Presentation on Pilgrim Np Ma Ndcap Monthly Meeting Update 9-21-20 Meeting
ML21094A000
Person / Time
Site: Palisades, Big Rock Point  File:Consumers Energy icon.png
Issue date: 09/21/2020
From:
Comprehensive Decommissioning International, Holtec Decommissioning International
To:
Office of Nuclear Material Safety and Safeguards
SECY RAS
References
50-155-LT-2, 50-255-LT-2, License Transfer, Palisades & Big Rock Point-LT-2, RAS 56043
Download: ML21094A000 (8)


Text

MA NDCAP Monthly Meeting Update September 21, 2020

Site Overview New Pad Location Switchyard Engineering Support Building Main Entrance/

MAC8 Gate Turbine Building Reactor Building New Pad Location Warehouse New Haul Path Main Stack Current ISFSI Outfall Intake Breakwater TCF S-110 Change Shack

CONFIDENTIAL / SENSITIVE DRAFT PILGRIM WATERFALL SCHEDULE FOR PLANNING PURPOSES

11 Casks loaded onto the pad (28 total on pad) -

Completed August 3

Next Fuel campaign will be in Spring of 2021

New Protected Area and Haul Path for Upper ISFSI Under Construction

Removal of Control Rod Drive Mechanisms (CRDMs) completed in August 2020

Reactor vessel internals segmentation and removal of Greater than Class C Waste to begin in Fall 2020 Fuel Campaign

Early Building Demolition - K-1 Building

Early Building Demolition - S-110 Buildings

Early Building Demolition - Main Stack, Met Tower, Change Shack, & Gas Bottle Storage Area 7

Community Support - Plymouth Area Chamber 8