March 4, 2015, NRC Generic Fundamentals Examination Results for Millstone Power Station, Unit No. 2 (Cover Letter Publicly Available, Enclosures Withheld from Public)
ML15091A211
Person / Time
Site: Millstone Dominion icon.png
Issue date: 03/30/2015
From: Diane Jackson
Operations Branch I
To: Daugherty J
Dominion Nuclear Connecticut
References
Download: ML15091A211 (2)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 March 30, 2015 Mr. John R. Daugherty Site Vice President Dominion Nuclear Connecticut, Inc.

Millstone Power Station, Unit 2 Rope Ferry Road, Route 156 PO Box 128 Waterford, CT 06385

SUBJECT:

MARCH 4, 2015, NRC GENERIC FUNDAMENTALS EXAMINATION RESULTS FOR MILLSTONE POWER STATION, UNIT NO. 2 (COVER LETTER PUBLICLY AVAILABLE, ENCLOSURES WITHHELD FROM PUBLIC)

Dear Mr. Daugherty:

On March 4, 2015, the NRC administered the generic fundamentals examination (GFE) section of the written operator licensing examination to employees of your facility. All nine applicants passed the exam. Enclosed with this letter are copies of the final answer key, the grading results for your facility, and copies of individual examination answer sheets for each of your employees. Please forward the results to the individuals along with the copies of their respective answer sheets.

A copy of the PWR GFE and the answer key are available for your review on the NRCs web site approximately 60 days following the examination administration date at:

http://www.nrc.gov/reactors/operator-licensing/generic-fundamentals-examinations/past-exams.html#pwr If you have any questions concerning the examination, please contact me at 610-337-5306.

Sincerely,

/RA/

Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket No. 50-336 Enclosures (Non-Public):

1. March 2015, NRC GFE Roster Report on Total and Grade for Millstone
2. Individual NRC Examination Answer Sheets cc w/o enclosures: Distribution via ListServ

Mr. John R. Daugherty Site Vice President Dominion Nuclear Connecticut, Inc.

Millstone Power Station, Unit 2 Rope Ferry Road, Route 156 PO Box 128 Waterford, CT 06385

SUBJECT:

MARCH 4, 2015, NRC GENERIC FUNDAMENTALS EXAMINATION RESULTS FOR MILLSTONE POWER STATION, UNIT NO. 2 (COVER LETTER PUBLICLY AVAILABLE, ENCLOSURES WITHHELD FROM PUBLIC)

Dear Mr. Daugherty:

On March 4, 2015, the NRC administered the generic fundamentals examination (GFE) section of the written operator licensing examination to employees of your facility. All nine applicants passed the exam. Enclosed with this letter are copies of the final answer key, the grading results for your facility, and copies of individual examination answer sheets for each of your employees. Please forward the results to the individuals along with the copies of their respective answer sheets.

A copy of the PWR GFE and the answer key are available for your review on the NRCs web site approximately 60 days following the examination administration date at:

http://www.nrc.gov/reactors/operator-licensing/generic-fundamentals-examinations/past-exams.html#pwr If you have any questions concerning the examination, please contact me at 610-337-5306.

Sincerely,

/RA/

Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket No. 50-336 Enclosures (Non-Public):

1. March 2015, NRC GFE Roster Report on Total and Grade for Millstone
2. Individual NRC Examination Answer Sheets cc w/o enclosures: Distribution via ListServ DOCUMENT NAME: G:\DRS\Operations Branch\GFE\2015\MS 03-04-GFE ResultsLtr.docx ADAMS PACKAGE NO.: ML15083A149 ADAMS NO.: ML15091A211 SUNSI Review Non-Sensitive Publicly Available OFFICE RI/DRS/OB RI/DRS/OB NAME GPowell/CBixler DEJackson DATE 03/24/15 03/30/15 OFFICIAL RECORD COPY