MONTHYEARML13154A2182013-05-29029 May 2013 License Renewal Boundary Drawings Project stage: Other ML13227A2492013-08-16016 August 2013 License Renewal Process and Environmental Scooping Meeting Project stage: Meeting ML13266A1832013-08-20020 August 2013 Public Scoping Meeting for the Byron Nuclear Station License Renewal Application Transcript - Afternoon Session Project stage: Meeting ML13266A1822013-08-20020 August 2013 Public Scoping Meeting for the Byron Nuclear Station License Renewal Application Transcript - Evening Session Project stage: Meeting ML13275A0402013-08-20020 August 2013 License Renewal Process and Environmental Scoping Meeting Slides Project stage: Meeting ML13248A2712013-08-21021 August 2013 Comment (3) by Sue Rezin Supporting Extension of Braidwood Nuclear Generating Station License Project stage: Request ML13261A1642013-08-21021 August 2013 0821NRC-154-Evening Project stage: Request ML13247A0092013-08-27027 August 2013 Comment (1) of Nancy Schultz Voots & Lawrence M. Walsh on Behalf of the County Board Will County, Illinois Supporting of the Renewal of the Operating License of the Exelon Generation Braidwood Nuclear Generating Station Project stage: Request ML13263A2192013-08-28028 August 2013 Comment (2) of Tom Zimmer Opposing Braidwood Nuclear Plant License Extension for 20 Years Due to Environmental and Health Issue Hazardous Project stage: Request ML13269A3692013-09-0404 September 2013 Comment (00004) of Anne E. Haaker, on Behalf of Il, Historic Preservation Agency, on License Renewal for Braidwood Station Project stage: Other ML13247A5412013-09-0505 September 2013 0821NRC2-154-Afternoon Project stage: Request ML13241A4442013-09-0606 September 2013 Open House-Agenda-Websites Handout Project stage: Request ML13274A2392013-09-16016 September 2013 Comment (6) of Kent Collier on Behalf of Kickapoo Tribe of Oklahoma Supporting the Renewal Application of Braidwood Station, Units 1 & 2 License Project stage: Other ML13263A2212013-09-16016 September 2013 Comment (1) of Kim P. Gouker on Behalf of Ogle County, Illinois Supporting the License Renewal Application of the Byron Power Generating Station Project stage: Other ML13269A3732013-09-24024 September 2013 Comment (00005) of Shawn Cirton, on Behalf of Us Fish and Wildlife Service, on Notice of Intent to Prepare an Environmental Impact Statement for Exelon Generation Company, LLC, License Renewal Application for Braidwood Station, Units 1 and Project stage: Request ML13246A4342013-09-27027 September 2013 Meeting Summary of Public Scoping Meetings Conducted Related to the Review of the Braidwood Station, Unit 1 and 2, License Renewal Application Project stage: Meeting ML13277A3052013-09-27027 September 2013 Comment (00007) of David Kraft on Behalf of Nuclear Energy Information Service on Generic Environmental Impact Statement for License Renewal Application for Braidwood Station, Units 1 and 2 Project stage: Request ML13277A3062013-09-27027 September 2013 Comment (2) of David Kraft on Behalf of Neis Re Supplement to NRCs Generic Environmental Impact Statement for License Renewal for the Byron Nuclear Power Station Project stage: Supplement ML13240A2342013-10-0404 October 2013 8/10/2013 - Summary of Public Scoping Meetings Conducted Related to the Review of the Byron Nuclear Station, License Renewal Application(Tac Nos. MF1790 and MF1791) Project stage: Meeting ML13270A1162013-10-29029 October 2013 License Renewal Environmental Site Audit Re Byron and Braidwood Stations - Severe Accident Mitigation Alternative (TAC Nos. MF1834/1835, MF1790/1791, MF1832/1833, and MF1792/1793) Project stage: Other ML13270A1262013-11-0707 November 2013 License Renewal Environmental Site Audit Regarding Braidwood Station (TAC Nos. ME1832/1833, MF1792/1793) Project stage: Other ML13318A2382013-12-0303 December 2013 Summary of Site Audit Related to the Review of the License Renewal Application for Braidwood Station, Units 1 and 2 (TAC Nos. MF1832, MF1833, and MF1792, MF1793 Project stage: Approval ML13312A3172013-12-13013 December 2013 Audit Trip Report SAMA Project stage: Other ML13350A5122013-12-20020 December 2013 Request for Additional Information for the Review of the Braidwood Nuclear Stations License Renewal Application - Environmental Audit Project stage: RAI ML13354B9372013-12-20020 December 2013 RAI Braidwood Nuclear Station Project stage: RAI ML13318A2082014-01-0606 January 2014 Request for Additional Information for the Review of the Byron and Braidwood Application - Severe Accident Mitigation Alternative Review (TAC Nos. MF1790, MF1791, MF1792, & MF1793) Project stage: RAI ML14013A3392014-01-13013 January 2014 Environmental RAIs - 1 Supplemental Request Project stage: RAI ML14007A2402014-01-23023 January 2014 SAMA RAI Conference Call Summary Project stage: RAI RS-14-033, Response to NRC Requests for Additional Information for the Severe Accident Mitigation Alternatives Review, Dated January 6, 2014 License Renewal Application2014-02-0404 February 2014 Response to NRC Requests for Additional Information for the Severe Accident Mitigation Alternatives Review, Dated January 6, 2014 License Renewal Application Project stage: Response to RAI ML14050A1012014-03-0404 March 2014 Summary of Telephone Conference Call Held on February 12, 2014, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Requests for Additional Information Pertaining to the Braidwood Station License Re Project stage: RAI ML13281A5372014-04-0303 April 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Application by Exelon Generation Company, LLC, for Renewal of the Operating Licenses for Braidwood Station, Units 1 and 2, (TAC No. MF1832, MF1833, Mf Project stage: Approval ML14092A3562014-04-15015 April 2014 Summary of Telephone Conference Call Held on March 31, 2014 Between the U.S. NRC and Exelon Generation Company, LLC, Concerning Requests for Additional Information Pertaining to the Braidwood Station, License Renewal Application Project stage: RAI ML14085A1102014-04-30030 April 2014 Summary of Telephone Conference Call Held on March 24, 2014 Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Requests for Additional Information Pertaining to the Braidwood Station, License Renew Project stage: RAI ML13337A5032014-04-30030 April 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Application by Exelon Generation Company, LLC, for Renewal for Braidwood Station, Units 1 and 2 Project stage: Approval ML14114A6712014-05-0101 May 2014 Summary of Telephone Conference Call Held on April 16, 2014, Between the U.S. Nuclear Regulatory Commission & Exelon Generation Company, LLC, Concerning Requests for Additional Information Pertaining to the Braidwood Station, License Renewa Project stage: RAI ML14104B1312014-05-0505 May 2014 Schedule Revision for Environmental Review of Byron and Braidwood Nuclear Stations License Renewal Application - Environmental Review Schedule Project stage: Approval ML14041A3342014-05-28028 May 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Byron Nuclear Station, Units 1 and 2, License Renewal Application Project stage: Approval ML14296A1762014-10-30030 October 2014 Safety Evaluation Report with Open Items Related to the License Renewal of Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2 Project stage: Approval ML14338A1282014-12-23023 December 2014 FRN for Notice of Availability of the Supplement 54 to the GEIS for License Renewal of Nuclear Plant Regarding Byron, Units 1 and 2 Project stage: Other ML14338A1242014-12-23023 December 2014 Notice of Availability of the Draft Plant Specific Supplement 54 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Byron, Units 1 and 2, Project stage: Draft Other ML14351A1612014-12-24024 December 2014 Notice of Availability of the Draft Plant-Specific Supplement 54 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Byron, Units 1 and 2, Project stage: Draft Other ML14357A0422014-12-31031 December 2014 NUREG-1437 - Supp 54, Draft Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Byron Station, Units 1 and 2. Project stage: Draft Other ML15008A4422015-01-29029 January 2015 Schedule Revision for the Review of the Byron and Braidwood Stations, Units 1 and 2, License Renewal Application Project stage: Approval ML15033A0972015-01-30030 January 2015 Email for Byron and Braidwood Schedule Revision for the Review of the Byron, Units 1 and 2, and Braidwood Stations, Units 1 and 2, License Renewal Application Project stage: Approval ML15058A1972015-02-12012 February 2015 Comment (4) of Kenneth A. Westlake on Behalf of Us Environmental Protection Agency (EPA) on Draft Plant-Specific Supplement 54 to the Generic Environmental Impact Statement for the License Renewal of Byron Station, Units 1 and 2 ML15020A3902015-03-18018 March 2015 Draft Supplement 55 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Project stage: Draft Other ML14351A4552015-03-18018 March 2015 Notice of Availability of the Draft Plant-Specific Supplement 55 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Braidwood Station, Units 1 and 2 Project stage: Draft Other ML15014A1682015-03-27027 March 2015 Notice of Availability of the Draft Plant-Specific Supplement 55 to Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Braidwood, Units 1 and 2, Project stage: Draft Other ML15062A4282015-03-31031 March 2015 NUREG-1437 Supplement 55 Draft Generic Environmental Impact Statement for License Renewal of Nuclear Plants Supplement 55 Regarding Braidwood Station, Units 1 and 2, Draft Report for Comment Project stage: Draft Other ML15077A2972015-07-16016 July 2015 FRN for Notice of Availability of the Final Plant-Specific Supplement 54 to the GEIS for License Renewal of Nuclear Plant Regarding Byron, Units 1 and 2 Project stage: Other 2014-01-23
[Table View] |
Text
LICENSEE:
Exelon Generation Company, LLC FACILITY:
Byron Nuclear Station (Byron) and Braidwood Nuclear Station (Braidwood)
SUBJECT:
SUMMARY
OF CALL HELD ON JANUARY 2, 2014, BETWEEN THE U.S.
NUCLEAR REGULATORY COMMISSION AND EXELON GENERATING COMPANY, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE BYRON AND BRAIDWOOD NUCLEAR STATIONS LICENSE RENEWAL APPLICATION-SEVERE ACCIDENT MITIGATION ALTERNATIVE REVIEW (TAC NOS. MF1790, MF1791, MF1792, AND MF1793)
The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Exelon Generation Company, LLC, held a telephone conference call on January 2, 2014, to discuss the request for additional information (RAis), pertaining to the severe accident mitigation alternatives review for the Byron and Braidwood license renewal application. The telephone conference call was useful in clarifying the RAis. provides a listing of the participants and Enclosure 2 contains a summary of the discussion.
The applicant had an opportunity to comment on this summary.
Docket Nos. 50-454, 50-455, 50-456, and 50-457
Enclosures:
- 1. List of Participants
- 2. Discussion Summary cc w/encls: Listserv
/
\\ci ---tL U
~J\\J'""<~'v "" -'".....?
Lois M. James, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation
ML14007A240 OFFICE LA:RPB1 :DLR PM:RPB2:DLR NAME YEdmonds LJames DATE 1/13/2014 1/16/2014 BC:RPB2:DLR BWittick 1/17/2014
SUBJECT:
SUMMARY
OF CALL HELD ON JANUARY 2, 2014, BETWEEN THE U.S.
NUCLEAR REGULATORY COMMISSION AND EXELON GENERATING COMPANY, LLC, CONCERNING REQUESTS FOR ADDITIONAL INFORMATION PERTAINING TO THE BYRON AND BRAIDWOOD NUCLEAR STATIONS LICENSE RENEWAL APPLICATION-SEVERE ACCIDENT MITIGATION ALTERNATIVE REVIEW (TAG NOS. MF1790, MF1791, MF1792, AND MF1793)
DISTRIBUTION:
HARDCOPY:
DLR/RPB2 r/f E-MAIL:
PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRerb Resource RidsNrrDirRarb Resource RidsNrrDirRasb Resource RidsOgcMaiiCenter Listserv Lois.James@nrc.gov Brian.Wittick@nrc.gov John. Daily@ nrc. gov Lindsay. Robinson@nrc.gov Christopher.Wilson2@exeloncorp.com Nancy. Ranek@exeloncorp. com
PARTICIPANTS Lois M. James John Parillo Bob Schmitt Bruce Schmitt Nancy Ranek Chris Wilson Don Macleod Alex Duvall Grant Teagarden Jeff Gabor TELEPHONE CONFERENCE CALL BYRON AND BRAIDWOOD NUCLEAR STATIONS LICENSE RENEWAL APPLICATION LIST OF PARTICIPANTS January 2, 2014 AFFILIATIONS Nuclear Regulatory Commission (NRC)
NRC Pacific Northwest National Laboratory (PNNL),
NRC Contractor PNNL, NRC Contractor Exelon Generation Company, LLC (Exelon)
Exelon ERIN Engineering and Research, Inc. (Erin Engineering), Exelon Contractor Erin Engineering, Exelon Contractor Erin Engineering, Exelon Contractor Erin Engineering, Exelon Contractor ENCLOSURE 1
SUMMARY
OF TELEPHONE CONFERENCE CALL ON REQUEST FOR ADDITIONAL INFORMATION SEVERE ACCIDENT MITIGATION ALTERNATIVES PERTAINING TO THE BYRON AND BRAIDWOOD NUCLEAR STATIONS LICENSE RENEWAL APPLICATION January 2, 2014 The U.S. Nuclear Regulatory Commission (NRC) staff and representatives of Exelon Generation Company, LLC (Exelon or the applicant) held a telephone conference call on January 2, 2014, to discuss the request for additional information (RAis) regarding the severe accident mitigation alternatives (SAMAs) for Byron and Braidwood Nuclear Stations license renewal application (LRA). The telephone conference call was useful in clarifying the RAis.
Discussion The staff and the applicant discussed the current draft RAis sent to the applicant on December 18, 2013, (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML13351A517) concerning the LRA and the SAMA review. On December 23, 2013, the applicant requested clarification regarding RAI No. 4, subpart L:
It is noted that both the internal events and total (internal + external events) MACR
[maximum averted cost-risk] for both Byron and Braidwood are generally significantly greater than the MACRs for other SAMA submittals. Provide a discussion of the major contributors/factors that lead to this result and provide an assessment of the realism or conservatism of these factors.
Specifically, the applicant requested clarification of the scope of the question and which specific SAMAs are included in the question, as written.
The discussion focused on what information the apparently large MACR results and the associated impact on the potentially cost-beneficial SAMAs. As a result of the discussion, the staff is revising the RAI question as follows:
Provide a discussion of the major contributors/factors that lead to the apparently large MACR and a qualitative assessment of the realism or conservatism of these factors.