure that design

documentation and work packages were complete, thorough, accurate, and current.

(H.7)

Enforcement. Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures,

and Drawings, states in part, that activities affecting quality shall be prescribed by

documented instructions, procedures, or drawings, of a type appropriate to the

circumstances and shall be accomplished in accordance with these instructions,

procedures, or drawings. Contrary to the above, on October 22, 2013, PSEG did not

provide proper procedures for the installation of SW pump discharge isolation valve

EAHV-2198C in work order 60112463-410, Step 1.D, after it was removed from service

during RF18 for maintenance activities. Because this violation is of very low safety

significance and has been entered into PSEGs corrective action program (NOTF

20704783), this violation is being treated as a NCV consistent with Section 2.3.2 of the

NRC Enforcement Policy. (NCV 05000354/2015007-02, Inadequate Work Order

Instructions and Drawings Resulting in Improper Installation of a Safety-Related

SW Valve)

.2.1.3 High Pressure Coolant Injection Steam Supply Isolation Valve (FD-HV-F001) and Steam

Supply Piping

a. Inspection Scope

The team inspected the high pressure coolant injection (HPCI) turbine steam supply

outboard containment isolation (FD-HV-F001) to verify that it was capable of performing

its design function in response to transients and accidents. The normally closed

FD-HV-F001 valve is required to open for the HPCI system to perform its ECCS function

and is required to close to isolate the main steam line and reactor vessel to prevent

depressurization in case of a HPCI steam line break. The team reviewed applicable

portions of Hope Creeks TSs, the UFSAR, and the HPCI system DBD to identify design

basis requirements for FD-HV-F001.

The team reviewed design calculations, including environmental qualifications, valve

specifications, and the operating history to verify that the valve was acceptable for HPCI

service, and to verify that it met the applicable American Society of Mechanical

Engineers (ASME) Code in-service testing requirements. The team reviewed a sample

of ST results to verify that valve performance met the acceptance criteria and that the

criteria were consistent with the design basis. The team interviewed the system

engineer and reviewed MOV diagnostic test results and trending to assess valve

11

performance capability and design margin. The team reviewed a sample of HPCI

system corrective action NOTFs, technical evaluations, the HPCI system health report,

and applicable test results to determine if there were any adverse operating trends and

to ensure that PSEG adequately identified and addressed any adverse conditions. The

team also performed several walkdowns of the valve, adjacent area, accessible portions

of the HPCI system steam piping, and associated control room instrumentation to

assess the material condition, operating environment, and configuration control.

b. Findings

No findings were identified.

.2.1.4 C and D Service Water Strainers and Motors (1C-F-509 & 1D-F-509)

a. Inspection Scope

The team inspected the C and D SW strainers to evaluate whether they were capable

of meeting their design basis and operational requirements to pass the required SW flow

rate while maintaining the SW system reasonably clean, to prevent debris from plugging

the safety-related SACS HXs, and to prevent a high pressure drop across the strainers

under all accident conditions. The team evaluated the strainers pressure drop and the

adequacy of their continuous backwash function to ensure continuous operation without

impeding the proper operation of the SW System. The team reviewed monthly testing,

flow rates and pressure drops as well as acceptance criteria affecting the strainers

function to verify that they were capable of performing their safety function and to

determine if PSEG had adequately evaluated the potential for strainer degradation. The

team interviewed the system and design engineers to assess the material condition of

the strainers and scheduled maintenance activities. The team conducted several

detailed walkdowns to visually inspect the physical/material condition of the strainers,

their motors, and their support systems to validate their design details such as the

seismic support of the cantilevered motor located at the top of each strainer, and to

ensure adequate configuration control. Finally, the team reviewed corrective action

documents and system health reports to evaluate whether there were any adverse

operating trends and to assess PSEGs ability to evaluate and correct problems.

b. Findings

No findings were identified.

.2.1.5 Safety Auxiliaries Cooling System Air-Operated Valves EG-AOV-2457B and

EG-AOV-2520B

a. Inspection Scope

The team inspected SACS air operated valves (AOVs) EG-AOV-2457B and

EG-AOV-2520B to verify that they were capable of performing their design function. The

SACS system has a safety-related function to provide cooling water to the engineered

safety features (ESFs) equipment, including the RHR pumps and HXs, during normal

12

operation, normal plant shutdown, LOP, and a LOCA. The 2457B valve is the SACS HX

temperature control bypass isolation valve. This valve is normally open and has an

active safety function to close to prevent flow diversion around the SACS HXs, which

could prevent the SACS system from performing its design heat removal safety function.

This valve has no safety function in the open position. The 2520B valve is the B RHR

pump cooler SACS supply valve. This valve has an active safety function in the open

position to provide SACS cooling water flow to the B RHR pump seal and motor bearing

coolers. This valve has no safety function in the closed position. The valve fails open on

loss of power or air and automatically opens on a B RHR pump start.

The team reviewed the UFSAR, calculations, associated TSs, and procedures to identify

the design basis requirements of the valves. The team also reviewed accident system

alignments to determine if component operation would be consistent with the design and

licensing bases assumptions. The team also reviewed valve testing procedures and

valve specifications to ensure consistency with design basis requirements. The team

reviewed periodic verification diagnostic test results and stroke test documentation to

verify acceptance criteria were met and consistent with the design basis. The team

interviewed the AOV program engineer to gain an understanding of maintenance issues

and overall reliability of the valves. The team conducted a walkdown to assess the

material condition of the valves, associated piping and supports, and to verify that the

installed valve configuration was consistent with design basis assumptions and plant

drawings. The team also reviewed the maintenance and operating history of the valves,

the SACS system health report, and applicable system test results to determine if there

were any adverse operating trends and to ensure that PSEG adequately identified and

addressed any adverse conditions. Finally, the team reviewed specific corrective action

documents to verify that PSEG appropriately identified and resolved deficiencies, and

properly maintained the valves.

b. Findings

No findings were identified.

.2.1.6 C 125 Volt Direct Current Battery

a. Inspection Scope

The team reviewed the design, testing, and operation of the C 125 volt direct current

(Vdc) station battery (1CD411) to verify that it was capable of performing its design

function of providing a reliable source of direct current (DC) power to connected loads

under operating, transient, and accident conditions. The team reviewed design

calculations to assess the adequacy of the batterys sizing to ensure that it could power

the required equipment for a sufficient duration, and at a voltage above the minimum

required for equipment operation. The team reviewed short circuit and breaker

coordination calculations to ensure that breakers were adequately sized and were

capable of interrupting short circuit faults. The team verified that proper breaker

coordination existed to provide adequate isolation of the affected portion of the circuit.

The team reviewed battery test results to ensure that the testing was in accordance with

13

design calculations, the HCGS TSs, and industry standards, and that the results

confirmed acceptable performance of the battery. The team interviewed design

engineers regarding design margin, operation, and testing of the DC system. The team

performed a walkdown of the battery, DC buses, battery chargers, and associated

distribution panels to assess the material condition, configuration control, and the

operating environment. Finally, the team reviewed a sample of corrective action NOTFs

to ensure that PSEG identified and properly corrected issues associated with the

C 125 Vdc (1CD411) station battery.

b. Findings

No findings were identified.

.2.1.7 Suppression Pool Water Level, Temperature, and Water Quality Control

a. Inspection Scope

The team inspected the suppression pool to verify that it was capable of performing its

design function. The team reviewed the design basis documents pertaining to the

suppression pool (torus) and the applicable sections of the UFSAR to determine the

design requirements. The team also reviewed torus internal coating inspection results

from inspections performed during the last two refueling outages to assess the material

condition and structural integrity of the torus. The team reviewed recent pressure

suppression chamber to drywell vacuum breaker and pressure suppression chamber to

reactor building vacuum breaker test results to verify that the vacuum breakers remained

operable and capable of performing their design function supporting suppression pool

integrity. The team also reviewed associated corrective action NOTFs, and applicable

instrumentation and control test results for the suppression pool temperature, pressure,

and level instruments to determine if there were any adverse trends and to ensure that

PSEG adequately identified and addressed any adverse conditions. The team

conducted an extensive walkdown of the accessible portions of the exterior of the torus

structure to assess the material condition (including evidence of leakage), structural

supports, potential hazards, and configuration control.

b. Findings

No findings were identified.

.2.1.8 C Emergency Diesel Generator Load Sequencer

a. Inspection Scope

The team reviewed TSs, the UFSAR, and system DBDs to identify design basis

requirements for the emergency load sequencer (ELS). The team reviewed drawings

and vendor documents to verify that the installed configuration supported the design

basis function under accident conditions. The team interviewed the system engineer,

reviewed the system health report, and performed several walkdowns of the ELS cabinet

to assess the observable material condition and operating environment. The team also

14

verified that the location and installation of the cabinet mounting fasteners were in

accordance with the installation drawings to ensure seismic adequacy. The team

reviewed test procedures and recent test results against DBDs to verify that acceptance

criteria for the tested sequenced time parameters were supported by calculations or

other engineering documents and that individual tests and analyses served to validate

component operation under accident conditions. The team reviewed vendor

documentation, system health reports, preventive and corrective maintenance history,

and corrective action system documents in order to verify that potential degradation was

monitored or prevented, and that scheduled component inspections or replacements

were consistent with vendor recommendations.

b. Findings

No findings were identified.

.2.1.9 Emergency Diesel Generator Fuel Oil Transfer Pumps

a. Inspection Scope

The team reviewed applicable portions of TSs, the UFSAR, and system DBDs to identify

design basis requirements for the EDG fuel oil transfer pumps (FOTPs). The team

inspected the FOTPs to evaluate whether they were capable of meeting their design

basis and operational requirements to maintain each EDG fuel oil day tank (FODT) with

sufficient fuel oil and with a flow rate greater than the peak fuel oil consumption rate of

the EDGs under all accident conditions, including LOP. The team evaluated the pumps

net positive suction head (NPSH) and suction under the minimum level at the storage

tank to ensure that pump operation would not be disrupted. The team reviewed the

sizing of the FODTs and the levels associated with the FOTPs start and stop to verify

that the TS-required fuel oil quantity was not compromised. The team reviewed flow rate

testing and in-service test (IST) results to verify that the pump performance bounded the

analyzed performance of each of the eight FOTPs, and to determine if PSEG had

adequately evaluated the potential for pump degradation. The team interviewed the

system and design engineers to assess the material condition of the FOTPs and

scheduled maintenance activities. The team also conducted several detailed walkdowns

to visually inspect the physical/material condition of the FOTPs and their support

systems, to validate the data associated with the instruments supporting FOTP

operation, and to ensure adequate configuration control. Finally, the team reviewed

corrective action documents and system health reports to evaluate whether there were

any adverse operating trends and to assess PSEGs ability to evaluate and correct

problems.

b. Findings

No findings were identified.

15

.2.1.10 A Safety Auxiliaries Cooling System Expansion Tank and A Safety Auxiliary

Cooling System Piping Integrity

a. Inspection Scope

The team reviewed the design, testing, inspection, and operation of the A SACS

expansion tank (1-EG-1AT-205), its associated tank level instruments, and associated

piping to evaluate whether it could perform its design basis function. The team reviewed

design calculations, drawings, and vendor specifications (including tank sizing and level

uncertainty analysis) to evaluate the adequacy and appropriateness of design

assumptions and operating limits. The team interviewed engineers, and reviewed test

records, alarm response procedures, and operating procedures to evaluate whether

maintenance and testing were adequate to ensure reliable operation, and to evaluate

whether those activities were performed in accordance with regulatory requirements,

industry standards, and vendor recommendations. The team also conducted walkdowns

of the tank and associated piping and supports to assess the material condition. Finally,

the team reviewed corrective action documents and system health reports to evaluate

whether there were any adverse trends associated with the A SACS expansion tank

and to assess PSEG's ability to evaluate and correct problems.

b. Findings

No findings were identified.

.2.1.11 A 250 Volt, Direct Current Motor Control Center (10D251)

a. Inspection Scope

The team reviewed the design, testing, and operation of the A 250 Vdc motor control

center (MCC) to verify its ability to meet design basis requirements during plant

transients and accidents. The MCC provides 250 Vdc power to HPCI system main and

auxiliary components, including the HPCI steam supply isolation valve (FD-HV-F001).

The team interviewed design engineers regarding design margin, operation, and testing

of the DC system. The team performed several walkdowns of the MCC to assess the

material condition, configuration control, and the operating environment. The team

reviewed HPCI MCC internal inspection preventive maintenance (PM), battery sizing

calculations, and voltage drop calculations. Finally, the team reviewed a sample of

corrective action NOTFs to ensure that PSEG identified and properly corrected issues

associated with the HPCI MCC.

b. Findings

No findings were identified.

16

.2.1.12 Drywell Spray Valve (BC-HV-F021B)

a. Inspection Scope

The team inspected the B drywell spray valve (BC-HV-F021B) to verify that it was

capable of performing its design function in response to transients and accidents. The

normally closed drywell spray valve has a safety function in the open position to allow

the RHR system to perform its containment cooling function of reducing and maintaining

primary containment pressure and temperature to within acceptable limits following a

LOCA. The drywell spray valve also has a safety function to close to provide a primary

containment isolation. The team reviewed applicable portions of Hope Creeks TSs, the

UFSAR, and the RHR system DBD to identify design basis requirements for

BC-HV-F021B. The team reviewed design calculations, including environmental

qualifications, valve specifications, and the operating history to verify that the valve was

acceptable for RHR service, and to verify that it met the applicable ASME Code

in-service testing requirements. The team reviewed a sample of ST results to verify that

valve performance met the acceptance criteria and that the criteria were consistent with

the design basis. The team interviewed the system engineer, and reviewed MOV

diagnostic test results and trending to assess valve performance capability and design

margin. The team reviewed a sample of related RHR system corrective action NOTFs,

technical evaluations, the RHR system health report, corrective and preventive

maintenance records, and applicable test results to determine if there were any adverse

operating trends and to ensure that PSEG adequately identified and addressed any

adverse conditions. The team also performed a walkdown of both drywell spray valves

(F021A and F021B), accessible portions of the RHR system piping, and associated

control room instrumentation to assess the material condition, operating environment,

and configuration control.

b. Findings

No findings were identified.

.2.1.13 C Residual Heat Removal Pump Breaker, C Service Water Pump Breaker, and

C Emergency Diesel Generator Output Circuit Breaker

a. Inspection Scope

The team reviewed TSs, the UFSAR, and system DBDs to identify design basis

requirements for the C RHR and C SW pump motors and the C EDG output circuit

breakers. The team reviewed voltage drop calculations for the breaker closing circuits to

assure that adequate voltage was available during limiting design basis conditions. The

team also reviewed the current system health report, selected drawings and

calculations, maintenance and test procedures, and corrective action NOTFs associated

with the C RHR and C SW pump motors and the C EDG output circuit breakers.

Specifically, the team reviewed the pump maximum brake horsepower requirements to

confirm the adequacy of the motor capability to supply power during worst case design

conditions. The team reviewed the adequacy of motor starting and running during

degraded offsite voltage conditions coincident with a postulated design basis accident.

17

The team verified motor overcurrent relay settings and periodic relay calibration test

results for adequacy to ensure reliable motor operation during the most limiting design

basis operating conditions. The team interviewed the system engineers and performed

several walkdowns of the motors and the associated 4KV switchgear, including the

control room panels, to assess the observable material condition, configuration control,

and operating environment.

b. Findings

No findings were identified.

.2.1.14 Emergency Instrument Air Compressor (10K100) and Instrument Air Header Piping

a. Inspection Scope

The team reviewed the design, testing, inspection, and operation of the emergency

instrument air compressor (EIAC) and instrument air header piping to evaluate whether

they could perform their design basis function. The non-safety related service air (SA)

system supplies normal air to the instrument air (IA) system. The IA system is also

non-safety related; however, it is important to safety and has a high risk function to

provide clean, dry, oil-free air at the normal temperature and pressure for the

air-operated instruments and devices throughout the plant. The EIAC provides the

motive force required to maintain IA system pressure should both SA compressors be

non-operational.

The team reviewed design calculations, drawings, system modifications, and vendor

specifications to evaluate the adequacy and appropriateness of design assumptions and

operating limits. The team interviewed engineers, and reviewed test records, alarm

response procedures, and operating procedures to evaluate whether maintenance and

testing were adequate to ensure reliable operation, and to evaluate whether those

activities were performed in accordance with regulatory requirements, industry

standards, and vendor recommendations. The team also conducted several walkdowns

of the SA compressors, IA dryers, EIAC, local alarm panels, associated control room

instrumentation, and accessible IA piping and supports to assess the material condition,

configuration control, and operating environment. Finally, the team reviewed corrective

action documents and system health reports to evaluate whether there were any

adverse trends associated with the EIAC or IA system and to assess PSEG's ability to

evaluate and correct problems.

b. Findings

No findings were identified.

18

.2.1.15 C 125Vdc Bus 10D430 and Distribution Panel 1CD417

a. Inspection Scope

The team inspected the C 125 Vdc bus (10D430) and DC distribution panel (1CD417)

to verify that they were capable of meeting their design basis requirements to distribute

preferred power to safety-related essential loads. The team reviewed the one-line

diagrams, control schematics, and the design basis as defined in the UFSAR to verify

the adequacy of the 125V bus to supply adequate voltage and current to the loads. The

team reviewed the associated voltage drop, load flow, and short circuit calculations to

verify that adequate voltage was available to components supplied by the bus under

worst case loading and degraded voltage conditions. The team reviewed the bus supply

and feeder breaker ratings and trip settings to verify that protection coordination was

provided for the loads and for the feeder conductors. The team reviewed vendor

specifications, nameplate data, and calculations related to the 125V bus supply. The

team interviewed system and design engineers to answer questions that arose during

document reviews to determine the adequacy of maintenance and configuration control.

The team performed several walkdowns of the 10D430 bus and associated DC

distribution panel to assess the material condition, configuration control, and the

operating environment. Finally, the team reviewed corrective action NOTFs and system

health reports to verify that PSEG appropriately identified and resolved deficiencies.

b. Findings

No findings were identified.

.2.1.16 A Standby Liquid Control Pump and Standby Liquid Control Tank

a. Inspection Scope

The team reviewed applicable portions of TSs, the UFSAR, and the system DBD to

identify design basis requirements for the standby liquid control (SLC) system. The

team inspected the A SLC pump and SLC tank to evaluate whether the pump, taking

suction from the tank, was capable of meeting its design basis and operational

requirements to provide the required borated water to the reactor vessel under the most

limiting accident conditions. The team evaluated the ability of the SLC pump to deliver

the design and licensing bases flow rates while the redundant B pump was operating

and assessed possible interactions between the two pumps. The team reviewed

surveillance testing using the SLC test tank, as well as IST acceptance criteria

associated with the SLC pump. The team also validated the tank capacity and reviewed

its operational capabilities with respect to Anticipated Transients Without Scram (ATWS)

and the reactor pressure vessel (RPV) control portion of the emergency operating

procedures (EOPs). The team also verified that the pump performance bounded the

flow requirements in the safety analysis and verified that PSEG had adequately

evaluated the potential for pump degradation. The team interviewed system and design

engineers as well as the IST Program Manager to gather information regarding the

condition of the pump, adequacy of pump maintenance, and outstanding issues affecting

the pump. The team conducted several detailed walkdowns of the pump, SLC tank,

19

associated support components and instruments, and control room indications to visually

inspect the physical/material condition and to ensure adequate configuration control.

Finally, the team reviewed corrective action documents and system health reports to

evaluate whether there were any adverse operating trends and to assess PSEGs ability

to evaluate and correct problems.

b. Findings

No findings were identified.

.2.2

Review of Industry Operating Experience and Generic Issues (5 samples)

The team reviewed selected OE issues for applicability at Hope Creek. The team

performed a detailed review of the OE issues listed below to verify that PSEG had

appropriately assessed potential applicability to site equipment and initiated corrective

actions when necessary.

.2.2.1 NRC Information Notice 2013-14: Potential Design Deficiency in Motor-Operated Valve

Control Circuitry

a. Inspection Scope

The team assessed PSEGs applicability review and disposition of NRC Information

Notice (IN) 2013-14. This information notice discussed recent industry OE regarding a

potential control circuit design deficiency in MOVs that could result in incorrect valve

position indication with the valve in an improper position during a LOCA. The team

reviewed PSEGs evaluation (70158062) performed in response to this OE. In addition,

the team reviewed design drawings and circuit diagrams to assess PSEGs review of the

issue.

b. Findings

No findings were identified.

.2.2.2 NRC Information Notice 2011-12: Reactor Trips Resulting from Water Intrusion into

Electrical Equipment

a. Inspection Scope

The team assessed PSEGs applicability review and disposition of NRC IN 2011-12.

The NRC issued the IN to inform licensees about OE regarding recent events involving

water intrusion into electrical equipment that resulted in reactor trips. In addition, the IN

described the root causes and corrective actions taken to prevent recurrence. The team

assessed PSEGs evaluation of the IN as it applied to HCGS, including their review of

the electrical equipment design to ensure that it remained reliable and that there were no

vulnerabilities associated with possible water intrusion events. The inspection included

a review of corrective action documents, interviews with electrical and design

engineering and operations personnel, and a complete walkdown of all accessible

20

safety-related and non-safety related electrical panels, MCCs, electrical cable spreading

rooms, and switchgear rooms.

b. Findings

No findings were identified.

.2.2.3 NRC Information Notice 2012-03: Design Vulnerability in Electric Power System

a. Inspection Scope

The team assessed PSEGs applicability review and disposition of NRC IN 2012-03.

The NRC issued the IN to inform licensees about OE involving the loss of one of the

three phases of the offsite power circuit. The team assessed PSEGs evaluation of the

IN as it applied to Hope Creek to confirm that PSEG performed an adequate review and

assessment of the issue, and to verify that adequate indications and procedures were

available to the operators to take appropriate actions when necessary. The inspection

also included a review of associated corrective action documents.

b. Findings

No findings were identified.

.2.2.4 NRC Information Notice 2013-17: Significant Plant Transient Induced by Safety-Related

Direct Current Bus Maintenance at Plant

a. Inspection Scope

The team assessed PSEGs applicability review and disposition of NRC IN 2013-17 for

Hope Creek. The NRC issued the IN to inform licensees of recent OE involving the loss

of one train of a DC distribution system at power in a nuclear power plant. The team

reviewed PSEGs evaluation of the systems, components, processes, and procedures

described in the assigned OE document to determine if similar deficiencies could

represent potential operability issues. PSEG determined that Hope Creek was not

vulnerable to the failure as their design differed in that the HCGS DC system has a fuse

with a 4 second time delay (rated at 500 percent) to allow the fuse to pass normal

current and surges instead of a breaker. The team reviewed the adequacy of PSEGs

determination that there were no similar deficiencies that could represent potential

operability issues and that the OE was not applicable at Hope Creek.

b. Findings

No findings were identified.

21

.2.2.5 NRC Information Notice 2010-03: Failures of Motor-Operated Valves due to Degraded

Stem Lubricant

a. Inspection Scope

The team assessed PSEGs applicability review and disposition of NRC IN 2010-03.

This IN discussed industry OE regarding recent failures and corrective actions for MOVs

due to degraded lubricant on the valve stem and actuator stem nut threaded area. The

team verified that PSEG entered the OE into their corrective action program (CAP) for

review (NOTF 20453813). The team reviewed PSEGs evaluation (70108019)

performed in response to this OE as well as PSEGs follow-up actions. The team also

reviewed changes to maintenance procedures and lubrication databases made in

response to this OE. In addition, the team assessed the adequacy of the PSEGs

corrective actions during walkdowns of various MOVs.

b. Findings

No findings were identified.

4.

OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems (IP 71152)

a. Inspection Scope

The team reviewed a sample of problems that PSEG had previously identified and

entered into the CAP. The team reviewed these issues to verify an appropriate threshold

for identifying issues and to evaluate the effectiveness of corrective actions. In addition,

the team reviewed NOTFs written on issues identified during the inspection to verify

adequate problem identification and incorporation of the problem into the CAP. The

specific corrective action documents that the team sampled and reviewed are listed in

the Attachment.

b. Findings

No findings were identified.

4OA6 Meetings, including Exit

On October 23, 2015, the team presented the inspection results to Mr. Eric Carr,

Plant Manager, and other members of the PSEG staff. The team verified that no

proprietary information was retained by the inspectors or documented in the report.

A-1

Attachment

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

PSEG Personnel

E. Carr, Plant Manager

M. Conroy, AOV Program Engineer

A. Contino, 4KV System Manager

S. DelMonte, Branch Manager

K. Denny, SW System Manager

P. Duca, Senior Engineer, Regulatory Assurance

D. Dunn, RHR System Manager

A. Ghose, Design Engineer Civil Structural

J. Lane, Design Engineer

T. MacEwen, Hope Creek Compliance Engineer

S. Madden, Design Manager

S. Nevelos, Regulatory Assurance Manager

C. Payne, HPCI & RCIC System Manager

M. Peterson, IA System Manager

C. Reed, Remote Shutdown System Manager

N. Rock, SACS System Manager

C. Torres, NSSS Manager

A. Tramontana, Hope Creek Programs Engineering Manager

Z. VanNess, Design Engineer

E. Wagner, Capital Projects

NRC personnel

C. Cahill, Senior Reactor Analyst

S. Haney, Resident Inspector

J. Hawkins, Senior Resident Inspector

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

Open and Closed

NCV 05000354/2015007-01

NCV

Failure to establish appropriate

acceptance criteria for RHR and core

spray pump start times during

simulated LOCA/LOP testing.

(Section 1R21.2.1.1)

NCV 05000354/2015007-02

NCV

Inadequate work order instructions

and drawings resulting in improper

installation of a safety-related SW

valve. (Section 1R21.2.1.2)

A-2

LIST OF DOCUMENTS REVIEWED

Audits and Self-Assessments

80113264, 2015 Focused Area Self-Assessment to Determine Readiness for NRC Component

Design Basis Inspection (CDBI), dated 3/20/15

Calculations

1EA-HV-2198C, AC Motor Operated GL96-05 Butterfly Valve, Revision 7 1EA-HV-2198D, AC

Motor Operated GL96-05 Butterfly Valve, Revision 4

12-0150, Suppression Pool Water Level Limitation for ECCS Pump Operation during Plant

Shutdown, Revision 1

646-8, Equipment Foundation, Revision 2 1108-0064-CLC-01, Differential Pressure across Hope

Creek Service Water Pump Discharge Valve 1EA-HV-2198C, Revision 0

1108-1407-0064, Differential Pressure across Hope Creek Service Water Pump Discharge Valve

1EA-HV-2198C, Revision 0

E-1.4, HC Class 1E 125 & 250VDC Systems: Short Circuit & Voltage Drop Studies, Revision 6

E-4.1, HC Class 1E 125 VDC Station Battery & Charger Sizing, Revision 17

E-4.2, Hope Creek Generating Station Class 1E DC Equipment & Component Voltage Study,

Revision 5

E-4.6, Hope Creek 125 VDC Beyond Design Basis Event Battery Sizing Calculation, Revision 0

E-5.1, HC Class 1E 250 VDC Station Battery & Charger Sizing, Revision 8

E-6.1, Non-Class 1E 250 & 125 VDC Station Battery and Charger Sizing, Revision 12

E-7.4, Class 1E 4.kV System Protective Relay Settings, Revision 6

E-7.9, 125VDC & 250VDC Class 1E System, Revision 4

E-9, Standby Class 1E Diesel Generator Sizing, Revision 9

E-15.1, Hope Creek Load Flow and Degraded Voltage Analysis, Revision 11

E-17B, Voltage Drop for 125 VDC Control Circuit, Revision 0

E-17D, 125 VDC, Voltage Drop from Distribution Panel to Load Panel 1CD417

(Class 1E Channel C), Revision 5

EA-0001, Differential Pressure Calculations, Revision 3

EA-0003, Station Service Water System Hydraulic Analysis, Revision 12

EQ-HC-021A, Environmental Qualification Binder for Limitorque, Motor Operated Valves Model

SMB Series, Revision 1

EQ-HC-021B, Environmental Qualification Binder for Limitorques, Motor Operated Valves Models

SMB Series DC Valve, Revision 1

EQ-HC-021C, Environmental Qualification Binder for Limitorque, Valve Actuator Components,

Revision 1

EQ-HC-028B, Environmental Qualification Binder for Automatic Switch Company (ASCO),

Solenoid Valve Model(s) NP8316 Series, Revision 1

EQ-HC-056A, Environmental Qualification Binder for Tyco Electronics, Control and Timing

Relays, Model(s) E7000 Series, Revision 1

EQ-HC-056B, Environmental Qualification Binder for Tyco Electronics, Control Timing Relays,

Model(s) ETR Series, Revision 1

H-1-BC-MDC-0922 (028), MOV Capability Assessment for 1BC-HV-F021B, Revision 1

H-1-EA-MDC-4010, Elastic - Plastic Finite Element Analysis of Hope Creek Service Water

Strainer Element, Revision 0

H-1-FD-MDC-0941 (002), MOV Capability Assessment for 1FD-HV-F001, Revision 1

H-1-GK-MDC-0735, Electrical Heat Load During the Station Blackout Event, Revision 1

A-3

H-1-JE-IST-6806, Fuel Oil Transfer Pumps Flow Rate, Revision 0

H-1-JE-IST-7510, Fuel Oil Transfer Pumps Suction Pressure, Revision 0

H-1-JE-IST-7513, Fuel Oil Transfer Pumps Discharge Pressure, Revision 0

H-1-KB-MDC-1007, Backup Pneumatic Supply for 1GSHV-4964 and 1GSHV-11541 Valves,

Revision 0

JE-13, Diesel Fuel Oil Day Tank, Revision 7

J-121, Suppression Pool Level Low, Revision 0

MIDACALC Results: 1BC-HV-F021B (HCGS-1) AC Motor Operated GL96-05 Gate Valve,

Revision 4

MIDACALC Results: 1FD-HV-F001 (HCGS-1) DC Motor Operated GL96-05 Gate Valve,

Revision 5

Report No. 879A, Stress Analysis Calculation of 28 Inch Model 596 Strain-O-Matic Strainer,

Revision 3

SC-JE-0059, Diesel Fuel Day Tank Level, Revision 7

XX-C-008, Drawing of Graphs to Show Contents of Tanks at all Levels, Revision 1

Completed Surveillance, Performance, and Functional Tests

HC.MD-ST.GS-0001, Torus to Drywell Vacuum Relief Valve 18 Month Testing, performed 11/4/13

HC.MD-ST.PK-0001, 125 Volt Weekly Battery Surveillance, performed 8/10/15

HC.MD-ST.PK-0002, 125 Volt Quarterly Battery Surveillance, performed 4/28/15 and 8/8/15

HC.MD-ST.PK-0006, 125 Volt Station Batteries Performance Discharge Test using BCT-2000

with Windows Software and Associated Surveillance Testing, performed 11/6/10

HC.MD-ST.PK-0007, 125 Volt Station Batteries 18 Month Service Test using BCT-2000 with

Windows Software and Associated Surveillance Testing, performed 4/29/15

HC.OP-FT.KB-0001, H1KB-10-K-100 Emergency Instrument Air Compressor, performed 8/6/15

HC.OP-IS.BC-0003, BP202, B Residual Heat Removal Pump In-Service Test, performed

10/14/15

HC.OP-IS.BC-0102, Residual Heat Removal Subsystem B Valves - In-Service Test, performed

11/2/13

HC.OP-IS.BJ-0001, HPCI Main and Booster Pump Set - OP204 and OP217 - In-Service Test,

performed 9/21/15

HC.OP-IS.EA-0101, Service Water Subsystem A Valves - In-Service Test, performed 7/4/15 &

10/9/15

HC.OP-IS.EG-0101, Safety Auxiliaries Cooling System - Subsystem A Valves - In-Service Test,

performed 4/2/15, 7/19/15, & 10/8/15

HC.OP-IS.EG-0102, Safety Auxiliaries Cooling System - Subsystem B Valves - In-Service Test,

performed 5/21/15 & 8/21/15

HC.OP-IS.JE-0008, H Diesel Fuel Oil Transfer Pump-HP401 - In-Service Test, performed 7/6/15

HP.OP-LR.BC-0203, Containment Isolation Valve Type C Leak Rate Test: CIVS 1BCHV-F021B,

Penetration P24A: B Drywell Spray, performed 11/2/13

HC.OP-ST.BC-0001, RHR System Piping and Flow Path Verification - Monthly, performed

10/14/15

HC.OP-ST.BC-0004, LPCI Subsystem C ECCS Time Response Functional Test - 18 months,

performed 1/29/14

HC.OP-ST.BC-0005, LPCI Subsystem C ECCS Time Response Functional Test - 18 months,

performed 6/11/14

HC.OP-ST.BC-0006, LPCI Subsystem C ECCS Time Response Functional Test - 18 months,

performed 3/6/14

A-4

HC.OP-ST.BC-0007, LPCI Subsystem C ECCS Time Response Functional Test - 18 months,

performed 9/6/13

HC.OP-ST.BH-0001, SLC Valve Operability Test - Monthly, performed 9/30/15

HC.OP-ST.BJ-0001, HPCI System Piping and Flow Path Verification - Monthly, performed

9/28/15

HC.OP-ST.EG-0001, SACS Flow Path Verification - Monthly, performed 9/27/15

HC.OP-ST.GS-0001, Drywell and Suppression Chamber Oxygen Concentration

Verification - Weekly, performed 10/3/15

HC.OP-ST.GS-0003, Reactor Building/Suppression Chamber Vacuum Breaker Operability

Test - Monthly, performed 10/18/15

HC.OP-ST.GS-0004, Suppression Chamber/Drywell Vacuum Breaker Operability Test - Monthly,

performed 10/19/15

HC.OP-ST.KJ-0002, Emergency Diesel Generator 1BG400 Operability Test - Monthly, performed

10/12/15

HC.OP-ST.KJ-0003, Emergency Diesel Generator 1CG400 Operability Test - Monthly, performed

6/5/15, 10/6/15

HC.OP-ST.KJ-0004, Emergency Diesel Generator 1DG400 Operability Test - Monthly, performed

10/20/15

HC.OP-ST.KJ-0005, Integrated Emergency Diesel Generator 1AG400 Test - 18 Months,

performed 11/8/10, 6/27/13, & 5/8/15

HC.OP-ST.KJ-0006, Integrated Emergency Diesel Generator 1BG400 Test - 18 Months,

performed 11/5/13 & 4/24/15

HC.OP-ST.KJ-0007, Integrated Emergency Diesel Generator 1CG400 Test - 18 Months,

performed 11/6/13 & 5/4/15

HC.OP-ST.KJ-0008, Integrated Emergency Diesel Generator 1DG400 Test - 18 Months,

performed 11/6/13 & 4/24/15

HC.OP-ST.SV-0001, Remote Shutdown Monitoring Instrumentation Channel Check - Monthly,

performed 8/9/15 & 10/11/15

HC.OP-ST.SV-0002, Remote Shutdown Control Operability - 18 Months RSP Transfer with A

Shutdown Cooling In-Service, performed 4/12/15

HC-OP-ST.ZZ-0006, Drywell to Suppression Chamber Leak Rate Test - 18 Months, performed

4/10/15

Completed Preventive Maintenance, Calibrations, and Inspections

Calibration Report, Crystal XP2 Pressure Gauge Digital 1001-3500 PSIG, dated 3/15/15

HC.IC-CC.BC-0006, RHR-Division 2, Channel E11-N652B Pump Discharge Flow, performed

9/18/10

HC.IC-CC.BJ-0010, HPCI - Division 3 Channel L-48011 Suppression Chamber Level, performed

4/11/14

HC.IC-CC.BJ-0011, HPCI - Division 1 Channel L-4085-1 Suppression Chamber Level,

performed 11/2/14

HC.IC-CC.GS-0009, Containment Atmosphere Control - Division 1 Channel P-4960A1

Suppression Chamber Pressure (Post Accident Monitoring), performed 1/1/15

HC.IC-CC.GS-0010, Containment Atmosphere Control - Division 4 Channel P-4960B1

Suppression Chamber Pressure (Post Accident Monitoring), performed 7/16/15

HC.IC-CC.GS-0014, Containment Atmosphere Control - Division 4 Channel P-4960B3

Suppression Chamber Pressure (Post Accident Monitoring), performed 7/17/15

A-5

HC.IC-CC.SB-0014, RPS - Non Divisional Monitor H1SB-1SBTY-3881B Suppression Pool Bulk

Water Temperature, performed 5/20/14

HC.OP-SO.EA-0001, Service Water System Operation (A/C Pump Swap), performed 10/15/15

Motor Operated Valve PVT Report, dated 6/26/15

OU-AA-335-016, Visual Examination of SACS Expansion Tank 1-EG-1BT-205, performed

11/2/10

RCN-029, Hope Creek H1R18 Torus Project Desludge, Coating Inspection and Repair, Final

SH.MD-EU.ZZ-0009, Motor Power Monitor Data Acquisition for Motor Operated Valves,

performed 4/26/03

S-IR-6H4-0011, Containment Coatings Condition Monitoring Report, Refueling Outage 1R19,

Hope Creek Generating Station, dated 9/21/15

VEN015-003, General Visual Examination Suppression Chamber, dated 4/24/15

VTD 432614, C & D Technologies Battery Inspection Report, dated 8/7/15

Corrective Action Notifications (NOTFs)

20188379

20192357

20249278

20381796

20404688

20442488

20453813

20498861

20503940

20519749

20521256

20555348

20555834

20556952

20558035

20559255

20560095

20563418

20568722

20571913

20573570

20577490

20584759

20584760

20584892

20590426

20593600

20594208

20595574

20597608

20597981

20598216

20598733

20599639

20600422

20605880

20608297

20612199

20613955

20617870

20618872

20619972

20620806

20621955

20625154

20626219

20627235

20627274

20627777

20627787

20628849

20631818

20635146

20641757

20643437

20653020

20653539

20663223

20668283

20670193

20670595

20673076

20680341

20681254

20684134

20684479

20685606

20686862

20687007

20687182

20688379

20688759

20688773

20688828

20689335

20694973

20695961

20696370

20698578

20698782*

20698783*

20698784*

20698785*

20698786*

20698787*

20698788*

20698941

20699521

20701108*

20701119

20702063

20702075

20702283

20702379

20702467

20702491

20702550

20702555

20702588

20702852

20702862

20702863

20702912

20702945

20703138*

20703139*

20703155

20703199

20703218

20703251*

20703257

20703302

20703309*

20703310*

20703343

20703433*

20703449*

20703642

20703728*

20703966

20703967

20704264*

20704347

20704352*

20704464*

20704532*

20704611*

20704622*

20704726*

20704783*

20704862*

20704884

20704910*

20704959*

20705022*

20705352

20705418*

20705420*

20705503*

20705506*

20705507*

20705513*

20705597

20705616*

20705872*

20705873*

20705874*

20705891*

20706542*

20706543*

20706703*

20706707*

20706710*

20706712*

20706717*

20706720*

20706856*

20706857*

20706937*

20706958*

20706937

20707004*

20707031*

20707089*

20707135*

  • NOTF written as a result of this inspection

A-6

Design and Licensing Bases

CD-143Y, Diesel Fuel Oil Storage and Transfer System Operation Commitment Document,

dated 6/7/85

CD-392X, Diesel Fuel Oil Storage and Transfer System Operation Commitment Document,

dated 6/7/85

D3.35, Design, Installation and Test Specification for Residual Heat Removal System for the

Hope Creek Generating Station, Revision 9

D7.5, Hope Creek Generating Station Environmental Design Criteria, Revision 22

DE-CB.BC-0036, Configuration Baseline Documentation for Residual Heat Removal System,

Hope Creek Generating Station, Revision 1

DE-CB.BJ/FD-0073, Configuration Baseline Documentation for High Pressure Coolant Injection

(HPCI) System, Hope Creek Generating Station, Revision 0

DE-CB.EA/EP-0052, Configuration Baseline Documentation for Station Service Water System,

Revision 2

DE-CB.KJ/PE-0083, Configuration Baseline Documentation Emergency Diesel-Generator

System, Revision 1

DE-CB.NB/PB-0045, Configuration Baseline Documentation for 4KV Auxiliary Power System,

Revision 1

H-1-VAR-MDS-0357, Design Specification for ECCS Suction Strainers, Revision 0

HC.DE-DB.BH-0001, Standby Liquid Control System, Revision 0

HC.DE-DB.KJ-0001, UFSAR Chapter 15 DB/LB System Validations HC EDG System,

Revision 0

HC.DE-PS.ZZ-0041, Hope Creek Station Blackout Program, Revision 3

Hope Creek In-service Testing Program Submittal Interval 3, Revision 8

PN0-E11-4010-0361-(01), Residual Heat Removal System Design Specification, Revision 3

Drawings

10855-E151, 200 Amp 125 VDC Chargers, Revision 39

83916, 28 Inch Model 956 Final Assembly, Revision D

11874141, Tank, 550 Gallons Fuel Oil Day Tank, ASME III, Revision 0

A-0201-0, General Plant Floor Plan, Level 1-Elevation 54-0, Revision 13

A-0202-0, General Plant Floor Plan, Level 1-Elevation 77-0, Revision 20

A-0203-0, General Plant Floor Plan, Level 1-Elevation 102-0, Revision 19

A-0531-0, Separation Criteria Reactor Building Plan- El 54-0, Revision 4

A-0532-0, Separation Criteria Reactor Building Plan- El 77-0, Revision 4

A-0533-0, Separation Criteria Reactor Building Plan- El 102-0, Revision 6

A-0535-0, Separation Criteria Reactor Building Plan-El 1450, Revision 5

A-0541-0, Separation Criteria Auxiliary Building-Control/Diesel El. 54-0, Revision 6

A-0542-0, Separation Criteria Auxiliary Building-Control/Diesel El. 77-0, Revision 9

A-0543-0, Separation Criteria Auxiliary Building-Control/Diesel El. 102-0, Revision 14

A-0544-0, Separation Criteria Auxiliary Building-Control/Diesel El. 117-6, El. 124-0,

El. 130-0, Revision 6

B617-5903, SACS Expansion Tank, dated 8/5/77

C-0399-0, Anchor Bolts Data for Remote generator & Engine Control Panels, Revision 3

DE-CB.BH-0079, Standby Liquid Control Mechanical Boundary, Revision 20

E-0001-0, Single Line Diagram Station, Revision 24

E-0006-1 Sh. 1, Single Line Meter & Relay Diagram 4.16 KV Class 1E Power System,

Revision 11

A-7

E-0008-1, Single Line Meter & Relay Diagram Diesel Generators, Revision 4

E-0009-1 Sh. 1, 125 VDC System - Channels A & C, Revision 25

E-0009-1 Shs. 3 & 5, 125 VDC System, Revisions 28 & 22

E-0009-1 Sh. 4, 125 V DC System Channels C & D, Revision 13

E-0011-1 Sh. 2, 250V DC System - Unit 1, Revision 19

E-0012-1 Shs. 1, 2, 3, 4, & 5, 120V AC Instrumentation & Misc. Systems,

Revisions 15, 30, 29, 8, and 39

E-0208-0 Sh. 3, Electrical Schematic Diagram 4.16KV Circuit Breaker Control Station Service

Water Pump, Revision 10

E-219-0, Electrical Schematic Diagram RHR Pump Seal & Motor BRG. CLG. WTR SPLY. SOL.

VLV ISV-2520B, Sheet 2, Revision 7

E-6234-0 Sh. 10, Electrical Schematic Diagram, Residual Heat Removal System, Containment

Spray (Inboard) Valve (HV-F021A), Revision 5

E-6441-0 Shs. 1 & 2, Electrical Schematic Diagram Class 1E 4.16KV CKT Breaker Control RHR

Pumps. 1DP202, Revisions 6 & 7

E-6443-0, Electrical Schematic Diagram 4.16 KV Circuit Breaker Control RHR Pump IBP202,

Revision 8

I-03511, Strainer Element Assembly, Revision L

I-770912-A, Strain-O-Matic 180º Flow, Revision 5

J-11-0-9, Safety Auxiliaries Cooling-RHR HX BE 205 Outlet Valve/Seal and BRG. CLG. Water

Valve, Revision 9

J105-0 Shs. 8 & 9, Logic Diagram Sequencer Fan Out, Revisions 6 & 5

M-10-1, Service Water, Revision 55

M-11-1 Shs. 1, 2, 3, & 4, Safety Auxiliaries Cooling, Reactor Building, Revisions 32, 42, 31, & 2

M-12-1 Shs. 1 & 2, Safety Auxiliaries Cooling, Auxiliary Building, Sheet 1, Revisions 31 & 1

M-15-0 Sh. 1, Compressed Air System, Sheet 1, Revisions 50 & 51

M-30-1, Sheet 1, Diesel Engine Auxiliary Systems Fuel Oil, Revision 19

M-48-1, Standby Liquid Control, Revision 16

M-48-1-BH-CBD, Standby Liquid Control, Revision 0

M-51-1 Sh. 1, Residual Heat Removal, Revision 47

M-55-1 Sh. 1, High Pressure Coolant Injection, Revision 24

M-56-1 Sh. 1, HPCI Pump Turbine, Revision 16

M-97-0, Intake Structure Building and Equipment Drains PI&D, Revision 7

O-P-EA-01, System Isometric Intake Structure Service Water, Revision 20

O-P-EA-012, Fab Isometric Intake Structure Service Water, Revision 20

PJ810-009 Shs. 1 & 2, Logic Diagram Emergency Load Sequencer Cabinet C, Revisions 7 & 6

PJ810-009 Sh. 3, Logic Diagram Step Timer Cabinet C, Revision 7

PJ810-009 Sh. 4, Logic Diagram Step Timer, Revision 7

PP302Q-0302 Sh. 0, H1/10-900 Flex Wedge Gate Valve, dated 4/26/12

Engineering Evaluations

1EGHV-2457 A&B, Air Operated Valve (AOV) Capability Evaluation, Revision 2

1EGHV-2520 A&B, Air Operated Valve (AOV) Capability Evaluation, Revision 2

10855-D7.3, Appendix E, Separation Review Data Sheet, Reactor Building Room 4218,

Elevation 77, Revision 1

10855-D7.3, Appendix E, Separation Review Data Sheet, Reactor Building Room 4301,

Elevation 102, Revision 1

A-8

317103(15), Maximum Thrust and Seismic Analysis for 10 - Class 900 Carbon Steel Flex

Wedge Gate valve with SMB-1-60 Limitorque Motor Actuator, Revision 2

317103(41)-01, Maximum Thrust and Seismic Analysis for 16 - Class 300 Carbon Steel Flex

Wedge Gate valve with SB-3-100 Limitorque Motor Actuator, Revision 0

70090160, Suppression Pool Level Low Alarm, dated 10/17/08

70102111-50, Determination of Whether the Reactor Building to Torus Vacuum Breaker,

H1GS-1GSPSV-5030, was able to Perform its Design Function as Defined in Tech Specs

and the Maintenance Rule Program, dated 10/15/09

70105023, Slowly Lowering Torus Level, dated 1/5/10

70106957, NRC Information Notice 2010-03, Revision 0

70124352, Functional Failure Cause Determination Evaluation: Suppression Pool Temperature,

dated 7/7/11

70125650 (NOTF 20516551), IST Pump Evaluation, dated 6/29/11

70139234, MOV 1FDHV-F001 Needs Margin Improvement, Revision 0

70158062, OPEX Response: Potential Design Deficiency in Motor-Operated Valve Control

Circuitry, dated 12/19/13

70158101, IST Rebaseline of H1BC-BC-HV-F021A, Revision 0

70162112, Maintenance Rule Functional Failure Cause Determination, BC-HV-021B Seat

Leakage, dated 2/4/14

70163546, Use-As-Is Interim Disposition Technical Evaluation for 1EAHV-2198C Reverse Flow,

Revision 0

70175293, HPCI Steam Admission Valve (FD-F001) Leakby, dated 5/14/15

70176210, Reportability Review for Rising Torus Level Trend (NOTF 20687007), dated 6/1/15

70176533, Valve H1BC-BC-HV-F021A In-service Test Valve Evaluation, Revision 0

70176608, Valve H1BC-BC-HV-F021A High As-found and As-left Open Thrust during Diagnostic

Testing in H1R19 (30138724), Revision 0

70177495-10, Impact of the RF19 As-Found F SRV Setpoint Pressure on the B Main Steam

Line and F SRV Discharge Line, dated 8/27/15

70177495-40, RF19 SRV Setpoint Test Failures Assessment, dated 8/25/15

70178126, HPCI Core Spray Injection Valve Failed to Open during IST (OP-Eval 15-007),

Revision 1

70180794, H1EA-EA-HV-2198C Reverse Flow Direction Evaluation, dated 10/20/15

80065877, Replace GE AKR DC Breakers, Revision 1

80078355, AKR 125 VDC and 250 VDC Breaker Replacement, Revision 0

80083976, Replace Model DC-2000 Trip Unit with Model DC-2000 NQ Trip Unit, Revision 1

80097309, HPCI Valve HV-8278 Replacement, Revision 0

80108793, C SSW Discharge Valve Failed IST Evaluation, dated 3/2/13

80110417, Technical Evaluation of As-Found leakage for Penetration P24A (1BCHV-F021B

exceeding Administrative Limit), Revision 0

80114188, Multiple Pieces of Tape Discovered in H T-quencher Piping Support Guide Lugs,

Weldsand Dampeners, dated 5/20/15

DEH 110079, Walkdown Information for IER 11-1 Recommendation 3, Capability to Mitigate

Internal and External Flooding Events, Revision 0

DEH 120195, SACS Expansion Tank Level Swings, Revision 1

DEH 120280, STACS Expansion Tanks Sluicing, Revision 10

EQ-HC-072A, Environmental Qualification Binder for Cutler-Hammer INC (EATON), Class 1E,

480V MCC, Reactor Area, Revision 0

A-9

H-1-BB-MEE-1168, Determination of Drywell Insulation Material Debris Sources and Quantities

Generated Due to Postulated High Energy Pipe Breaks, Revision 2

H-1-ZZ-MEE-0864, Motor Operated Gate Valve Pressure Locking/Thermal Binding Review,

Revision 0

HC15-008, Adverse Condition Monitoring and Contingency Plan: HPCI Steam Admission Valve

(FD-F001) Leakby, Revision 3

Orders (Evaluations): 70056192, 70059015, 70060868, 70111202, 70115714, 70128893,

70134962, 70138725, 70139229, 70141532, 70150554, 70158231, 70159261, 70162113,

70163046, 70173642, 80104106, 80108793, 80108856, 80112286

TCCP 4HT-14-028, Defeat High Flow Switch 1KBFSH-7618 for Air Dryer 10F104, Revision 0

Maintenance Work Orders

30013826

30040357

30077629

30087884

30119900

30123531

30138724

30148196

30148488

30157118

30158854

30165813

30174260

30179032

30179104

30190587

30200706

30208969

30218556

30221175

30227181

30234076

30264028

30265252

30272880

60015966

60022564

60079674

60084133

60106988

60107486

60107487

60107488

60109690

60109691

60112463

60121909

60122197

Miscellaneous

Hope Creek Generating Station LER 96-001-00, Safety and Auxiliaries Cooling Systems Heat

Exchangers Fouled with Grass Due to a Failed Service Water Strainer, dated 2/15/96

Hope Creek Generating Station LER 97-021-00, dated 9/22/97

Hope Creek Generating Station LER 97-027-00, Technical Specification Surveillance

Requirement Implementation Deficiencies - 125/250 VDC Batteries, dated 12/15/97

Hope Creek Generating Station LER 98-007-00, dated 11/9/98

Hope Creek Generating Station LER 99-007-00, License Condition Violation - Class 1E Battery

Charging, dated 7/19/99

Hope Creek MOV Program Basis Document, Revision 0

In-Service Testing Scoping Basis, H1BC -BC-HV-F021B, Revision 3.8

In-Service Testing Scoping Basis, H1FD -FD-HV-F001, Revision 3.12

OP-SH-111-101-1001, Hope Creek Narrative Log, dated 10/25/13 - 10/30/13 and 4/28/15 -

5/2/15

QCIR No. 1-CC-428-1-C-1.55, Installation and Testing of Undercut Anchors Inspection record,

dated 9/4/84

Regulatory Guide 1.97, Instrumentation for Light-Water-Cooled Nuclear Power Plants to Assess

Plant and Environs Conditions During and Following an Accident, Revision 2

WCDs: 4381567, 4382795

Normal and Special (Abnormal) Operations Procedures

HC.OP-AB.COMP-0001, Instrument and/or Service Air, Revision 6

HC.OP-AB.COOL-0002, Safety/Turbine Auxiliaries Cooling System, Revision 8

HC.OP-AB-ZZ-0024, CRIDS Computer Points Book 5 D3624 thru D4288, Revision 11

HC.OP-AB-ZZ-0025, CRIDS Computer Points Book 6 D4303 thru D4596, Revision 10

HC.OP-AB.ZZ-0149, 250 VDC System Malfunction, Revision 4

HC.OP-AB.ZZ-0150, 125 VDC Malfunction, Revision 7

A-10

HC.OP-AB.ZZ-0172, Loss of 4.16KV Bus 10A403, Revision 7

HC.OP-IO.ZZ-0008, Shutdown from Outside Control Room, Revision 34

HC.OP-SO.BC-0001, Residual Heat Removal System Operation, Revision 53

HC.OP-SO.BJ-0001, High Pressure Coolant Injection System Operation, Revision 48

HC.OP-SO.EE-0001, Torus Water Cleanup System Operation, Revision 14

HC.OP-SO.JE-0001, Diesel Fuel Oil Storage and Transfer System Operation, Revision 32

HC.OP-SO.KB-0001, Instrument Air System Operation, Revision 23

HC.OP-SO.KJ-0001, Emergency Diesel Generators Operation, Revision 72

HC.OP-SO.PB-0001, 4.16KV System Operation, Revision 29

HC.OP-SO.PJ-0001, 250 VDC Electrical Distribution System Operation, Revision 9

HC.OP-SO.PK-0001, 125 VDC Electrical Distribution System Operation, Revision 24

Operating Experience

10CFR Part 21 Interim Reporting of Tricentric Triple Offset Butterfly Valves, dated 2/7/14

NRC Information Notice 85-20: Motor-operated Valve Failures Due to Hammering Effect, dated

3/12/85

NRC Information Notice 92-26: Pressure Locking Of Motor-Operated Flexible Wedge Gate

Valves, dated 4/2/92

NRC Information Notice 93-98: Motor Brakes on Valve Actuator Motors, dated 12/20/93

NRC Information Notice 2010-03: Failures of Motor-Operated Valves Due to Degraded Stem

Lubricant, dated 2/3/10

NRC Information Notice 2011-12, Reactor Trips Resulting from Water Intrusion into Electrical

Equipment, dated 6/16/11

NRC Information Notice 2012-03: Design Vulnerability in Electric Power System, dated 3/1/12

NRC Information Notice 2013-05: Battery Expected Life and Its Potential Impact on Surveillance

Requirements, dated 3/19/13

NRC Information Notice 2013-14: Potential Design Deficiency in Motor-Operated Valve Control

Circuitry, dated 8/23/13

NRC Information Notice 2013-17: Significant Plant Transient Induced by Safety-Related Direct

Current Bus Maintenance at Power, dated 9/6/13

Weir Valves & Controls USA Letter to PSEG, 28 - 150 Tricentric (EA-HV-2198C) Part 21

Concern, dated 10/26/15

Procedures

CC-AA-11, Nonconforming Materials, Parts, or Components, Revision 5

ER-AA-300, Motor Operated Valve Program Administrative Procedure, Revision 4

ER-AA-302-1003, MOV Margin Analysis and Periodic Verification Test Intervals, Revision 6

ER-AA-302-1008, MOV Diagnostic Test Preparation Instructions, Revision 8

ER-HC-310-1009, Hope Creek System Function Level Maintenance Rule Scoping, Revision 7

ER-SH-330-0009, PSEG Nuclear Repair Program Manual for the Control of R and NR

Certificates of Authorization, Revision 7

HC.IC-CC.BE-0012, Core Spray Division 1 Channels E21A-K22A and E21A and K21A Pump

Start Delay - Normal and Emergency Power, Revision 10

HC.IC-CC.BE-0013, Core Spray Division 2 Channels E21A-K22B and E21A and K21B Pump

Start Delay - Normal and Emergency Power, Revision 10

A-11

HC.IC-CC.BE-0014, Core Spray Division 3 Channels E21A-K22C and E21A and K21C Pump

Start Delay - Normal and Emergency Power, Revision 11

HC.IC-CC.BE-0015, Core Spray Division 4 Channels E21A-K22D and E21A and K21D Pump

Start Delay - Normal and Emergency Power, Revision 9

HC.IC-CC.BJ-0010, HPCI - Division 3 Channel L-48011 Suppression Chamber Level, Revision 8

HC.IC-CC.BJ-0011, HPCI - Division 1 Channel L-4085-1 Suppression Chamber Level,

Revision 10

HC.IC-CC.GS-0005, Containment Atmosphere Control - Division 1, Channel PD-5029,

Reactor Building to Suppression Chamber Pressure Relief (Inboard Isolation Valve Control),

Revision 9

HC.IC-CC.GS-0006, Containment Atmosphere Control - Division 2, Channel PD-5031, Reactor

Building to Suppression Chamber Pressure Relief (Inboard Isolation Valve Control),

Revision 7

HC.IC-CC.GS-0007, Containment Atmosphere Control - Division 1, Channel PD-5029,

Containment/Reactor Building Differential Pressure, Revision 11

HC.IC-CC.GS-0009, Containment Atmosphere Control - Division 2, Channel PD-5031,

Containment/Reactor Building Differential Pressure, Revision 10

HC.IC-CC.GS-0009, Containment Atmosphere Control - Division 1 Channel P-4960A1

Suppression Chamber Pressure (Post Accident Monitoring), Revision 8

HC.IC-CC.GS-0010, Containment Atmosphere Control - Division 4 Channel P-4960B1

Suppression Chamber Pressure (Post Accident Monitoring), Revision 8

HC.IC-CC.GS-0014, Containment Atmosphere Control - Division 4 Channel P-4960B3

Suppression Chamber Pressure (Post Accident Monitoring), Revision 9

HC.IC-CC.SB-0014, RPS - Non Divisional Monitor H1SB-1SBTY-3881B Suppression Pool Bulk

Water Temperature, Revision 21

HC.IC-DC.ZZ-0064, General Electric Ammeters and Voltmeters, Types AB and DB; and

Westinghouse Ammeters and Voltmeters, Type KX-241, KA-241 and KC-241, Revision 9

HC.IC-FT.PE-0003, Emergency Load Sequencer System, Revision 7

HC.IC-FT.PE-0007, Time Interval Test, Revision 8

HC.IC-SC.BJ-0011, HPCI - Division 1 Channel H1BJ-1BJLT-4805-1 Suppression Chamber

Water Level, Revision 13

HC.IC-SC.GS-0001, Containment Atmosphere Control - Division 1 Channel P-4960A1

Suppression Chamber, Revision 8

HC.IC-SC.GS-0002, Containment Atmosphere Control - Division 4 Channel P-4960B1

Suppression Chamber (Accident Monitoring), Revision 7

HC.IC-SC.GS-0003, Containment Atmosphere Control - Division 1 Channel P-4960A2 Drywell

Pressure (Accident Monitoring), Revision 5

HC.IC-SC.GS-0004, Containment Atmosphere Control - Division 4 Channel P-4960B2 Drywell

Pressure (Accident Monitoring), Revision 5

HC.IC-SC.GS-0005, Sensor Calibration Containment Atmosphere Control - Division 1 Channel

P-4960A3 Drywell Pressure, Revision 5

HC.MD-GP.ZZ.0113, Maintenance of Anchor Darling Flexible Wedge Type Gate Valves,

Revision 3

HC.MD-PM.ZZ-0006, General Preventive Maintenance for Distribution Panels, MCCs, Unit

Substations, and Switchgear, Revision 20

HC.MD-ST.GS-0001, Torus to Drywell Vacuum Relief Valve 18 Month Testing, Revision 14

HC.MD-ST.GS-0002, Reactor Building to Torus Vacuum Relief Valve 18 Month Testing,

Revision 12

A-12

HC.MD-ST.PJ-0002, 250 Volt Quarterly Battery Surveillance, Revision 32

HC.MD-ST.PK-0001, 125 Volt Weekly Battery Surveillance, Revision 29

HC.MD-ST.ZZ-0009, Motor Operated Valve Thermal Overload Protection Surveillance,

Revision 21

HC.OP-DL.ZZ-0026, Surveillance Log, Revision 150

HC.OP-IS.BC-0102, Residual Heat Removal Subsystem B Valves - In-service Test, Revision 43

HC.OP-IS.BH-0003, Standby Liquid Control Pump-AP208 - In-Service Test, Revision 16

HC.OP-IS.BJ-0001, HPCI Main and Booster Pump Set - OP204 and OP217 - In-service Test,

Revision 63

HC.OP-IS.GS-0101, Containment Atmosphere Control System Valves - In-Service Test,

Revision 49

HC.OP-IS.JE-0001, A Diesel Fuel Oil Transfer Pump - AP401 - In-Service Test, Revision 33

HP.OP-LR.BC-0203, Containment Isolation Valve Type C Leak Rate Test: CIVS 1BCHV-F021B,

Penetration P24A: B Drywell Spray, Revision 1

HC.OP-ST.BC-0004, LPCI Subsystem A ECCS Time Response Functional Test - 18 months,

Revision 15

HC.OP-ST.BC-0005, LPCI Subsystem B ECCS Time Response Functional Test - 18 months,

Revision 16

HC.OP-ST.BC-0006, LPCI Subsystem C ECCS Time Response Functional Test - 18 months,

Revision 14

HC.OP-ST.GS-0003, Reactor Building/Suppression Chamber Vacuum Breaker Operability Test -

Monthly, Revision 8

HC.OP-ST.GS-0004, Suppression Chamber/Drywell Vacuum Breaker Operability Test - Monthly,

Revision 13

HC.OP-ST.KJ-0005, Integrated Emergency Diesel Generator 1AG400 Test - 18 Months,

Revision 42

HC.OP-ST.KJ-0007, Integrated Emergency Diesel Generator 1CG400 Test - 18 months,

Revision 46

HP.OP-ST.SV-0001, Remote shutdown Monitoring Instrumentation Channel Check - Monthly,

Revision 26

HC.OP-ST.ZZ-0006, Drywell to Suppression Chamber Leak Rate Test - 18 Months, Revision 17

LS-AA-120, Issue Identification and Screening Process, Revision 13

LS-AA-125, Corrective Action Program, Revision 20

LS-HC-1000-1001, Hope Creek Generating Station, Surveillance Frequency Control Program,

List of Surveillance Frequencies, Revision 6

MA-AA-716-210-1001, Performance Centered Maintenance (PCM) Templates, Revision 12

MA-AA-723-300, Diagnostic Testing and Inspection of Motor Operated Valves, Revision 10

MA-AA-723-300-1005, Review and Evaluation of Motor Operated Valve Test Data, Revision 4

MA-AA-723-301, Periodic Inspection of Limitorque Model SMB/SB/SBD-000 through 5 Motor

Operated Valves, Revision 9

MA-AA-724-113, Meggering of Electrical Equipment (Non-Rotating), Revision 7

OP-AA-108-115, Operability Determinations & Functionality Assessments, Revision 4

OP-AA-108-115-1001, Operability Assessment and Equipment Control Program, Revision 30

OP-AA-111-1001, Severe Weather and Natural Disaster Guidelines, Revision 12

SH.MD-GP.ZZ-0242, Limitorque Valve Actuator Removal and Installation, Revision 6

A-13

Risk and Margin Management

CC-HC-102-1001, Control of Time Critical Operator Actions, Revision 2

H-13-0092, MOV 1FDHV-F001 Margin Improvement, dated 9/17/15

Hope Creek Generating Station Individual Plant Examination, April 1994

Hope Creek Generating Station Individual Plant Examination for External Events, July 1997

Risk-Informed Inspection Notebook for Hope Creek Generating Station, Revision 2.1a

System Health Reports, System Walkdowns, & Trending

4.16 KV AC (Class 1E & Non-1E) System Health Report, Q2-2015

125 VDC (Class 1E) System Health Report, Q2-2015

2014 Breakers Component Health Report, dated 9/30/14

Air Operated Valve Program Health Report, P2-2015

Battery Replacement Schedule, dated 9/24/15

Equipment Qualification Program Health Report, P2-2015

Generic Letter 89-13 (Safety Related Service Water System) Program Health Report, P2-2015

HPCI System Health Report, Q2-2015

In-Service Testing Program Health Report, P2-2015

Instrument Air System Health Report, Q2-2015 & Q1-2015

Motor Operated Valve Program Health Report, P2-2015

RHR System Health Report, Q2-2015

SACS A Loop Expansion Tank Level Trend Data, dated 10/9/12 to 7/14/15

SACS B Loop Expansion Tank Level Trend Data, dated 10/9/12 to 7/14/15

SACS System Health Report, Q2-2015 & Q1-2015

Service Water System Health Report, Q2-2015

Vendor Technical Manuals & Specifications

10SA-A092, Recommended Spare Parts, Revision 0

10855-P-303, Technical Specification for Nuclear Service Steel Gate, Globe, and Check Valves,

2 and Smaller, Revision 5

10855-M707-22-1, Expansion Tanks & Accumulators, Seismic Category 1, B617-9907,

Surface Preparation and Painting-Carbon Steel Vessels, dated 11/23/77

10855 Specification M-70763, Appendix I, SACS Expansion Tank

309448, Standby Battery Vented Cell Installation and Operating Instructions, Revision 9

313628, Maintenance Manual for Flexible Wedge Type Gate Valves, Revision 2

322440, Hayward Tyler Inc. Doc. No. 01-000-077, Revision 1

322441, Hayward Tyler Inc. Doc. No. 01-000-078, Revision 1

322442, Hayward Tyler Inc. Doc. No. 01-000-079, Revision 1

322443, Hayward Tyler Inc. Doc. No. 01-000-083, Revision 1

323981, Atwood and Morrill Instruction Manual for Butterfly Valves, Revision 1

H-1-VAR-MGS-0010 (002) Sheet 40, Valve Data Specification Sheet (1EAV-474), dated 2/28/96

Limitorque SMB-1 Torque Switch Setting Chart, dated 1/1/91

PE051-0014, 250 Volt Chargers Operating Instructions, Revision 4

PE051-0015, General Purpose Relay Series 70, dated 3/1/04

PE109Q-0173, Brown Boveri Electric, Inc., Metal Clad Switchgear, Revision 0

PE112BQ-0002, General Electric Instruction Book GEH 3292C, Revision 11

PE117-0128, Transformer Test Report, Revision 0

PE120Q-0014, Indoor AKD-6 Powermaster SWGR, 06/09/15

PE121Q-0034, IC7700 Motor Control Center 10D251, Revision 8

A-14

PE121Q-0081, Instruction Manual - Motor Control Centers 10D251, 10D261, dated 4/19/99

PJ810Q-0097 Sh. 1, Operation and Maintenance Instructions Emergency Load Sequencer

(ELS), Revision 3

PM-018-0345 Sh. 8, Electrical Schematic Local PT & Exciter Control Panel (1AC420),

Revision 14

PM-018-0366 Sh. 2, Electrical Schematic Engine Control, Revision 12

PM150-0050, Instruction Manual for Model Number LD240-383, Revision 6

PM150AQ-0013, Instruction Manual for Model Number LD240-447, Revision 7

PN0-E21-4010-0007-(01), Core Spray System Design Specification Data Sheet, dated 2/15/90

PN1E11C0020047, Ingersoll-Rand Company Pump 34APKD-4 Curve N760, Revision 0

PP303AQ-0305, Type SMB Instruction & Maintenance Manual, Revision 4

LIST OF ACRONYMS

ADAMS

Agencywide Documents Access and Management System

AOV

Air-Operated Valve

ASME

American Society of Mechanical Engineers

ATWS

Anticipated Transients Without Scram

CAP

Corrective Action Program

CDBI

Component Design Bases Inspection

CFR

Code of Federal Regulations

DBD

Design Basis Document

DC

Direct Current

DP

Differential Pressure

DRS

Division of Reactor Safety

ECCS

Emergency Core Cooling System

EDG

Emergency Diesel Generator

EIAC

Emergency Instrument Air Compressor

ELS

Emergency Load Sequencer

EOP

Emergency Operating Procedure

ESF

Engineered Safety Feature

FODT

Fuel Oil Day Tank

FOTP

Fuel Oil Transfer Pump

GE

General Electric

HCGS

Hope Creek Generating Station

HPCI

High Pressure Coolant Injection

HX

Heat Exchanger

IA

Instrument Air

IMC

Inspection Manual Chapter

IN

Information Notice

IP

Inspection Procedure

IST

In-Service Test

LCO

Limiting Condition for Operation

LER

Licensee Event Report

LERF

Large Early Release Frequency

LOCA

Loss-of-Coolant Accident

LOP

Loss-of-Offsite Power

A-15

MCC

Motor Control Center

MOV

Motor-Operated Valve

NCV

Non-Cited Violation

NOTF

Notification

NPSH

Net Positive Suction Head

NRC

Nuclear Regulatory Commission

OE

Operating Experience

PARS

Publicly Available Records

PM

Preventive Maintenance

PRA

Probabilistic Risk Assessment

PRIB

Plant Risk Information e-Book

PSEG

Public Service Enterprise Group

PSID

Pounds Square Inch Differential

PVT

Periodic Verification Test

RACS

Reactor Auxiliaries Cooling System

RAW

Risk Achievement Worth

RF

Refueling Outage

RHR

Residual Heat Removal

RPV

Reactor Pressure Vessel

RRW

Risk Reduction Worth

SA

Service Air

SACS

Safety Auxiliaries Cooling System

SDP

Significance Determination Process

SLC

Standby Liquid Control

SPAR

Standardized Plant Analysis Risk

ST

Surveillance Test

SW

Service Water

TS

Technical Specification

UFSAR

Updated Final Safety Analysis Report

VDC

Volts, Direct Current

VTD

Vendor Technical Document

WCD

Work Clearance Document