Dominion Energy Nuclear Connecticut, Inc.
5000 Dominion Boulevard, Glen Allen, VA 23060 Dominion Energy.com December 20, 2023 United States Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001 DOMINION ENERGY NUCLEAR CONNECTICUT, INC.
MILLSTONE POWER STATION UNITS 2 AND 3 ii@!;. Dominion
~
Energf)FR 50
~
10CFR51 Serial No.:
NRA/DEA:
Docket Nos.:
License Nos.:
10 CFR 54 23-405 RO 50-336 50-423 DPR-65 NPF-49 INTENT TO PURSUE SUBSEQUENT LICENSE RENEWAL This letter provides advance notification that Dominion Energy Nuclear Connecticut (DENG), on behalf of itself, Green Mountain Power Corporation and Massachusetts Municipal Wholesale Electric Company, intends to submit subsequent license renewal applications for Millstone Power Station Unit 2 (MPS2) and Unit 3 (MPS3).
The first renewed Operating Licenses for MPS2 and MPS3 were issued on November 28, 2005, and will expire at midnight on July 31, 2035, and November 25, 2045, respectively.
DENG intends to submit separate applications for subsequent renewal of the MPS2 and MPS3 renewed Operating Licenses in accordance with 10 CFR Part 54, "Requirements for Renewal of Operating Licenses for Nuclear Power Plants," by the end of the 4th quarter of 2027.
This notification is consistent with NRC Regulatory Issue Summary (RIS) 2009-06, "Importance of Giving NRC Advance Notice of Intent to Pursue License Renewal" (ADAMS Accession No. ML090540789). As discussed in RIS 2009-006, DENC will inform the NRC of any changes to the anticipated schedule for filing the subsequent license renewal applications for Millstone Power Station to facilitate NRC efforts to plan for processing of the subsequent license renewal applications.
If there are any questions regarding this submittal or if additional information is needed, please contact Mr. Keith Miller at keith.j.miller@dominionenergy.com.
Sincerely,
~
James E. Holloway Vice President - Nuclear Engineering and Fleet Support Commitments made in this letter: None
cc: U.S. Nuclear Regulatory Commission Region I 475 Allendale Road, Suite 105 King of Prussia, PA 19406-1415 Mr. Brian W. Smith Director, Division of New and Renewed Licenses U.S. Nuclear Regulatory Commission One White Flint North Mail Stop 012 E-4 11555 Rockville Pike Rockville, Maryland 20852-2738 Mr. Richard V. Guzman NRC Senior Project Manager U. S. Nuclear Regulatory Commission One White Flint North Mail Stop 09 E-3 11555 Rockville Pike Rockville, Maryland 20852-2738 NRC Senior Resident Inspector Millstone Power Station Serial No.: 23-405 Docket Nos.: 50-336/425 Page 2 of 2