October 23, 2014 L-2014-3i9 FPL Mark Bates Chief Examiner, Region II U. S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Initial Operator Examination Outlines In accordance with the requirements of NUREG- 1021, Operator Licensing Examination Standards for Power Reactors, Revision 9 Supp. 1, Florida Power and Light (FPL) is submitting herein the following initial license examination outlines for the Turkey Point Nuclear Plant for the January 2015 examination:

ES-20l-2 Examination Outline Quality Checklist ES-201-3 Examination Security Agreement (copy)

ES-3 01-1 Administrative Topics Outline (RO)

ES-301-l Administrative Topics Outline (SRO-1 and U)

ES-301-2 Control Roomlln-Plant Systems Outline (RO)

ES-301-2 Control Roomlln-Plant Systems Outline (SRO-1)

ES-30l-2 Control Room/in-Plant Systems Outline (SRO-U)

ES-30l-5 Transient and Event Checklist (4 scenarios listed)

ES-D-1 Scenario Outline (4 scenarios)

ES-401 -4 Record of Rejected KIAs PTN KIA Suppression List Florida Power & Light Company 9760 SW. 344° Street Homestead, FL 33035

L-2014-319 Page 2 Pursuant to the provisions of NUREG 1021. Revision 9, Supp. 1, the enclos ed material shall be withheld from public disclosure until after the examinations are compl ete. Should there be any questions, please contact Mark Wilson at (305) 246-6900.

Very truly yours, Michael W. Kiley.

Vice President Turkey Point Nuclear Plant Enclosure cc: Chief, Operations Branch, Division of Reactor Safety, Region II, w/o enclosure Document Control Desk, USNRC, Washington, D.C., w/o enclosure Senior Resident Inspector, USNRC, Turkey Point Nuclear Plant, wlo enclos ure

November 26, 2014 L-2014-356 FL. 10 CFR2.390 Mark Bates Chief Examiner, Region II U. S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta. GA 30303-1257 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-25 1 Initial Operator Examination 45 Day Submittal In accordance with the requirements ofNUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9, Florida Power and Light (FPL) is submitting herein the following initial license examination checklists, outlines, scenarios and JPMs for the Turkey Point Nuclear Plant for the January 2015 examination:

ES-201-2 Examination Outline Quality Checklist ES-201-3 Examination Security Agreement (copy)

ES-301-l Administrative Topics Outline (RO)

ES-301-1 Administrative Topics Outline (SRO-I and U)

ES-301-2 Control Room/In-Plant Systems Outline (RO)

ES-301-2 Control Roomlln-Plant Systems Outline (SRO-l)

ES-301-2 Control Roomlln-Plant Systems Outline (SRO-U)

ES-301-3 Operating Test Quality Checklist ES-3 01-4 Simulator Scenario Quality Checklist ES-301-5 Transient and Event Checklist ES-3 01-6 Competencies Checklist ES C-I Administrative JPMs (seven)

ES C-i Control Room and In-Plant JPMs (eleven)

ES-D-Is Scenario Outlines (four)

ES-D-2s Simulator Scenarios (four)

Requested Electronic Exam Material Florida Power & Light Company 9760 SW. 344 Street Homestead. FL 33035

L-2014-356 Page 2 Pursuant to the provisions ofNUREG 1021. Revision 9, Supp. 1, the enclosed material shall be withheld from public disclosure until after the examinations are complete. Should there be any questions, please contact Mark Wilson at (305) 246-6900.

Very truly yours.

Michael W. Kiley.

Vice President Turkey Point Nuclear Plant Enclosure cc: Chief, Operations Branch, Division of Reactor Safety, Region II, w/o enclosure Document Control Desk, USNRC. Washington, D.C.. wlo enclosure Senior Resident Inspector, USNRC. Turkey Point Nuclear Plant. w/o enclosure

0 PPL DEC 042014 Mark Bates Chief Examiner, Region II U. S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-25 1 Initial Operator Examination 45 Day Submittal In accordance with the requirements ofNUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9, Florida Power and Light (FPL) is submitting herein the following initial license examination checklists and written examination (plus key) for the Turkey Point Nuclear Plant for the January 2015 examination:

ES-20 1-2 Examination Outline Quality Checklist ES-401-5 Written Examination Key with Reference Material for Each Question ES-401-6 Written Examination Quality Checklist Requested Electronic Exam Material Pursuant to the provisions of NUREG 1021, Revision 9, Supp. 1, the enclosed material shall be withheld from public disclosure until after the examinations are complete. Should there be any questions, please contact Mark Wilson at (305) 246-6900.

Very truly yours, Michael W. Kiley.

Vice President Turkey Point Nuclear Plant Enclosure cc: Chief, Operations Branch, Division of Reactor Safety, Region II, w!o enclosure Document Control Desk, USNRC, Washington, D.C., w/o enclosure Senior Resident Inspector, USNRC, Turkey Point Nuclear Plant, w/o enclosure FlorEda Power & LiQht Company 9760 SW. 344th Street Homestead, FL 33035

2015 L-2015-005 FPL. 10 CFR 2.3 90 Mark Bates Chief Examiner, Region II U. S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 Initial Operator Final Operating Examination Submittal In accordance with the requirements ofNUREG-1021, Operator Licensing Exami nation Standards for Power Reactors, Revision 9, Florida Power and Light (FPL) is submitting herein the following initial license examination checklists, outlines, scenarios, and JPMs for the Turkey Point Nuclear Plant for the January 2015 examination:

ES-201-2 Examination Outline Quality Checklist ES-201-3 Examination Security Agreement (copy)

ES-301-1 Administrative Topics Outlines (RO) and (SRO-I and U)

ES-301-2 Control Room/In-Plant Systems Outlines (RO), (SRO-I), and (SRO-U)

ES-30l-3 Operating Test Quality Checklist ES-30l-4 Simulator Scenario Quality Checklist ES-30l-5 Transient and Event Checklist ES-301-6 Competencies Checklist ES C-I Administrative JPMs (seven)

ES C-I Control Room and In-Plant JPMs (eleven)

ES-D- is Scenario Outlines (four)

ES-D-2s Simulator Scenarios (four)

Pursuant to the provisions of NUREG 1021, Revision 9, Supp. I, the enclosed materi al shall be withheld from public disclosure until after the examinations are complete. Should there be any questions, please contact Mark Wilson at (305) 246-6900.

Very truly yours, Michael Kiley.

Vice President Turkey Point Nuclear Plant Enclosure cc: Chief Operations Branch, Division of Reactor Safety, Region II, w/o enclos ure Regional Administrator, Region II, USNRC Document Control Desk, USNRC, Washington, D.C., w/o enclosure Senior Resident Inspector, USNRC, Turkey Point Nuclear Plant, w/o enclosure Florida Power & Light Company 9760 SW. 344 th Street Homestead, FL 33035

FEB 102015 L-2015-039 FPL. 10 CFR 2.390 Mark Bates Chief Examiner. Region 11 U. S. Nuclear Regulatory Com mission Marquis One Tower 245 Peachtree Center Ave.. NE Suite 1200 Atlanta. GA 30303-1257 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 tial Operator Written Examination Submittal In accordance with the requiremen ts ofNUREG-1021. Operator Lic Power Reactors. Revision 9. Flo ensing Examination Standards for rida Power and Light (FPL) is sub license examination checklists and mit ting herein the following initial written examination (plus key) the February 201 5 examination: for the Turkey Point Nuclear Plant for ES-201-2 Examination Outline Qua lity Checklist ES-40 I -4 Record of Rejected K/A s

ES-401-5 Written Examination Key with Reference Material for Each ES-401-6 Written Examination Qua Question lity Checklist Requested Electronic Exam Materi al Pursuant to the provisions ofNUR EG 1021. Revision 9. Supp. 1. the from public disclosure until afier enclosed material shall be withheld the examinations are complete. Sho contact Mark Wilson at (305) 246 uld there be any questions, please

-6900.

Ven truh yours.

Michael Kilev.

Vice President Turkey Point Nuclear Plant Enclosure cc: Chiet Operations Branch. Divisio n of Reactor Safety. Region II, w/o enc Document Control Desk. USNRC. Wa losure shington, D.C.. w/o enclosure Senior Resident Inspector. USNRC. Tur key Point Nuclear Plant. w/o enclosu re Florida Power& Light Company 9760 SW 344tF Street Homestead, FL 33035

FEB242015 10 CFR 2.390 PPL. L-201 5-02 1 Victor McCree Regional Administrator, Region II Attn: Mark Bates U. S. Nuclear Regulatory Commission Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, GA 30303-1257 Re: Turkey Point Units 3 and 4 Docket Nos. 50-250 and 50-251 FPL Comments for the 2015 Written NRC License Exami nation In accordance with NUREG-1021, Operators Licensing Exami nation Standards for Power Reactors, Section ES-402, Administering Initial Written Examination, Subsection E.5, Post-Examination Reviews, Florida Power & Light Company (FPL) submits herein for your review and evaluation applicant comments for the site-specific licensed operator written examination, administered at Turkey Point on February 18, 2015.

FPL has considered the guidance provided in ES-403 Sect ion Dl, Evaluate Questions and Comments, and found that four of these comments meet the review criteria and should be submitted to NRC for post examination modification of the answer key. FPL is providing a recommendation as to whether the answer should be chan ged or the question should be deleted for each of the comments submitted.

The written examination answer key is provided in Atta chment 1. The post written examination comments and related information are provided in Attachm ent 2.

The attachments shall be withheld from public disclosur e due to examination sensitive material.

Should there be any questions, please contact Mark Wilson at (305) 246-6900.

Sincer ly Michael Kiley Vice President Turkey Point Nuclear Plant Attachments SM cc: Chief, Operations Branch, Division of Reactor Safety, Regi on II, USNRC Chief Examiner, Region II, USNRC Senior Resident Inspector, USNRC, Turkey Point Plant Document Control Desk, USNRC, Washington, D.C.