Request for Additional Information Related to the Review of the Diablo Canyon Nuclear Power Plant, Units 1 and 2, License Renewal Application (TAC Nos. ME2896 and ME2897) - Fire Protection
ML102660541
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 09/30/2010
From: Ferrer N
License Renewal Projects Branch 1
To: Conway J
Pacific Gas & Electric Co
Ferrer, N B, NRR/DLR, 415-1045
References
TAC ME2896, TAC ME2897
Download: ML102660541 (4)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 September 30, 2010 Mr. John Conway Senior Vice President Generation and Chief Nuclear Officer Pacific Gas and Electric Company 77 Beale Street,* MC B32 San Francisco, CA 94105

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REVIEW OF THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME2896 AND ME2897) - FIRE PROTECTION

Dear Mr. Conway:

By letter dated November 23, 2009, Pacific Gas & Electric Company submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses for Diablo Canyon Nuclear Power Plant, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.

The request for additional information was discussed with Mr. Terry Grebel, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-1045 or bye-mail at nathaniel.ferrer@nrc.gov.

Sincerely, Nathaniel Ferrer, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323

Enclosure:

As stated cc w/encl: Distribution via Listserv

Diablo Canyon Nuclear Power Plant, Units 1 and 2 License Renewal Application Request for Additional Information Set 28 Fire Protection - Clarification on responses Based on the staff's review of PG&E's response dated July 28, 2010, please provide responses to the following:

RAI 2.3.3.12-4 (follow-up)

By letter dated July 28, 2010, the applicant responded to request for additional information (RAI) 2.3.3.12-4 and clarified a discrepancy between license renewal boundary drawing LR DCPP-18-1 06718-12 and Final Safety Analysis Report Section 9.5.1.2.6.1, regarding areas and locations of low pressure CO2 fire hose reel coverage. However, the RAI response did not provide the CO2 fire hose reel location for "25kV Potential Transformer Area," listed in RAI 2.3.3.12-4. The staff requests that the applicant identify the location of the CO2 fire hose reel for the "25kV Potential Transformer Area."

ENCLOSURE

September 30, 2010 Mr. John Conway Senior Vice President Generation and Chief Nuclear Officer Pacific Gas and Electric Company 77 Beale Street, MC B32 San Francisco, CA 94105 SURIECT:

REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REVIEW OF THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME2896 AND ME2897) - FIRE PROTECTION

Dear Mr. Conway:

By letter dated November 23, 2009, Pacific Gas &Electric Company submitted an application pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew the operating licenses for Diablo Canyon Nuclear Power Plant, Units 1 and 2, for review by the U.S. Nuclear Regulatory Commission (NRC or the staff). The staff is reviewing the information contained in the license renewal application and has identified, in the enclosure, areas where additional information is needed to complete the review.

The request for additional information was discussed with Mr. Terry Grebel, and a mutually agreeable date for the response is within 30 days from the date of this letter. If you have any questions, please contact me at 301-415-1045 ore-mail nathaniel.ferrer@nrc.gov.

Sincerely, IRA!

Nathaniel Ferrer, Project Manager Projects Branch 2 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323

Enclosure:

As stated cc w/encl: Distribution via Listserv DISTRIBUTION:

See next page ADAMS Accession No'.. ML102660541 OFFICE PM:RPB2:DLR LADLR BC:RPB2:DLR PM:RPB2:DLR NAME NFerrer YEdmonds DWrona NFerrer DATE 9/29/10 9/29/10 9/30/10 9/30/10 OFFICIAL RECORD COpy

Letter to John Conway from Nathaniel Ferrer dated September 30, 2010

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION RELATED TO THE REVIEW OF THE DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. ME2896 AND ME2897) - FIRE PROTECTION DISTRIBUTION:

HARD COPY:

DLR RF E*MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRarb Resource RidsNrrDlrRapb Resource RidsNrrDlrRasb Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsOgcMailCenter Resource NFerrer KGreen AStuyvenberg DWrona AWang MPeck, RIV TBrown, RI GMiller, RIV NO'Keefe, RIV ICouret, OPA VDricks,OPA WMaier, RIV JWeil,OCA EWilliamson, OGC SUttal,OGC RRihm, EDO