April 12, 2011 Dr. Mohamad Al-Sheikhly, Professor and Director Radiation Facilities and Nuclear Reactor Chemical and Nuclear Engineering Building 090 University of Maryland College Park, MD 20742

SUBJECT:

UNIVERSITY OF MARYLAND - APPROVAL OF REQUEST FOR AN EXTENSION (TAC NO. ME1592)

Dear Dr. Al-Sheikhly:

The U. S. Nuclear Regulatory Commission (NRC) received your letter dated March 17, 2011 (Agencywide Document Access and Management System (ADAMS) Accession No. ML110800045). In your letter you requested an extension of time from March 18, 2011, to May 2, 2011, to submit your final proposed Technical Specification (TS) document and your responses to our request for additional information (RAI) transmitted to you through a letter dated August 20, 2010 (ADAMS Accession No. ML102230338). In your letter you stated as the reasons for your request for extension that the dose calculations had not been completed, the calculation of the departure from nucleate boiling ratio (DNBR) had not been prepared by your contractor, GA, and the University would be closed during March 21-24, 2011.

We have reviewed and approved your extension request and have discussed the following two commitments during a teleconference with you on March 29, 2011:

1.

You will provide us within one week of the date of this letter a schedule with intermediate milestones for completing each individual RAI and your final proposed TS.

2.

Based on the above schedule, you will provide us status updates and deliverables on a weekly basis with a confirmation that you will meet the due date for responding to the RAIs, DNBR and final proposed TS by May 2, 2011.

In accordance with Title 10 of the Code of Federal Regulations (10CFR), Section 50.30(b), you must execute your final response in a signed original document under oath or affirmation. Your response must be submitted in accordance with 10 CFR 50.4, Written Communications.

Information included in your response that is considered security, sensitive, or proprietary, that you seek to have withheld from the public, must be marked in accordance with 10 CFR 2.390, Public inspections, exemptions, requests for withholding.

M. Al-Sheikhly If you have any questions please contact Spyros A. Traiforos at 301-415-3965 or by electronic mail at Spyros.Traiforos@nrc.gov or myself at 301-415-1127 or by electronic mail at Alexander.Adams@nrc.gov.

Sincerely,

/RA/

Alexander Adams, Jr., Senior Project Manager Research and Test Reactors Licensing Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-166 License No. R-70 cc: See next page

University of Maryland Docket No. 50-166 cc:

Director, Dept. of Natural Resources Power Plant Siting Program Energy & Coastal Zone Administration Tawes State Office Building Annapolis, MD 21401 Mr. Roland G. Fletcher, Program Manager IV Radiological Health Program Maryland Department of Environment 1800 Washington Blvd., Suite 750 Baltimore, MD 21230 Mr. Vincent G. Adams Facility Coordinator Chemical and Nuclear Engineering Building 090 University of Maryland College Park, MD 20742 Tom OBrien Radiation Safety Officer Department of Environmental Safety 3115 Chesapeake Building 338 University of Maryland College Park, MD 20742 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611

ML110950056 NRR-106 OFFICE PRPB: PM PRLB : PM PRPB: LA PRLB: BC PRLB : PM NAME STraiforos AAdams GLappert JQuichocho AAdams DATE 4/5/2011 4/5/2011 4/5/2011 4/8/2011 4/12/2011