University of Maryland - Approval of Request for an Extension, University of Maryland Response to Request for Additional Information Dated May 27, 2010
ML102740245
Person / Time
Site: University of Maryland
Issue date: 10/08/2010
From: Alexander Adams
Research and Test Reactors Licensing Branch
To: Al-Sheikhly M
Univ of Maryland
Traiforos S, NRR/PRPB, 301-415-3965
References
TAC ME1592
Download: ML102740245 (3)


Text

October 8, 2010 Dr. Mohamad Al-Sheikhly, Professor and Director Radiation Facilities and Nuclear Reactor Chemical and Nuclear Engineering Building 090 University of Maryland College Park, MD 20742

SUBJECT:

UNIVERSITY OF MARYLAND - APPROVAL OF REQUEST FOR AN EXTENSION, RE: UNIVERSITY OF MARYLAND RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION DATED MAY 27, 2010 (TAC NO. ME1592)

Dear Dr. Al-Sheikhly:

The U. S. Nuclear Regulatory Commission (NRC) received your letter dated August 27, 2010 (Agencywide Document Access and Management System (ADAMS) Accession No. ML102440116), requesting an extension to the response time proposed in your letter dated May 27, 2010 (ADAMS Accession No. ML101670413). With your letter dated May 27, 2010, you provided responses to financial requests for additional information (RAIs) and response dates for five additional technical RAIs. Your proposed response date for RAI 2 from the Department of Energy (DOE) contractor to you was August 31, 2010.

In your letter dated August 27, 2010, you requested an extension to November 15, 2010, to complete your response to RAI 2. We have reviewed and approved your extension request for the following reasons: 1) recently there has been progress in responding to RAIs and 2) you need additional time to generate the required input, by the DOE contractor, for the thermal hydraulic analysis of the Maryland University Training Reactor core.

If you have any questions please contact Spyros A. Traiforos at 301-415-3965 or by electronic mail at Spyros.Traiforos@nrc.gov or myself at 301-415-1127 or by electronic mail at Alexander.Adams@nrc.gov.

Sincerely,

/RA/

Alexander Adams, Jr., Senior Project Manager Research and Test Reactors Licensing Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-166 License No. R-70 cc: See next page

University of Maryland Docket No. 50-166 cc:

Director, Dept. of Natural Resources Power Plant Siting Program Energy & Coastal Zone Administration Tawes State Office Building Annapolis, MD 21401 Mr. Roland G. Fletcher, Program Manager IV Radiological Health Program Maryland Department of Environment 1800 Washington Blvd., Suite 750 Baltimore, MD 21230 Mr. Vincent G. Adams Facility Coordinator Chemical and Nuclear Engineering Building 090 University of Maryland College Park, MD 20742 Tom OBrien Radiation Safety Officer Department of Environmental Safety 3115 Chesapeake Building 338 University of Maryland College Park, MD 20742 Test, Research, and Training Reactor Newsletter University of Florida 202 Nuclear Sciences Center Gainesville, FL 32611

ML101670413). With your letter dated May 27, 2010, you provided responses to financial requests for additional information (RAIs) and response dates for five additional technical RAIs. Your proposed response date for RAI 2 from the Department of Energy (DOE) contractor to you was August 31, 2010.

In your letter dated August 27, 2010, you requested an extension to November 15, 2010, to complete your response to RAI 2. We have reviewed and approved your extension request for the following reasons: 1) recently there has been progress in responding to RAIs and 2) you need additional time to generate the required input, by the DOE contractor, for the thermal hydraulic analysis of the Maryland University Training Reactor core.

If you have any questions please contact Spyros A. Traiforos at 301-415-3965 or by electronic mail at Spyros.Traiforos@nrc.gov or myself at 301-415-1127 or by electronic mail at Alexander.Adams@nrc.gov.

Sincerely,

/RA/

Alexander Adams, Jr., Senior Project Manager Research and Test Reactors Licensing Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Docket No. 50-166 License No. R-70 cc: See next page DISTRIBUTION:

PUBLIC RidsNrrDprPrta RidsNrrDpr PRLB r/f STraiforos, NRR GLappert, NRR AAdams, NRR ADAMS Accession No: ML102740245 NRR-106 OFFICE PRPB: PM PRPB : PM PRPB: LA PRLB: BC PRPB : PM NAME STraiforos AAdams GLappert JQuichocho AAdams DATE 10/5/2010 10/7/2010 10/5/2010 10/8/2010 10/8/2010