Schedule Revision for Environmental Review of Byron and Braidwood Nuclear Stations License Renewal Application - Environmental Review Schedule
ML14104B131
Person / Time
Site: Byron, Braidwood  
Issue date: 05/05/2014
From: John Lubinski
Division of License Renewal
To: Gallagher M
Exelon Generation Co
James L
References
TAC MF1790, TAC MF1791, TAC MF1792, TAC MF1793
Download: ML14104B131 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 5, 2014 Mr. Michael P. Gallagher Vice President, License Renewal Projects Exelon Generation Company, LLC 200 Exelon Way Kennett Square, PA 19348

SUBJECT:

SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE BYRON STATION AND BRAIDWOOD STATION LICENSE RENEWAL APPLICATION-ENVIRONMENTAL REVIEW SCHEDULE (TAC NOS MF1790, MF1791, MF1792, AND MF1793)

Dear Mr. Gallagher:

By letter, dated May 29, 2013, Exelon Generation Company, LLC (Exelon), submitted an application pursuant to Title 10 of the Code of Federal Regulations (CFR) Part 54, to renew the operating licenses for Byron Station (Byron) and Braidwood Station (Braidwood), for review by the U.S. Nuclear Regulatory Commission (NRC) staff. The staff is reviewing the information contained in the license renewal application and has determined that a revised environmental schedule is needed, in order to support the Waste Confidence update.

The Waste Confidence update is a high priority agency level activity that is integral to NRC's licensing function and necessitates the commitment of all necessary resources to its completion to ensure that commitments and expectations are being met. This requirement has resulted in the temporary reassignment of resources from license renewal environmental reviews. As a result, the environmental review schedules for Byron and Braidwood have been impacted and the schedules revised accordingly. Specifically, the schedules for Byron and Braidwood environmental reviews have been delayed by two and three months, respectfully. The Byron draft Supplemental Environmental Impact Statement (SEIS) is now scheduled to be issued in October 2014, with the final SEIS to be issued July 2015. The Braidwood draft SEIS is now scheduled to be issued in January 2015, with the final SEIS to be issued September 2015.

NRC will continue to assess the resource and schedules associated with the Byron and Braidwood environmental reviews, and make adjustments as feasible or necessary.

The NRC will continue to follow established review procedures and the enclosed environmental review schedule to complete the reviews required by 10 CFR Part 51. If you have any questions on this revised schedule, please contact the NRC's Environmental Project Manager for Byron, Ms. Lois James, at 301-415-3306 or by e-mail at lois.james@nrc.gov or NRC's Environmental Project Manager for Braidwood, Mr. Tam Tran, at 301-415-3617 or by e-mail at tam.tran@nrc.gov.

Sincerely, l'bl>l(' c\\ki, Director Divi n of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-454, 50-455; 50-456, and 50-457

Enclosure:

Revised Schedule cc w/encl: Listserv

BYRON STATION AND BRAIDWOOD STATION LICENSE RENEWAL APPLICATION UPDATED ENVIRONMENTAL REVIEW SCHEDULE Milestones Receive license renewal application (LRA)

Publish Federal Register Notice (FRN)- LRA availability Publish FRN -acceptance/rejection and opportunity for hearing Publish FRN -environmental seeping meeting Audit-Seeping & Screening Methodology 1 (at Byron)

Audit-Aging Management Programs 1 (at Byron)

Public Meeting - License Renewal Overview and Environmental Seeping meetings Deadline for filing hearing requests and petitions for intervention Audit-Environmental (Byron)

Environmental seeping period ends Audit-Seeping & Screening Methodology 2 (at Braidwood)

Audit-Aging Management Programs 2 (at Braidwood)

Audit-Environmental (Braidwood)

Regional Inspection (Byron)

Issue draft supplemental environmental impact statement (SEIS) - Byron Publish FRN - Byron draft SEIS available for comments Public Meeting - Byron draft SEIS meeting End of draft SEIS comment period - Byron Regional Inspection (Braidwood)

Issue draft SEIS ~ Braidwood Publish FRN-Braidwood draft SEIS available for comments Public Meeting - Braidwood draft SEIS meeting Schedule Date Actual Date 05129113 05129113 0612013 06113113 0712013 07124113 0712013 08106113 0712013 0712013 0812013 0812013 08120113-08120113 08121113 (Byron) 08121113 (Braidwood) 0912013 09123113 0912013 09119113 0912013 09127113 1012013 12102113-12104113 1012013 12102113-12106113 1112013 11119113 0812014 1012014 1012014 1112014 1212014 0912014 0112015 0112015 02/2015 ENCLOSURE Milestones End of draft SEIS comment period - Braidwood Advisory Committee on Reactor Safeguards (ACRS)

Subcommittee meeting Issue final SER Issue final SEIS-Byron U.S. Environmental Protection Agency FRN Published-availability of final SEIS-Byron ACRS full committee meeting Issue final SEIS-Braidwood U.S. Environmental Protection Agency FRN Published -

availability of final SEIS - Braidwood Decision-Director, NRR Commission decision, if hearing granted Schedule Date 03/2015 12/2014 04/2015 07/2015 07/2015 05/2015 09/2015 09/2015 1112015 TBD Actual Date

Letter to M. Gallagher from J. Lubinski dated May 5, 2014 SUBJECT SCHEDULE REVISION FOR THE ENVIRONMENTAL REVIEW OF THE BYRON STATION AND BRAIDWOOD STATION LICENSE RENEWAL APPLICATION-ENVIRONMENTAL REVIEW SCHEDULE (TAG NOS. MF1790, MF1791, MF1792, AND MF1793)

DISTRIBUTION:

HARDCOPY:

DLR RF E-MAIL:

PUBLIC RidsNrrDir Resource RidsNrrDirRpb1 Resource RidsNrrDirRpb2 Resource RidsNrrDirRerb Resource RidsNrrDirRpob Resource RidsNrrOraApla Resource RidsOgcMaiiCenter JDaily Tiran A Buford DMclntyre, OPA BSingal, DORL WWalker, RIV JDixon, RIV BTharakan, RIV WMaier, RIV VDricks, RIV NOKeefe, RIV AVegel, RIV GPick, RIV