MONTHYEARML13154A2182013-05-29029 May 2013 License Renewal Boundary Drawings Project stage: Other ML13227A2492013-08-16016 August 2013 License Renewal Process and Environmental Scooping Meeting Project stage: Meeting ML13266A1832013-08-20020 August 2013 Public Scoping Meeting for the Byron Nuclear Station License Renewal Application Transcript - Afternoon Session Project stage: Meeting ML13266A1822013-08-20020 August 2013 Public Scoping Meeting for the Byron Nuclear Station License Renewal Application Transcript - Evening Session Project stage: Meeting ML13275A0402013-08-20020 August 2013 License Renewal Process and Environmental Scoping Meeting Slides Project stage: Meeting ML13248A2712013-08-21021 August 2013 Comment (3) by Sue Rezin Supporting Extension of Braidwood Nuclear Generating Station License Project stage: Request ML13261A1642013-08-21021 August 2013 0821NRC-154-Evening Project stage: Request ML13247A0092013-08-27027 August 2013 Comment (1) of Nancy Schultz Voots & Lawrence M. Walsh on Behalf of the County Board Will County, Illinois Supporting of the Renewal of the Operating License of the Exelon Generation Braidwood Nuclear Generating Station Project stage: Request ML13263A2192013-08-28028 August 2013 Comment (2) of Tom Zimmer Opposing Braidwood Nuclear Plant License Extension for 20 Years Due to Environmental and Health Issue Hazardous Project stage: Request ML13269A3692013-09-0404 September 2013 Comment (00004) of Anne E. Haaker, on Behalf of Il, Historic Preservation Agency, on License Renewal for Braidwood Station Project stage: Other ML13247A5412013-09-0505 September 2013 0821NRC2-154-Afternoon Project stage: Request ML13241A4442013-09-0606 September 2013 Open House-Agenda-Websites Handout Project stage: Request ML13274A2392013-09-16016 September 2013 Comment (6) of Kent Collier on Behalf of Kickapoo Tribe of Oklahoma Supporting the Renewal Application of Braidwood Station, Units 1 & 2 License Project stage: Other ML13263A2212013-09-16016 September 2013 Comment (1) of Kim P. Gouker on Behalf of Ogle County, Illinois Supporting the License Renewal Application of the Byron Power Generating Station Project stage: Other ML13269A3732013-09-24024 September 2013 Comment (00005) of Shawn Cirton, on Behalf of Us Fish and Wildlife Service, on Notice of Intent to Prepare an Environmental Impact Statement for Exelon Generation Company, LLC, License Renewal Application for Braidwood Station, Units 1 and Project stage: Request ML13246A4342013-09-27027 September 2013 Meeting Summary of Public Scoping Meetings Conducted Related to the Review of the Braidwood Station, Unit 1 and 2, License Renewal Application Project stage: Meeting ML13277A3052013-09-27027 September 2013 Comment (00007) of David Kraft on Behalf of Nuclear Energy Information Service on Generic Environmental Impact Statement for License Renewal Application for Braidwood Station, Units 1 and 2 Project stage: Request ML13277A3062013-09-27027 September 2013 Comment (2) of David Kraft on Behalf of Neis Re Supplement to NRCs Generic Environmental Impact Statement for License Renewal for the Byron Nuclear Power Station Project stage: Supplement ML13240A2342013-10-0404 October 2013 8/10/2013 - Summary of Public Scoping Meetings Conducted Related to the Review of the Byron Nuclear Station, License Renewal Application(Tac Nos. MF1790 and MF1791) Project stage: Meeting ML13270A1162013-10-29029 October 2013 License Renewal Environmental Site Audit Re Byron and Braidwood Stations - Severe Accident Mitigation Alternative (TAC Nos. MF1834/1835, MF1790/1791, MF1832/1833, and MF1792/1793) Project stage: Other ML13270A1262013-11-0707 November 2013 License Renewal Environmental Site Audit Regarding Braidwood Station (TAC Nos. ME1832/1833, MF1792/1793) Project stage: Other ML13318A2382013-12-0303 December 2013 Summary of Site Audit Related to the Review of the License Renewal Application for Braidwood Station, Units 1 and 2 (TAC Nos. MF1832, MF1833, and MF1792, MF1793 Project stage: Approval ML13312A3172013-12-13013 December 2013 Audit Trip Report SAMA Project stage: Other ML13350A5122013-12-20020 December 2013 Request for Additional Information for the Review of the Braidwood Nuclear Stations License Renewal Application - Environmental Audit Project stage: RAI ML13354B9372013-12-20020 December 2013 RAI Braidwood Nuclear Station Project stage: RAI ML13318A2082014-01-0606 January 2014 Request for Additional Information for the Review of the Byron and Braidwood Application - Severe Accident Mitigation Alternative Review (TAC Nos. MF1790, MF1791, MF1792, & MF1793) Project stage: RAI ML14013A3392014-01-13013 January 2014 Environmental RAIs - 1 Supplemental Request Project stage: RAI ML14007A2402014-01-23023 January 2014 SAMA RAI Conference Call Summary Project stage: RAI RS-14-033, Response to NRC Requests for Additional Information for the Severe Accident Mitigation Alternatives Review, Dated January 6, 2014 License Renewal Application2014-02-0404 February 2014 Response to NRC Requests for Additional Information for the Severe Accident Mitigation Alternatives Review, Dated January 6, 2014 License Renewal Application Project stage: Response to RAI ML14050A1012014-03-0404 March 2014 Summary of Telephone Conference Call Held on February 12, 2014, Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Requests for Additional Information Pertaining to the Braidwood Station License Re Project stage: RAI ML13281A5372014-04-0303 April 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Application by Exelon Generation Company, LLC, for Renewal of the Operating Licenses for Braidwood Station, Units 1 and 2, (TAC No. MF1832, MF1833, Mf Project stage: Approval ML14092A3562014-04-15015 April 2014 Summary of Telephone Conference Call Held on March 31, 2014 Between the U.S. NRC and Exelon Generation Company, LLC, Concerning Requests for Additional Information Pertaining to the Braidwood Station, License Renewal Application Project stage: RAI ML14085A1102014-04-30030 April 2014 Summary of Telephone Conference Call Held on March 24, 2014 Between the U.S. Nuclear Regulatory Commission and Exelon Generation Company, LLC, Concerning Requests for Additional Information Pertaining to the Braidwood Station, License Renew Project stage: RAI ML13337A5032014-04-30030 April 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Application by Exelon Generation Company, LLC, for Renewal for Braidwood Station, Units 1 and 2 Project stage: Approval ML14114A6712014-05-0101 May 2014 Summary of Telephone Conference Call Held on April 16, 2014, Between the U.S. Nuclear Regulatory Commission & Exelon Generation Company, LLC, Concerning Requests for Additional Information Pertaining to the Braidwood Station, License Renewa Project stage: RAI ML14104B1312014-05-0505 May 2014 Schedule Revision for Environmental Review of Byron and Braidwood Nuclear Stations License Renewal Application - Environmental Review Schedule Project stage: Approval ML14041A3342014-05-28028 May 2014 Issuance of Environmental Scoping Summary Report Associated with the Staffs Review of the Byron Nuclear Station, Units 1 and 2, License Renewal Application Project stage: Approval ML14296A1762014-10-30030 October 2014 Safety Evaluation Report with Open Items Related to the License Renewal of Byron Station, Units 1 and 2, and Braidwood Station, Units 1 and 2 Project stage: Approval ML14338A1282014-12-23023 December 2014 FRN for Notice of Availability of the Supplement 54 to the GEIS for License Renewal of Nuclear Plant Regarding Byron, Units 1 and 2 Project stage: Other ML14338A1242014-12-23023 December 2014 Notice of Availability of the Draft Plant Specific Supplement 54 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Byron, Units 1 and 2, Project stage: Draft Other ML14351A1612014-12-24024 December 2014 Notice of Availability of the Draft Plant-Specific Supplement 54 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Byron, Units 1 and 2, Project stage: Draft Other ML14357A0422014-12-31031 December 2014 NUREG-1437 - Supp 54, Draft Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Byron Station, Units 1 and 2. Project stage: Draft Other ML15008A4422015-01-29029 January 2015 Schedule Revision for the Review of the Byron and Braidwood Stations, Units 1 and 2, License Renewal Application Project stage: Approval ML15033A0972015-01-30030 January 2015 Email for Byron and Braidwood Schedule Revision for the Review of the Byron, Units 1 and 2, and Braidwood Stations, Units 1 and 2, License Renewal Application Project stage: Approval ML15058A1972015-02-12012 February 2015 Comment (4) of Kenneth A. Westlake on Behalf of Us Environmental Protection Agency (EPA) on Draft Plant-Specific Supplement 54 to the Generic Environmental Impact Statement for the License Renewal of Byron Station, Units 1 and 2 ML15020A3902015-03-18018 March 2015 Draft Supplement 55 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Project stage: Draft Other ML14351A4552015-03-18018 March 2015 Notice of Availability of the Draft Plant-Specific Supplement 55 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Braidwood Station, Units 1 and 2 Project stage: Draft Other ML15014A1682015-03-27027 March 2015 Notice of Availability of the Draft Plant-Specific Supplement 55 to Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Braidwood, Units 1 and 2, Project stage: Draft Other ML15062A4282015-03-31031 March 2015 NUREG-1437 Supplement 55 Draft Generic Environmental Impact Statement for License Renewal of Nuclear Plants Supplement 55 Regarding Braidwood Station, Units 1 and 2, Draft Report for Comment Project stage: Draft Other ML15077A2972015-07-16016 July 2015 FRN for Notice of Availability of the Final Plant-Specific Supplement 54 to the GEIS for License Renewal of Nuclear Plant Regarding Byron, Units 1 and 2 Project stage: Other 2014-01-23
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 5, 2014 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE BYRON STATION AND BRAIDWOOD STATION LICENSE RENEWAL APPLICATION-ENVIRONMENTAL REVIEW SCHEDULE (TAC NOS MF1790, MF1791, MF1792, AND MF1793)
Dear Mr. Gallagher:
By letter, dated May 29, 2013, Exelon Generation Company, LLC (Exelon), submitted an application pursuant to Title 10 of the Code of Federal Regulations (CFR) Part 54, to renew the operating licenses for Byron Station (Byron) and Braidwood Station (Braidwood), for review by the U.S. Nuclear Regulatory Commission (NRC) staff. The staff is reviewing the information contained in the license renewal application and has determined that a revised environmental schedule is needed, in order to support the Waste Confidence update.
The Waste Confidence update is a high priority agency level activity that is integral to NRC's licensing function and necessitates the commitment of all necessary resources to its completion to ensure that commitments and expectations are being met. This requirement has resulted in the temporary reassignment of resources from license renewal environmental reviews. As a result, the environmental review schedules for Byron and Braidwood have been impacted and the schedules revised accordingly. Specifically, the schedules for Byron and Braidwood environmental reviews have been delayed by two and three months, respectfully. The Byron draft Supplemental Environmental Impact Statement (SEIS) is now scheduled to be issued in October 2014, with the final SEIS to be issued July 2015. The Braidwood draft SEIS is now scheduled to be issued in January 2015, with the final SEIS to be issued September 2015.
NRC will continue to assess the resource and schedules associated with the Byron and Braidwood environmental reviews, and make adjustments as feasible or necessary.
The NRC will continue to follow established review procedures and the enclosed environmental review schedule to complete the reviews required by 10 CFR Part 51. If you have any questions on this revised schedule, please contact the NRC's Environmental Project Manager for Byron, Ms. Lois James, at 301-415-3306 or by e-mail at lois.james@nrc.gov or NRC's Environmental Project Manager for Braidwood, Mr. Tam Tran, at 301-415-3617 or by e-mail at tam.tran@nrc.gov.
Sincerely, l'bl>l(' c\\ki, Director Divi n of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-454, 50-455; 50-456, and 50-457
Enclosure:
Revised Schedule cc w/encl: Listserv
BYRON STATION AND BRAIDWOOD STATION LICENSE RENEWAL APPLICATION UPDATED ENVIRONMENTAL REVIEW SCHEDULE Milestones Receive license renewal application (LRA)
Publish Federal Register Notice (FRN)- LRA availability Publish FRN -acceptance/rejection and opportunity for hearing Publish FRN -environmental seeping meeting Audit-Seeping & Screening Methodology 1 (at Byron)
Audit-Aging Management Programs 1 (at Byron)
Public Meeting - License Renewal Overview and Environmental Seeping meetings Deadline for filing hearing requests and petitions for intervention Audit-Environmental (Byron)
Environmental seeping period ends Audit-Seeping & Screening Methodology 2 (at Braidwood)
Audit-Aging Management Programs 2 (at Braidwood)
Audit-Environmental (Braidwood)
Regional Inspection (Byron)
Issue draft supplemental environmental impact statement (SEIS) - Byron Publish FRN - Byron draft SEIS available for comments Public Meeting - Byron draft SEIS meeting End of draft SEIS comment period - Byron Regional Inspection (Braidwood)
Issue draft SEIS ~ Braidwood Publish FRN-Braidwood draft SEIS available for comments Public Meeting - Braidwood draft SEIS meeting Schedule Date Actual Date 05129113 05129113 0612013 06113113 0712013 07124113 0712013 08106113 0712013 0712013 0812013 0812013 08120113-08120113 08121113 (Byron) 08121113 (Braidwood) 0912013 09123113 0912013 09119113 0912013 09127113 1012013 12102113-12104113 1012013 12102113-12106113 1112013 11119113 0812014 1012014 1012014 1112014 1212014 0912014 0112015 0112015 02/2015 ENCLOSURE Milestones End of draft SEIS comment period - Braidwood Advisory Committee on Reactor Safeguards (ACRS)
Subcommittee meeting Issue final SER Issue final SEIS-Byron U.S. Environmental Protection Agency FRN Published-availability of final SEIS-Byron ACRS full committee meeting Issue final SEIS-Braidwood U.S. Environmental Protection Agency FRN Published -
availability of final SEIS - Braidwood Decision-Director, NRR Commission decision, if hearing granted Schedule Date 03/2015 12/2014 04/2015 07/2015 07/2015 05/2015 09/2015 09/2015 1112015 TBD Actual Date
Letter to M. Gallagher from J. Lubinski dated May 5, 2014 SUBJECT SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE BYRON STATION AND BRAIDWOOD STATION LICENSE RENEWAL APPLICATION-ENVIRONMENTAL REVIEW SCHEDULE (TAG NOS. MF1790, MF1791, MF1792, AND MF1793)
DISTRIBUTION:
HARDCOPY:
DLR RF E-MAIL:
PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource RidsNrrOraApla Resource RidsOgcMaiiCenter JDaily Tiran A Buford DMclntyre, OPA BSingal, DORL WWalker, RIV JDixon, RIV BTharakan, RIV WMaier, RIV VDricks, RIV NOKeefe, RIV AVegel, RIV GPick, RIV