E-mail, Draft Request for Additional Information, 60-Day Response to NRC Bulletin 2011-01, Mitigating Strategies
ML113220244
Person / Time
Site: Cooper Entergy icon.png
Issue date: 11/17/2011
From: Lynnea Wilkins
Plant Licensing Branch IV
To: Mccutchen E
Nebraska Public Power District (NPPD)
Wilkins, L E, NRR/DORL/LPL4, 415-1377
Shared Package
ML113220241 List:
References
TAC ME6420, BL-11-001
Download: ML113220244 (1)


Text

From: Wilkins, Lynnea Sent: Thursday, November 17, 2011 6:02 PM To: McCutchen, Edward L.

Cc: Lent, Susan; Burkhardt, Janet

Subject:

DRAFT RAIs for Cooper Nuclear Station Re: 60-Day Response To Bulletin 2011 01, Mitigation Strategies (TAC NO. ME6420)

Attachments: ME6420 RAIs Email.docx Ed, On May 11, 2011, the U.S. Nuclear Regulatory Commission (NRC) issued Bulletin 2011-01, Mitigating Strategies (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML111250360), to all holders of operating licenses for nuclear power reactors, except those that have permanently ceased operation and have certified that fuel has been removed from the reactor vessel. The purpose of the bulletin was to obtain a comprehensive verification that licensees mitigating strategies to maintain or restore core cooling, spent fuel cooling, and containment following a large explosion or fire were compliant with Title 10 of the Code of Federal Regulations (10 CFR) Section 50.54(hh)(2). The bulletin requested information on licensee 10 CFR 50.54(hh)(2) mitigating strategies in light of the recent events at Japans Fukushima Daiichi facility to determine if (1) additional assessment of program implementation is needed, (2) the current inspection program should be enhanced, or (3) further regulatory action is warranted.

The bulletin required two sets of responses pursuant to the provisions of 10 CFR 50.54(f). The first responses were due 30 days after issuance of the bulletin, by June 10, 2011. The second responses were due 60 days after issuance of the bulletin, by July 11, 2011. By letters dated June 10, 2011 and July 7, 2011 (ADAMS Accession Nos. ML11164A266 and ML11192A032, respectively), you provided responses for Cooper Nuclear Station.

The NRC staff has reviewed the submitted information and has determined that the information specified in the attached draft Request for Additional Information (RAI) is needed regarding your 60-day response to the bulletin.

Please contact me if a clarifying teleconference is needed for the attached RAIs.