UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PA 19406-2713 September 4, 2018 Mr. Daniel G. Stoddard Senior Vice President and Chief Nuclear Officer Dominion Energy, Inc.

Innsbrook Technical Center 5000 Dominion Blvd.

Glen Allen, VA 23060-6711

SUBJECT:

MILLSTONE POWER STATION, UNIT 2 - OPERATOR LICENSING EXAMINATION APPROVAL

Dear Mr. Stoddard:

The purpose of this letter is to confirm the final arrangements for the upcoming operator licensing examinations at Millstone Power Station, Unit 2.

The U.S. Nuclear Regulatory Commission (NRC) has completed its review of the operator license applications submitted in connection with this examination and separately provided a list of approved applicants to Mr. Jeffrey T. Stafford, Manager, Nuclear Training. Note that any examination waivers, excusals, and application denials have been addressed in separate correspondence.

The NRC has approved the subject examinations, and you may administer the written examination in accordance with Revision 11 to NUREG-1021, Operator Licensing Examination Standards for Power Reactors, the week of September 25, 2018. The NRC staff will administer the operating tests during the weeks of September 10 and 17, 2018. The examination has undergone extensive review by my staff and representatives responsible for licensed operator training at your facility. Based on this review, I have concluded that the examination meets the guidelines of NUREG-1021 for content, operational, and discrimination validity. By administering this examination, you also agree that it meets NUREG-1021 guidelines and is appropriate for measuring the qualifications of licensed operator applicants at your facility. If you determine that this examination is not appropriate for licensed operators at your facility, do not administer the examination and contact me at 610-337-5306.

D. Stoddard 2 Please contact your Chief Examiner, Brian Fuller, at 610-337-5077, if you have any questions or identify any errors or changes in the license level (RO or SRO) or type of examination (partial or complete written examination or operating test) specified for each applicant.

Sincerely,

/RA/

Donald E. Jackson, Chief Operations Branch Division of Reactor Safety Docket No. 50-336 License No. DPR-65 cc: Distribution via ListServ

D. Stoddard 3

SUBJECT:

MILLSTONE POWER STATION, UNIT 2 - OPERATOR LICENSING EXAMINATION APPROVAL DATED SEPTEMBER 4, 2018 DISTRIBUTION: (via email)

DLew, RA (R1ORAMAIL Resource)

JGiessner, DRA (R1ORAMAIL Resource)

RLorson, DRP (R1DRPMAIL Resource)

DPelton, DRP (R1DRPMAIL Resource)

JYerokun, DRS (R1DRSMAIL Resource)

BWelling, DRS (R1DRSMAIL Resource)

DSchroeder, DRP TSetzer, DRP MHenrion, DRP JFuller, DRP, SRI LMcKown, DRP, RI CHighley, DRP, RI ARancourt, DRP, AA CCook, RI OEDO RidsNrrPMMillstone Resource RidsNrrDorlLpl1 Resource DJackson, DRS BFuller, DRS DOCUMENT NAME: G:\DRS\Operations Branch\FULLER\Exam FY18 - Millstone 2\FY18 MS2 Exam Approval Ltr.docx ADAMS Accession Number (Package):ML17234A732 ADAMS Accession Number (Letter):ML18248A266 SUNSI Review Non-Sensitive Publicly Available OFFICE RI/DRS/OB:CE RI/DRS/OB:BC NAME BFuller DEJackson DATE 9/4/18 9/4/18 OFFICIAL RECORD COPY