UNITE D STATE S N UCLEAR REGULATORY C OMMI SS I ON WASHINGTON, DC 20555 - 0001 August 28, 2015 Administrative Judge Administrative Judge Ronald M. Spritzer, Chair Dr. Gary S. Arnold Atomic Safety and Licensing Board Panel Atomic Safety and Licensing Board Panel Mail Stop T-3 F23 Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Washington, DC 20555-0001 Administrative Judge Dr. Thomas J. Hirons Atomic Safety and Licensing Board Panel Mail Stop T-3 F23 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 In the Matter of ENTERGY NUCLEAR OPERATIONS, INC.

(Palisades Nuclear Plant)

Docket Nos. 50-255-LA-2

Dear Administrative Judges:

Pursuant to the Atomic Safety and Licensing Boards July 14, 2015, Initial Scheduling Order (ISO), the U.S. Nuclear Regulatory Commission (NRC) staff (Staff) is providing notification that the hearing file has been supplemented for this proceeding. An index containing the Agencywide Documents Access and Management System (ADAMS) accession number, date, and title or description of each item in the hearing file is appended hereto as Attachment 1.

On or about September 10, 2015, the documents identified in the hearing file may be accessed through ADAMS or through the Electronic Hearing Docket (EHD), which may be accessed at http://adams.nrc.gov/ehd/. The hearing file will be contained in the Staff Discovery Materials tab of the EHD, in a sub-folder entitled, Palisades Hearing File, Update 1 in the Palisades_50-255-LA-2" folder.

In addition, pursuant to 10 C.F.R. § 2.336(c), attached is the Affidavit of Jennivine K. Rankin, certifying that all relevant materials required by this section have been disclosed, and that the disclosures are accurate and complete as to documents identified by August 18, 2015.

Finally, the NRC Staff notes that it has made a good faith effort to identify and characterize all documents meeting the criteria of 10 C.F.R. § 2.336(b), 10 C.F.R. § 2.1203, and the ISO in this proceeding. In identifying these documents, the Staff does not concede their relevance to the issues to be decided in this proceeding.

Judge Spritzer August 28, 2015 Judge Arnold Judge Hirons Sincerely,

/Signed (electronically) by/

David E. Roth Counsel for NRC Staff

Enclosures:

Attachment 1 - Palisades Hearing File Index - Update 1 Affidavit of Jennivine K. Rankin cc w/Encls.: Service List

Attachment 1 - Palisades Hearing File Index Update 1 - August 28, 2015 Document ID# Location Title Date 02-0001 ML15230A137 12/31/1979 NUREG-0569, "Evaluation of the Integrity of SEP Reactor Vessels."

02-0002 ML15230A136 10/31/1982 NUREG-0744, Vol. 1, Rev. 1, "Resolution of the Task A-11 Reactor Vessel Materials Toughness Safety Issue." Part I - Main Report, Part II - Staff Responses to Public Comments, and Appendices A & B.

02-0003 ML15230A141 11/30/1990 NUREG-1424, "Safety Evaluation Report Related to the Full-Term Operating License for Palisades Nuclear Plant."

02-0004 ML020810482 02/21/1991 Palisades, Issuance of Full-Term Operating License DPR-20, Superseding Provisional Operating License.

02-0005 ML003768802 11/14/2000 Palisades Plant, Reactor Vessel Neutron Fluence Evaluation and Revised Schedule for Reaching Pressurized Thermal Shock Screening Criteria 02-0006 ML010890301 03/31/2001 Regulatory Guide 1.190, Calculational and Dosimetry Methods for Determining Pressure Vessel Neutron Fluence 02-0007 ML050940446 03/22/2005 Palisades Nuclear Plant, Application for Renewed Operating License. Cover Page through Appendix D.

02-0008 ML112870050 12/07/2011 Updated Reactor Pressure Vessel Pressurized Thermal Shock Evaluation for Palisades Nuclear Plant.

02-0009 ML13233A147 05/31/2013 Doel and Tihange 2 Reactor Pressure Vessels Final Evaluation Report.

02-0010 ML13242A263 09/22/2013 IN 2013-19 Quasi-Laminar Indications in Reactor Pressure Vessel Forgings.

02-0011 ML14038A265 01/30/2014 Potential Non-Conservatism in NRC Branch Technical Position 5-3.

02-0012 ML14070A206 03/13/2014 Memo: Results Of Periodic Review Of Regulatory Guide (RG) 1.161.

02-0013 ML14070A207 03/13/2014 RG 1.161 Periodic Review.

02-0014 ML15226A020 09/15/2014 Palisades Nuclear Plant Revision 31 to Final Safety Analysis Report, Section 4 Reference.

02-0015 ML15226A045 09/15/2014 Palisades Nuclear Plant Revision 31 to Final Safety Analysis Report, Section 4, Figure 4-11.

02-0016 ML15226A046 09/15/2014 Palisades Nuclear Plant Revision 31 to Final Safety Analysis Report, Section 4, Figure 4-12.

02-0017 ML15226A047 09/15/2014 Palisades Nuclear Plant Revision 31 to Final Safety Analysis Report, Section 4, Figure 4-13.

02-0018 ML15226A048 09/15/2014 Palisades Nuclear Plant Revision 31 to Final Safety Analysis Report, Section 4, Figure 4-14.

02-0019 ML15226A029 09/15/2014 Palisades Nuclear Plant Revision 31 to Final Safety Analysis Report, Section 4, Table 4-17.

02-0020 ML15226A030 09/15/2014 Palisades Nuclear Plant Revision 31 to Final Safety Analysis Report, Section 4, Table 4-18.

02-0021 ML15226A031 09/15/2014 Palisades Nuclear Plant Revision 31 to Final Safety Analysis Report, Section 4, Table 4-19.

02-0022 ML15226A033 09/15/2014 Palisades Nuclear Plant Revision 31 to Final Safety Analysis Report, Section 4, Table 4-20.

02-0023 ML15226A016 09/15/2014 Palisades Nuclear Plant Revision 31 to Final Safety Analysis Report, Section 4.5.

02-0024 ML15061A065 02/19/2015 Part I Assessment of BTP 5-3 Protocols - Public Meeting on February 19, 2015.

August 25, 2015 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

ENTERGY NUCLEAR OPERATIONS, INC. ) Docket Nos. 50-255-LA-2

)

(Palisades Nuclear Plant) )

AFFIDAVIT OF JENNIVINE K. RANKIN CONCERNING MANDATORY DISCLOSURE REQUIREMENT OF 10 C.F.R. § 2.336(b)

I, Jennivine K. Rankin, do hereby state as follows:

1. I am employed as a Project Manager in the U.S. Nuclear Regulatory Commissions (NRC) Office of Nuclear Reactor Regulation. I currently serve as a project manager for the Palisades Nuclear Plant. Among other things, I have been assisting with the preparation of the hearing file and mandatory disclosures in connection with the license amendment request at issue in this proceeding.
2. I hereby certify that all relevant materials required to be disclosed pursuant to 10 C.F.R. §§ 2.336 (b)-(c) and 2.1203 and the Boards July 14, 2015 Initial Scheduling Order in the captioned proceeding have been disclosed, and that the disclosures are accurate and complete for documents identified as of August 18, 2015.
3. I declare under penalty of perjury that the foregoing is true and correct to the best of my knowledge, information and belief.

Executed in Accord with 10 CFR 2.304(d)

Jennivine K. Rankin Project Manager U.S. Nuclear Regulatory Commission Washington, DC 20555 Telephone: (301) 415-1530 Email: Jennivine.Rankin@nrc.gov Executed in Rockville, Maryland this 25th day of August 2015

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION BEFORE THE ATOMIC SAFETY AND LICENSING BOARD In the Matter of )

)

ENTERGY NUCLEAR OPERATIONS, INC. ) Docket Nos. 50-255-LA-2

)

(Palisades Nuclear Plant) )

CERTIFICATE OF SERVICE Pursuant to 10 C.F.R § 2.305, I hereby certify that copies of the foregoing Letter to the Atomic Safety and Licensing Board regarding the Palisades Hearing File, including: Attachment 1 - Palisades Hearing File Index - Update 1 and Affidavit of Jennivine K. Rankin, dated August 25, 2015, in the above-captioned proceeding have been served upon the Electronic Information Exchange, the NRCs E-Filing System, this 28th day of August, 2015.

/Signed (electronically) by/

David E. Roth Counsel for NRC Staff U.S. Nuclear Regulatory Commission Office of the General Counsel Mail Stop - O-15D21 Washington, DC 20555 Telephone: (301) 415-2749 E-mail: david.roth@nrc.gov Date of signature: August 28, 2015