Letter Sequence RAI |
---|
|
|
MONTHYEARML1022300202010-08-10010 August 2010 Found the Licensee'S Cyber Security Application for Amendment Acceptable for Review Project stage: Other ML1027101272010-09-24024 September 2010 Notification Letter Designating Prairie Island, Units 1 & 2, and Monticello, Balance of Plant Systems within the Cyber Security Rule Scope Project stage: Other ML1101105082011-01-0707 January 2011 Xcel (Monticello and Prairie Island) Cyber Security Plan LAR - Draft RAI #1 Project stage: Draft RAI ML1103203542011-02-15015 February 2011 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Request for Additional Information Related to License Amendment Request for Approval of Cyber Security Plan Project stage: RAI ML1106009802011-03-0404 March 2011 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Request for Additional Information Related to License Amendment Request for Approval of Cyber Security Plan Project stage: RAI ML1109400962011-04-0101 April 2011 Supplement to License Amendment Request (LAR) for Approval of Northern States Power Company - Minnesota Cyber Security Plan (TAC ME4294, ME4295, & ME4272) Project stage: Supplement ML1114604742011-05-26026 May 2011 Supplement to License Amendment Request (LAR) for Approval of the Northern States Power Company - Minnesota Cyber Security Plan Project stage: Supplement ML11186A9922011-07-29029 July 2011 Issuance of Amendment No. 166 Regarding Cyber Security Plan Project stage: Approval ML11187A2312011-07-29029 July 2011 Issuance of Amendment Nos. 202 (for Unit 1) and 189 (for Unit 2) Regarding Cyber Security Project stage: Approval ML1122200902011-08-11011 August 2011 Correction to License Page Included with Amendment No. 189 Regarding Cyber Security Plan Project stage: Other ML13333B6742013-11-27027 November 2013 License Amendment Request (LAR) for Northern States Power Company, Minnesota (NSPM) Cyber Security Plan Implementation Date Extension Project stage: Request 2011-03-04
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML24290A0452024-10-0707 October 2024 Attachment - Monticello SLRA - 3rd Round Request for Additional Information 3rd Round RAI ML24254A4542024-08-26026 August 2024 RAI-holding Ponds ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval ML24198A2372024-07-18018 July 2024 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Monticello Nuclear Generating Plant ML24197A2012024-07-15015 July 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2024004 ML24149A3712024-05-29029 May 2024 (Ping) - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML24141A0452024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24141A1782024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24131A0802024-05-10010 May 2024 Final RAI for LAR to Revise TS 3.8.6, Battery Parameters, SR 3.8.6.6 ML24116A2532024-04-25025 April 2024 Final Request for Additional Information for LAR to Revise SR 3.8.1.2 Note 3 (EPID: L- 2023-LLA-0135) ML24045A0862024-02-12012 February 2024 Final RAI for Alternative RR-09 ML24040A0482024-02-12012 February 2024 – Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000263/2024010 ML24022A0212024-01-20020 January 2024 NRR E-mail Capture - Monticello - Request for Additional Information ISI RR-002 Alternative to Use IWB-2500(f) ML23335A1152023-12-0101 December 2023 NRR E-mail Capture - Prairie Island Units 1 and 2 - Request for Additional Information LAR to Revise TS 3.7.8 Required Actions ML23268A0252023-09-25025 September 2023 SLRA - Requests for Confirmation of Information - Set 2 ML23248A3462023-09-0505 September 2023 NRR E-mail Capture - Request for Additional Information for Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant - Decommissioning Funding Status Reports ML23237A4832023-08-25025 August 2023 SLRA - Request for Additional Information - Set 3 ML23219A1072023-08-0707 August 2023 SLRA - Requests for Additional Information - Set 2 - Email from Marieliz Johnson to Shawn Hafen ML23219A1082023-08-0707 August 2023 SLRA - Requests for Additional Information - Set 2 ML23214A2032023-08-0202 August 2023 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000282/2024010; 05000306/2024010 ML23201A0352023-07-24024 July 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23200A3502023-07-19019 July 2023 SLRA - Requests for Additional Information - Set 1 - Email from Marieliz Johnson to Christopher Domingos ML23200A3512023-07-19019 July 2023 SLRA - Request for Additional Information - Set 1 ML23199A0922023-07-18018 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000306/2023004 ML23096A3082023-04-0707 April 2023 Notification of Inspection an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23059A3522023-03-0101 March 2023 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000263/2023010 ML23055B0562023-02-27027 February 2023 Request for Information for NRC Commercial Grade Dedication Inspection Inspection Report 05000282/2023010 and 05000306/2023010 ML23058A1522023-02-27027 February 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000263/2023002 ML23053A1432023-02-22022 February 2023 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Prairie Island Nuclear Generating Plant ML23004A1982023-01-0404 January 2023 NRR E-mail Capture - Draft Request for Additional Information Monticello Nuclear Generating Plant Request Pr 08, HPCI Pump Quarterly Testing ML22206A1662022-07-25025 July 2022 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Monticello Nuclear Generating Plant ML22181A1962022-06-24024 June 2022 NRR E-mail Capture - Draft RAI Monticello Alternative VR-08 ML22175A1602022-06-24024 June 2022 NRR E-mail Capture - RAI Monticello Fuel Oil Storage Tank Inspection ML22166A4112022-06-15015 June 2022 NRR E-mail Capture - Request for Additional Information Prairie Island Nuclear Generating Plant, Unit 2, Alternative RR-08, PIV Leakage ML22160A6022022-06-0909 June 2022 NRR E-mail Capture - Draft Request for Additional Information Prairie Island Nuclear Generating Plant, Units 1 and 2, 24-Month Operating Cycle Amendment ML22145A4152022-05-25025 May 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000282/2022402 05000306/2022402 ML22130A5792022-05-11011 May 2022 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML22131A2652022-05-11011 May 2022 NRR E-mail Capture - Request for Additional Information Xcel Energy Amendment Request to Create a Common Eplan and EOF for Monticello and Prairie Island ML22123A2822022-05-0303 May 2022 NRR E-mail Capture - Request for Additional Information Monticello Alternative VR-10, EFCV Testing Frequency ML21322A2362021-11-18018 November 2021 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000263/2022401 ML21321A0452021-11-10010 November 2021 Request for Additional Information: Prairie Island 24-Month Cycle Amendment Request ML21305A0102021-10-29029 October 2021 NRR E-mail Capture - Request for Additional Information Prairie Island Cooling Water Amendment ML21252A0122021-08-30030 August 2021 NRR E-mail Capture - Request for Additional Information Amendment Request to Adopt TSTF-471 and 517-T for Prairie Island ML21147A5232021-06-0303 June 2021 Prarie Island Nuclear Generating Plant, Units 1 and 2 - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML21131A0752021-05-10010 May 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2021004; 05000306/2021004 ML21099A0972021-04-0909 April 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000282/2021012 and 05000306/2021012 ML21085A8582021-03-26026 March 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team): Inspection Report 05000263/2021010 ML21068A2772021-03-0909 March 2021 NRR E-mail Capture - Monticello TSTF-505, Request for Additional Information ML21062A0532021-03-0202 March 2021 Information Request to Support Upcomng Problem Identification and Resolution (Pi&R) Inspection at the Prairie Island Nuclear Generating Plant ML21033A6112021-02-0101 February 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000282/2021010 and 05000306/2021010 2024-08-05
[Table view] Category:Letter
MONTHYEARL-MT-24-038, Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI2024-10-15015 October 2024 Subsequent License Renewal Application Response to Request for Additional Information - 3rd Round RAI ML24277A0202024-10-0303 October 2024 Operator Licensing Examination Approval Monticello Nuclear Generating Plant, October 2024 ML24277A1012024-10-0303 October 2024 Closure of Interim Report of a Potential Deviation or Failure to Comply Associated with Bentley Systems Incorporated Autopipe Software IR 05000263/20240112024-10-0101 October 2024 Biennial Problem Identification and Resolution Inspection Report 05000263/2024011 L-MT-24-025, Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements2024-09-26026 September 2024 Application to Revise Technical Specifications to Adopt TSTF-554, Revise Reactor Coolant Leakage Requirements ML24241A1682024-09-23023 September 2024 Transmittal Letter Amendment No. 13 to Materials License No. Special Nuclear Material-2506 for the Prairie Island Independent Spent Fuel Storage Installation 05000282/LER-2024-001, Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies2024-09-16016 September 2024 Auxiliary Building Special Ventilation System Inoperable During Movement of Irradiated Fuel Assemblies IR 05000282/20243012024-09-13013 September 2024 NRC Initial License Examination Report 05000282/2024301 and 05000306/2024301 L-MT-24-029, Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI2024-09-13013 September 2024 Subsequent License Renewal Application Response to Request for Additional Information and Request for Confirmation of Information-Supplement to Set 1 Part 2 and Response to 2ci Round RAI IR 05000263/20240052024-08-30030 August 2024 Updated Inspection Plan and Follow-Up Letter for Monticello Nuclear Generating Plant, Unit 1 (Report 05000263/2024005) L-MT-24-028, Response to RCI for RR-017 ISI Impracticality2024-08-28028 August 2024 Response to RCI for RR-017 ISI Impracticality IR 05000282/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2024005 and 05000306/2024005) 05000263/LER-2024-002, Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure2024-08-27027 August 2024 Low Pressure Coolant Injection Inoperable Due to Motor Valve Failure ML24222A1822024-08-27027 August 2024 – Proposed Alternative Request VR-09 to the Inservice Testing Requirements of the ASME OM Code for Main Steam Safety Relief Valves L-PI-24-040, Post-Submittal Package Letter2024-08-23023 August 2024 Post-Submittal Package Letter IR 05000263/20244202024-08-21021 August 2024 Security Baseline Inspection Report 05000263/2024420 - Cover Letter IR 05000263/20240022024-08-14014 August 2024 Integrated Inspection Report 05000263/2024002 ML24218A2282024-08-0505 August 2024 Request for Confirmation of Information for Relief Request RR-017, Inservice Inspection Impracticality During the Fifth Ten-Year Interval IR 05000282/20245012024-08-0505 August 2024 Emergency Preparedness Inspection Report 05000282/2024501 and 05000306/2024501 ML24213A1592024-07-31031 July 2024 Operator Licensing Examination Approval - Prairie Island Nuclear Generating Plant IR 05000282/20240022024-07-30030 July 2024 Integrated Inspection Report 05000282/2024002 and 05000306/2024002 ML24208A1502024-07-26026 July 2024 Independent Spent Fuel Storage Installation - Submittal of Quality Assurance Topical Report (NSPM-1) ML24215A2992024-07-23023 July 2024 Minnesota State Historic Preservation Office Comments on Monticello SLR Draft EIS ML24198A2372024-07-18018 July 2024 Information Request to Support Upcoming Biennial Problem Identification and Resolution (Pi&R) Inspection at Monticello Nuclear Generating Plant ML24197A2012024-07-15015 July 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000282/2024004 L-MT-24-022, – Preparation and Scheduling of Operator Licensing Examinations2024-07-0909 July 2024 – Preparation and Scheduling of Operator Licensing Examinations IR 05000282/20240102024-06-28028 June 2024 Comprehensive Engineering Team Inspection Report 05000282/2024010 and 05000306/2024010 L-PI-24-036, – Preparation and Scheduling of Operator Licensing Examinations2024-06-28028 June 2024 – Preparation and Scheduling of Operator Licensing Examinations L-MT-24-019, Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii)2024-06-10010 June 2024 Submittal of ASME Section XI, Section IWB-3720 Analytical Evaluation in Accordance with 10 CFR 50.55a(b)(2)(xliii) ML24164A2402024-06-10010 June 2024 Minnesota State Historic Preservation Office- Comments on Draft Monticello SLR Draft EIS ML24158A5912024-06-0606 June 2024 CFR 50.46 LOCA Annual Report L-PI-24-031, Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2)2024-06-0505 June 2024 Independent Spent Fuel Storage Installation, Supplement to License Amendment Request to Revise Independent Spent Fuel Storage Installation (ISFSI) License Conditions 23(a), 24(A)(2), and 24(B)(2) L-MT-24-017, Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-01602024-06-0404 June 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Monticello Technical Specification Surveillance Requirement 3.8.6.6 (EPID-L-2023-LLA-0160 ML24137A2792024-06-0303 June 2024 Audit Summary for License Amendment Request to Revise Technical Specification 3.8.6, Battery Parameters, Surveillance Requirement 3.8.6.6 L-PI-24-014, License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption2024-06-0303 June 2024 License Amendment Request to Revise the Technical Specification Definition of Reactor Trip System (RTS) Response Time and Apply Response Time Testing to RTS Trip Functions with Time Delay Assumption ML24155A1952024-05-31031 May 2024 Reactor Trip and Auto-Start Actuation of Auxiliary Feedwater Due to Loss of Suction to the 22 Main Feedwater Pump ML24155A1922024-05-31031 May 2024 Refueling Outage Unit 2 R33 Owners Activity Report for Class 1, 2, 3 and Mc Inservice Inspections IR 05000263/20244012024-05-30030 May 2024 Public - Monticello Nuclear Generating Plant - Cyber Security Inspection Report 05000263/2024401 ML24149A3712024-05-29029 May 2024 (Ping) - Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection ML24262A1992024-05-29029 May 2024 L-PI-24-018 PINGP 75 Day Letter L-PI-24-030, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.12024-05-22022 May 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.8.1 ML24141A1292024-05-22022 May 2024 Northern States Power Company - Use of Encryption Software for Electronic Transmission of Safeguards Information ML24141A1782024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24141A0452024-05-20020 May 2024 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML24128A2572024-05-16016 May 2024 ISFSI A13 Acceptance Letter L-MT-24-015, Response to Request for Additional Information - Alternative Request VR-09 for OMN-172024-05-16016 May 2024 Response to Request for Additional Information - Alternative Request VR-09 for OMN-17 IR 05000282/20240012024-05-15015 May 2024 Integrated Inspection Report 05000282/2024001 and 05000306/2024001 L-MT-24-013, 2023 Annual Radiological Environmental Operating Report2024-05-14014 May 2024 2023 Annual Radiological Environmental Operating Report ML24135A1902024-05-14014 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report IR 05000263/20240102024-05-13013 May 2024 Age-Related Degrading Inspection Report 05000263/2024010 2024-09-26
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555*0001 February 15, 2011 Mr. Gabor Salamon Director, Nuclear licensing and Emergency Preparedness Northern States Power Company - Minnesota 414 Nicollett Mall- MP4 Minneapolis, MN 55401
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT AND PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO LICENSE AMENDMENT REQUEST FOR APPROVAL OF CYBER SECURITY PLAN (TAC NOS. ME4272, ME4294 AND ME4295)
Dear Mr. Salamon:
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated July 20, 2010, Northern States Power Company, a Minnesota corporation (NSPM, the licensee), doing business as Xcel Energy, submitted a request for approval of the NSPM Cyber Security Plan and provided a proposed implementation schedule for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant, Units 1 and 2.
The NRC staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter. During a discussion with your staff on January 31,2011, it was agreed that you would provide a response by February 28, 2011.
The NRC staff considers that timely responses to requests for additional information help ensure sufficient time is available for staff review and contribute toward the NRC's goal of efficient and effective use of staff resources. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-4037.
Sincerely,
~~d~~
Thomas J. Wengert, seniOr~rOject Manager Plant licensing Branch 111-1 Division of Operating Reactor licensing Office of Nuclear Reactor Regulation Docket Nos. 50-263, 50-282 and 50-306
Enclosure:
Request for Additional Information cc w/encl: Distribution via listServ
REQUEST FOR ADDITIONAL INFORIVIATION (RAI)
REGARDING APPROVAL OF CYBER SECURITY PLAN NORTHERN STATES POWER COMPANY - MINNESOTA MONTICELLO NUCLEAR GENERATING PLANT. UNIT 1 PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 DOCKET NOS. SO-263. SO-282, AND SO-306 In reviewing the Northern States Power Company, a Minnesota corporation (NSPM, the licensee), doing business as Xcel Energy, submittal dated July 20,2010 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML102020164), which requested approval of the Cyber Security Plan (CSP) for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant, Units 1 and 2, the U.S. Nuclear Regulatory Commission (NRC) staff has determined that the following information is needed to complete its review:
Cyber Security Plan (CSP) Section 4: Establishing, Implementing, and Maintaining the Cyber Security Program RAI 1: Clarifying the Site Defensive Model Title 10 of the Code of Federal Regulations (10 CFR) Section 73.S4(c)(2) calls for the licensee to "apply and maintain defense-in-depth protective strategies ... " and 10 CFR 73.S4(d)(2) calls for the licensee to evaluate and manage cyber risks.
Nuclear Energy Institute (NEI) 08-09 Revision 6, page A-12, section 4.3, provides two examples of an effective defensive model to meet the requirements of 10 CFR 73.S4. Example 1 states (in part): Information flows between Levels 3 and 4 are restricted through the use of a firewall and a network-based intrusion detection system. Example 2 states (in part): Information flows between security critical digital assets (CDAs) in one level and security CDAs in another level are restricted through the use of a firewall and a network-based intrusion detection system.
The Monticello and Prairie Island CSP (as found on page 12, section 4.3, third paragraph) states (in part): The boundary between Level 3 and Level 2 is implemented by one or more devices or methods [emphasis added] that isolate CDAs in or above Level 3. Information flows between Levels 3 and 4 are restricted through the use of defense-in-depth techniques that utilize technologies such as [emphasis added] firewalls and network-based intrusion detection systems and strategic local area network architecture designs.
There are two parts to the RAI, but both relate to the defensive architecture:
Enclosure
-2
- 1. What are the "devices or methods" (these words are not used in the NEI 08-09 template) referred to in the Monticello and Prairie Island CSP? Provide an explanation of how this is equivalent to unidirectional communication devices (e.g., data diodes) or air gaps.
- 2. The Monticello and Prairie Island CSP uses the term "such as", which means these are just examples and the application of only one approach (e.g., a firewall alone) may suffice. Clarify how this approach is equivalent to an approach that incorporates both a firewall and a network intrusion detection system (i.e., two independent protection methods).
RAI2: Timeframe for Verifying Security Controls Section 73.54(g) of 10 CFR states: "The licensee shall review the cyber security program as a component of the physical security program in accordance with the requirements of § 73.55(m),
including the periodicity requirements." And, 10 CFR 73.55(m) states that the Security Program be reviewed: "(1) As a minimum the licensee shall review each element of the physical protection program at least every 24 months."
Monticello and Prairie Island CSP states on page 14, section 4.4.3, last paragraph: Ongoing assessments are performed to verify that the cyber security controls implemented for CDAs remain in place throughout the life cycle. The assessment process verifies the status of these cyber security controls at least every 36 months [emphasis added] or in accordance with the specific requirements for utilized cyber security controls as described in Appendices 0 and E of NEI 08-09, Revision 6, whichever is more frequent.
Clarify how a periodicity of 36 months for the assessment of cyber security controls meets the requirements of 10 CFR 73.55(m) for 24 months.
February 15, 2011 Mr. Gabor Salamon Director, Nuclear Licensing and Emergency Preparedness Northern States Power Company - Minnesota 414 Nicollett Mall- MP4 Minneapolis, MN 55401
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT AND PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 - REQUEST FOR ADDITIONAL INFORMATION RELATED TO LICENSE AMENDMENT REQUEST FOR APPROVAL OF CYBER SECURITY PLAN (TAC NOS. ME4272, ME4294 AND ME4295)
Dear Mr. Salamon:
By letter to the U.S. Nuclear Regulatory Commission (NRC) dated July 20, 2010, Northern States Power Company, a Minnesota corporation (NSPM, the licensee), doing business as Xcel Energy, submitted a request for approval of the NSPM Cyber Security Plan and provided a proposed implementation schedule for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant, Units 1 and 2.
The NRC staff is reviewing your submittal and has determined that additional information is required to complete the review. The specific information requested is addressed in the enclosure to this letter. During a discussion with your staff on January 31, 2011, it was agreed that you would provide a response by February 28, 2011.
The NRC staff considers that timely responses to requests for additional information help ensure sufficient time is available for staff review and contribute toward the NRC's goal of efficient and effective use of staff resources. If circumstances result in the need to revise the requested response date, please contact me at (301) 415-4037.
Sincerely, IRAI Thomas J. Wengert, Senior Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-263, 50-282 and 50-306
Enclosure:
Request for Additional Information cc w/encl: Distribution via ListServ DISTRIBUTION:
PUBLIC LPL3-1 R/F RidsNrrPMMonticello Resource RidsNrrDorlDpr Resource RidsNrrDorlLpl3-1 Resource RidsAcrsAcnw_MailCTR Resou rce PPederson, NSIR RidsNRRPMPrairielsland Resource RidsOgcRp Resource RidsNrrLABTully Resource RidsRgn3MailCenter Resource ADAMS Accession Number" IVIL110320354 OFFICE LPL3-1/PM LPL3-1/LA LPL3-1/BC NAME TWengert BTuily RPascarelii DATE 02/07/11 02/02/11 02/15/11 OFFICIAL RECORD COPY