Letter Sequence Other |
---|
|
|
MONTHYEARMNS-14-025, Submittal of Flood Hazard Reevaluation Report, Response to NRC 10 CFR 50.54(f) Request for Information Re Recommendations 2.1, 2.3 & 9.3 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident2014-03-12012 March 2014 Submittal of Flood Hazard Reevaluation Report, Response to NRC 10 CFR 50.54(f) Request for Information Re Recommendations 2.1, 2.3 & 9.3 of the Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident Project stage: Request ML14142A3512014-05-28028 May 2014 Request for Additional Information Regarding Flood Hazard Reevaluation Report Project stage: RAI ML15100A3662015-04-0909 April 2015 NRR E-mail Capture - McGuire Nuclear Station-Fukushima 2.1 Flooding-FHRR Review RAIs Project stage: Other ML15230A0702015-09-0303 September 2015 Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10CFR50.54 Information Request - Flood Causing Mechanism Reevaluation Project stage: Other ML15226A5252015-09-0303 September 2015 HAhn_8-13-2015 Project stage: Other ML16293A6662016-10-31031 October 2016 Staff Assessment of Response to 10 CFR 50.54(f) Information Request - Flood Causing Mechanism Reevaluation (CAC Nos. MF3623 and MF3624) Project stage: Other MNS-17-030, Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal2017-06-28028 June 2017 Response to March 12, 2012, Request for Information Enclosure 2, Recommendation 2.1, Flooding, Required Response 3, Flooding Focused Evaluation Summary Submittal Project stage: Request 2015-04-09
[Table View] |
|
---|
Category:Graphics incl Charts and Tables
MONTHYEARRA-20-0263, Duke Energy Corp. - Request to Use Provision of Later Edition and Addenda of ASME Boiler and Pressure Vessel Code, Section XI for Repair/Replacement Activities in Accordance with 10 CFR 50.55a(g)(4)(iv)2020-09-16016 September 2020 Duke Energy Corp. - Request to Use Provision of Later Edition and Addenda of ASME Boiler and Pressure Vessel Code, Section XI for Repair/Replacement Activities in Accordance with 10 CFR 50.55a(g)(4)(iv) ML16056A1392016-03-11011 March 2016 Correction to the U.S. Nuclear Regulatory Commission Analysis of Licensees' Decommissioning Funding Status Reports ML15230A0702015-09-0303 September 2015 Interim Staff Response to Reevaluated Flood Hazards Submitted in Response to 10CFR50.54 Information Request - Flood Causing Mechanism Reevaluation ML15226A5252015-09-0303 September 2015 HAhn_8-13-2015 ML15141A0542015-05-0707 May 2015 Enclosure 6, MNS EAL Wallcharts ML14307B7072014-12-10010 December 2014 Supplemental Information Related to Development of Seismic Risk Evaluations for Information Request Pursuant to Title 10 of the Code of Federal Regulations 50.54(f) Regarding Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-T ML1214500142012-05-23023 May 2012 NFPA 805 LAR Status Matrix - May 2012 ML11207A4572011-07-21021 July 2011 Report Pursuant to 10 CFR 50.46, Changes to or Errors in an ECCS Evaluation Model ML1025600662010-09-0808 September 2010 Response to Request for Additional Information Related to the License Amendment Request Applicable to Technical Specification (TS) 3.8.4 DC Sources-Operating ML0828300142008-10-0606 October 2008 Response to Request for Additional Information License Amendment Request for Implementation of Alternative Source Term ML0823302222008-08-20020 August 2008 Choice Letter Attachment Q - Pump Strainer Dp Data Analysis ML0728203072007-10-11011 October 2007 Electronic Distribtion Initiative Letter, Licensee List, Electronic Distribution Input Information, Division Plant Mailing Lists ML0715002972007-05-22022 May 2007 Units 1 & 2 - Report Pursuant to 10 CFR 50.46, Changes to or Errors in an ECCS Evaluation Model 2020-09-16
[Table view] Category:Letter
MONTHYEARIR 05000369/20230042024-01-31031 January 2024 Integrated Inspection Report 05000369/2023004 and 05000370/2023004 ML24019A1392024-01-25025 January 2024 TSTF 505 and 50.69 Audit Summary ML24019A2002024-01-24024 January 2024 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection IR 05000369/20234022023-12-14014 December 2023 Material Control and Accounting Program Inspection Report 05000369/2023402 and 05000370/2023402 ML23317A2272023-11-17017 November 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Transmittal of Dam Inspection Report - Non-Proprietary ML23317A3462023-11-14014 November 2023 Duke Fleet - Correction Letter to License Amendment Nos. 312 & 340 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230032023-10-24024 October 2023 Integrated Inspection Report 05000369/2023003 and 05000370/2023003; and Inspection Report 07200038/2023001 IR 05000369/20240102023-10-13013 October 2023 Notification of McGuire Nuclear Station Comprehensive Engineering Team Inspection U.S. Nuclear Regulatory Commission Inspection Report 05000369, 370/2024010 IR 05000369/20230102023-10-13013 October 2023 Age Related Degradation Inspection Report 05000369/2023010 and 05000370/2023010 ML23256A0882023-09-25025 September 2023 Issuance of Alternative to Steam Generator Welds IR 05000369/20233012023-09-20020 September 2023 William B. McGuire Nuclear Station - NRC Examination Report 05000369/2023301 and 05000370/2023301 ML23230A0652023-08-31031 August 2023 William B. McGuire Nuclear Station, Units 1 and 2 - Relief Request Use of Later Edition of ASME Code ML23195A0782023-08-29029 August 2023 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-554, Revision 1 IR 05000369/20230052023-08-25025 August 2023 Updated Inspection Plan for McGuire Nuclear Station Units 1 and 2 (Report 05000369/2023005 and 05000370/2023005) IR 05000369/20230022023-07-28028 July 2023 Integrated Inspection Report 05000369/2023002 and 05000370/2023002 IR 05000369/20234202023-07-24024 July 2023 Security Baseline Inspection Report 050003692023420 and 050003702023420 ML23206A0092023-07-24024 July 2023 William B. McGuire Nuclear Station Operator Licensing Written Examination Approval 05000369/2023301 and 05000370/2023301 ML23207A0762023-07-14014 July 2023 EN 56557 - Update to Part 21 Report Re Potential Defect with Trane External Auto/Stop Emergency Stop Relay Card Pn: XI2650728-06 ML23159A2712023-06-20020 June 2023 William B. McGuire Nuclear Station, Unit 1 - Relief Request Impractical Reactor System Welds ML23237A2672023-06-13013 June 2023 June 13, 2002 - Meeting Announcement - McGuire and Catawba Nuclear Stations 50-369, 50-370 and 50-413, 50-414 ML23159A0052023-06-0505 June 2023 56557-EN 56557 - Paragon - Redlined ML23115A2122023-05-0101 May 2023 Review of the Spring 2022 Steam Generator Tube Inspection Report ML23118A0762023-05-0101 May 2023 Approval for Use of Specific Provision of a Later Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI IR 05000369/20230012023-05-0101 May 2023 Integrated Inspection Report 05000369/2023001 and 05000370/2023001 ML23094A1832023-04-18018 April 2023 Audit Plan TSTF-505, Rev. 2, RITSTF Initiative 4B & 10 CFR 50.69, Risk-Informed Categorization & Treatment of Structures, Systems & Components for Nuclear Power Reactors (EPIDs L-2023-LLA-0021 & L-2023-LLA-0022) ML22332A4932023-03-10010 March 2023 William States Lee III 1 and 2 - Issuance of Amendments Regarding the Relocation of the Emergency Operations Facility IR 05000369/20220062023-03-0101 March 2023 Annual Assessment Letter for McGuire Nuclear Station Units 1 and 2 (NRC Inspection Report 05000369/2022006 and 05000370 2022006) IR 05000369/20220042023-01-30030 January 2023 Mcguire Nuclear Station - Integrated Inspection Report 05000369/2022004 and 05000370/2022004 IR 05000369/20224202023-01-11011 January 2023 Security Baseline Inspection Report 05000369/2022420 and 05000370/2022420 ML22356A0512022-12-14014 December 2022 Curtiss-Wright Nuclear Division, Letter Regarding Potential Efect in a Configuration of the 11/2 Inch Quick Disconnect Connector Cable Assemblies Supplied to Duke Energy (See Attached Spreadsheet) for a Total of 460 of Connectors Only Suppl ML22347A1512022-12-13013 December 2022 William B. Mcguire Nuclear Station Notification of Licensed Operator Initial Examination 05000369/2023301 and 05000370/2023301 ML22340A6662022-12-0808 December 2022 Summary of November 30, 2022, Public Meeting with Duke Energy Carolinas, LLC for McGuire Nuclear Station, Units 1 & 2 Proposed LAR to Adopt TSTF-505, Rev. 2 and 10 CFR 50.69 Risk-Informed Categorization and Treatment of Structures, Systems ML22290A1012022-11-29029 November 2022 Issuance of Amendment Nos. 326 and 305, Regarding Changes to Technical Specification 3.4.3, Reactor Coolant System Pressure Temperature Limits ML22096A0032022-11-18018 November 2022 McGuire Nuclear Station and Shearon Harris Nuclear Power Plant Authorization of RA-19-0352 Regarding Use of Alternative for RPV Head Closure Stud Examinations ML22256A2532022-11-14014 November 2022 Issuance of Amendments Regarding the Adoption of Technical Specifications Task Force Traveler TSTF-541, Rev. 2 IR 05000369/20220032022-10-27027 October 2022 Integrated Inspection Report 05000369/2022003 and 05000370/2022003 IR 05000369/20220112022-09-29029 September 2022 Biennial Problem Identification and Resolution Inspection Report 05000369/2022011 and 05000370/2022011 ML22266A0782022-09-26026 September 2022 William B. Mcguire Nuclear Station, Unit 2 Pressurizer Power Operated Relief Valve Relief Request ML22258A0302022-09-15015 September 2022 Evacuation Time Estimate Reports ML22242A0022022-09-12012 September 2022 Issuance of Amendments to Adopt TSTF 569, Revision 2, Revise Response Time Testing Definition IR 07200038/20220012022-09-12012 September 2022 Operation of an Independent Spent Fuel Storage Installation Report 07200038/2022001 ML22230B6132022-09-0101 September 2022 Review of the Draft Environmental Assessment and Finding of No Significant Impact for Brunswick Steam Electric Plant and McGuire Nuclear Station Independent Spent Fuel Storage Installations Decommissioning Funding Plans IR 05000369/20220052022-08-29029 August 2022 Updated Inspection Plan for McGuire Nuclear Station Units 1 and 2 NRC Inspection Report 05000369/2022005 and 05000370/2022005 IR 05000369/20220022022-07-26026 July 2022 Integrated Inspection Report 05000369/2022002 and 05000370/2022002 ML22215A2502022-07-25025 July 2022 EN 55960 - Update - Curtiss Wright ML22164A0362022-07-19019 July 2022 Mcguire Nuclear Station, Units 1 and 2; Issuance of Amendments to Revise the Conditional Exemption of the End-Of-Cycle Moderator Temperature Coefficient Measurement Methodology (EPID L-2021-LLA-0198) Public ML22175A0162022-06-24024 June 2022 Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML22046A0222022-06-14014 June 2022 Issuance of Amendments to Adopt TSTF-439, Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML22111A3112022-05-16016 May 2022 Letter Issuing Exemption to McGuire IR 05000369/20224012022-05-12012 May 2022 Cyber Security Inspection Report 05000369/2022401 and 05000370/2022401 2024-01-31
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 3, 2015 Mr. Steven D. Capps Vice President - McGuire Site Duke Energy Carolinas, LLC McGuire Nuclear Station 12700 Hagers Ferry Road Huntersville, NC 28078-8985
SUBJECT:
MCGUIRE NUCLEAR STATION, UNITS 1 AND 2 - INTERIM STAFF RESPONSE TO REEVALUATED FLOOD HAZARDS SUBMITTED IN RESPONSE TO 10 CFR 50.54(f) INFORMATION REQUEST- FLOOD-CAUSING MECHANISM REEVALUATION (TAC NOS. MF3623 AND MF3624)
Dear Mr. Capps:
The purpose of this letter is to provide a summary of the U.S. Nuclear Regulatory Commission (NRC) staff's assessment of the re-evaluated flood-causing mechanisms described in the March 12, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14083A415), flood hazard reevaluation report (FHRR) submitted by Duke Energy Carolinas, LLC (Duke, the licensee) for the McGuire Nuclear Station, Units 1 and 2 (McGuire), as well as supplemental information resulting from requests for additional information and audits.
By letter dated March 12, 2012, the NRC issued a request for information pursuant to Title 10 of the Code of Federal Regulations, Section 50.54(f) (hereafter referred to as the 50.54(f) letter)
(ADAMS Accession No. ML12053A340). The request was issued as part of implementing lessons-learned from the accident at the Fukushima Dai-ichi nuclear power plant. Enclosure 2 to the 50.54(f) letter requested licensees to re-evaluate flood-causing mechanisms using present-day methodologies and guidance. Concurrently, with the reevaluation of flooding hazards, licensees were required to develop and implement mitigating strategies in accordance with NRC Order EA-12-049, "Requirements for Mitigation Strategies for Beyond-Design-Basis External Events" (ADAMS Accession No. ML12054A735). On March 30, 2015, the Commission provided Staff Requirements Memoranda (SRM) (ADAMS Accession No. ML15089A236) to COMSECY-14-0037, "Integration of Mitigating Strategies for Beyond-Design-Basis External Events and the Reevaluation of Flooding Hazards," dated November 21, 2014 (ADAMS Accession No. ML14309A256), affirming that licensees need to address the reevaluated flooding hazards within their mitigating strategies for beyond-design-basis external events.
The NRC staff has reviewed this information and has summarized the results of the review in the tables provided as an Enclosure to this letter. Table 1 provides the current design-basis flood hazard mechanisms. Table 2 provides the reevaluated flood hazard mechanisms;
S. Capps however, the reevaluated flood hazard mechanisms bounded by the current design-basis (Table
- 1) are not included.
The NRC staff has concluded that the licensee's reevaluated flood hazards information, as summarized in the Enclosure, is suitable for the assessment of mitigating strategies developed in response to Order EA-12-049 (i.e., defines the mitigating strategies flood hazard information described in guidance documents currently being finalized by the industry and NRC staff), for McGuire. Further, the NRC staff has concluded that the licensee's reevaluated flood hazard information is a suitable input for other assessments associated with Near-Term Task Force Recommendation 2.1 "Flooding". The NRC staff plans to issue a staff assessment documenting the basis for these conclusions at a later time.
In addition, NEI 12-06 "Diverse and Flexible Coping Strategies (FLEX) Implementation Guide" is currently being revised. This revision will include a methodology to perform a Mitigating Strategies Assessment (MSA) with respect to the reevaluated flood hazards. Once this methodology is endorsed by the NRC, flood event duration parameters and applicable flood associated effects should be considered as part of the McGuire MSA. The NRC staff will evaluate the flood event duration parameters (including warning time and period of inundation) and flood-related associated effects developed by the licensee during the NRC staff's review of the MSA.
As stated above, Table 2 of the enclosure to this letter describes the reevaluated flood hazards that exceed the current design-basis. In order to complete its response to the information requested by Enclosure 2 to the 50.54(f) letter, the licensee is expected to submit an integrated assessment or a focused evaluation, as appropriate, to address these reevaluated flood hazards, as described in the NRC letter, "Coordination of Request for Information Regarding Flooding Hazard Reevaluation and Mitigating Strategies for Beyond Design Basis External Events" (ADAMS Accession No. ML15174A257). This letter describes the changes in the NRC's approach to the flood hazard reevaluations that were approved by the Commission in its SRM to COMSECY-15-0019, "Closure Plan for the Reevaluation of Flooding Hazards for Operating Nuclear Power Plants" (ADAMS Accession No. ML15209A682).
S. Capps If you have any questions, please contact me at (301) 415-3809 or e-mail at Juan.Uribe@nrc.gov.
Sincerely, 1 J:1 Uribe, Project Manager ._
Hazards Management Branch Japan Lessons-Learned Division Office of Nuclear Reactor Regulation Docket Nos. 50-369 and 50-370
Enclosure:
Summary of Results of Flooding Hazard Re-Evaluation Report cc w/encl: Distribution via Listserv
ENCLOSURE:
SUMMARY
TABLES OF REEVALUATED FLOOD HAZARD LEVELS
McGuire, Units 1 & 2 Table 1. Current Design Basis Flood Hazards for Use in the MSA Mechanism Stillwater Waves/ Design Basis Reference I Elevation Run up Hazard I
- --- - - - -- ~ ----
Elevation Local Intense Precipitation 760.4 ft msl 0.0 ft 760.4 ft msl FHRR Section 1.2.1 Streams and Rivers Reservoir Level at Cowans 767.9 ft msl 5.1 ft 773.0 ft msl FHRR Section 1.2.2 I
Ford Dam FHRR Section 1.2.8 (Table 1.2.8-1)
Failure of Dams and Onsite Water Control/Storage Structures Upstream Dam Failures 762.6 ft msl 5.1 ft I 767.7 ft msl FHRR Section 1.2.3 (combined event) FHRR Section 1.2.3 (Table 1.2.8-1)
I i
Standby Nuclear Service Water 746.9 ft msl 1.5 ft 748.4 ft msl FHRR Table 3-1 Pond (combined event)
Standby Nuclear Service Water 727.8 ft msl Not 727.8 ft msl FHRR Table 3-1 Pond Dam Downstream applicable (combined event)
Storm Surge Surge in Lake Norman 760.0 ft msl 14.8 ft 774.8 ft msl FHRR Section 1.2.4 Seiche No Impact No Impact No Impact FHRR Section 1.2.4 on the Site on the Site on the Site Identified Identified Identified Tsunami Not included Not included Not included FHRR Section 1.2 in DB in DB in DB I
-- - - - - -- ____j_ ----------- ---- _____L
McGuire, Units 1 & 2 Table 1. Current Design Basis Flood Hazards for Use in the MSA I Mechanism Stillwater Waves/ Design Basis Reference I
I Elevation Run up Hazard I i Elevation I Ice-Induced Flooding i
I Not included Not included Not included FHRR Section 1.2 in DB in DB in DB I I I I Channel Migrations/Diversions Not included Not included Not included FHRR Section 1.2 in DB in DB in DB Note 1: Reported values are rounded to the nearest one-tenth of a foot.
Note 2: The wave hieght value of 5.1 ft for the Streams and Rivers, and Upstream Dam Failures (combined event) is wave setup plus runup.
McGuire, Units 1 & 2 Table 2. Reevaluated Flood Hazards for Flood-Causing Mechanisms for Use in the MSA 1- - --
Mechanism Stillwater Waves/ Reevaluated Reference Elevation Run up Hazard Elevation Local Intense Precipitation 761.1ftmsl Minimal 761.1ftmsl FHRR Section 2.1 I
I Strea~s and Rivers ___ --+---- . , ,.
I River PMF in Lake Norman 777.9 ft msl Not 777.9 ft msl FHRR Section 2.2 and 2.8 applicable I
Failure of Dams and Onsite Water Control/Storage Structures Upstream Dam Failures 778.5 ft msl Not 778.5 ft msl FHRR Section 2.3 and 2.8 (combined event) applicable Standby Nuclear Service Water 735.9 ft msl 0.9 ft 736.8 ft msl FHRR Tables 2.4.2-1 and 2.4.2-2 Pond Dam Downstream (combined event)
Storm Surge 778.5 ft msl 0.0 ft 778.5 ft msl FHRR Table 3-1 FHRR Section 2.4.1(Table2.4.1-1)
Note 1: The licensee is expected to develop flood event duration parameters and applicable flood associated effects to conduct the MSA. The staff will evaluate the flood event duration parameters (including warning time and period of inundation) and flood associated effects during its review of the MSA.
Note 2: Reevaluated hazard mechanisms bounded by the current design basis (see Table 1) are not included in this table.
Note 3: Reported values are rounded to the nearest one-tenth 6f a foot.
PKG ML15230A161, LTR: ML15230A070, ENCL: ML15226A525 *via email OFFICE NRR/JLD/JHMB/PM NRR/JLD/LA NRO/DSEA/RHM2ffR*
NAME JUribe Slent HAhn DATE 8/18/2015 8/18/2015 8 / 17 /15 OFFICE NRR/JLD/JHMB/BC NRO/DSEA/RHM2/BC* NRR/JLD/JHMB/PM NAME MShams ARivera-Varona JUribe DATE 8 / 28 /15 8 / 17 /15 9 / 3 /15